Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by

Size: px
Start display at page:

Download "Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by"

Transcription

1 MONTHLY PROGRESS REPORT Through June 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company

2 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report Capital Projects Gunn High School New Classroom Buildings A & B page 7 Gunn High School Phase I Parking and Drop off Sitework Improvement page 8 Gunn High School New Gymnasium page 9 Palo Alto High School Athletic Stadium Improvements page 10 Palo Alto High School Project Classroom Building and Media Arts page 11 Palo Alto High School Performing Arts Center page 12 Jordan Middle School page 13 J.L. Stanford Middle School page 14 Terman Middle School page 15 Fairmeadow Elementary School page 16 Duveneck Elementary School page 17 Technology page 18 Completed Capital Projects Palo Alto High School Haymarket and Tower Building Boiler Replacement page 19 Ohlone Elementary School page 20 Property Acquisition 525 San Antonio Rd page 21 Jordan Middle School Interim Classrooms page 22 Gunn High School Air Conditioning of Existing Buildings page 23 J.L. Stanford Middle School Interim Classrooms page 24 Fairmeadow Elementary School Portable Relocation page 25 Elementary Classroom Improvements Interactive Whiteboard & Sound Assist System page 26 Palo Alto High School Multi use Field page 27 Gunn High School Industrial Arts Renovation page 28 Gunn High School Aquatic Center page 29 Middle School Pre Design page 30 Inactive Capital Projects Garland Elementary School page 31 Elementary School Teaching Walls Phase 1 Schools page 32 High School Master Plan page 33 Hoover Elementary School page 34 Elementary Classroom Improvements Phase 1 Schools Barron Park and El Carmelo page 35 Appendix Exhibit A Bond Project List Page 2

3 EXECUTIVE SUMMARY Gunn High School New Classroom Buildings A & B BRCO Constructors continued welding steel and metal decking at the Math and English building. Steel welding is anticipated to continue through July At the World Languages building, BRCO completed metal decking installation and started wall framing. Preparations occurred for a campus wide power shutdown to replace an electrical substation schedule in early July Gunn High School Phase I Parking and Drop off Sitework Improvement DLM submitted schemes for district review on June 19, The Board of Education (BOE) approved the project and for DLM to continue design efforts on the Phase I Parking and Drop off project off Miranda Ave. on June 26, Both schemes will be studied with the site s input to make a recommendation for schematic design to the BOE in fall Gunn High School New Gymnasium S.J. Amoroso began installation of the underground storm drain, sanitary sewer and fire water systems. Interior wall framing commenced and will continue through July Palo Alto High School Athletics Stadium Improvements Taisei (TCC) commenced installation of the clay tile roof and exterior plaster on the concessions building, which will continue through July The new bleachers and press box are in the final stages of DSA review, and are on schedule to be completed after the 2012 football season. Palo Alto High School Classroom Building and Media Arts Building TCC completed welding of structural steel and poured the second floor deck at the Math/Social Sciences building. Structural steel welding and installation of metal decking continued for the Media Arts building and will continue through July Also, storm drain work restarted in the parking lot, and should be complete before school begins in August Palo Alto High School Performing Arts Center (PAC) DLM submitted design development drawings to the district for review and estimating efforts at the end of June Estimates are anticipated to wrap up by the end of July 2012, with plan reviews to continue through August, when staff returns from summer break. Jordan Middle School S.J. Amoroso continued wall framing at the new classroom building and cafetorium expansion. Installation of underground utilities commenced with the demolition of the fire lane behind H wing. Modernization work commenced at the gymnasium with window demolition and abatement, and structural shear wall installation also commenced at classroom wings A and B. J.L. Stanford Middle School Sausal Corporation mobilized on site June 8, 2012 by installing temporary construction fencing around the new two story classroom building site. Demolition of the existing paving for the sport courts, rally court and new bike cage location commenced on June 11, Art and music classroom renovations have also begun. Terman Middle School Hagensen Pacific poured the slab on grade and completed structural steel installation at the library expansion. Mechanical, electrical and plumbing rough in will continue through July 2012 at the new drama classroom. Modernization work, including mechanical equipment installation and window shading installation, commenced in multiple classroom wings and the gymnasium. Page 3

4 Fairmeadow Elementary School New Classroom Building and Modernization Best Contracting Services (BCS) continued CMU wall installation and preparations to pour the second floor deck of the new 2 story classroom building. BCS completed the wall framing for the library expansion and commenced interior renovations of the existing library. Modernization work including new casework and flooring commenced in the Jackson building. Duveneck Elementary School New Classroom Buildings and Modernization Gelfand submitted construction documents to DSA on February 27, Bids for the relocation of seven portable classrooms re bid were opened on June 4, Coulter Construction was awarded the project at the June 12, 2012 Board of Education meeting. Construction commenced on June 15, 2012 and anticipated completion is August 1, Technology Implementation of the district wide Voice over IP (VoIP) telephone system will wrap up during summer break. Installation of access points to increase the broadband of wireless access will occur during summer break. Also, installation of wireless antennas at each school is planned to commence in August COMPLETED CAPITAL PROJECTS Palo Alto High School Haymarket and Tower Building Boiler Replacement Environmental Services Inc. (ESI) initiated project closeout. Staff continues to work on other improvements within the Tower building to improve the heating distribution and controls systems. 525 San Antonio Road Site Acquisition The advisory committee has recommended to the BOE on January 31, 2012 to lease the property on a short term basis to one or more tenants. Ohlone Elementary School New Classroom Building and Modernization Move in to the new building and other existing classrooms occurred in December Students occupied the new building on January 3, Jordan Middle School Interim Classrooms The portables were installed and moved into for fall All documents were submitted to DSA for closeout November 2, Gunn High School Air Conditioning of Existing Buildings Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating summer J.L. Stanford Middle School Interim Classrooms Coulter Construction completed the work on the relocated portables in August Fairmeadow Elementary School Portable Relocation Relocation of the portable was complete on August 8, All documents were submitted to DSA for closeout October 11, Elementary Classroom Improvements Installation of Interactive Whiteboards and Sound Assist Systems Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school classrooms and libraries in April Palo Alto High School Multi use Field The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9, Page 4

