Easthampton High School Building Project. Public Information Forum #3
|
|
- June Jackson
- 6 years ago
- Views:
Transcription
1 Building Project Public Information Forum #3 May 4, 2010 CAOLO & BIENIEK ASSOCIATES, INC. Architecture Planning Interior Design
2 Presentation Agenda Introduction - Michael Buehrle, Chair EHS Building Committee Project Overview & Needs - Superintendent Carter Project Solution - Ken Jodrie, CBA Project Architect - Dr. Vito Perrone, EHS Principal Next Steps - Mel Overmoyer, SBS Owner s Project Manager Questions & Answers
3 Why the Project? After more than 10 years of planning, the needs of the school facilities are significant In 2005 voters approved $1.2 million to study Elementary & s EHS has been identified by MSBA as one of the top 50 schools in Massachusetts in need of funding project satisfies more eligibility criteria for State funding EHS Accreditation status in jeopardy EHS was chosen by Building Committee because only one building project could receive funding Does not require acquisition of additional land
4 Most Pressing Academic Needs Currently on Warning status with NEASC accreditation Overcrowded program spaces Undersized classrooms per State standards Inadequate facilities for modern special programs
5 Most Pressing Academic Needs Lacks infrastructure for current technology No auditorium for active music & drama programs Importance of perception of quality of schools
6 Pressing Building Deficiencies 1961 building does not meet modern building codes Does not comply with ADA requirements for handicap accessibility Building lacks fire suppression ( sprinkler ) system Building does not meet current structural & seismic codes
7 Pressing Building Deficiencies Poorly organized, inflexible building and space configurations Insufficient storage Structural cracking Worn finishes
8 Pressing Building Deficiencies Antiquated building operating systems Inefficient and poorly controlled heating and ventilation systems Outdated & inefficient windows / poor ventilation Inadequate electrical and data infrastructure
9 Building on the Current Site Avoids issues of non-reimbursable acquisition costs, and lack of suitable land available for new site Existing site preserves open space in the community, and provides efficiency & cost savings through use of adjacent athletic fields and central location Project proposed fully complies with all Zoning regulations. No special permits or variances required
10 EHS Site - Central location & proximity to playing fields Downtown EHS Nonotuck Park
11 Site Circulation - Existing Facility student parking student parking student parking parking parking trash receiving staff & student parking
12 Existing Building & Site (8.258 Acres) Williston Ave. Geryk Court Daley Field Taft Ave NORTH Bryan Ave.
13 Existing Building Typical Classroom Main Entrance Library Bus Entrance Accessible Entrance Music / Theatre
14 Renovations & Additions vs. New EHS Facility Total Project Costs of renovation/addition solutions are significantly higher than a new building Renovations require high costs for temporary facilities which are not reimbursed by MSBA New building reduces time of construction inconvenience, and eliminates disruption of phased renovation New building results in a better facility than renovated
15 Feasibility Study Concept Options Concept A Full Relocation - No Construction Phasing Concept B Phased Relocation & Construction Concept C New Facility - No Relocation or Phasing Project Cost $50,200,000 Project Cost $52,700,000 Project Cost $48,000,000 PROS CONS PROS CONS PROS CONS Reuse 87.5% Good contractor staging area Entire facility available for construction Less efficient MSBA guidelines (new only) Portables + temp facilities Seismic retrofit Reuse 76.8% Good contractor staging area Construction in Occupied facility Phased construction Longest duration MSBA guidelines (new only) Portables + temp facilities 100% Design Flexibility 100% MSBA guidelines No Portables Improved site & building circulation Least Costly Limited on site staging area APPROVED by MSBA 11/18/09 Seismic retrofit Temporary parking
16 MSBA Press Release November 18, 2009 BOSTON, MA The Massachusetts School Building Authority ( MSBA ) announced today that the MSBA Board voted to move the High School into the next phase in the process for potential funding. The project will move into the Schematic Design phase where the Town of will work in collaboration with the MSBA to produce the most fiscally responsible and educationally appropriate solution to the facility problems. Springfield Republican November 19, 2009 Katherine P. Craven, Massachusetts School Building Authority Executive Director, said that High School posed the clearest need for construction of an entirely new facility. She called the potential for renovation very limited.
