PROJECT MANUAL LAKE SERENE CENTER Building A. Project # For: Emerald Bay Equity, LLC. June 17, 2010

Size: px
Start display at page:

Download "PROJECT MANUAL LAKE SERENE CENTER Building A. Project # For: Emerald Bay Equity, LLC. June 17, 2010"

Transcription

1 PROJECT MANUAL LAKE SERENE CENTER Building A Project # For: Emerald Bay Equity, LLC June 17, NE 85 TH ST Suite 101 Redmond, WA T F

2 TABLE OF CONTENTS Lake Serene Center Building A CONDITIONS OF THE CONTRACT Substitution Request Form Drawing Index DIVISION ONE - GENERAL REQUIREMENTS Applications for Payment Modification Procedures Project Coordination Field Engineering Regulatory Requirements Abbreviations & Symbols Reference Standards and Definitions Project Meetings Submittals Quality Control Services Temporary Facilities & Controls Materials and Equipment Product Substitutions Project Closeout Warranties and Bonds DIVISION TWO - SITE WORK Site Clearing Earthwork Compaction Control Test Trenching Asphaltic Concrete Paving Portland Cement Concrete Paving Site Utilities Site Storm Sewerage Systems Site Sanitary Sewerage Systems Site Furnishings DIVISION THREE CONCRETE Concrete Cast in Place Concrete Interior Concrete Slab-on-Grade Concrete Sealer DIVISION FOUR - MASONRY TABLE OF CONTENTS - 1

3 04200 Unit Masonry Brick Veneer Masonry DIVISION FIVE - METALS Structural Steel Miscellaneous Metal Fabrication DIVISION SIX - CARPENTRY & MILLWORK Miscellaneous Carpentry Structural Glue-Laminated Timber Metal-Plate-Connected Wood Trusses Finish Carpentry DIVISION SEVEN -THERMAL & MOISTURE PROTECTION Water Repellants Building Insulation Exterior Insulation & Finish Systems (EIFS) Class PB (Copings) Manufactured Roof Panels TPO Thermoplastic Single-Ply Roofing Flashing and Sheet Metal Roof Accessories Joint Sealants DIVISION EIGHT - DOORS, WINDOWS & GLASS Standard Steel Doors & Frames Aluminum Entrances and Storefronts Finish Hardware Glass & Glazing DIVISION NINE -FINISHES Exterior Portland Cement Plaster Gypsum Board Assemblies Ceramic Tile Resilient Flooring Painting DIVISION TEN - SPECIALTIES Identifying Devices Toilet Accessories DIVISION ELEVEN - EQUIPMENT Not Used DIVISION TWELVE -FURNISHINGS TABLE OF CONTENTS - 2

4 Not Used DIVISION THIRTEEN - SPECIAL CONSTRUCTION Not Used DIVISION FOURTEEN - CONVEYING SYSTEMS Not Used DIVISION FIFTEEN - MECHANICAL General Provisions Pipe & Pipefitting Insulation Fire Sprinkler System (Design/ Build) Plumbing Fixtures Floor Drains & Miscellaneous in Slab Fittings Heating, Ventilation & Air Conditioning Controls & Instrumentation DIVISION SIXTEEN - ELECTRICAL Electrical Fire Alarm and Detection System END OF SECTION TABLE OF CONTENTS - 3

5 This page intentionally left blank. TABLE OF CONTENTS - 4

6 SECTION SUBSTITUTION REQUEST FORM TO: DONAHOU DESIGN GROUP, ARCHITECTS, LLC NE 85 th St Suite 101 Redmond, WA PROJECT: Lake Serene Center Building A We hereby submit for your consideration the following product as a substitution for the specified item. SECTION: PARAGRAPH: SPECIFIED ITEM: ITEM PROPOSED: Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper and complete installation. Attach complete technical data. Include laboratory tests if applicable. Fill in blanks below (Attach additional sheets as required): A. Does the substitution affect dimensions shown on Drawings? B. Will the undersigned pay for changes to the building design, including architectural and engineering detailing costs caused by the requested substitution? C. What effect does substitution have on other trades? D. Differences between proposed substitution and specified item? E. Manufacturer's guarantees of the proposed and specified items are: [ ] Same [ ] Different (explain on attachment) F. Does the substitution affect the Contract Price? How?

7 The undersigned states that the function, appearances and quality are equivalent or superior to the specified item. Submitted by: (Signature) (Firm) (Address) (Date) Architect's Review: (Telephone) [ ] Reviewed, no exceptions taken. [ ] Reviewed, comments noted. [ ] Not in conformance with Design Concept. [ ] Received too late for review. By: Date: Remarks: END OF FORM

8 SECTION DRAWING INDEX Lake Serene Center Building A Drawing No. Title G-001 Cover Sheet C-1.0 Detailed Civil Plan A-101 Site Plan A-111 Floor Plan/ Wall Types A-112 Schedules A-113 Restroom Interior Elevations A-120 Reflected Ceiling Plan/ Details A-130 Roof Plan/ Details A-201 Exterior Elevations A-301 Building Sections A-302 Building Sections A-303 Building Sections A-401 Wall Sections A-402 Wall Sections A-403 Wall Sections A-404 Wall Sections A-501 Details S-1 Structural General Notes & Schedules S-2 Structural Foundation & Roof Framing Plan S-3 Structural Sections & Details S-4 Structural Sections & Details S-5 Structural Sections & Details MEP-1 Mechanical, Electrical & Plumbing Plans L-1 Landscape Plan (Reference Only) END OF SECTION

9 SECTION APPLICATIONS FOR PAYMENT PART I GENERAL 1.1 GENERAL CONDITIONS A. This section specifies administrative and procedural requirements for payment. 1.2 GENERAL REQUIREMENTS A. Original Documents: It is imperative that all payouts be made on the original AIA- G702 and AIA-G703 forms. Originals of all AIA forms are available from local AIA offices across the nation. No copies or computer generated forms will be accepted for processing. B. Guidelines: The following guidelines should be used when preparing all applications for payment: 1. Relation to other documents: Correlate line items in the Schedule of Values with other schedules and forms, including: a. Contractor's Construction Schedule. b. List of subcontractors. c. List of products. d. Schedule of submittals. 2. Format and Content: Use the G703 document as a guide to establish the format. a. Identification: Include the following identification: 1) Project name and location. 2) Name of the Architect. 3) Contractor's name and address. 4) Date of submittal. b. Arrange the Schedule in tabular form with columns to indicate the following for each item: 1) Generic name. 2) Name of subcontractor. 3) Name of manufacturer or fabricator. 4) Name of supplier. 5) Change Orders (numbers) that have affected value. 6) Dollar value. 7) Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total 100 percent. c. Break Contract Sum down in enough detail to facilitate evaluation of Applications for Payment. Break subcontract amounts down into several line items. Round amounts off to the nearest dollar; the total shall equal the Contract Sum. d. For each item where an Application for Payment includes products purchased or fabricated and stored, but not installed, provide separate line items for initial cost, each subsequent stage of completion, and installed value. e. Show line items for indirect costs, and margins on costs, to extent that such items will be listed individually in Applications for Payment. Each