5 Gunn High School Industrial Arts Addition & Renovation This facility was available for instruction in January DSA closeout received on July 18, Gunn High School Aquatic Center This facility was available for use in July 2009, and has been closed out with DSA. Middle Schools Pre Design Jordan, J.L. Stanford and Terman AEDIS presented recommended concept plans for each campus to the Board of Education for approval on September 8, which became the program documents for the new projects at each campus. These projects for predesign work have been closed, and funds were transferred to the program contingency on June 14, INACTIVE CAPITAL PROJECTS Garland Elementary School Renovation The Board of Education has put new development for Garland on hold until a growth plan is established for the elementary schools. The board voted to terminate the lease with Stratford School in June Discussions with the Board on future plans for growth at the elementary schools are ongoing. Elementary School Teaching Walls Phase 1 Schools The district placed this project on hold after review of the implementation of other classroom improvements, as recommended by the elementary school principals. This project was renamed Elementary Classroom Improvements (see Capital Projects summary below). High School Master Plan The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed, with funds transferred to the respective campus reserve funds. Hoover Elementary School Pre Design This project has been put on hold until a growth plan is established for the elementary schools. Elementary Classroom Improvements Phase 1 Schools Barron Park and El Carmelo The project has been placed on hold pending further discussions with the BOE about elementary growth planning. Page 5

6 Board Actions in June June 12, 2012 Action 16 Authorization to Award Contract for Duveneck Elementary School Portable Building Relocation June 19, 2012 Consent 2 J.L. Stanford Middle School Design Update Consent 4 Authorization to Issue Addendum No. 7 to AEDIS Architecture and Planning for Additional Services at Jordan Middle School Consent 5 Reappointment of Four Members of the Citizens Oversight Committee for the Strong Schools Bond Consent 6 Authorization to Issue Addendum No. 15 to Gelfand Partners Architects for Additional Services at Fairmeadow Elementary School Consent 7 Authorization to Issue an Addendum for Commissioning Agent Services with Enovity and TestMarc June 26, 2012 Consent 12 Design Update on Duveneck Elementary School Project Consent 13 Approval of Project Scope and Addendum to DLM Architects for the Parking and Drop off Project Consent 18 Certificated Personnel Action: Approval of Bond Manager Contract Consent 21 Approval of Strong Schools Bond Change Orders Page 6

7 Palo Alto Unified School District Strong Schools Bond Preliminary 6/29/2012 School Name - Project Name A B C C / A B - C C / B A - B Percent of Contract Percent of Committed Expenditures Balance Expended Balance Expended Gunn High School - High School Master Plan 142, , , % 18, % 6,061 Gunn High School 1 - Aquatic Center 4,865,423 4,862,530 4,862, % % 2,893 Gunn High School 2 - I.A Building 5,082,403 5,049,527 5,049, % % 32,876 Gunn High School 3 - AD2- close out 5,777 5,777 5, % % 0 Gunn High School 4 - New classroom Buildings 25,035,200 23,902,618 8,773, % 15,129, % 1,132,582 Gunn High School 5 - Parking & Drop Off improvements 3,940, , , % 235, % 3,588,889 Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 11,067,449 5,345, % 5,721, % 1,847,351 Gunn High School 7- A/C 2,600,000 2,293,021 2,102, % 190, % 306,979 Gunn High School - Reserved 21,525, % % 21,525,081 Palo Alto High Schools - High School Master Plan 142, , , % 4, % 5,240 Palo Alto High School 1 - Stadium Field 5,090,000 4,594,792 2,122, % 2,471, % 495,208 Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609, % % 0 Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 33,711,854 13,711, % 20,000, % 3,428,146 Palo Alto High School 4 - New Theater 24,395,049 1,590, , % 1,229, % 22,805,029 Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,500, , , % 35, % 1,050,680 Palo Alto High School - Reserved 27,915, % % 27,915,818 Jordan Middle School -Program Management- MS Pre-Design 18,890 18,890 17, % 1, % 0 Jordan Middle Schools 1- Interim Classrooms 600, , , % 14, % 149,407 Jordan Middle School 2- Improvements 19,891,564 18,651,774 4,339, % 14,311, % 1,239,790 J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,799 18, % % 0 J.L.S Middle School 1 - Interim Classrooms 446, , , % 8% 7, % 60,475 J.L.S Middle School 2- Improvements 17,184,699 3,568,717 2,388, % 1,180, % 13,615,982 Terman Middle School - Program Management- MS Pre-Design 18,799 18,799 18, % % 0 Terman Middle School 1- Improvements 13,312,971 12,660,938 3,437, % 9,223, % 652,033 PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 86, % 11, % 46,520 Addison Elementary School 1-Phase I 21,267 21,267 21, % % 0 Duveneck Elementary School 1-Phase I 11,088,759 1,680, , % 994, % 9,408,426 Garland Elementary School 1- Phase I 22,178, , , % 1, % 21,897,265 Fairmeadow Elementary School 1- Phase I 9,543,750 8,961,918 2,231, % 6,730, % 581,832 Hoover Elementary School 1-Phase I 70,550 70,550 57, % 13, % 0 Ohlone Elementary School 1- Phase I 11,667,965 10,817,056 9,882, % 934, % 850,909 Elementary Schools 1 - Elementary Classroom Improvements * 2,004,889 1,914,741 1,863, % 50, % 90,148 Elementary Schools - Reserved 33,457, % % 33,457,555 PAUSD - Program Management 6,652,006 5,135,747 4,835, % 300, % 1,516,259 PAUSD - Technology 8,238,257 6,788,805 6,375, % 413, % 1,449,452 PAUSD - Technology -Reserved 5,669, % % 5,669,108 PAUSD - Reserved 5,759, % % 5,759, San Antonio -Property Acquisition 8,500,000 8,500,000 8,500, % % 0 Bond Issuance Cost 1,840,700 1,840,700 1,840, % % 0 Total 353,234, ,647,881 93,421,031 79,226, ,587,064 Prepared by: Business Services Department based on QSS accounting System