17 Site Plan - New Facility Bryan Ave. fence / buffer fence / buffer fence / buffer Emergency Access Drive fence / buffer Receiving & Service fence / buffer Parent Drop Off Staff & Student Parking Williston Ave. GerykCourt Zoning District: R-10 Min. Lot Area Min. Frontage Min. Front Yard Setback Min. Side Yard Setback Min. Rear Yard Setback Max. Building Height Max. Height, Stories Max. Bldg. Coverage Req d/allowed 10,000 sq. ft. 120 ft. 20 ft. 10 ft. 30 ft. 40 ft. 3 25% Proposed 357,192 sq. ft. 80 ft. 87 ft. 51 ft. 63 ft. 40 ft % Existing 357,192 sq. ft. 80 ft. 72 ft. 232 ft. 65 ft ft %
18 Aerial View from South-East Bryan Ave. Taft Ave. Garfield Ave. Daley Field E x i s t i n g B u i l d i n g Existing Driveway Existing Parking Geryk Court Williston Ave.
19 Building Massing
20 Main Entrance
21 Ground Floor
22 Main Office & Support Areas Health Guidance
23 Gymnasium & Support Areas
24 Athletic Facilities Cafe - Commons Team Team Main Entrance Fitness Room Gymnasium
25 Auditorium & Support Areas (Band / Chorus & Drama Classrooms)
26 Auditorium
27 Community Use
28 Main Entrance viewed from Cafe - Commons Area Library Gym Main Entrance Office Auditorium Cafeteria - Commons
29 Academic Wing
30 Second Floor
31 2 nd Floor Community Use
32 Library / Media Center
33 Third Floor
34 Collaborative Learning Environments natural lighting & ventilation (typical) natural lighting & ventilation Flexible Group Breakout Spaces Learning Labs Moveable Wall Integrated Technology Transparency natural lighting & ventilation
35 Project Budget approved by MSBA Total Project Budget $43,691,108 Ineligible Costs ($3,042,063) (administrative costs; temporary conditions; infrastructure & off-site improvements; Sustainable Design features; haz-mat abatement) Subtotal (Basis of Grant) $40,649,045 Reimbursement Rate 62.84% (Base Rate +2 incentive points for Sustainable Design +1 incentive point for maintenance practices) State Grant $25,543,860 s $18,147,248 Maximum Cost
36 Debt Exclusion s Impact to Taxes s cost will be funded by a 20 year conventional bond Repayment of bond will begin in 2013 Impact to quarterly taxes will decrease every year that follows, as shown in the chart below FY 2013 Quarterly Impact to Average Single Family Home $69.32 Grant from MSBA $25,543,860 (at 62.84% reimbursement rate) s Maximum Cost $18,147,248 Total Project Budget $43,691,108 *Actual tax impact will be less than the numbers stated above due to other debt coming off the tax rolls
37 Project Schedule MSBA Board vote March 2010
38 Next Steps March 10 April - May 10 May 18, 2010 June 10 thru January 11 Spring 11 Spring 13 Summer 13 Fall 13 MSBA Board approves EHS Project Funding Agreement Community Information Forums Debt Exclusion VOTE Complete final design & bid documents Begin Construction of new facility Complete Construction Demolish existing EHS building School opens in new facility
39 The Future of our Schools has serious school facility issues which need to be systematically addressed Construction & Borrowing costs are both currently at historical lows Earliest impact to taxes beginning January 2013 It is clear from MSBA, if does not move forward with the project, it will be many years before the city will be considered for any further funding assistance toward their school facilities.
40 The Future of our Community State Treasurer Tim Cahill, who oversees the School Building Authority, said projects being built now are enjoying a savings in building costs thanks to the slow construction market. "This is the time to build. Even though it is a tough time to be asking people for money, everyone seems to see the value of building now."
41 The Future of "This is the time to build. Even though it is a tough time to be asking people for money, everyone seems to see the value of building now. State Treasurer Tim Cahill, MSBA Chairman May 18, 2010 Debt Exclusion VOTE for additional information go to
Longmeadow High School Project. Public Forum April 08, 2010 LHS Cafeteria
1 Longmeadow High School Project Public Forum April 08, 2010 LHS Cafeteria 2 Your School Building Committee* Bobby Barkett, Co-Chair - Select Board Christine Swanson, Co-Chair - School Committee Gwen Bruns
More informationIssue Paper # 7: Modernization Replacement Projects
Issue Paper # 7: Modernization Replacement Projects 1. Background BSD s student population has grown since the last capital bond in 2006 and facilities have experienced normal wear and aging leading to
More informationMADISON HIGH SCHOOL // Executive Summary
MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*
More informationArchitect and Engineer: Friar Associates inc.
