1 FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture

2 AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement 4. 5 Questions and Comments

3 DISTRICT FACILIITES

4 4

5

6 HIGHLIGHTS 6 1. Code Miscellaneous ADA and some Building Code upgrades required 2. Site Some site related storm drainage repairs and improvements 3. Roofing Variety roof types requiring removal and replace to existing roof deck 4. Windows Good condition and recently replaced. (sealant deteriorating) 5. Envelope Miscellaneous locations require repointing of brick 6. Finishes Fair condition. Some floors, ceilings, casework replacement, repaint 7. Electrical upgrade obsolete branch panels and service. 8. Technology Being upgraded by District currently 9. HVAC No central building automation system is in place. Upgrade in entirety 10. Plumbing Piping infrastructure and fixtures nearing end of useful life. (Fixtures are aged and Non-ADA) 11. Environmental Abate in entirety, VAT, Pipe insulation & fittings

7 CONCEPTUAL RENOVATION COSTS HAYCOCK ELEMENTARY SCHOOL GRANDVIEW ELEMENTARY SCHOOL Construction Cost $ 2,390,796 Soft Costs $ 717,238 TOTAL CONCEPTUAL COSTS $ 3,108,033 7

8 CONCEPTUAL RENOVATION COSTS HAYCOCK ELEMENTARY SCHOOL MAIN SCHOOL/DISTRICT ADMIN BUILDING Construction Cost $ 13,817,489 Soft Costs $ 4,145,247 TOTAL CONCEPTUAL COSTS $ 17,962,736 8

9 DISTRICT CONCEPTUAL RENOVATION COSTS BUILDING Est. Soft Costs TOTAL COSTS Const. Costs Grandview Elementary $ 2,390,796 $ 717,238 $ 3,108,033 Main School and District Admin $ 13,817,489 $ 4,145,247 $ 17,962,736 TOTAL $ 16,208,285 $ 4,862,485 $ 21,070,769

10 RECOMMENDED SCOPE FOR EACH SCHOOL

11 MORRISVILLE HIGH SCHOOL, MIDDLE AND INTERMEDIATE SCHOOL AND DISTRICT ADMINISTRATION HEALTH, LIFE SAFETY, ADA AND CODE ITEMS (Recommended projects identified in June 2017 report) Exterior Sidewalks and paving $87,000 $26,100 $113,100 Bid or eziqc 1 $113,100 Summer 2018 Whole Building Branch panelboards, HVAC, Exhaust, Building Controls $2,443,396 $733,019 $3,176,415 ESCo $3,176,415 Fall 2018 through Summer 2019 Front Office Secure entry vestibule $50,000 $15,000 $65,000 ESCo* $65,000 Fall 2018 through Summer 2019 Corridors Provide ADA water coolers $25,000 $7,500 $32,500 ESCo $32,500 Fall 2018 through Summer 2019 Replace cork, curtains, provide ADA Auditorium $122,900 $36,870 $159,770 Bid/ezIQC/SC 2 $159,770 Summer 2018 into Fall 2018 if Needed access via a lift Restrooms C+D Renovate $550,000 $165,000 $715,000 ESCo $715,000 Fall 2018 through Summer 2019 District Office Secure entry vestibule $25,000 $7,500 $32,500 ESCo* $32,500 Fall 2018 through Summer 2019 Locker Rooms Update for ADA girls and boys $60,000 $18,000 $78,000 ESCo $78,000 Fall 2018 through Summer 2019 Health, Life Safety, ADA and Code Sub total $3,363,296 $1,008,989 $4,372,285 GRANDVIEW ELEMENTARY SCHOOL HEALTH, LIFE SAFETY, ADA AND CODE ITEMS (Recommended projects identified in June 2017 report) Remove existing roof down to the deck. Roof #2 Install new insulation and multi ply roof with 30 year warranty $274,000 $82,320 $356,320 ESCo $356,320 Fall 2018 through Summer 2019 Front Office Secure entry vestibule $50,000 $15,000 $65,000 ESCo* $65,000 Fall 2018 through Summer 2019 Corridors Provide ADA water coolers $9,000 $3,000 $12,000 ESCo $12,000 Fall 2018 through Summer 2019 Multi purpose Room Abate and replace floor tile $6,000 $2,000 $8,000 Bid Abate/Floor $8,000 Summer 2018 Restrooms Complete rebuild; update for ADA $36,000 $10,800 $46,800 ESCo $46,800 Fall 2018 through Summer 2019 Restrooms Complete rebuild; update for ADA $15,000 $4,500 $19,500 ESCo $19,500 Fall 2018 through Summer 2019 Health, Life Safety, ADA and Code Sub total $390,000 $117,620 $507,620 HS, MS, IS AND DAO + GRANDVIEW ES SUB TOTAL RECOMMENDED HEALTH, LIFE SAETY, ADA AND CODE ITEMS $4,879,905