8 Gunn High School New Classroom Buildings A & B BRCO Constructors continued welding steel and metal decking at the Math and English building. Steel welding is anticipated to continue through July At the World Languages building, BRCO completed metal decking installation and started wall framing. Preparations occurred for a campus wide power shutdown to replace an electrical substation schedule in early July Strong Schools Bond Funds $25,035,200 Other $0 Total $25,035,200 Salaries and Benefits $13,253 Supplies $0 Contracts & Services $4,463,732 Construction & Equipment $20,482,302 Soft Costs Contingency $75,913 Total $25,035,200 Percent of Expended 35.0% Change Order Contingency Starting Contingency Balance $ 1,763,200 Remaining Contingency Balance $ 1,602,772 Percent of Changes 9.1% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA May 27, 2011 Bid Opening July 13, 2011 Award of Contract (1) July 22, 2011 Notice to Proceed August 24, 2011 Substantial Completion March 23, 2013* Planned Occupancy August 1, 2013* C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4 This project is proceeding on schedule and is within budget. Page 7

9 Gunn High School Phase I Parking and Drop off Sitework Improvement DLM submitted schemes for district review on June 19, The Board of Education (BOE) approved the project and for DLM to continue design efforts on the Phase I Parking and Drop off project off Miranda Ave. on June 26, Both schemes will be studied with the site s input to make a recommendation for schematic design to the BOE in fall Strong Schools Bond Funds $3,940,000 Other $0 Total $3,940,000 Salaries and Benefits $0 Supplies $0 Contracts & Services $898,978 Construction & Equipment $2,919,840 Soft Costs Contingency $121,182 Total $3,940,000 Percent of Expended 2.9% Current Phase: Conceptual Design Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) Schematic Design (2) September 4, 2012* September 18, 2012* Submit to DSA December 12, 2012* Approval by DSA April 2, 2013* Authorize to Bid (2) March 25, 2013* April 5, 2013* Bid Opening May 13, 2013* Award of Contract (1) May 28, 2013* Notice to Proceed June 5, 2013* Substantial Completion August 16, 2013* C. BOND PROJECT LIST REFERENCE: 5.5 BOE approved the Phase I, Miranda Ave. parking and drop off project to continue design on June 26, 2012 Page 8

10 Gunn High School New Gymnasium S.J. Amoroso began installation of the underground storm drain, sanitary sewer and fire water systems. Interior wall framing commenced and will continue through July Strong Schools Bond Funds $12,914,800 Other $0 Total $12,914,800 Salaries and Benefits $0 Supplies $1,001 Contracts & Services $2,677,293 Construction & Equipment $10,158,210 Soft Costs Contingency $78,296 Total $12,914,800 Percent of Expended 41.4% Change Order Contingency Starting Contingency Balance $834,700 Remaining Contingency Balance $740,926 Percent of Changes 8.7% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA May 27, 2011 Bid Opening July 13, 2011 Award of Contract (1) July 20, 2011 Notice to Proceed August 1, 2011 Substantial Completion November 25, 2012* Planned Occupancy January 1, 2013* C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13 This project is proceeding on schedule and is within budget. Page 9

11 Palo Alto High School Athletic Stadium Improvements Taisei (TCC) commenced installation of the clay tile roof and exterior plaster on the concessions building, which will continue through July The new bleachers and press box are in the final stages of DSA review, and are on schedule to be completed after the 2012 football season. Strong Schools Bond Funds $5,090,000 Other $0 Total $5,090,000 Salaries and Benefits $882 Supplies $0 Contracts & Services $842,156 Construction & Equipment $4,221,162 Soft Costs Contingency $25,800 Total $5,090,000 Percent of Expended 41.7% Change Order Contingency Starting Contingency Balance $310,200 Remaining Contingency Balance $269,816 Percent of Changes 4.3% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) January 26, 2010 February 9, 2010 Conceptual Design (2) June 1, 2010 June 22, 2010 Schematic Design (2) February 22, 2011 March 8, 2011 Submit to DSA April 4, 2011 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA July 26, 2011 Bid Opening December 1, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed January 4, 2012 Substantial Completion Concession August 31, 2012* Bleachers March 1, 2013* Planned Occupancy Concessions September 10, 2012* C. BOND PROJECT LIST REFERENCE: 4.13 The project is proceeding one month behind schedule occupancy for the concessions building, therefore occupancy of the concessions building is now anticipated in September There project remains within budget. Page 10

12 Palo Alto High School Classroom Building and Media Arts TCC completed welding of structural steel and poured the second floor deck at the Math/Social Sciences building. Structural steel welding and installation of metal decking continued for the Media Arts building and will continue through July Also, storm drain work restarted in the parking lot, and should be complete before school begins in August Strong Schools Bond Funds $37,140,000 Other $0 Total $37,140,000 Salaries and Benefits $14,721 Supplies $0 Contracts & Services $7,066,446 Construction & Equipment $29,740,000 Soft Costs Contingency $318,833 Total $37,140,000 Percent of Expended 36.9% Change Order Contingency Starting Contingency Balance $2,515,000 Remaining Contingency Balance $2,212,835 Percent of Changes 12.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA April 28, 2011 Bid Opening June 30, 2011 Award of Contract (1) July 12, 2011 Notice to Proceed August 4, 2011 Substantial Completion August 13, 2013* Planned Occupancy December, 2013* C. BOND PROJECT LIST REFERENCE: This project is proceeding two months behind scheduled occupancy therefore occupancy is now anticipated in December The project remains within budget. Page 11

13 Palo Alto High School Performing Arts Center (PAC) DLM submitted design development drawings to the district for review and estimating efforts at the end of June Estimates are anticipated to wrap up by the end of July 2012, with plan reviews to continue through August, when staff returns from summer break. Strong Schools Bond Funds $24,395,049 Other $0 Total $24,395,049 Salaries and Benefits $0 Supplies $0 Contracts & Services $4,481,640 Construction & Equipment $19,745,000 Soft Costs Contingency $168,409 Total $24,395,049 Percent of Expended 1.5% Current Phase: Design Development Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) June 1, 2010 June 22, 2010 Schematic Design (3) June 14, 2011 December 13, 2011 January 17, 2012 Submit to DSA January 3, 2013* Approval by DSA August 27, 2013* Authorize to Bid (2) August 20, 2013* September 9, 2013* Bid Opening October 22, 2013* Award of Contract (1) October 28, 2013* Notice to Proceed November 11, 2013* Substantial Completion May 13, 2015* Planned Occupancy August 17, 2015* C. BOND PROJECT LIST REFERENCE: 4.11 Project is proceeding on schedule and within budget. Page 12