10 item in the Schedule of Values and Applications for Payment shall be complete including total cost and share of overhead and profit. 1) Temporary facilities and items that are not direct cost of Work-inplace may be shown as separate line items or distributed as general overhead expense. f. Update and resubmit the schedule when Change Orders or Construction Change Directives change the Contract Sum. C. Applications for Payment: Each Application for Payment shall be consistent with previous applications and payments as certified by the Architect and paid for by the Owner. 1. Payment Application Times: Payment dates are indicated in the Agreement. The period covered by each application is the period indicated. 2. Application Preparation: Complete every entry, including notarization and execution by person authorized to sign on behalf of the Owner. Incomplete applications will be returned without action. a. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions have been made. b. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the period covered by the application. 3. Transmittal: Submit four original executed copies of each application to the owner and one copy to the Architect within 24 hours. Transmit each copy with a transmittal listing attachments, and recording information related to the application. 4. Waivers of Lien: With each application, submit waivers of lien from every entity who may file a lien arising out of the Contract, and related to the Work covered by the payment. a. Submit partial waivers on each item for amount requested, prior to deduction for retainer, on each item. b. When an application shows completion of an item, submit final or full waivers. c. Waiver Delays: Submit each application with Contractor's waiver of lien for the period covered by the application. d. Submit final Application for Payment with final waivers from every entity involved with performance of Work covered by the application who could be entitled to a lien. e. Waiver Forms: Submit waivers of lien on forms, and executed in a manner, acceptable to Owner. D. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include: (submit each item on a separate sheet of paper) 1. List of subcontractors including addresses and 24 hour phone numbers. 2. List of suppliers and fabricators. 3. Contractor's Construction Schedule (preliminary if not final). 4. Submittal Schedule (preliminary if not final). 5. List of Contractor's staff assignments including 24 hour phone numbers. 6. Copies of building permits

11 7. Waiver of Lien from the General Contractor 8. Copies of licenses from governing authorities. 9. Certificates of insurance and insurance policies. 10. Performance and payment bonds (if required). E. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion (AIA document G704), submit an Application for Payment; reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions. Administrative actions and submittals that precede or coincide with this application include: 1. Occupancy permits. 2. Warranties and maintenance agreements fully completed. 3. Test/adjust/balance records. 4. Preliminary Commissioning Report. 5. Maintenance instructions/manuals. 6. As-built document. 7. Meter readings. 8. Change-over information related to Owner's occupancy. 9. Final cleaning. 10. Application for reduction of retainer, and consent of surety. F. Final Payment Application: Administrative actions and submittals which must precede or coincide with submittal of the final payment application include: 1. Completion of Project closeout requirements. 2. Completion of items specified for completion after Substantial Completion. 3. Transmittal of required Project construction records to Owner. 4. Certified property survey. 5. Proof that taxes, fees and similar obligations have been paid. 6. Final Waivers or Lien from General Contractor and all Subcontractors who have not previously submitted them. END OF SECTION

12 This page intentionally left blank

13 SECTION MODIFICATION PROCEDURES PART I GENERAL 1.1 GENERAL CONDITIONS A. This section specifies administrative and procedural requirements for handling and processing Contract modifications. 1.2 GENERAL REQUIREMENTS A. Minor Changes in the Work: Supplemental instructions authorizing minor changes in the Work, not involving adjustment to Contract Sum or Time, will be issued by the Architect on AIA form G710. Originals of all AIA forms are available from local AIA offices across the nation. B. Proposal Request Form: Use AIA Document G Change Order Proposal Requests: Proposal requests that require adjustment to the Contract Sum or Time if accepted, will be issued by the Architect, with a detailed description of the proposed change and supplemental or revised Drawings and Specification. Proposal requests are for information only and shall not be considered as instruction to stop work in progress, or to execute the change. a. Unless otherwise indicated, within seven (7) days of receipt, submit an estimate of cost to execute the change. 1) Include a list of quantities of products to be purchased and unit costs, along with the amount of purchases to be made. If requested, furnish survey data to substantiate quantities. 2) Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. 3) Include a statement indicating the effect the proposed change in the Work will have on the Contract time. 2. Contractor Initiated Change Order Proposal Requests: When unforeseen conditions require modifications to the Contract, the Contractor may propose changes by submitting a request to the Architect. a. Include a statement outlining reasons for the change. Provide a complete description of the change. Indicate effect of the proposed change on the Contract Sum and Time. b. Include a list of quantities of products to be purchased and unit costs, along with amount of purchases to be made. If requested, furnish survey data to substantiate quantities. c. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. d. Comply with requirements in Section "Product Substitutions" if the change requires substitution of one product or system for product or system specified. C. Allowance Adjustment: Base each change order proposal request for an allowance cost adjustment on the difference between the actual purchase amount and the

14 allowance, multiplied by the final measurement of work-in-place, with reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections and similar margins. 1. Include installation costs in the purchase amount only where indicated as part of the allowance. 2. When requested, prepare explanations and documentation to substantiate margins claimed. 3. Submit substantiation of a change in scope of work claimed in the change orders related to unit-cost allowances. 4. The Owner reserves the right to establish the actual quantity of work-in-place by independent quantity survey, measure or count. D. Submit claims for increased costs because of change in scope or nature of the allowance described in contract documents, whether for purchase amount or Contractor's handling, labor, installation, overhead and profit, within 7 days of receipt of change order or construction change directive authorizing work to proceed. Claims submitted later than twenty (20) days will be rejected. 1. Change order cost amount shall not include Contractor's or subcontractor's indirect expense except when clearly demonstrated that the nature or scope of work required was changed from what could have been foreseen from the allowance description and other information in contract documents. 2. No change to the Contractor's indirect expense is permitted for selection of higher or lower priced materials or systems, of the same scope and nature as originally indicated. E. Construction Change Directive: When the Owner and Contractor are not in agreement on terms of a Change Order Proposal Request, the Architect may issue Construction Change Directive on AIA Form G714, instructing the Contractor to proceed with a change, for subsequent inclusion in a Change Order. 1. Construction Change Directive will contain a complete description of the change and designate method to be followed to determine change in the Contract Sum or Time. F. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. After completion of the change submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract. G. Change Order Procedures: Upon the Owner's approval of a Change Order Proposal Request, the Architect will issue a Change Order for signatures of the Owner and Contractor on AIA Form G701, as provided in the Conditions of the Contract. END OF SECTION

15 SECTION PROJECT COORDINATION PART I GENERAL 1.1 GENERAL CONDITIONS A. This Section specifies administration and procedural requirements for project coordination including: 1. Coordination. 2. Administrative and supervisory personnel. 3. General installation provisions. 4. Cleaning and protection. 1.2 GENERAL REQUIREMENTS A. Project Coordination: 1. Coordinate activities included in various Sections to assure efficient and orderly installation of each component. Coordinate operations included under different Sections that are dependent on each other for proper installation and operation. a. Where installation of one component depends on installation of other components before or after its own installation, schedule activities in the sequence required to obtain the best results. b. Where space is limited, coordinate installation of different components to assure maximum accessibility for maintenance, service and repair. c. Make provisions to accommodate items scheduled for later installation. d. Make provisions for any and all separate Contractors hired by the Owner to complete portions of the work. 2. Prepare memoranda for distribution to each party involved outlining required coordination procedures. Include required notices, reports, and attendance at meetings. a. Prepare similar memoranda for the Owner and separate Contractors where coordination of their Work is required. 3. Coordination Drawings: Prepare Coordination Drawings where close coordination is required for installation of products and materials fabricated offsite by separate entities, and where limited space necessitates maximum utilization of space for efficient installation of different components. a. Show relationship of components shown on separate Shop Drawings. b. Indicate required installation sequences. c. Refer to Division-15 Section "Basic Mechanical Requirements," and Division-16 Section "Basic Electrical Requirements" for requirements for mechanical and electrical installations. 4. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other activities to avoid conflicts and ensure orderly progress. Such activities include: a. Preparation of schedules. b. Installation and removal of temporary facilities. c. Delivery and processing of submittals. d. Progress meetings