12 ALTERNATIVE SCOPE ITEMS FOR CONSIDERATION Project Description Estimated Construction Costs Soft 30% Total Project Costs GYMNASIUM RENOVATIONS GYMNASIUM RENOVATIONS Auditorium Paint CMU walls $9,900 $2,970 $ 12,870 ESCo* $ 12,870 Fall 2018 Stage Prep and paint hard ceiling; install new ceiling/acoustical clouds $139,000 $41,700 $ 180,700 ESCo* $ 180,700 Fall 2018 Replace carpet in aisles $27,900 $8,370 $ 36,270 ESCo* $ 36,270 Fall 2018 Provide stage theater lighting system and new house lighting Stage rigging,scaffolding, and miscellaneous (programming/testing) Replace the stage floor with T&G painted black $200,000 $60,000 $ 260,000 Bid/ezIQC/SC 2 $ 260,000 Summer 2018 into Fall 2018 $200,000 $60,000 $ 260,000 Bid/ezIQC/SC 2 $ 260,000 Summer 2018 into Fall 2018 $14,250 $4,275 $ 18,525 ESCo* $ 18,525 Fall 2018 Support Convert School Store to Dressing Rooms $26,250 $7,875 $34,125 ESCo* $ 34,125 Fall 2018 Auditorium and Stage Renovations $617,300 $185,190 $802,490 GYMNASIUM RENOVATIONS GYMNASIUM RENOVATIONS Gymnasium Prep and paint ceiling $54,045 $16,214 $ 70,259 ESCo* $ 70,259 Fall 2018 through Summer 2019 Paint CMU walls $29,425 $8,828 $ 38,253 ESCo* $ 38,253 Fall 2018 through Summer 2019 Remove (4) existing basketball standards. Convert (8) manual $75,000 $22,500 $ 97,500 ESCo* $ 97,500 Fall 2018 through Summer 2019 Replace HVAC System $135,713 $40,714 $ 176,427 ESCo $ 176,427 Fall 2018 through Summer 2019 Gymnasium Renovations $294,183 $88,255 $382,438 BUILDING UPGRADES BUILDING UPGRADES Asbestos Abatement Building wide $375,000 $112,500 $ 487,500 Bid Abate/Floor $ 487,500 Summer 2018 New Finishes Replace asbestos floor tile with new VCT $119,544 $35,863 $ 155,407 Bid Abate/Floor $ 155,407 Summer 2018 Building Upgrades $494,544 $148,363 $642,907 SUB TOTAL AUDITORIUM, STAGE, GYMNASIUM AND BUILDING UPGRADES WITH SOFT COSTS $1,827,835

13 Scope of Work Project Delivery Method Construction Timeframe High Priority IS/MS/HS Sidewalks and Paving Public Bid or Other Summer 2018 IS/MS/HS HVAC, Electrical, Controls ESCo Energy Scopes Fall 2018 through Summer 2019 IS/MS/HS ADA Water Coolers/Locker Rooms ESCo Energy Scopes Fall 2018 through Summer 2019 IS/MS/HS Toilet Room Upgrades ESCo Energy Scopes Fall 2018 through Summer 2019 IS/MS/HS Security Vestibules ESCo Non Energy Scopes Fall 2018 through Summer 2019 GES Roof ESCo Energy Scopes Fall 2018 through Summer 2019 GES ADA Water Coolers, Toilet Room Upgrades ESCo Energy Scopes Fall 2018 through Summer 2019 GES Security Vestibule ESCo Non Energy Scopes Fall 2018 through Summer 2019 GES Cafeteria Floor Abatement & Replacement Public Bid or Other Summer 2018 Alternative Scopes Auditorium Painting Walls & Ceilings and Carpet ESCo Non Energy Scopes Fall 2018 through Summer 2019 Auditorium Stage Rigging, Lighting, and Floors Public Bic or Other Summer 2018 Auditorium Cork, Curtains and Lift Public Bic or Other Summer 2018 Gymnasium Painting and Equipment ESCo Non Energy Scopes Fall 2018 through Summer 2019 Gymnasium HVAC, Controls ESCo Energy Scopes Fall 2018 through Summer 2019 IS/MS/HS Floor Abatement & Replacement Public Bid or Other Summers of 2018 and 2019

14 OPTIONAL PROCUREMENT PROCESS

15 PROCUREMENT GESA (Guaranteed Energy Saving Project) or ESCo (Energy Services Company) is a design/build project that provies for a guaranteed performance related to energy use a. HVAC, plumbing electrical roofing, windows and code related work b. Plus 15% of non-energy using scopes (like finishes and security vestibules) c. Qualifications/pre-approved subcontractors and vendors target local firms 2. Scopes that are publically bid a. State contract or exiqc with multiple vendors competing b. Work to include siteworkm work at stage, abatement/re-flooring 3. Schedule a. Begin GESA/ESCo scopes in the fall of 2018 to get best pricing when contractors are less constrained. b. Goal provide a method to get the most scope for least money