14 Jordan Middle School S.J. Amoroso continued wall framing at the new classroom building and cafetorium expansion. Installation of underground utilities commenced with the demolition of the fire lane behind H wing. Modernization work commenced at the gymnasium with window demolition and abatement, and structural shear wall installation also commenced at classroom wings A and B. Strong Schools Bond Funds $19,891,546 Other $0 Total $19,891,546 Salaries and Benefits $0 Supplies $0 Contracts & Services $3,592,148 Construction & Equipment $16,007,031 Soft Costs Contingency $292,385 Total $19,891,564 Percent of Expended 21.8% Change Order Contingency Starting Contingency Balance $1,398,700 Remaining Contingency Balance $1,389,617 Percent of Changes 0.1% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) March 23, 2010 April 27, 2010 Submit to DSA December 21, 2010 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA October 5, 2011 Bid Opening December 8, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed December 27, 2011 Substantial Completion August 1, 2013* Planned Occupancy August 26, 2013* C. BOND PROJECT LIST REFERENCE: , , , The project is proceeding on schedule and within budget. Page 13

15 J.L. Stanford Middle School Sausal Corporation mobilized on site June 8, 2012 by installing temporary construction fencing around the new two story classroom building site. Demolition of the existing paving for the sport courts, rally court and new bike cage location commenced on June 11, Art and music classroom renovations have also begun. Strong Schools Bond Funds $17,184,699 Other $0 Total $17,184,699 Salaries and Benefits $0 Supplies $3,458 Contracts & Services $3,464,670 Construction & Equipment $13,421,500 Soft Costs Contingency $295,071 Total $17,184,699 Percent of Expended 13.9% Change Order Contingency Starting Contingency Balance $1,057,800 Remaining Contingency Balance $1,057,800 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (3) June 1, 2010 June 22, 2010 (Sitework) September 28, 2010 Submit to DSA May 6, 2011 Authorize to Bid (2) November 29, 2011 December 13, 2011 Approval by DSA January 24, 2012 Bid Opening May 3, 2012 Award of Contract (1) May 8, 2012 Notice to Proceed May 30, 2012 Substantial Completion August 24, 2013* Planned Occupancy January 1, 2014* C. BOND PROJECT LIST REFERENCE: , , , 6.4, 6.5 Sausal Corporation mobilized on site and commenced construction on June 8, Page 14

16 Terman Middle School Hagensen Pacific poured the slab on grade and completed structural steel installation at the library expansion. Mechanical, electrical and plumbing rough in will continue through July 2012 at the new drama classroom. Modernization work, including mechanical equipment installation and window shading installation, commenced in multiple classroom wings and the gymnasium. Strong Schools Bond Funds $13,312,971 Other $0 Total $13,312,971 Salaries and Benefits $0 Supplies $0 Contracts & Services $2,635,774 Construction & Equipment $10,517,515 Soft Costs Contingency $159,682 Total $13,312,971 Percent of Expended 25.8% Change Order Contingency Starting Contingency Balance $929,900 Remaining Contingency Balance $929,900 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) May 11, 2010 May 25, 2010 Submit to DSA December 21, 2010 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA September 1, 2011 Bid Opening December 6, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed December 27, 2011 Substantial Completion August 7, 2013* Planned Occupancy September 4, 2013* C. BOND PROJECT LIST REFERENCE: , The project proceeding on schedule and within budget. Page 15

17 Fairmeadow Elementary School New Classroom Building and Modernization Best Contracting Services (BCS) continued CMU wall installation and preparations to pour the second floor deck of the new 2 story classroom building. BCS completed the wall framing for the library expansion and commenced interior renovations of the existing library. Modernization work including new casework and flooring commenced in the Jackson building. Strong Schools Bond Funds $9,543,750 Other $0 Total $9,543,750 Salaries and Benefits $0 Supplies $3,132 Contracts & Services $1,938,402 Construction & Equipment $7,500,180 Soft Costs Contingency $102,036 Total $9,543,750 Percent of Expended 23.4% Change Order Contingency Starting Contingency Balance $642,300 Remaining Contingency Balance $642,300 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 13, 2009 October 27, 2009 Conceptual Design (2) March 23, 2010 April 6, 2010 Schematic Design (2) September 14, 2010 September 28, 2010 Submit to DSA April 18, 2011 Authorize to Bid (2) October 11, 2011 October 25, 2011 Approval by DSA November 14, 2011 Bid Opening December 5, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed January 3, 2012 Substantial Completion August 5, 2013* Planned Occupancy August 20, 2013* C. BOND PROJECT LIST REFERENCE: , The project is proceeding on schedule and within budget. Page 16

18 Duveneck Elementary School New Classroom Buildings and Modernization Gelfand submitted construction documents to DSA on February 27, Bids for the relocation of seven portable classrooms re bid were opened on June 4, Coulter Construction was awarded the project at the June 12, 2012 Board of Education meeting. Construction commenced on June 15, 2012 and anticipated completion is August 1, Strong Schools Bond Funds $11,088,759 Other $0 Total $11,088,759 Salaries and Benefits $0 Supplies $0 Contracts & Services $2,159,389 Construction & Equipment $8,803,087 Soft Costs Contingency $126,283 Total $11,088,759 Percent of Expended 6.2% Current Phase: DSA Review Architect Contract (2) April 27, 2010 May 11, 2010 Conceptual Design (2) December 14, 2010 January 11, 2011 Schematic Design (2) June 14, 2011 June 28, 2011 Submit to DSA February 27, 2012 Approval by DSA October 8, 2012* Authorize to Bid (2) October 28, 2012* November 9, 2012* Bid Opening December 22, 2012* Award of Contract (1) December 27, 2012* Notice to Proceed January 5, 2013* Substantial Completion May 16, 2014* Planned Occupancy August 1, 2014* C. BOND PROJECT LIST REFERENCE: , Project plans submitted to DSA on February 27, Project is on schedule and within budget. Page 17