16 e. Project close out activities. B. Administrative and Supervisory Personnel: 1. Staff Names: Within fifteen (15) days of Notice to Proceed, submit a list of Contractor's staff assignments, including Superintendent and personnel at the site; identify individuals, their duties and responsibilities, addresses and telephone numbers. a. Post copies in the Project meeting room, the field office, and at each temporary telephone. b. Provide the Owner with a list of emergency contacts and their (24 hours/day, 7 days/week) phone numbers. C. General Installation Provisions: 1. Inspection of Conditions: The Installer of each component shall inspect the substrate and conditions under which Work is performed. Do not proceed until unsatisfactory conditions have been corrected. 2. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that they are more stringent than requirements in Contract Documents. 3. Inspect material immediately upon delivery and again prior to installation. Reject damaged and defective items. 4. Provide attachment and connection devices and methods necessary for securing each construction element. Secure each construction element true to line and level. Allow for expansion and building movement. 5. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints to obtain the best effect. Refer questionable choices to the Architect for decision. 6. Recheck measurements and dimensions, before starting installation. 7. Install each component during weather conditions and project status that will ensure the best results. Isolate each part from incompatible material as necessary to prevent deterioration. 8. Coordinate temporary enclosures with inspections and tests, to minimize uncovering completed construction for that purpose. 9. Mounting Heights: Where mounting heights are not indicated, install components at standard heights for the application indicated and as required by code. Refer questionable decisions to the Architect. D. Cleaning and Protecting: 1. Cleaning and Protection: During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion. a. Clean and maintain completed construction as often as necessary through the construction period. Adjust and lubricate operable components to ensure operability without damaging effects. b. Limiting Exposures: Supervise operations to ensure that no part of construction, completed or in progress, is subject to harmful or deleterious exposure. Such exposures include:

17 1) Excessive static or dynamic loading. 2) Excessive internal or external pressures. 3) Excessive weathering. 4) Excessively high or low temperatures or humidity. 5) Air contamination or pollution. 6) Water or ice. 7) Chemicals or solvents. 8) Heavy traffic, soiling, staining and corrosion. 9) Rodent and insect infestation. 10) Unusual wear or other misuse. 11) Contact between incompatible materials. 12) Theft or vandalism. END OF SECTION

18 This page intentionally left blank

19 SECTION FIELD ENGINEERING PART I GENERAL 1.1 GENERAL CONDITIONS A. This Section specifies administrative and procedural requirements for field engineering. 1.2 GENERAL REQUIREMENTS A. Engage a Land Surveyor registered in the State where the Project is located, to perform land surveying required. B. The Owner will identify existing control points and property line corner stakes. 1. Surveyor's Log: Maintain a surveyor's log of control and other surveys. Make this log available for reference. a. Record deviations from required lines and levels. Advise the Architect when deviations that exceed indicated or recognized tolerances are detected. On record Drawings, record deviations that are accepted and not corrected. b. On completion of foundation walls, major site improvements, and other construction requiring field engineering services, prepare a certified survey showing dimensions, locations, angles and elevations of construction and site Work. 2. Verify layout information shown on the Drawings, in relation to the property survey and existing benchmarks before proceeding to layout the Work. Protect existing benchmarks and control points. Preserve permanent reference points during construction. a. Do not change or relocate benchmarks or control points without prior written approval. Report lost or destroyed reference points, or requirements to relocate reference points because of necessary changes in grades or locations. b. Promptly replace lost or destroyed project control points. Base replacements on the original survey control points. 3. Establish and maintain a minimum of two permanent benchmarks on the site, referenced to data established by survey control points. a. Record benchmark locations, with horizontal and vertical data, on Project Record Documents. 4. Performance: Working from lines and levels established by the property survey, establish benchmarks and markers to set lines and levels at each story of construction and where needed to properly locate each element. Calculate and measure required dimensions within indicated or recognized tolerances. Do not scale Drawings to determine dimensions. a. Advise entities engaged in construction activities, of marked lines and levels provided for their use. b. As construction proceeds, check every major element for line, level and plumb

20 5. Site Improvements: Locate and lay out site improvements, including pavements, stakes for grading, fill and topsoil placement, utility slopes and invert elevations by instrumentation and similar appropriate means. 6. Existing utilities and equipment: The existence and location of underground utilities and construction indicated as existing are not guaranteed. Before beginning site work, verify the existence and location of underground utilities and other construction. a. Prior to construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer and water service piping. 7. Existing Utilities: Furnish information necessary to adjust, move or relocate existing structures, utility poles, lines, services or other appurtenances located in, or affected by construction. Coordinate with local authorities having jurisdiction. 8. Building Lines and Levels: Locate and lay out batter boards for structures, building foundations, column grids and locations, floor levels and control lines and levels required for mechanical and electrical Work. 9. Final Property Survey: Before Substantial Completion, prepare a final property survey showing significant features for the Project. Include a certification, signed by the Surveyor, to the effect that metes, bounds, lines and levels of the Project are accurately positioned as shown on the survey. a. Recording: At Substantial Completion, have the final survey recorded by or with local authorities as the official "property survey". 1.3 SUBMITTALS A. Certificates: Submit a certificate signed by the Land Surveyor certifying that the location and elevation of improvements comply with Contract Documents. B. Final Property Survey: Submit ten (10) copies of the final property survey. C. Project Record Documents: Submit a record of Work performed and record survey data required under provisions of Section Submittals and Section Project Closeout. END OF SECTION

21 SECTION REGULATORY REQUIREMENTS PART I GENERAL 1.1 GENERAL CONDITIONS As specified in drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 - General Requirements. 1.2 GENERAL REQUIREMENTS A. Codes: All construction shall be in accordance with the building codes referenced herein. B. Specifications and Standards Material specified by reference to the number, symbol or title of a specific standard, such as Commercial Standard, Federal Specification, a grade association standard or other similar standard, shall comply with the requirements in the latest revision thereof and any amendment or supplement thereto in effect on the date of these Specifications, except as limited to type, class or grade, or modified in such reference, and unless specific non-current date is stipulated. The standard referred to, except as modified in the Specifications, shall have full force and effect as though printed in the Specifications. C. The Contractor shall familiarize himself with all applicable codes and standards and shall obtain references as required to construct the project in compliance therewith. PART II PRODUCTS 2.1 APPLICABLE CODES, ORDINANCES, AND REGULATIONS A. "Uniform" Codes shall be regulations written under the authority of the International Code Council. B. "Latest edition" shall mean the latest published edition as revised and adopted by the governmental authority having jurisdiction over the Work. C. Applicable Codes, Ordinances, and Regulations shall include, but not be limited to: 1. International Building Code (I.B.C.), Uniform Plumbing Code, (U.P.C.), International Mechanical Code, (I.M.C.), International Fire Code, (I.F.C.), National Electric Code (N.E.C.), latest edition. 6. Washington State Barrier Free Rules and Regulations, latest edition. 7. Washington State Energy Code, Telephone Company Rules and Regulations