16 Partnering to enhance the student experience! THANK YOU!

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

Project Status Report Property and Finance Committee Meeting August 6, 2013

Project Status Report Property and Finance Committee Meeting August 6, 2013 Westmont Hilltop School District Project Status Report Property and Finance Committee Meeting August 6, 2013 S. Dwight Knouse II, AIA, LEED AP Russell D. Greaser, Project Manager Matthew T. Filan, PE,

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

BUILDING FOR OUR FUTURE

BUILDING FOR OUR FUTURE MIDDLE TOWNSHIP PUBLIC SCHOOLS BOND REFERENDUM March 8, 2016 Bond Referendum BUILDING FOR OUR FUTURE ADDRESSING THE DISTRICT S CRITICAL FACILITY AND SITE NEEDS CURRENTLY THE BAND-AID APPROACH COSTS MONEY

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

Cherry Hill School District Building Project Summary. August 8, 2018

Cherry Hill School District Building Project Summary. August 8, 2018 Cherry Hill School District Building Project Summary August 8, 2018 Progress Update: Bond Referendum 2018 As of August 8, 2018, the Cherry Hill Public School District has not yet received approval from

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

Crockett Elementary School Renovations

Crockett Elementary School Renovations We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included

More information

Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School

Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School ADDENDUM No. 002 For Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School DALLAS INDEPENDENT SCHOOL DISTRICT September 24, 2014 The following items modify the Project

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

Madison School District. Strategic Five-Year Facility Maintenance Plan

Madison School District. Strategic Five-Year Facility Maintenance Plan Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets

More information

DAVIS ELEMENTARY SCHOOL

DAVIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-

More information

GARFIELD ELEMENTARY SCHOOL

GARFIELD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1910 BUILDING AREA 58,908 SF CURRENT PROGRAM CAPACITY 446 ENROLLMENT 2008 278 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan GARFIELD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

STUART-HOBSON MIDDLE SCHOOL

STUART-HOBSON MIDDLE SCHOOL INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012 Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

SHEPHERD ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

2019 Construction

2019 Construction 2019 Construction Estimates @ 18 10 01 1 Oak Flat Elementary IDENTIFIED BASE BID SCOPE ITEMS Project BSSD replace door hardware to meet ADA, including re-key to master system $ 75,000 Shelter Lockdown

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

City High Middle School pre-design recommendations. March 29, 2017

City High Middle School pre-design recommendations. March 29, 2017 City High Middle School pre-design recommendations March 29, 2017 City High Middle School table of contents 2 3 4 5 6 7 8 9 10 11 12 13 table of contents project description and purpose existing systems

More information

MAURY ELEMENTARY SCHOOL

MAURY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

WATKINS ELEMENTARY SCHOOL

WATKINS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

What is a Master Plan

What is a Master Plan What is a Master Plan Master planning A long-term, comprehensive approach to facilities planning (10-12 years) Align facilities plan with mission, vision, strategic goals and community values Recognizes

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

MADELEY RANCH ELEMENTARY SCHOOL

MADELEY RANCH ELEMENTARY SCHOOL MADELEY RANCH ELEMENTARY SCHOOL CAMPUS DATA MADELEY RANCH ELEMENTARY SCHOOL 3500 Madeley Ranch Road, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 94,750 Pre-K - 4 th

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 WORK LEGEND OVERALL WORK TO BOTH BUILDINGS 1 2 3 4 Existing corridors will receive new

More information

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1 GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

Basic renewal/restoration and safety projects

Basic renewal/restoration and safety projects Basic renewal/restoration and safety projects Board Update September 9, 2013 Bond Team Support Team Agenda Program Management Goals Program Budget Status 2013 Project Updates Labor Distribution Study 2014

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community. SYLVAN MIDDLE SCHOOL The mission of Sylvan Middle School is consistent with that of the San Juan Unified School District, which is to inspire each student tosucceed and responsibly contribute to a radically

More information

Stevens High School Pre Bond Presentation Claremont, NH

Stevens High School Pre Bond Presentation Claremont, NH Stevens High School Pre Bond Presentation Claremont, NH Existing Conditions Existing Conditions Existing Conditions Existing Conditions Proposed site features New main entry that is ADA accessible New

More information

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN GREENWICH PUBLIC SCHOOLS Greenwich, CT November 27, 2017 Addendum to Agenda Item: 2018-2019 SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN Please note edited pages should replace original sheets in

More information

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening

More information

La Conner School District

La Conner School District hoarch.com La Conner School District Capital Bond Planning Meeting 4 - Master Plan Options / Budget Estimates July 18th, 2012 4010 Lake Washington Blvd, NE, Suite 320 Kirkland, Wa 425 828 8948 Agenda Meeting

More information

Table of Contents Hampton Dumont Community School District November 5, 2013

Table of Contents Hampton Dumont Community School District November 5, 2013 Table of Contents Hampton Dumont Community School District November 5, 2013 Facility Assessment Overview & Proposed Design Options 1. Option 1 Alleviate Congestion at South Side Elementary Existing Facility

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

Hampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects

Hampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects 2018 High School Feasibility Study Final Feasibility Study Presentation January 28, 2019 1 Study Updates I. Latest HS Concepts for Academic / Wellness Redesign II. Associated Conceptual Construction Costs

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

38% 62% Project Funding. TPS Systems and Infrastructure needs

38% 62% Project Funding. TPS Systems and Infrastructure needs TPS Systems and Infrastructure needs Project Funding Roof replacements (BGP, TMS) Plumbing upgrades Boiler replacements Code compliant systems, PA, Fire Alarm, Area of Refuge Concrete repair Floor repair

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S.372 ANNEX - K, 215 FIRST STREET, New York, 11215 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-03-06

More information

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Information Session Agenda Background. Scope of work and why these renovations are important. Project cost. How

More information

North Allegheny School District

North Allegheny School District North Allegheny School District January 18, 2017 Preparing all students for success in a changing world NAI was last renovated in 1997 Money was set aside during recent bond issue for renovations to occur

More information

Prepared by. Christopher La Follette. Fidelis Management, Inc.

Prepared by. Christopher La Follette. Fidelis Management, Inc. 2012 Prepared by Christopher La Follette Fidelis Management, Inc. TEN-YEAR FACILITIES MAINTENANCE PLAN The purpose of this plan is to perform a facility audit on all facilities to determine any remaining

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Cost Estimate Details

Cost Estimate Details C 0131 1 Inadequate Parking Construct or Expand Parking Lots $67,000 F 0132 1 Inadequate Drop Off Zone Widen Sidewalk, Construct Pathway and $77,000 Canopy RR 0132 2 No Landings at Classroom Exits Construct

More information

ROD Grant Round 4 Presentation June 9, 2014

ROD Grant Round 4 Presentation June 9, 2014 ROD rant Round 4 Presentation June 9, 2014 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 2 Agenda NJDOE Application

More information

Alterations, disproportionality, and the 20% rule

Alterations, disproportionality, and the 20% rule Alterations, disproportionality, and the 20% rule By M. Bradley Gaskins, AIA, CASp and Ellis L. McIntosh Jr., AIA, LEED AP The MCintosh group 1850 South Boulder Avenue Tulsa, OK 74119 918.585.8555 tmgada.com

More information

Merritt Island High School

Merritt Island High School Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

PACKAGE 3 ELEMENTARY AND MIDDLE SCHOOLS IMPROVEMENTS REPORT December 2015 Issue 1

PACKAGE 3 ELEMENTARY AND MIDDLE SCHOOLS IMPROVEMENTS REPORT December 2015 Issue 1 PACKAGE 3 ELEMENTARY AND MIDDLE SCHOOLS IMPROVEMENTS REPORT December 2015 Issue 1 This document created by: BG Consultants, Inc 1405 Wakarusa Drive Lawrence, Kansas 66049 PACKAGE 3 ELEMENTARY AND MIDDLE

More information

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies

More information

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for

More information

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet FLANDERS ELEMENTARY SCHOOL Located at 167 Boston Post Road, East Lyme, Connecticut the school s original structure was built in 1964 and replaced the Central Office Building as the elementary school. Two

More information

FEASIBILITY STUDY SEPTEMBER 1 8,

FEASIBILITY STUDY SEPTEMBER 1 8, FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study

More information

Middle High School Bus Garage Subtotal

Middle High School Bus Garage Subtotal Summary Data BCS Survey Scottsville, Y TJ Connor Elementary Schoo 26-20-0-04-0-002-xxx Sub-Total General Construction $4,689,472 Incidental $974,336 2 26-20-0-04-0-003-xxx Sub-Total $5,663,808 General

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

DALLAS INDEPENDENT SCHOOL DISTRICT. BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations

DALLAS INDEPENDENT SCHOOL DISTRICT. BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations DALLAS INDEPENDENT SCHOOL DISTRICT PROCUREMENT SERVICES CONSTRUCTION SERVICES DOCUMENT DISTRIBUTION CONSTRUCTION SERVICES BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations 1.

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

NYC Department of Education

NYC Department of Education Building Assessment Survey 2017-2018 Asset: P.S. 841- QUEENS, 48-25 37TH STREET, New York, 11104 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-04-02 12:17 PM 2018-04-10

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information