Architect and Engineer: Friar Associates inc. BACKGROUND In June, after soliciting and interviewing several professional firms, Friar Associates was hired to perform an Existing Conditions Survey and Facilities
More informationPeter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report
Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Kirk Elementary
More informationNEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING. Neidig Community Meeting July 2018
NEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING Neidig Community Meeting July 2018 PROPOSED NEIDIG ELEMENTARY SCHOOL Expanded parking Separate bus loop Gymnasium Addition 2 story classroom wing
More informationUpper Adams School District Facility Study Presentation Part 2 November 17, 2016
Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current
More informationDarien Public Schools. Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018
Darien Public Schools Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018 BACKGROUND MASTER PLAN REPORT SUBMITTED DECEMBER 2016 DOCUMENTED DISTRICT-WIDE INFRASTRUCTURE
More informationBLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS
BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020
More informationBond Referendum: Proposed Capital Project
BRONXVILLE UNION FREE SCHOOL DISTRICT Building for the next 100 years Bond Referendum: Proposed Capital Project Overview Process started several years ago Review of 100 year old building needs: Five Year
More informationManchester Memorial Elementary School Community Meeting #2
Manchester Memorial Elementary School Community Meeting #2 November 1, 2017 TODAY S AGENDA Welcome Organization/ Project Team Process & Schedule Sites Considered Options to be Explored Discussion Next
More informationLisbon School Department. 5 Year Plan-Buildings, Grounds, Equipment, & Technology. April 2016
April 2016 Following is a list of items that the Lisbon School Department deems necessary for Capital Improvements for the next 5 years. Capital Improvements shall mean any construction project exceeding
More informationBRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW
HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included
More informationAndover Schools Facilities Update
Town Facilitlies Garage Andover Schools Facilities Update Andover High School Finance Committee May 9, 2018 West Middle School Collins Center Andover High School Facility Study Committee and Andover School
More informationINTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1
Best2 - Daylighting a New England Elementary School - Session EE 7-3 INTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1 ABSTRACT The Town of Concord,
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More informationBecker Morgan Group, Inc. (architectural and site systems) Gipe Associates, Inc. (mech./elec./plumbing systems) Morabito Associates, Inc.
AGENDA REVIEW PROJECT BACKGROUND & PURPOSE REVIEW PROJECT FINDINGS REVIEW THE 4 OPTIONS DEVELOPED OPTION COMPARISONS REVIEW PROJECT SCHEDULE COMMUNITY COMMENTS / QUESTIONS TEAM Becker Morgan Group, Inc.
More informationPROJECT UPDATE SEPTEMBER 11, 2014
PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT
More informationMIDDLEBOROUGH HIGH SCHOOL. Middleborough, Massachusetts
Middleborough, Massachusetts PROCESS OVERVIEW Project Schedule Process-Driven Decision Making WELCOME Addition/Renovation Options A & A1 A A1 A New Construction Options A & B A B Addition/Renovation Option
More informationExhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number
Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary
More informationJuanita High School Modernization vs. New-in-lieu of Modernization Report
Juanita High School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Juanita High School
More informationFacilities Feasibility Study Frederick Douglass HS Condition Assessment
Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies
More informationSpringfield High School Master Plan Presentation Town Hal Meeting 3 Phasing / Traffic and Parking
1 3.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 3 Phasing / Traffic and Parking December 11th, 2014 2 3.2 Town Hall Meetings
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationRevised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi
Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts
More informationDEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION
DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,
More informationOur Students. Our Schools. Our Future.