22 9. Federal Occupational Safety and Health Standards, and State General Safety and Health Standards. 10. All standards and regulations of the governing agencies having jurisdiction over the Work. 11. All standards and regulations of the Utility and Service companies serving or traversing the site. 2.2 REFERENCE SPECIFICATIONS AND STANDARDS A. Applicable reference specifications and standards shall include, but not be limited to, the following: 1. Building Code (I.B.C.) Standards edition as published and adopted by I.C.C. 2. Reference Specifications - "ASTM" shall mean Specifications, standards and methods of test issued by the American Society for Testing Materials, 1916 Race Street, Philadelphia, Pennsylvania. 3. "Federal Specifications" shall mean "United States Federal Specifications" prepared by the General Services Administration and distributed by the Superintendent of Documents, Government Printing Office, Washington, D.C. 4. "Commercial Standard" and "Simplified Practice Recommendation" shall mean those publications recording voluntary standards and practices of various trades made available by the United Stated Department of Commerce and distributed by the Superintendent of Documents, Government Printing Office, Washington, D.C. 5. "Military Specifications" shall mean those reference standards so entitled and made available by Commanding Officer, Naval Publications and Forms Center, 5801 Tabor Avenue, Philadelphia, Pennsylvania, "ACI Building Code" shall mean Building Code requirements for Reinforced Concrete (ACI ) issued by the American Concrete Institute, Detroit, Michigan. 7. "ANSI" shall mean standards and specifications distributed by American National Standards Institute (formerly American Standards Association) 1430 Broadway, New York, N.Y "APWA" shall mean the "Standard Specification for Municipal Public Works Construction", published by the American Public Works Association, Washington State Chapter, 1977 Edition. 9. Sheet Metal and Air Conditioning Contractors National Association (S.M.A.C.C.N.A.), latest edition. 10. Underwriters Laboratories, Inc. (U.L.). 11. American Woodworking Institute (A.W.I.). 12. American Institute of Steel Construction (A.I.S.C.). 13. American Society of Heating, Refrigeration and Air-Conditioning Engineers (A.S.H.R.A.E.). 14. American Institute of Timber Construction (A.I.T.C.). 15. American Concrete Institute (A.C.I.). 16. American Plywood Association (A.P.A.). 17. American Wood Preservers Bureau (A.W.P.B.). END OF SECTION

23 SECTION ABBREVIATIONS & SYMBOLS PART I GENERAL 1.1 GENERAL CONDITIONS As specified in drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 - General Requirements. 1.2 GENERAL REQUIREMENTS A. RELATED SECTION 1. Section Regulatory Requirements B. WORDING 1. These Specifications are abbreviated or "streamlined" type and frequently include incomplete sentences. Words such as "shall," "shall be," "the Contractor shall" and similar mandatory phrases shall be supplied by inference in the same manner as they are in a note on the Drawings. The Contractor shall provide all items and shall perform all operations listed, and shall furnish all labor, materials, equipment, services and incidentals required for their completion. 2. Abbreviations used in the Drawings and Project Manual are listed on the Drawings. 3. Wherever in this Project Manual an article, device, or piece of equipment is referred to in the singular number, such reference shall include as many such articles as are shown on the Drawings or required to complete the Work. C. SYMBOLS Symbols illustrated on the Drawings are typically identified in the schedules and/or symbols key. It is the contractor's responsibility to request, prior to bid date, definition of all symbols which he does not understand or are not identified. END OF SECTION

24 This page intentionally left blank

25 SECTION REFERENCE STANDARDS AND DEFINITIONS PART I GENERAL 1.1 GENERAL CONDITIONS A. Basic Contract definitions are included in the Conditions of the Contract. 1.2 DEFINITIONS A. Owner: Lake Serene Investments LLC B. Indicated: Refers to graphic representations, notes, or schedules on the Drawings; Paragraphs or Schedules in the Specifications; and similar requirements in the Contract Documents. Terms such as shown, noted, scheduled, and specified are used to help the reader locate the reference. There is no limitation on location. C. Directed: Terms such as directed, requested, authorized, selected, approved, required, and permitted mean directed by the Architect, requested by the Architect, and similar phrases. D. Approve: When used in conjunction with the Architect's action on submittals, applications, and requests, is limited to the Architect's duties and responsibilities as stated in the Conditions of the Contract. E. Regulation: Includes laws, ordinances, statutes, and lawful orders issued by authorities with jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work. F. Furnish: Means to supply and deliver to the Project site, ready for unloading, unpacking, assembly, installation, and similar operations. G. Install: Describes operations at the Project site including unloading, unpacking, assembly, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations. H. Provide: Means to furnish and install, complete and ready for the intended use. I. Installer: Is the Contractor or another entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier, to perform a particular construction activity, including installation, erection, application, and similar operations. Installers are required to be experienced in the operations they are engaged to perform. 1. The term experienced, when used with the term Installer means having a minimum of five previous projects similar in size and scope to this Project, being familiar with the special requirements indicated, and having complied with requirements of the authority with jurisdiction

26 J. Project site: Is the space available for performing construction activities, either exclusively or in conjunction with others performing other work as part of the Project. The extent of the Project site is shown on the Drawings and may or may not be identical with the description of the land on which the Project is to be built. K. Testing Agencies: A testing agency is an independent entity engaged to perform specific inspections or tests, either at the Project site or elsewhere, and to report on and, if required, to interpret results of those inspections or tests. L. Specification Format: These Specifications are organized into Divisions and Sections based on the Construction Specifications Institute's 16-Division format and Construction Specifications Institute's numbering system. 1. Abbreviated Language: Language used in Specifications is abbreviated. Implied words and meanings shall be interpreted as appropriate. Singular words will be interpreted as plural and plural words interpreted as singular where applicable and the context so indicates. 2. Imperative language is used generally. Requirements expressed in the imperative mood are to be performed by the Contractor. At certain locations in the Text, subjective language is used for clarity to describe responsibilities that must be fulfilled indirectly by the Contractor, or by others when so noted. a. The words "shall be" are implied wherever a colon (:) is used within a sentence or phrase. M. Abbreviations and Names: Where acronyms or abbreviations are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-generating organization, authority with jurisdiction, or other entity applicable to the context of the Text provision. Refer to the "Encyclopedia of Associations," published by Gale Research Co., available in most libraries. N. Permits, Licenses, and Certificates: For the Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence, and records established in conjunction with compliance with standards and regulations bearing upon performance of the Work. END OF SECTION

27 SECTION PROJECT MEETINGS PART I GENERAL 1.1 GENERAL CONDITIONS A. This Section specifies administrative and procedural requirements for Project meetings including: 1. Pre-Construction Conference. 2. Pre-Installation Conferences. 3. Progress Meetings. 1.2 GENERAL REQUIREMENTS A. Pre-construction Conference: Conduct a pre-construction conference after execution of the Agreement and prior to commencement of construction activities. Review responsibilities and personnel assignments. 1. Attendees: The Owner, Architect and their consultants, the Contractor and its superintendent, subcontractors, suppliers, manufacturers, and other concerned parties shall be represented by persons authorized to conclude matters relating to the Work. 2. Agenda: Discuss significant items that could affect progress, including the tentative construction schedule, critical sequencing, use of the premises, procedures for processing Change Orders and equipment deliveries. B. Pre-installation Conference: Conduct a pre-installation conference before each activity that requires coordination with other construction. The Installer and representatives of manufacturers and fabricators involved in the installation, and coordination or integration with other materials and installations that have preceded or will follow, shall attend. Advise the Architect of scheduled meeting dates. 1. Review progress of other activities and preparations for the activity under consideration at each conference, including time schedules, manufacturer's recommendations, weather limitations, substrate acceptability, compatibility problems and inspection and testing requirements. 2. Record significant discussions, agreements and disagreements of each conference, along with the approved schedule. Distribute the meeting record to everyone concerned, promptly, including the Owner and Architect. 3. Do not proceed if the conference cannot be successfully concluded. Initiate necessary actions to resolve impediments and reconvene the conference at the earliest feasible date. C. Progress Meetings: Conduct progress meetings at regular intervals. Notify the Owner and Architect of scheduled dates. Coordinate meeting dates with preparation of the payment request. 1. Attendees: The Owner and Architect, each subcontractor, supplier or other entity concerned with progress or involved in planning, coordination or

28 performance of future activities shall be represented by persons familiar with the Project and authorized to conclude matters relating to progress. 2. Agenda: Review minutes of the previous progress meeting. Review significant items that could affect progress. Include topics appropriate to the current status of the Project. 3. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. 4. Review the present and future needs of each entity present, including such items as: a. Time. b. Sequences. c. Deliveries. d. Off-site fabrication problems. e. Site utilization. f. Temporary facilities and services. g. Hazards and risks. h. Quality and Work standards. i. Change Orders. j. Documentation of information for payment requests. k. Schedule of owner furnished items. D. Reporting: No later than three (3) days after each meeting, distribute copies of minutes of the meeting to each party present and to parties who should have been present. Include a summary, in narrative form, of progress since the previous meeting. END OF SECTION

29 SECTION SUBMITTALS PART I GENERAL 1.1 GENERAL CONDITIONS A. This Section specifies administrative and procedural requirements for handling submittals. B. ASPI requires that within seven (7) days of being awarded the contract, the Contractor is to submit the entire roofing system submittals. C. General Procedures: Coordinate submittal preparation with performance of construction activities, and with purchasing or fabrication, delivery, other submittals and related activities. Transmit in advance of performance of related activities to avoid delay. 1. Coordinate transmittal of different submittals for related elements so processing will not be delayed by the need to review concurrently for coordination. The Architect reserves the right to withhold action on a submittal requiring coordination until related submittals are received. 2. Processing: Allow two (2) weeks for initial review. Allow more time if processing must be delayed for coordination with other submittals. The Architect will advise the Contractor when a submittal must be delayed for coordination. Allow two weeks for reprocessing each submittal. a. No extension of time will be authorized because of failure to transmit submittals sufficiently in advance of the Work to permit processing. 1.2 GENERAL REQUIREMENTS A. Submittal Preparation: Place a label or title block on each submittal for identification. Provide a 4" x 5" space on the label or beside the title block on Shop Drawings to record Contractor's review and approval markings and action taken. Include the following information on the label for processing and recording action taken. 1. Project name. 2. Date. 3. Name and address of Architect. 4. Name and address of Contractor. 5. Name and address of subcontractor. 6. Name and address of supplier. 7. Name of manufacturer. B. Submittal Transmittal: Package submittals appropriately for transmittal and handling. Transmit with a transmittal form. Submittals received from other than the Contractor will be returned without action. 1. Transmittal Form: Use AIA Document G 810. On the form record requests for data, and deviations from Contract Documents. Include Contractor's certification that information complies with Contract Documents

30 C. Contractor's Construction Schedule: Submit a fully developed, bar-chart type construction schedule, within thirty (30) days of the date established for Commencement of the Work. Provide a separate bar for each construction activity and a vertical line to identify the first working day of each week. Use the breakdown of units of Work as indicated in the "Schedule of Values". 1. Within each time bar indicate estimated completion percentage in ten percent (10 %) increments. As Work progresses, place a contrasting mark in each bar to indicate Actual Completion. 2. Prepare the schedule on sheets of stable transparency, or other reproducible media, of sufficient width to show data for the entire construction period. 3. Secure commitments for performing critical construction operations from parties involved. Coordinate each activity with other activities and show in proper sequence; include minor elements involved in the construction sequence. Indicate sequences necessary for completion of related portions. 4. Coordinate the Construction Schedule with the Schedule of Values, list of subcontracts, Submittal Schedule, progress reports, payment requests and other schedules. 5. Indicate completion in advance of the date established for Substantial Completion. Indicate Substantial Completion on the Schedule to allow time for the Architect's procedures necessary for certification of Substantial Completion. 6. Area Separations: Provide a separate time bar to identify each construction area for each major part of the Work. Indicate where each element must be sequenced with other activities. D. Submittal Schedule: Submit the Submittal Schedule within ten (10) days of the Construction Schedule. Coordinate the Schedule with the list of subcontracts, Schedule of Values and list of products as well as the Construction Schedule. 1. Prepare the Schedule in chronological order; include submittals required during the first ninety (90) days of construction. Provide the following information: a. Submittal log number (in sequential order). b. Scheduled date for the first submittal. c. Related Section number. d. Name of subcontractor. e. Description of the construction element covered. f. Scheduled date the Architect's final release or approval. E. Distribution of Schedules: Distribute copies of the Construction and Submittal Schedules to the Architect, Owner, subcontractors, and other parties required to comply with scheduled dates. Post copies in the temporary field office. When revisions are made, distribute to the same parties and post in the same locations. 1. Updating: Revise each Schedule after each meeting or activity, where revisions have been made. Issue the updated Schedules concurrently with report of each meeting. F. Daily Construction Reports: Prepare a daily construction report, recording information concerning events at the site. Submit duplicate copies to the Architect at weekly intervals. Include the following information:

31 1. List of subcontractors at the site. 2. High and low temperatures, general weather conditions. 3. Accidents, stoppages, delays, shortages, losses. 4. Emergency procedures. 5. Change Orders received, implemented. 6. Partial Completions, occupancies. 7. Substantial Completions authorized. G. Shop Drawings: Submit new information, drawn to accurate scale. Indicate deviations from Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Include the following information: 1. Dimensions. 2. Identification of products and materials included. 3. Notation of coordination requirements. 4. Notation of dimensions established by field measurement. 5. Sheet Size: Except for templates, patterns and similar full- size Drawings, submit Shop Drawings on sheets at least 8-1/2" x 11" but no larger than 36" x 48". 6. Initial Submittal: Submit one correctable translucent print and one blue-line print for review; the reproducible print will be returned. 7. Final Submittal: Submit three (3) blue-line prints; if the Drawing is required for maintenance manuals, submit five (5) prints. Two (2) prints will be retained; the remainder will be returned. One of the prints returned shall be maintained as a "Record Document". 8. Do not use Shop Drawings without a final stamp indicating action taken in connection with construction. H. Product Data: Collect Product Data into a single submittal for each element or system. Mark each copy to show applicable choices and options. Where Product Data includes information on several products, some of which are not required, mark copies to indicate the applicable information. Include the following information: 1. Manufacturer's printed recommendations. 2. Compliance with recognized trade association standards. 3. Compliance with recognized testing agency standards. 4. Application of testing agency labels and seals. 5. Notation of dimensions verified by field measurement. 6. Notation of coordination requirements. 7. Preliminary Submittal: Submit a preliminary single-copy where selection of options is required. 8. Submittals: Submit two (2) copies of each required submittal; submit four (4) copies where required for maintenance manuals. The Architect will retain one and will return the other marked with action taken and corrections or modifications required. a. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal. 9. Distribution: Furnish copies of final submittal to installers, and others required for performance of construction activities. Show distribution on transmittal forms. Do not proceed with installation until an applicable copy of Product Data is in the installer's possession

32 a. Do not permit use of unmarked copies of Product Data in connection with construction. I. Samples: Submit full-size Samples cured and finished as specified and identical to the product proposed. Mount, display, or package Samples to facilitate review. Prepare Samples to match the Architect's Sample. Include the following: 1. Generic description. 2. Source. 3. Product name or name of manufacturer. 4. Compliance with recognized standards. 5. Availability and delivery time. 6. Submit Samples for review of kind, color, pattern, and texture, for a final check of these characteristics, and a comparison of these characteristics between the final submittal and the component as delivered and installed. Where variations are inherent in the product, submit multiple units that show limits of the variations. a. Refer to other Sections for Samples that illustrate details of assembly, fabrication techniques, workmanship, connections, operation and similar characteristics. b. Refer to other Sections for Samples to be returned for incorporation in the Work. Such Samples must be undamaged at time of use. On the transmittal, indicate special requests regarding disposition of Sample submittals. 7. Preliminary submittals: Where Samples are for selection of characteristics from a range of choices, submit a full set of choices for the product. Preliminary submittals will be reviewed and returned indicating selection and other action. 8. Submittals: Except for Samples illustrating assembly details, workmanship, fabrication techniques, connections, operation and similar characteristics, submit three (3) sets; one will be returned marked with the action taken. Maintain Sample sets at the Project site, for quality comparisons. a. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal. b. Sample sets may be used to obtain final acceptance of the construction associated with each set. J. Distribution: Prepare additional sets for subcontractors, manufacturers, fabricators, installers, and others as required for performance. Show distribution on transmittal forms. K. Architect's Action: Except for submittals for record, information or similar purposes, where action and return is required, the Architect will review each submittal, mark to indicate action taken, and return. Compliance with specified characteristics is the Contractor's responsibility. 1. Action Stamp: The Architect will stamp each submittal with a self-explanatory action stamp. The stamp will be appropriately marked to indicate action taken. L. Division 15 (Mechanical) & Division 16 (Electrical) Submittals: Submit directly to engineer with copies to Owner and Architect, unless specifically indicated otherwise. END OF SECTION

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set PROJECT MANUAL POINT BLANK RANGE & GUN SHOP 600 Corporate way Knoxville, TN Bid/Permit Set Division Section Title SPECIFICATIONS GROUP DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012600 CONTRACT

More information

TOWNES + architects, P.A.

TOWNES + architects, P.A. TOWNES + architects, P.A. 2421 North 12th Avenue, Pensacola, Florida 32503 Telephone: (850) 433-0203 Florida Registration AA-26001051 PROJECT MANUAL City of Pensacola Fleet Maintenace Garage Re ovation

More information

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

DeKalb County Library Dunwoody Library Staff Area Renovation

DeKalb County Library Dunwoody Library Staff Area Renovation PROJECT MANUAL DeKalb County Library Dunwoody Library Staff Area Renovation OWNER: DeKalb County Library Email: kimbroj@dekalblibrary.org Contact: Jackee Kimbro 404-508-719-, ext. 2236 ARCHITECT: MEP ENGINEER:

More information

INVITATION FOR BIDS FOR

INVITATION FOR BIDS FOR ********************************************************************************************** IFB NO. Y18-749-RM ISSUED: March 16, 2018 INVITATION FOR BIDS FOR EAST ORANGE HEAD START MODULAR RELOCATION

More information

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109 RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS

More information

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT PROJECT MANUAL RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT CITY OF RICHMOND Richmond, Virginia Architect s Project No. 563107 ARCHITECT/ENGINEER RICHMOND, VIRGINIA A/E s Project No. 563107 set

More information

PARKING LOTS 4 AND 5 (DEMOLITION)

PARKING LOTS 4 AND 5 (DEMOLITION) TECHNICAL SPECIFICATIONS PARKING LOTS 4 AND 5 (DEMOLITION) AT 9200 Valley View Street Cypress, CA 90630 1830 Romneya Drive Anaheim, CA 92801-1819 Tel. (714) 808-4747 WW Project No. 17030.00 October 25,

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL PERMIT SET FEBRUARY 27, 2017 Commonwealth Architects 101 Shockoe Slip Richmond, VA 23219 CITY

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018 CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL BID SET April 4, 2018 Commonwealth Architects 101 Shockoe Slip, Fl 3 Richmond, VA 23219 CITY

More information

New Mexico State University Herritage Farm Interpretive Trail

New Mexico State University Herritage Farm Interpretive Trail PROJECT MANUAL PROJECT MANAGER: SHELLEY ZIVKOVICH 575-646-1991 shelleyz@nmsu.edu New Mexico State University Herritage Farm Interpretive Trail APRIL 28, 2017 PROJECT #206-88 WDG ARCHITECTS 1014 South Main

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV.

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents VAE VIEW ELEMENTARY WINDOW REPLACEMENT 1750 West 1600 North Layton, UT 84041 Specifications 19 March 2018 TABLE OF CONTENTS DIVISION 00 PREREQUIREMENT AND CONTRACTING REQUIREMENTS A101 A201 A310 A312 G701

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 PROJECT MANUAL For UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 Prepared For: UNIVERSITY OF COLORADO AT COLORADO SPRINGS September 27, 2010 Prepared By: SCHENDT ENGINEERING CORP. 2912 Beacon Street

More information

ORANGE COUNTY UTILITIES RS&H OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS

ORANGE COUNTY UTILITIES RS&H OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS ORANGE COUNTY UTILITIES RS&H 107-0745-001 OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS 100% PERMIT SUBMITTAL March 15, 2013 PART DESCRIPTION SECTION H TECHNICAL PROVISIONS DIVISION 1 GENERAL REQUIREMENTS

More information

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States SPECIFICATIONS May 25, 2018 Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States Ellicott Station Development, LLC 500 Seneca Street Suite

More information

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION

More information

WOOD FLOORING WOOD FLOORING

WOOD FLOORING WOOD FLOORING 09550 - WOOD FLOORING 09550-1 PART ONE: GENERAL 1.1 Description WOOD FLOORING 1.1.1 Work in this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance

More information

OSNI PONCA OFFICE REMODEL

OSNI PONCA OFFICE REMODEL OSNI PONCA OFFICE REMODEL PROJECT MANUAL OCTOBER 2016 SCHEMMER PROJECT NO. 06571.002 OSNI PONCA OFFICE REMODEL TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000115 LIST OF DRAWING

More information

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION 1

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

SPECIFICATIONS. September 27, 2016 Bid Set

SPECIFICATIONS. September 27, 2016 Bid Set SPECIFICATIONS September 27, 2016 Bid Set CITY HALL SUITE 100 & 102 RENOVATIONS TABLE OF CONTENTS (Refer to Project Book under separate cover for additional requirements) SPECIFICATIONS DIVISION 1 - GENERAL

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION CITY OF PENSACOLA November 2018 SECTION 011000- SUMMARY OF WORK PART 1 - GENERAL 1.1 DOCUMENTS A. Drawings and general

More information

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools Division Section Title SPECIFICATIONS GROUP General Requirements Subgroup DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012600 CONTRACT MODIFICATION PROCEDURES 012900 PAYMENT

More information

University Apartments on Brooklyn PROJECT MANUAL

University Apartments on Brooklyn PROJECT MANUAL Section 011000 - Summary PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Phased construction. 4. Work under separate contracts. 5. Access

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

A. Remove Table of Contents and insert new attached Table of Contents.

A. Remove Table of Contents and insert new attached Table of Contents. ADDENDUM NO. 01 PROJECT Colby Glass E.S. Window Upgrades and ADA Work PROJECT NO. 16043 DATE February 07, 2018 TO: All Prime Contract Bidders and all others to whom Drawings and Specifications have been

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

BOWIE STATE UNIVERSITY CAR PARKING LOT

BOWIE STATE UNIVERSITY CAR PARKING LOT BOWIE STATE UNIVERSITY CAR PARKING LOT TECHNICAL SPECIFICATIONS 100% CD SUBMISSION NOVEMBER 2, 2018 Prepared by WHITNEY, BAILEY COX & MAGNANI, LLC 300 East Joppa Road, Suite 200 Baltimore, Maryland 21286

More information

Renovations for South Morrison Library 746 Adams Drive Newport News, Virginia

Renovations for South Morrison Library 746 Adams Drive Newport News, Virginia Specifications Prepared by 22 Enterprise Parkway, Suite 200, Hampton, Virginia 23666 Project #13069 November 8, 2013 SECTION 00002 - PROJECT DIRECTORY Owner: Contact: Electrical Engineer: City of Newport

More information

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION for Chubb Floor 4 34 Corporate Woods 10950 Grandview Drive Overland Park KS 66210 Issued for Bid & Permit July 18, 2016 SECTION 000110 TABLE OF CONTENTS

More information

DALLAS-FORT WORTH INTERNATIONAL AIRPORT

DALLAS-FORT WORTH INTERNATIONAL AIRPORT DALLAS-FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 2 TO THE REQUEST FOR BIDS Contract No. 9500445 Restroom Rehabilitation at Terminal B (Phase 3 & 4) December 20, 2010 THE REQUEST FOR BIDS (RFB) FOR

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS NEW MIDDLE SCHOOL CONSTRUCTION ON HULL STREET CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-108-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS

More information

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers DIVISION 01 GENERAL REQUIREMENTS 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013150 Requests for Information 013200 Construction Progress

More information

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No SPECIFICATIONS Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS ARCHITECT RICHMOND, VIRGINIA MECHANICAL, PLUMBING, FIRE PROTECTION, AND ELECTRICAL ENGINEERS GLEN ALLEN, VIRGINIA A/E s Project No. 563109

More information

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada 1 County of Elko, Nevada Requirements, Specifications and Contract Documents for Jackpot Recreation Center Mechanical System Upgrade 2016 Project in Jackpot, Elko County, Nevada Department of Community

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS E.S.H. GREENE ELEMENTARY SCHOOL CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-144-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS ARCHITECTURE

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS 23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters

More information

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012900 PAYMENT PROCEDURES 013100 PROJECT MANAGEMENT AND COORDINATION 013200 CONSTRUCTION PROGRESS DOCUMENTATION

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Willow Oak Veterinary Hospital

Willow Oak Veterinary Hospital Project Manual For Willow Oak Veterinary Hospital Durham, North Carolina Linton Architects Project #1219 September 11, 2013 Linton Architects 331 West Main Street, Suite 608 Durham, North Carolina 27701

More information

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n

More information

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey SPECIFICATIONS ARCHITECTURAL & M.E.P. DREW UNIVERSITY HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION 36 Madison Avenue Madison, New Jersey NK Project #2199.000 ISSUED FOR REVIEW March 09, 2018 95 Washington

More information

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

ADDENDUM NO. 2 Consisting of 3 pages and Attachments 10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 Project Manual for Alterations & Building Addition to: Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 SCHEMATIC DESIGN ISSUE NOT FOR CONSTRUCTION

More information

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC PROJECT MANUAL Phi Delta Theta Phase 2 120 NW 13 th Street Corvallis, OR 97330 Varitone Architecture LLC 231 SW 2nd Ave. PO Box 3420 Albany, Oregon 97321 Project Contacts Owner Phi Delta Theta Chapter

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

SANTA FE STATION KDOT Grant No. 23 TE

SANTA FE STATION KDOT Grant No. 23 TE SANTA FE STATION KDOT Grant No. 23 TE-0373-01 PRESERVATION PROJECT 413 E 7 TH Street - Lawrence, Kansas Project Manual Issue Date: July 15, 2015 KANSAS DEPT. OF TRANSPORTATION Dwight D. Eisenhower State

More information

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction

More information

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 07 4243 - PART 1 GENERAL 1.01 SECTION INCLUDES A. Composite wall panel system consisting of aluminum-faced composite panels in a rainscreen application as part of the assembly described below.

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16.

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16. SECTION 01 77 00 - PROJECT CLOSE-OUT PART 1 - GENERAL DESCRIPTION OF REQUIREMENTS: Definitions: Project close-out is the term used to describe certain collective project requirements, indicating completion

More information

Expansion Joint Covers

Expansion Joint Covers Expansion Joint Covers 07 95 00 (079513) PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions, Supplementary Conditions and Division-1

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

Corium Brick Rainscreen System Specifications

Corium Brick Rainscreen System Specifications CORIUM BRICK RAINSCREEN SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Work Included: The Work of this Section shall include but not be limited to the following: 1. Corium brick plates 2. Galvanized and coated

More information

EXECUTION REQUIREMENTS

EXECUTION REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: Execution requirements. B. Related Requirements: 1. Specification Sections 2 through 49. PART 2 - PRODUCTS (Not Used). PART 3 - EXECUTION 3.1 SAFETY 01

More information

DEAN + TYLER + BURNS ARCHITECTURE

DEAN + TYLER + BURNS ARCHITECTURE DEAN + TYLER + BURNS ARCHITECTURE May 17, 2017 Community Safe Room for the City Springville 580 Indian Crest Drive Indian Springs, AL 35124 tel.: 205.427.7890 email: m@rchitecture-e.com ADDENDUM NO. 3

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information

Chapter 6, Construction

Chapter 6, Construction Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference

More information

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual.

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no. 1801.01 07 12 2018 Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing

More information

IBMF STATE OF GOOD REPAIR UPGRADES

IBMF STATE OF GOOD REPAIR UPGRADES IBMF STATE OF GOOD REPAIR UPGRADES City of North Las Vegas, Nevada SPECIFICATIONS For 14-092 December 26, 2013 TABLE OF CONTENTS SECTION 01100 SECTION 01250 SECTION 01290 SECTION 01310 SECTION 01322 SECTION

More information

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents Architect s Project Number: 420.01.01 Issued: November 11, 2016 PEACOCK a r c h i t e c t s 5525

More information

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017 NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 Project Manual Technical Specifications Review

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

A. Project Identification: Wiggums Park Place Renovation. D. See Section Project Team List for additional information.

A. Project Identification: Wiggums Park Place Renovation. D. See Section Project Team List for additional information. SECTION 01 10 00 - SUMMARY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Specification and drawing conventions. 4. Miscellaneous provisions.

More information

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014 PROJECT SPECIFICATIONS for Grossmont Community College El Cajon, CA Bid Number B18.014 Grossmont College Specification TOC 07/11/2018 DIVISION 01 GENERAL REQUIREMENTS 01 10 00 ~ Summary 01 14 00 ~ Work

More information

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL PALMDALE AIRPORT TERMINAL REMODEL 21000 20 TH STREET EAST, PALMDALE, CA 93550 for ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT 3041 WEST AVENUE K LANCASTER, CALIFORNIA 93536-5436 PROJECT MANUAL AUGUST 15,

More information

Item # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities

Item # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities ADDENDUM NO. 1 Proposed Residence 422 Hickory Street Buffalo, New York 14204 February 15, 2019 Long Associates, Architects 189 Kenmore Avenue Buffalo, New York 14223 This addendum is issued to amend the

More information

Expansion Joint Covers (079513)

Expansion Joint Covers (079513) Expansion Joint Covers 07 95 00 (079513) PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions, Supplementary Conditions and Division-1

More information

WAYNE COMMUNITY COLLEGE SECTION

WAYNE COMMUNITY COLLEGE SECTION WAYNE COMMUNITY COLLEGE SECTION 00-01-15 LIST OF DRAWING SHEETS SECTION 00-01-15 LIST OF DRAWING SHEETS 1.1 LIST OF DRAWINGS A. Drawings: Drawings consist of the Contract Drawings and other drawings listed

More information

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure.

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure. Prospective bidders: The Board of Education, Unified School District No. 489, will receive bids for the fabrication and construction of two pre-manufactured metal building in the designated area at the

More information

PROJECT MANUAL & SPECIFICATIONS FOR GRACE LUTHERAN CURCH Newlin Gulch Boulevard Parker, Colorado, 80134

PROJECT MANUAL & SPECIFICATIONS FOR GRACE LUTHERAN CURCH Newlin Gulch Boulevard Parker, Colorado, 80134 PROJECT MANUAL & SPECIFICATIONS FOR GRACE LUTHERAN CURCH 11135 Newlin Gulch Boulevard Parker, Colorado, 80134 Date 12.10.13 BUILDING OWNER Name GRACE LUTHERAN CHURCH 11135 Newlin Gulch Boulevard Parker,

More information

ruby ridge terrace apartments

ruby ridge terrace apartments p r o j e c t m a n u a l for: ruby ridge terrace apartments 550 South, 12th Street 89801 Re-Bid Package 01 May 14, 2014 TABLE OF CONTENTS 1. Title page 2. Table of Contents 3. Invitation to Bid 4. Bid

More information

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate.

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate. SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Welded stainless steel railing systems. 1.2 RELATED SECTIONS A. Section 03300 - Cast-In-Place Concrete; coordination with substrate.

More information

Façade Access Upgrade Project

Façade Access Upgrade Project University of California Hastings College of Law Façade Access Upgrade Project 200 McAllister Street, San Francisco, CA 94102 Project Number 12042.04 ITB #56-0160 (Revised) August 20, 2015 PROJECT MANUAL

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Baseball Performance Development Center A Prevailing Wage Project

Baseball Performance Development Center A Prevailing Wage Project June 30, 2016 Baseball Performance Development Center A Prevailing Wage Project PROJECT MANUAL Owner CENTRAL MICHIGAN UNIVERISTY 206 Combined Services Building Mount Pleasant, Michigan PROJECT NUMBER 15-231

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

Northridge High School Remodel

Northridge High School Remodel CONSTRUCTION DOCUMENTS general construction volume divisions 0 thru 48 1 Northridge High School Remodel 2 4 3 0 N H I L L F I E L D R O A D I L A Y T O N, U T A H OWNER D a v i s S c h o o l D i s t r

More information

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE PROJECT MANUAL / TECHNICAL SPECIFICATIONS WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS - FENCING PACKAGE 3201 E. HOUSTON STREET SAN ANTONIO, TEXAS 78219 OCTOBER 6, 2017 HUMBERTO SALDANA & ASSOCIATES, INC.

More information

Northern Lights Park and Ride Lot

Northern Lights Park and Ride Lot PROJECT MANUAL For the Northern Lights Park and Ride Lot Central Ohio Transit Authority (COTA) Cleveland Avenue Columbus, Ohio BID SET June 5, 2017 Page 1 of 2 06/05/17 DESIGN TEAM Owner/Project Manager:

More information

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) 1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) The use of an existing elevator during construction shall be strictly prohibited. Any deviation

More information

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Issue Date: 18 March 2013 Project Number 13-201.1 9400 Gateway Drive, Suite B Reno, NV 89521 775.852.3977 (p) 775.852.6543

More information

CONTRACTOR S PROPOSAL

CONTRACTOR S PROPOSAL WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER PREQUALIFICATION

More information

SECTION GENERAL REQUIREMENTS

SECTION GENERAL REQUIREMENTS SECTION 01005 GENERAL REQUIREMENTS PART 1 GENERAL 1.01 WORK COVERED BY CONTRACT DOCUMENTS A. Work of this Contract comprises the chiller and cooling tower replacement at Five Oaks Middle School which includes

More information

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

A. This Section includes administrative and procedural requirements for quality assurance and quality control. SECTION 01400 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

UMC El Paso Far East Clinic and Neighborhood Healthcare Center West Issue for Construction Page Project No and April 13, 2015

UMC El Paso Far East Clinic and Neighborhood Healthcare Center West Issue for Construction Page Project No and April 13, 2015 Page Project No. 414018 and 414019 April 13, 2015 Table of Contents Division Section Title Pages PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 003100

More information

ENTRY SECURITY MODIFICATIONS

ENTRY SECURITY MODIFICATIONS Rio Rancho Public Schools ENTRY SECURITY MODIFICATIONS Volume 2 of 2 Divisions 01 through 28 Mountain View Middle School Project Number 083105-16-002 Rio Rancho Cyber Academy Project Number 083018-16-001

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01600 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information