19 Technology Improvements Implementation of the district wide Voice over IP (VoIP) telephone system will wrap up during summer break. Installation of access points to increase the broadband of wireless access will occur during summer break. Also, installation of wireless antennas at each school is planned to commence in August Strong Schools Bond Funds $8,238,257 Other $0 Total $8,238,257 Salaries and Benefits $0 Supplies & Computers $7,855,662 Contracts & Services $180,173 Construction & Equipment $202,422 Soft Costs Contingency $0 Total $8,238,257 Percent of Expended 77.4% Current Phase: Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: VOIP implementation on going. Bids for network upgrade will be opened in May Page 18

20 Palo Alto High School Boiler Replacement System Environmental Services Inc. (ESI) initiated project closeout and a notice of completion has been filed. Staff continues to work on other improvements within the Tower building to improve the heating distribution and controls systems. Strong Schools Bond Funds $1,500,000 Other $0 Total $1,500,000 Salaries and Benefits $0 Supplies $400 Contracts & Services $179,000 Construction & Equipment $1,289,600 Soft Costs Contingency $31,000 Total $1,500,000 Percent of Expended 42.5% Change Order Contingency Starting Contingency Balance $39,200 Remaining Contingency Balance $33,930 Percent of Changes 1.2% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Close out Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA June 30, 2011 Authorize to Bid (2) May 10, 2011 May 24, 2011 Approval by DSA August 24, 2011 Bid Opening September 28, 2011 Award of Contract (1) October 11, 2011 Notice to Proceed November 7, 2011 Substantial Completion January 6, 2012 C. BOND PROJECT LIST REFERENCE: Project completed on schedule and within budget. Page 19

21 Ohlone Elementary School New Classroom Building and Modernization Move in to the new building and other existing classrooms occurred in December Students occupied the new building on January 3, Strong Schools Bond Funds $11,667,965 Other $0 Total $11,667,965 Salaries and Benefits $7,196 Supplies $44,253 Contracts & Services $2,364,457 Construction & Equipment $9,189,461 Soft Costs Contingency $62,598 Total $11,667,965 Percent of Expended 84.2% Change Order Contingency Starting Contingency Balance $748,400 Remaining Contingency Balance $602,714 Percent of Changes 1.9% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy January 3, 2012 Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) March 3, 2009 March 17, 2009 Schematic Design (2) June 2, 2009 June 23, 2009 Submit to DSA November 24, 2009 Authorize to Bid (2) April 27, 2010 May 11, 2010 Approval by DSA May 18, 2010 Bid Opening July 13, 2010 Award of Contract (1) August 3, 2010 Notice to Proceed August 19, 2010 Substantial Completion November 18, 2011 Planned Occupancy January 3, 2012 C. BOND PROJECT LIST REFERENCE: , Occupancy occurred on January 3, Project completed on schedule and within budget. Page 20

22 Site Acquisition 525 San Antonio Rd The advisory committee has recommended to the BOE on January 31, 2012 to lease the property on a shortterm basis to one or more tenants. Strong Schools Bond Funds $8,500,000 Other $0 Total $8,500,000 Salaries and Benefits $0 Supplies $0 Contracts & Services $8,500,000 Construction & Equipment $0 Soft Costs Contingency $0 Total $8,500,000 Percent of Expended 100.0% Current Phase: Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: , BOE discussion on committee recommendation occurred on January 31, Page 21

23 Jordan Middle Schools Interim Classrooms The portables were installed and moved into for fall All documents were submitted to DSA for closeout November 2, Strong Schools Bond Funds $392,120 Other $208,222 Total $600,342 Salaries and Benefits $0 Supplies $0 Contracts & Services $180,286 Construction & Equipment $419,292 Soft Costs Contingency $764 Total $600,342 Percent of Expended 70.4%* * previously expended Current Phase: Move in Approval by DSA June 16, 2011 Authorize to Bid (2) June 14, 2011 June 28, 2011 Bid Opening July 14, 2011 Award of Contract (1) July 20, 2011 Notice to Proceed July 27, 2011 Substantial Completion September 20, 2011 Occupancy September 30, 2011 C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5 This project completed ahead of schedule and under budget. Move in occurred on September 30, Page 22

24 Gunn High School Air Conditioning of Existing Buildings Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating summer Strong Schools Bond Funds $2,600,000 Other $0 Total $2,600,000 Salaries and Benefits $1,919 Supplies $0 Contracts & Services $454,160 Construction & Equipment $2,120,580 Soft Costs Contingency $22,891 Total $2,600,000 Percent of Expended 80.9% Current Phase: Close out Architect Contract (2) March 27, 2010 April 6, 2010 Conceptual Design (2) Schematic Design (2) Submit to DSA October 20, 2010 Approval by DSA February 10, 2011 Authorize to Bid (2) February 22, 2011 March 8, 2011 Bid Opening March 28, 2011 Award of Contract (1) April 8, 2011 Notice to Proceed April 11, 2011 Substantial Completion August 8, 2011 C. BOND PROJECT LIST REFERENCE: 3.7 Project in close out. Page 23

25 J.L. Stanford Middle School Interim Classrooms Coulter Construction completed the work on the relocated portables in August Current Phase: Occupancy August 11, 2011 This portable relocation project funded by main JLS project. Refer to pg. 14 Approval by DSA April 19, 2011 Jordan Project June 16, 2011 Authorize to Bid (2) May 10, 2011 May 24, 2011 Bid Opening June 1, 2011 Award of Contract (1) June 13, 2011 Notice to Proceed June 20, 2011 Substantial Completion August 8, 2011 Planned Occupancy August 15, 2011 C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5 Project completed on schedule and is currently in close out. Page 24

26 Fairmeadow Elementary School Portable Relocation Project Relocation of the portable was complete on August 8, documents were submitted to DSA for closeout October 11, All Current Phase: Occupancy August 8, 2011 This portable relocation project funded by main JLS project. Refer to pg. 14 Architect Contract (2) February 15, 2011 Conceptual Design (2) Schematic Design (2) Submit to DSA March 3, 2011 Approval by DSA March 3, 2011 Authorize to Bid (2) May 11, 2011 May 24, 2011 Bid Opening June 14, 2011 Award of Contract (1) June 14, 2011 Notice to Proceed June 20, 2011 Substantial Completion August 1, 2011 Planned Occupancy August 8, 2011 C. BOND PROJECT LIST REFERENCE: 6.4 Project completed ahead of schedule on August 8, Page 25

27 Elementary Classroom Improvements Interactive Whiteboards and Sound Assist System Installation Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the installation April 29, Phase 4 and 5 schools were the final elementary schools to receive interactive whiteboards and sound assist systems. Strong Schools Bond Funds $2,004,889 Other $0 Total $2,004,889 Salaries and Benefits $0 Supplies $0 Contracts & Services $325,488 Construction & Equipment $1,679,401 Soft Costs Contingency $0 Total $2,004,889 Percent of Expended 93.0% Current Phase: Complete May 15, 2011 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) November 9, 2010 November 23, 2010 Bid Opening February 25, 2011 Award of Contract (1) March 8, 2011 Notice to Proceed March 9, 2011 Completion May 15, 2011 C. BOND PROJECT LIST REFERENCE: All SmartBoards and Lightspeed sound systems installed. Page 26

28 Palo Alto High School Multi Use Field The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9, Strong Schools Bond Funds $2,609,680 Other $1,007,255 Total $3,616,935 Salaries and Benefits $0 Supplies $1,506 Contracts & Services $698,293 Construction & Equipment $2,916,682 Soft Costs Contingency $454 Total $3,616,935 Percent of Expended 100.0% Change Order Contingency Starting Contingency Balance $269,300 Remaining Contingency Balance $230,579 Percent of Changes 1.7% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy February 1, 2011 Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) Schematic Design (2) November 18, 2008 December 09, 2008 Submit to DSA March 19, 2009 Approval by DSA September 30, 2009 Authorize to Bid (2) February 24, 2009 March 17, 2009 Bid Opening March 16, 2010 Award of Contract (1) April 7, 2010 Notice to Proceed June 1, 2010 Substantial Completion January 31, 2011 Planned Occupancy February 1, 2011 C. BOND PROJECT LIST REFERENCE: 4.14 Field was open for use on February 1, Page 27

29 Gunn High School Industrial Arts Addition and Renovation This facility was available for instruction in January DSA closeout received on July 18, Strong Schools Bond Funds $5,082,402 Other $0 Total $5,082,402 Salaries and Benefits $1,061 Supplies $88,985 Contracts & Services $1,000,861 Construction & Equipment $3,991,495 Soft Costs Contingency $0 Total $5,082,402 Percent of Expended 99.3% Change Order Contingency Starting Contingency Balance $349,000 Remaining Contingency Balance $141,967 Percent of Changes 41.6% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy January 4, 2010 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA June 17, 2008 Approval by DSA December 24, 2008 Authorize to Bid (2) October 14, 2008 October 28, 2008 Bid Opening December 16, 2008 Award of Contract (1) December 24, 2008 Notice to Proceed January 6, 2009 Substantial Completion November 25, 2009 Planned Occupancy January 4, 2010 C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11 The building occupied as scheduled, and the project completed within budget. Page 28

30 Gunn High School Aquatic Center This facility was available for use in July 2009, and has been closed out with DSA. Strong Schools Bond Funds $4,865,423 Other $0 Total $4,865,423 Salaries and Benefits $0 Supplies $0 Contracts & Services $647,169 Construction & Equipment $4,218,253 Soft Costs Contingency $0 Total $4,865,423 Percent of Expended 99.9% Change Order Contingency Starting Contingency Balance $389,887 Remaining Contingency Balance $195,148 Percent of Changes 49.9% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy June 15, 2009 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA December 11, 2007 Approval by DSA April 24, 2008 Authorize to Bid (2) April 8, 2008 April 22, 2008 Bid Opening May 28, 2008 Award of Contract (1) June 4, 2008 Notice to Proceed December 6, 2008 Substantial Completion June 15, 2009 Planned Occupancy June 15, 2009 C. BOND PROJECT LIST REFERENCE: 3.12 This project completed within budget. Page 29

31 Middle School Pre Design Jordan, J.L. Stanford and Terman AEDIS presented recommended concept plans for each campus to the Board of Education for approval on September 8, which became the program documents for the new projects at each campus. These projects for pre design work have been closed, and funds will be transferred to the program contingency on June 14, Strong Schools Bond Funds $56,488 Other $0 Total $56,488 Salaries and Benefits $0 Supplies $0 Contracts & Services $56,488 Construction & Equipment $0 Soft Costs Contingency $0 Total $56,488 Percent of Expended 96.8% Current Phase: Complete Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: This project has been completed. Board approval received on September 8, Page 30

32 Garland Elementary School Campus Modernization The Board of Education has put new development for Garland on hold until a growth plan is established for the elementary schools. The board voted to terminate the lease with Stratford School in June Discussions with the Board on future plans for growth at the elementary schools are ongoing. Strong Schools Bond Funds $22,178,544 Other $0 Total $22,178,544 Salaries and Benefits $0 Supplies $0 Contracts & Services $3,915,789 Construction & Equipment $17,400,000 Soft Costs Contingency $862,755 Total $22,178,544 Percent of Expended 1.3% Current Phase: On Hold Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) February 10, 2009 February 24, 2009 Schematic Design (2) June 2, 2009 June 23, 2009 Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: 1.1, This project has been placed on hold. Page 31

33 Elementary School Teaching Walls Phase 1 Schools The district placed this project on hold after review of the implementation of other classroom improvements, as recommended by the elementary school principals. This project has been renamed Elementary Classroom Improvements (see Capital Projects summary below). Strong Schools Bond Funds $0 Other $0 Total $0 Salaries and Benefits $0 Supplies $0 Contracts & Services $0 Construction & Equipment $0 Soft Costs Contingency $0 Total $0 Percent of Expended 0% Current Phase: Project Renamed. See Classroom Improvements Project Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: 1.9 This project has been renamed Elementary Classroom Improvements (see Capital Projects summary above). Page 32

34 High School Master Plan Palo Alto HS and Gunn HS The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed, with funds transferred to the respective campus reserve funds. Strong Schools Bond Funds $285,387 Other $0 Total $285,387 Salaries and Benefits $0 Supplies $0 Contracts & Services $285,387 Construction & Equipment $0 Soft Costs Contingency $0 Total $285,387 Percent of Expended 86.2% Current Phase: Complete Architect Contract (2) March 31, 2009 April 14, 2009 Initial Master Plan Approval (2) September 8, 2009 September 22, 2009 Paly CEQA Approval (2) February 9, 2010 February 23, 2010 Gunn Master Plan Update (2) March 23, 2010 April 6, 2010 Gunn CEQA Approval (2) April 27, 2010 May 11, 2010 Master Plan Revision Approval (2) September 14, 2010 Paly MP Revision Approval (2) October 9, 2010 Gunn MP Revision Approval (2) October 12, 2010 C. BOND PROJECT LIST REFERENCE: , Master planning effort complete. Page 33

35 Hoover Elementary School Pre Design This project has been put on hold until a growth plan is established for the elementary schools. Strong Schools Bond Funds $70,550 Other $0 Total $70,550 Salaries and Benefits $0 Supplies $0 Contracts & Services $70,550 Construction & Equipment $60 Soft Costs Contingency $0 Total $70,550 Current Phase: On Hold Architect Contract (2) April 27, 2010 May 11, 2010 Conceptual Design (2) November 9, 2010 Schematic Design (2) Submit to DSA Approval by DSA Percent of Expended 100.0% Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: , Project is currently on hold. Page 34

36 Elementary Classroom Improvements Phase 1 Barron Park and El Carmelo DSA comments were returned to Gelfand for Phase 1 plans that include new lighting, adding operable windows and coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary schools. The authorization to bid has been placed on hold pending further discussions with the BOE about elementary growth planning. Strong Schools Bond Funds $2,004,889 Other $0 Total $2,004,889 Salaries and Benefits $0 Supplies $0 Contracts & Services $325,488 Construction & Equipment $1,679,401 Soft Costs Contingency $0 Total $2,004,889 Percent of Expended 93.0% Phase 1 Schools: Barron Park and El Carmelo Current Phase: On Hold Architect Contract (2) June 8, 2010 June 22, 2010 Conceptual Design (2) Schematic Design (2) November 9, 2010 December 7, 2010 Submit to DSA December 23, 2010 Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: This project has been placed on hold. Page 35

37 Numbers Added EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. OHS WEST: A-1

38 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. OHS WEST: A-2

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through November 2010 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

Santa Teresa High School

Santa Teresa High School Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew

More information

Independence Adult Center

Independence Adult Center Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus

More information

James Lick High School

James Lick High School James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.

More information

Boynton High School & Blackford Site

Boynton High School & Blackford Site Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066

More information

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T DEFINED: Measure T is a local ballot measure on the November 2014 ballot seeking voter authorization

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

N o v e m b e r

N o v e m b e r WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G February 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Schedule

More information

Frost Technical Center

Frost Technical Center Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA

SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA 25 August 2009 All meetings are at 3:15 p.m. unless otherwise noted. Meeting dates are scheduled in advance and dates without agendas may or may not be

More information

AZUSA UNIFIED SCHOOL DISTRICT

AZUSA UNIFIED SCHOOL DISTRICT AZUSA UNIFIED SCHOOL DISTRICT BOARD STUDY SESSION June 9, 2014 EVALUATION OF STATUS OF FACILITES AND FUTURE NEEDS NEEDS vs. FUNDING SETTING PRIORITIES 5) OTHER ADDITIONAL IMPROVEMENTS 4) OTHER ARCHITECTURAL

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report Moreno Valley Unified School District Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report November 19, 2015 District Long Term School Funding Program Revenue Sources

More information

SANTA ROSA JUNIOR COLLEGE

SANTA ROSA JUNIOR COLLEGE EXPENDITURES Eligible Bond Program Costs 1,363,848 451,690 622,090 74,757 10,295 85,053 2,522,681 RENOVATION AND MODERNIZATION Upgrade classrooms, laboratories, support service space at all locations 298,139

More information

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

Capital Projects Report

Capital Projects Report Capital Projects Report t o t h e Board of Trustees of the Sierra Sands Unified School District December 11, 2014 1 BURROUGHS HIGH SCHOOL Address 500 E. French Ave. Ridgecrest, CA 93555 Project Maas Steve

More information

HIDDEN VALLEY ELEMENTARY SCHOOL

HIDDEN VALLEY ELEMENTARY SCHOOL SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802

More information

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN EL CAMINO COLLEGE Facilities Master Plan Report November 2008 PROJECTS IN DESIGN I. Math, Business & Allied Health Building (MBA) The scope of this building is the construction of a new building at the

More information

FULL TEXT BALLOT PROPOSITION OF THE AMADOR COUNTY UNIFIED SCHOOL DISTRICT BOND MEASURE ELECTION NOVEMBER 6, 2018

FULL TEXT BALLOT PROPOSITION OF THE AMADOR COUNTY UNIFIED SCHOOL DISTRICT BOND MEASURE ELECTION NOVEMBER 6, 2018 FULL TEXT BALLOT PROPOSITION OF THE AMADOR COUNTY UNIFIED SCHOOL DISTRICT BOND MEASURE ELECTION NOVEMBER 6, 2018 The following is the full proposition presented to the voters by the Amador County Unified

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

Grossmont-Cuyamaca Community College District Facilities Construction Update

Grossmont-Cuyamaca Community College District Facilities Construction Update Grossmont-Cuyamaca Community College District Facilities Construction Update September 13, 2016 Presented by Penny McGrew Program Manager Gafcon, Inc. Bond Program Update Agenda Districtwide Energy Conservation

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015 FACILITIES PROJECTS UPDATE BOARD OF EDUCATION August 11, 2015 AGENDA Measure R Bond Projects Fund 40 Capital Projects Maintenance Projects MEASURE R BOND PROJECTS KINDERGARTEN MODERNIZATIONS PROGRAM BUDGET:

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community. SYLVAN MIDDLE SCHOOL The mission of Sylvan Middle School is consistent with that of the San Juan Unified School District, which is to inspire each student tosucceed and responsibly contribute to a radically

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

PROJECT LIST ALTERNATIVE #1

PROJECT LIST ALTERNATIVE #1 PROJECT LIST ALTERNATIVE #1 TEMECULA VALLEY UNIFIED SCHOOL DISTRICT BOND PROJECT LIST To protect the quality of education in schools within the Temecula Valley Unified School District ( School District

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

(Continued on next page)

(Continued on next page) FULL TEXT OF BALLOT MEASURE E LONG BEACH UNIFIED SCHOOL DISTRICT REPAIR AND SAFETY MEASURE. To improve outdated classrooms/neighborhood schools by: improving technology/labs/career education classrooms/electrical

More information

Architectural Services Consultant Registration Form

Architectural Services Consultant Registration Form Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,

More information

Birmingham Public Schools

Birmingham Public Schools Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress

More information

January 2017 Project Update

January 2017 Project Update January 2017 Project Update Overall Referendum Project Status: ON SCHEDULE/ON BUDGET All elements of the project completed to date have been completed on or ahead of schedule and final costs were under

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

MVSD FACILITY PRIORITY NEEDS

MVSD FACILITY PRIORITY NEEDS Mountain View School District 3320 Gilman Road El Monte, CA 91732 626-652-4000 MVSD FACILITY PRIORITY NEEDS June 23, 2016 80 AGE OF PERMANENT FACILITIES (as of October 2011) 70 60 50 40 30 20 10 0 AGE

More information

Project Update Prop M Bond Series A & B

Project Update Prop M Bond Series A & B Update Prop M Bond Series A & B Name Independent Citizen s Oversight Committee Report March 2012 Construction Scope Status 2071001 Natural Science Bldg. Completion & Equipment 2102002 PC North Education

More information

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

East Los Angeles College Project Priority List Occupancy Date

East Los Angeles College Project Priority List Occupancy Date East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

Merritt Island High School

Merritt Island High School Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

School Assessment Report

School Assessment Report School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program. MONTHLY REPORT March 31, 2009

CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program. MONTHLY REPORT March 31, 2009 CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program MONTHLY REPORT March 31, 2009 Construction Management 414 W. 4 th Street, Suite L Santa Ana, CA. 92701 Table of

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Repair & Replacement Study

Repair & Replacement Study Donald Lum Elementary School Repair & Replacement Study 23 January 2018 ALAMEDA UNIFIED SCHOOL DISTRICT 1495.05 1 PROJECT BACKGROUND Overview of Engineering Studies Miller Pacific Geotechnical Report -

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020

More information

School Assessment Report

School Assessment Report School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School

More information

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

CESAR CHAVEZ LANGUAGE ACADEMY

CESAR CHAVEZ LANGUAGE ACADEMY SCHOOL DAA Address: 2570 West Steele Lane Santa Rosa, CA 95403 Established: Campus - 1972, CCLA - 2013 Permanent Classrooms: 14 Portable Classrooms: 4 Building Area: Site Area: 17,000 sq. ft. 24.08 acres

More information

NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST

NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST The New Haven Unified School District will use bonds funds to provide up to date classrooms, renovate athletic fields and related facilities, replace

More information

TWIN RIVERS UNIFIED SCHOOL DISTRICT 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015

TWIN RIVERS UNIFIED SCHOOL DISTRICT 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015 AGENDA I. LRFMP BRANDING UPDATE II. LRFMP FOCUS GROUP UPDATE III. ENROLLMENT PROJECTIONS / DEMOGRAPHICS IV. FINALIZE

More information

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 1 ACTIVE PROJECTS Santa Ana College Chavez Hall Renovation Temporary Village Phase 2 Santiago Canyon College Orange Education Center

More information

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST March 10, 2018 TABLE OF CONTENTS PROJECT SUMMARY LIST AND COST PROJECT DESCRIPTIONS MISSION COLLEGE PROJECT DESCRIPTIONS WEST VALLEY COLLEGE PROJECT DESCRIPTIONS

More information

Prepared By Construction Manager September 2011

Prepared By Construction Manager September 2011 Prepared By: Construction Manager September 2011 INTRODUCTION P.J. Dick Incorporated is pleased to present the Upper St. Clair Board of School Directors with the following Construction Report for the Fort

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

27 January 2011, 3:30 pm-5:00 pm

27 January 2011, 3:30 pm-5:00 pm PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES DATE: SUBJECT: ATTENDEES: 27 January 2011, 3:30 pm-5:00 pm ATHLETIC FIELD IMPROVEMENTS SUBCOMMITTEE MEETING NO. 6 Sign-in sheet (attached)

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

Measure YY. Approved by the Board of Education

Measure YY. Approved by the Board of Education Measure YY Approved by the Board of Education July 10, 2018 San Diego Unified has 226 educational facilities with over 1,400 permanent buildings and more than 2,000 portable classrooms. In 2008, a study

More information

Proposition E Independent Citizens Oversight Committee. Report to the Board of Education June 21, 2017

Proposition E Independent Citizens Oversight Committee. Report to the Board of Education June 21, 2017 Proposition E Independent Citizens Oversight Committee Report to the Board of Education June 21, 2017 Ballot Proposition November 6, 2012 Repair, renovate, construct, and upgrade classrooms and school

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

School Assessment Report

School Assessment Report School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

PROJECT UPDATE SEPTEMBER 11, 2014

PROJECT UPDATE SEPTEMBER 11, 2014 PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

Design Advisory Committee Meeting #5. December 19, 2017

Design Advisory Committee Meeting #5. December 19, 2017 Design Advisory Committee Meeting #5 December 19, 2017 1 Meeting Agenda 1. Agenda / Attendance Sheet 5 minutes 2. BEST Grant Recap 3. Review Funding Options additional information 4. Master Plan Summary

More information

Master Plan, January 16, 2012 Roesling Nakamura Terada Architects

Master Plan, January 16, 2012 Roesling Nakamura Terada Architects L a C o s t a C a n y o n H i g h S c h o o l Master Plan, January 16, 2012 Roesling Nakamura Terada Architects I n t r o d u c t i o n 1.0 INTRODUCTION -Programming -Site and Facilities Development upgrades

More information

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely

More information

Safety Update Crossing study is in final review stages. Facilities Update Construction Progress

Safety Update Crossing study is in final review stages. Facilities Update Construction Progress Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.

More information