HARRISON CENTRAL SCHOOL DISTRICT PROPOSED CAPITAL IMPROVEMENTS Our Students. Our Schools. Our Future. VOTE OCTOBER 18, 2016 At your local elementary school WHAT IS THE NEED FOR A BOND REFERENDUM? Bonding
More informationPROJECT UPDATE August 28, 2014
PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT
More informationWARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic
More informationSTILLWATER COUNTY COURTHOUSE ALTERNATE 1
STILLWATER COUNTY COURTHOUSE ALTERNATE 1 ALTERNATE 1: The current plan developed for the Old Hospital will bring all County services into this facility except for the following: 1. Sheriff, 2. County Attorney,
More informationGibbons Middle School Repair Project
Gibbons Middle School Repair Project Sarah Gibbons Repair Project In the spring of 2012 Town Meeting approved a Feasibility Study for repairing Gibbons Middle School. A Building Committee was formed and
More informationEASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923
INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting
CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening
More informationSouthampton Public Schools District Office WHAT YOU SHOULD KNOW
Southampton Public Schools District Office WHAT YOU SHOULD KNOW CURRENT DISTRICT OFFICE BUILDING WHO WORKS IN THE DISTRICT OFFICE? Currently we have 22 full time employees with 2-4 part time state-mandated
More information(Continued on next page)
FULL TEXT OF BALLOT MEASURE E LONG BEACH UNIFIED SCHOOL DISTRICT REPAIR AND SAFETY MEASURE. To improve outdated classrooms/neighborhood schools by: improving technology/labs/career education classrooms/electrical
More informationBUILDING FOR OUR FUTURE
MIDDLE TOWNSHIP PUBLIC SCHOOLS BOND REFERENDUM March 8, 2016 Bond Referendum BUILDING FOR OUR FUTURE ADDRESSING THE DISTRICT S CRITICAL FACILITY AND SITE NEEDS CURRENTLY THE BAND-AID APPROACH COSTS MONEY
More informationEdmonton Public School District No. 7
EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive
More informationCollins Middle School
Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0
More informationW. EDWARD BALMER SCHOOL
W. EDWARD BALMER SCHOOL NORTHBRIDGE, MA SCHEMATIC DESIGN SCHOOL BUILDING COMMITTEE MEETING FEBRUARY 28, 2018 N O R T H B R I D G E PUBLIC SCHOOLS 1. SITE PLANNING UPDATE 2. BUILDING DESIGN UPDATE 3. MECHANICAL
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More informationFrost Technical Center
Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationIntroduction & Project Background
Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing
More information2016 BOND INFORMATION
2016 BOND INFORMATION This publication is provided as a public service by the offices of Operations and Maintenance, Communications and Financial Services. www.svvsd.org @svvsd 395 South Pratt Parkway,
More informationHIDDEN VALLEY ELEMENTARY SCHOOL
SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802
More informationSITE ASSESSMENT REPORT Addendum #2
SITE ASSESSMENT REPORT Addendum #2 Board of Education Fall Retreat September 28, 2013 Executive Summary In September 2012, Operations Staff presented Phase 1 of the 10 Year Facilities Master Plan, which
More informationMeasure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014
Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T DEFINED: Measure T is a local ballot measure on the November 2014 ballot seeking voter authorization
More informationSec Development Standards in P-N-T Districts.
Sec. 4-9. Development Standards in P-N-T Districts. a. Intent: The purpose of this district is to recognize predominately residential areas which: (1) Front along major or secondary arterial streets, (2)
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationWhy a Feasibility Study is Your First Step Towards a Successful Building Project By Amy Green, AIA, Owner, Architect, Interior Designer & LEED AP of
Why a Feasibility Study is Your First Step Towards a Successful Building Project By Amy Green, AIA, Owner, Architect, Interior Designer & LEED AP of amy green design 579 W 177th St. #51, NYC, NY 10033
More informationMontague DPW Facility Planning Committee Public Works Facility Public Information Session. April 4, Photo Credit: Recorder
Montague DPW Facility Planning Committee Public Works Facility Public Information Session April 4, 2017 Photo Credit: Recorder 500 Avenue A Tour Agenda Meet the Committee and Engineer Presentation of Project
More informationWilliam Paca / Old Post Road Elementary School
William Paca / Old Post Road Elementary School Scope Study Presentation Submitted to: Harford County Public Schools 102 South Hickory Avenue Bel Air, Maryland 21014 Prepared by: 11415 Isaac Newton Square
More informationThrough. June Current Strong Schools Bond Capital Improvement Projects. Prepared by
MONTHLY PROGRESS REPORT Through June 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab
More informationAl Behrman Elementary School
Mulberry Street Al Behrman Elementary School Relocate reception and principal s office to be adjacent to main entrance doors; provide secure entrance sequence and increase transparency to the exterior
More informationWaverley Elementary School Feasibility Study
Waverley Elementary School Feasibility Study FREDERICK COUTY PUBLIC SCHOOLS Feasibility Study Meeting #7 February 1, 2018 1 AGEDA 1. PROJECT OVERVIEW schedule 2. SITE ISSUES ALTA survey, site constraints
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationDRAFT September 26th, 2003
Harrelson Hall Renovation and Replacement Study DRAFT September 26th, 2003 Summary of Renovation Issues As part of the 2000 Capital Bond Program, funds were allocated for the renovation of Harrelson Hall
More informationCENTENNIAL SCHOOL DISTRICT
CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites
More informationEdmonton Public School District No. 7
EXECUTIVE SUMMARY 1. Overall Impressions Sherwood Elementary School resides in a quiet residential neighborhood with a shared parking area adjacent to the community league on the north and a generous play
More informationMadison School District. Strategic Five-Year Facility Maintenance Plan
Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since
More informationHampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects
2018 High School Feasibility Study Final Feasibility Study Presentation January 28, 2019 1 Study Updates I. Latest HS Concepts for Academic / Wellness Redesign II. Associated Conceptual Construction Costs
More informationLANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent
RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural
More informationBond Referendum Information. Sebeka School District #820 Vote on August 8, 2017
Bond Referendum Information Sebeka School District #820 Vote on August 8, 2017 Sebeka Student Enrollment Projection to 2024/25 Factors Considered in Projection Pattern of student enrollment change within
More informationEast Los Angeles College Project Priority List Occupancy Date
East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationLa Conner School District
hoarch.com La Conner School District Capital Bond Planning Meeting 4 - Master Plan Options / Budget Estimates July 18th, 2012 4010 Lake Washington Blvd, NE, Suite 320 Kirkland, Wa 425 828 8948 Agenda Meeting
More informationTimeline of Events with Meyers High School & Memorial Stadium
Timeline of Events with Meyers High School & Memorial Stadium During the 2016-2017 school year, the district has been monitoring several areas of concern at Meyers High School and Memorial Stadium. These
More informationSouth Windsor Public Schools. Elementary School Facilities Existing Condition Survey & Master Plan. Executive Summary 10/22/13
South Windsor Public Schools Elementary School Facilities Executive Summary 10/22/13 SOUTH WINDSOR PUBLIC SCHOOLS ELEMENTARY SCHOOL FACILITIES EXISTING CONDITION SURVEY & MASTER PLAN EXECUTIVE SUMMARY
More informationDesign Advisory Committee Meeting #5. December 19, 2017
Design Advisory Committee Meeting #5 December 19, 2017 1 Meeting Agenda 1. Agenda / Attendance Sheet 5 minutes 2. BEST Grant Recap 3. Review Funding Options additional information 4. Master Plan Summary
More informationROD Grant Round 4 Presentation June 9, 2014
ROD rant Round 4 Presentation June 9, 2014 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 2 Agenda NJDOE Application
More information2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:
MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.
More informationSOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED
SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for
More informationCazenovia Central Schools Proposed Building Project Information Session December 17, 2013
Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Information Session Agenda Background. Scope of work and why these renovations are important. Project cost. How
More informationCorsicana High School
Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0
More informationBoard Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016
Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation June 13, 2016 Schedule/Major Milestones 2015 November December Data Collection Board Meeting- Update 2016 January
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationDENNIS TOWNSHIP FEASIBILITY STUDY
DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT
More informationFRIDLEY SCHOOL DISTRICT West Moore Lake Drive Fridley, MN REVIEW AND COMMENT DOCUMENT
FRIDLEY SCHOOL DISTRICT 14 6000 West Moore Lake Drive Fridley, MN 55432 REVIEW AND COMMENT DOCUMENT For submission to Minnesota Department of Education June 20, 2012 SUMMARY The Fridley Public Schools
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More informationHodgson Road. Randolph Road Variable Public Right of Way VICINITY MAP NOT TO SCALE. 50' Public Right of Way
Site Development Data: MPV Properties Development Standards 07/18/18 Rezoning Petition No. 2018-061 --Acreage: ± 2.192 acres --Tax Parcel #: portion of 185-033-01 --Existing Zoning: R-3 --Proposed Zoning:
More informationMassachusetts School Building Authority
Massachusetts School Building Authority School District Bellingham District Contact Edward Fleury TEL: (508) 883-1706 Submission Date 11/29/2011 *** Note: This is a recertified Statement of Interest ***
More informationReferendum Implementation
SPACE Net Gain (new) Classrooms Claremont = +47 Hillcrest & Elizabeth = +20 Utilization Gain SGS = +25 at 6-8 MS level SAFETY Annex Connection To Franklin Park Repair Parking Lots, Sidewalks & Outdoor
More informationLongmeadow High School Section 12.1
Longmeadow High School Section 12.1 Schematic Design 12 Total Project Budget and MSBA Form 3011 The attached Total Project Budget and Form 3011 includes all costs associated with Administrative, Architecture
More informationPottsgrove School District
Pottsgrove School District Pottsgrove High School Additions/Renovations Project Summary February 7, 2014 Eight East Broad Street Hatfield, PA 19440-2401 215.368.5806 Executive Summary In the summer of
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationTown of Ellington Board of Education
Crystal Lake Elementary School Presentation to Town of Ellington Board of Education SCHOOLS STUDY TASK B November 10, 2011 Windermere Intermediate / Elementary School MOSER PILON NELSON A R C H I T E C
More informationThrough. February Current Strong Schools Bond Capital Improvement Projects. Prepared by
MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive
More informationPaulsboro Public Schools
BOND REFERENDUM PRESENTATION January 27, 2015 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 1 05-12-14 AGENDA NJDOE
More informationSTRUCTURAL/SEISMIC REPORT Roosevelt Elementary School. Report prepared by DCI Engineers. For. Medford School District. Completed By: DCI Engineers
J. Mark D Amato Guy A. Conversano Elizabeth A. Jensen Roger L. Heeringa Mark D. Aden Harry Jones II Troy E. Bean Tom C. Xia, Ph.D. Richard L. Hemmen Grant C. Buckingham Wade W. Younie STRUCTURAL/SEISMIC
More informationM E M O R A N D U M O F C O N F E R E N C E
January 26, 2017 M E M O R A N D U M O F C O N F E R E N C E PROJECT Potomac Elementary School Revitalization and Expansion Montgomery County Public Schools ARCHITECT S PROJECT NO. 522031 DATE AND LOCATION
More informationBLIND BROOK-RYE PUBLIC SCHOOLS
BLIND BROOK-RYE PUBLIC SCHOOLS PROPOSED FACILITIES IMPROVEMENT PLAN Frequently Asked Questions with Answers 1. Why are we proposing a renovation of this scope in the District? The District s five-year
More informationNorth Middlesex Regional High School
North Middlesex Regional High School Ashby, Pepperell, Townsend Schematic Design Kick-Off BUILDING COMMITTEE MISSION STATEMENT We will proactively work with the OPM, design team and the community, to develop
More informationPlanning Commission Agenda Item
Planning Commission Agenda Item TO: THRU: FROM: Chair Gladson and Members of the Planning Commission Anna Pehoushek Assistant Community Development Director Monique Schwartz Assistant Planner SUBJECT PUBLIC
More informationPRESENTATION JANUARY 24, 2017
4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction
More informationPOTENTIAL NEW DECORAH ELEMENTARY SCHOOL. Information and Planning
POTENTIAL NEW DECORAH ELEMENTARY SCHOOL Information and Planning EXTENSIVE PROBLEMS WITH EXISTING ELEMENTARY FACILITIES There are not enough classrooms to accommodate six sections per grade. The classrooms
More informationA PPEARANCE REVIEW BOARD
ARB Staff Report A PPEARANCE REVIEW BOARD July 21, 2016 Case Number AGENDA ITEM 4 619, 621, 623 E. PINE ST. THE OLIVE TOWNHOMES ARB2016-00037 Applicant Michael Wenrich Michael Wenrich Architects Owner
More informationPATTERSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationProject Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope
Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope