1 TOWN OF NORWOOD NEW NORWOOD HIGH SCHOOL MONTHLY PROGRESS REPORT MARCH 2010 Prepared by: 266 Main Street Suite 31A Medfield, MA
2 Table of Contents: I. Executive Summary II. III. IV. Progress Report by Participant 30 Day Look Ahead Schedule Status V. Budget Status VI. VII. VIII. IX. Cash Flow Analysis Change Order Status Report Safety Performance Review QA/QC Review X. Environmental Compliance Review XI. XII. XIII. XIV. XV. Community Issues Review MBE/WBE Activity Review Additional Issues or Concerns Progress Photos Attachments
3 I. Executive Summary: Project Overview: Despite historical rainfall amounts, Agostini Construction (ACCI) continued to make strong progress. Roofing began on Zone C. Masons completed the high walls between Zones B/ C, continued on the courtyard walls of Zone B, and began working on the exterior of Zones A, B, and D. Slab on grade work started in Zone C. Window installation began on the courtyard elevation of Zone A. Rough inspections were completed on the 2 nd and 3rd floor of Zone A and the 3 rd floor of Zone B. Interior wallboard and plaster work began in Zone A. Site work resumed with the continuation of the utility (sewer and water) lines in front of the new building. In March, workforce levels ranged from workers per day with an average of 95 workers per day, up from February s average of 81. Weekly construction meetings to discuss construction status, involving representatives from Agostini, Ai3, Compass, NPS, and the Norwood PBCC, were held on-site every Tuesday morning at 10 AM. The FF&E team began to finalize its preliminary program and budget. The Technology team began to finalize its requirements and identified a vendor for the project. Schedule Status: Overall, the entire project remains ahead of schedule and is about six (6) weeks ahead of schedule as compared to the Whitman Hanson as-built schedule. Budget Status: There was $2,985,972 in approved expenditures for March. ACCI s March Application for Payment was submitted and approved for $2,855,942. The Town of Norwood also approved ten (10) additional invoices in March for a total amount of $130,030. As of the end of March, actual expenditures are higher than planned expenditures. Planned expenditures were projected to be $21,807,188 and actual expenditures are $24,764,894 to date. Although this month s expenditures are in line with cash flow projections, expenditures to date remain about 14% higher than planned. This is a positive reflection of the project s progress to date, as overall work is about six (6) weeks ahead of the planned progress. In March, the PBCC approved Change Order #7 resulting in a net add of $18, Currently, there are fifty-two (52) other Pending Change Orders (PCOs) with a net estimated exposure of $123,840. Issues or Concerns: There are no major issues or concerns to report.
4 II. Progress Report by Participant: Despite historical rainfall amounts during the month, Agostini Construction (ACCI) continued to make strong progress. Structural steel detailing was completed in Zone D. Roofing began on Zone C. Exterior masonry work was completed on the high walls between Zones B/ C, continued on the courtyard walls of Zone B, and began on the exterior of Zones A, B, and D. Interior metal stud framing continued in Zones A and B. Interior masonry continued in Zones A and B. Stairs 3 and 4 were installed. MEP contractors continued rough-in work of mechanical, electrical, and plumbing systems in Zones B and under-slab utilities in Zone C. Fire sprinkler rough-in continued in Zones A & B. Concrete was placed at the elevated walking track around the gym in Zone D. Preparation work for slab on grade placement started in Zone C. Window installation began on the courtyard elevation of Zone A. Rough inspections were completed on the 2 nd and 3rd floor of Zone A and the 3 rd floor of Zone B. Interior wallboard and plaster work began in Zone A. Site work resumed with the continuation of the utility (sewer and water) lines in front of the new building. For the month, the project had workforce levels that ranged from workers per day with an average workforce of 95 workers per day, up from February s average of 81. Please refer to Attachment 1 ACCI Monthly Progress Report Ai3 continued construction administration services including review of all submittals, RFI s, CORs, and change orders. Ai3 maintained the construction administration database used to manage and share all associated documentation. Ai3 performed several progress inspections and also coordinated progress inspections performed by their MEP engineers. Please refer to Attachment 2 Ai3 Services Summary. Compass continued full-time monitoring of both construction administration and on-site work including managing all quality assurance measures. Compass continued to manage the efforts of the Owner s testing agency, UTS, and commissioning agents, RFS and Gale Associates. Compass reviewed, analyzed, and negotiated all CORs and applications for payment during the month. Compass also continued to coordinate the FF&E and IT planning efforts. Please refer to Attachment 3 Compass Monthly Services Summary.
5 III. 30 Day Look Ahead by Participant: ACCI s planned construction activities for the coming month include the following in Zones A &B: interior masonry; interior framing; MEP and fire-protection rough-in work; installation of interior insulation, gypsum wall board and plaster. Exterior masonry will also continue in the courtyard, along the elevations in Zones A&B, and along the Zone D (gymnasium) elevations, weather permitting. Window installation will continue in the courtyard. Roof work will continue in Zone C and D, weather permitting. Delivery and installation of roof-top mechanical equipment for the HVAC system is also planned. MEP contractors will continue to build-out the mechanical and electrical rooms. Preparation and placement of concrete for slabs on grade will continue in Zone C and D. Site work operations will continue with installation of site utilities and retaining walls. Ai3 will continue to manage the construction administration processes including review and approval all product submittals. Compass will continue to monitor all construction administration and on-site work. Compass will continue to manage the Information Technology and Furniture, Fixtures, and Equipment (FF&E) planning efforts for the new high school. The FF&E team is planning to finalize its preliminary program and budget by the end of April. IV. Schedule Status: Phase I: April 2009 June 2011 The phase includes the demolition of the southwest corner of the existing building and the construction of the new school facility including the rear stadium. Overall, the entire project remains ahead of schedule and is about six (6) weeks ahead of schedule as compared to the Whitman Hanson as-built schedule. Compass received ACCI s March Schedule Update which indicates that the stadium is scheduled to be completed in July of Compass will continue to work with ACCI to fine tune the construction schedule to ensure that the proposed milestones can be achieved. Compass will provide an updated schedule analysis in the April Monthly Progress Report. Compass is working to finalize the overall project schedule which includes the construction, the installation of the FF&E and Technology, and the move mitigation for the existing school.
6 V. Budget Status: There was $2,985,972 in approved expenditures for March. ACCI s March Application for Payment was submitted and approved for $2,855,942. The Town of Norwood also approved ten (10) additional invoices in March for a total amount of $130,030. Please refer to Attachment 4 Monthly Expenditures List The Town approved one (1) contract amendment(s) during the month. Amendment # Date Contract/w Description Amount 14 3/11/10 Ai3 Design blue light emergency system $1, The Project Budget Status Report shows total expenditures to date of $24,764,894 which represents 36% of the total project budget of $68,655,476. Please refer to Attachment 5 Project Budget Status Report VI. Cash Flow Analysis: As of the end of March, actual expenditures are higher than planned expenditures. Planned expenditures were projected to be $21,807,188 and actual expenditures are $24,764,894 to date. Although this month s expenditures are in line with cash flow projections, expenditures to date remain about 14% higher than planned. This is a positive reflection of the project s progress to date, as overall work is about six (6) weeks ahead of the planned progress. Please refer to Attachment 6 Project Cash Flow by Month and Attachment 7 Cash Flow Analysis Chart.
7 VII. Change Order Status Report: In March, the PBCC approved Change Order #7 resulting in a net add of $18, Change Order #7 consisted of several Pending Change Orders (PCOs) from the PCO Log. CO # PCO # Description Amount 7 21 Furnish and install exterior light at existing building $ Credit for appliances -$ Modification to Fire Alarm per Norwood FD request. $6, Electrical and data modification to Foreign Language Lab $ Furnish and install hollow metal frame type 4 in lieu of type 8 at door 106H1 $ Remove from contract scope window in control room 106B -$ Create drainage swale on southwest driveway $5, Masonry modifications at door C203 $ Provide fire dampers per result of coordination process $ Total $18, Currently, there are fifty-two (52) other Pending Change Orders with a net estimated exposure of $123,840. Please refer to Attachment 8 Pending Change Order (PCO) Log
8 VIII. Safety Performance Review: No lost work days due to injury were reported during the month. March 31st was the 33rd consecutive Safe Work Day with no reportable incidents since the last injury claim. ACCI and all subcontractors continue to hold weekly safety meetings to discuss job site safety, rules, and regulations plus any material/work specific safety information. ACCI s third party inspection agency, Contractors Risk Management, performed five (5) safety inspections during the month. Inspections were performed on 3/5, 3/11, 3/17, 3/24, and 3/31. All inspections were unannounced. During the 3/17 inspection, CRM sited ACCI s site contractor, E. Guigli and Sons, for unsafe trench conditions. Guigli corrected the conditions and suspended trench operations until safe working conditions could be provided and maintained. CRM facilitated an on-site safety training seminar with ACCI and Guigli on 3/18. Please refer to Attachment 9 ACC Safety Update Report.
9 IX. QA/QC Review: Compass is actively monitoring the Quality Control measures in the field and is managing the overall Quality Assurance testing for the project. Compass continued to maintain a log of all QA/QC inspections and testing corresponding to the Structural Inspection and Testing Program. Gale Associates, the project s Building Envelope Commissioning Agent, made several site visits during the month to review air/vapor barrier and roofing installation. Reports were issued for all visits. Universal Testing Service (UTS) was on-site weekly during the month performing the following: spray fireproofing coverage and adhesion testing and grout/mortar testing. UTS also continued regular inspections of structural steel work under the direction of the Structural Engineer of Record (SER). UTS resumed monitoring site-work activity and providing compaction testing as necessary. Reports were issued for all tests and inspections and all are noted on Compass Structural Inspection and Testing Log. Civil Engineers from PARE Corp were on-site during the month to review site conditions and erosion control measures in conjunction with site work resuming and the month s heavy rainfall. Reports were issued for all visits. The SER from Engineers Design Group (EDG) made several site visits during the month to inspect masonry and structural steel work. Reports were issued for all visits and are noted on Compass Structural Inspection and Testing Log. Town of Norwood Building Department officials made multiple site visits throughout the month to review and inspect project work. Ai3 continued formal inspections of project progress, inspecting work for adherence to project specification and workmanship standards. Results of these inspections were documented on Architect Field Observation Reports (AFORs). Ai3 issued five (5) AFORs during the month. MEP engineers also continued inspecting installed materials for adherence to project specification and workmanship standards. Results of these inspections were documented on reports from the respective engineer. Ai3 continued to review the construction of the project s exterior Mock-up panel to ensure workmanship and detailing meet the project s specifications and standards. Documented analysis and direction were provided after each review. ACCI provided a monthly update to their Quality Control program. Please refer to Attachment 10 ACC Quality Control Program Monthly Update. No quality issues were encountered during the month.
10 X. Environmental Compliance Review: ACCI continued execution of their Storm Water Pollution Protection Plan (SWPPP). ACCI and site subcontractor Guigli issued two (2) SWPPP Reports during the month. Due to the historical amounts of rainfall, the project dealt with a few issues. A summary of the reports is as follows: Date SWPPP Issue Corrective Action Taken Issue resolved 03/15/10 Heavy rains overwhelmed some SWPPP measures causing minor surface flooding. Cleaned or replaced silt-sacks as needed. Replaced hay bales and silt fence as needed. Performed street sweeping as necessary. Yes 3/22/10 Heavy rains caused minor silt infiltration of the Town s storm drainage system and some downstream water bodies. Catch basins were vacuumed. Replaced all silt-sacks. Created silt retention ponds around catch basins. Yes Compass is working closely with the Town of Norwood s Department of Public Works and Conservation Commission to ensure that all SWPPP measures are working properly and are being maintained. ACCI continued execution of their Waste Management Plan in efforts to meet the requirements of the project s MA-CHPS waste management and recycling program. The project s goal is to recycle or salvage 90% of all waste material. Currently, the project is recycling approximately 82% of its waste material. Please refer to Attachment 11 Waste Management Log. ACCI and Ai3 continued to ensure that the required MA-CHPS product data sheets were completed on all material and/or product submittals. ACCI, Ai3, and Compass will be meeting ion 4/13 to review the MA-CHPS plan and project status to date.
11 XI. Community Issues Review: There are no major community issues to report. Neighborhood Meetings were held on 3/05, 3/12, 3/19, and 3/26 at Town Hall. Minutes were distributed via and posted on the project s website. Project information and pictures continue to be posted to the construction web-page maintained by Norwood Public Schools. The web address is: Compass continued to maintain the project s log, tracking and responding to all s received through the project s address, construction@norwood.k12.ma.us. The log is entered into the weekly Neighborhood Meeting during the open discussion period. XII. MBE/WBE Activity Review: Requirements for the project are: MBE =7.4% and WBE = 4% Current percentages remain unchanged from last month. Current percentages are: MBE = 3.63% and WBE = 10.6%. Please to Attachment 12 MBE/WBE Activity Report. XIII. Additional Issues or Concerns: There are no additional issues or concerns at this time. XIV. Progress Photos: Please to Attachment 13 MPR Progress Photos
12 XV. Attachments: 1. ACCI Monthly Progress Report 2. Ai3 Services Summary 3. Compass Monthly Services Summary 4. Monthly Expenditures List 5. Project Budget Status Report 6. Project Cash Flow by Month 7. Project Cash Flow Analysis Chart 8. Pending Change Order (PCO) Log 9. ACCI Safety Update Report 10. ACCI Quality Control Program Monthly Update 11. Waste Management Log 12. MBE/WBE Activity Report 13. MPR Progress Photos
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationCARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationCommercial Submittal Packet
Commercial Submittal Packet City of Pepper Pike Building Department 28000 Shaker Boulevard Pepper Pike, Ohio 44124 Phone: (216) 896-6134 Fax: (216) 831-6525 www.pepperpike.org Submitting for the Architectural
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationInspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.
Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure
More information29.56% 25%* * 36.25% 30%** ** PROJECT DESCRIPTION: PROJECT INFORMATION: 06 NOVEMBER LAST REPORT CURRENT REPORT SOUTHBOROUGH PUBLIC SAFETY COMPLEX
Report Date: Prepared By: Prepared For: December 3, 2018 M O N T H LY P RO G R E S S R E P O RT 06 NOVEMBER REPORT LISTING SOUTHBOROUGH, MASSACHUSETTS Project Description 1 Project Information 1 Payment
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More informationCARPENTER TRADE REGULATION
Province of Alberta APPRENTICESHIP AND INDUSTRY TRAINING ACT CARPENTER TRADE REGULATION Alberta Regulation 267/2000 With amendments up to and including Alberta Regulation 119/2018 Current as of June 20,
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationThe following information is required when submitting a building permit application:
Dept. of Planning and Zoning Town of Greensboro PO Box 340 Greensboro, MD 21639 410-482-6222 The following information is required when submitting a building permit application: 1. A Completed building
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationAbove the Flood: Elevating Your Floodprone House. FEMA 347/ May 2000 FEMA
Above the Flood: Elevating Your Floodprone House FEMA 347/ May 2000 FEMA Cover photograph provided by The Weather Channel. Table of Contents Chapter 1 Introduction...1-1 Chapter 2 Homeowner Options...2-1
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationProject Management Course Syllabus
Project Management Course Syllabus 2 Hours (Interactive) Introduction & Overview to Project Management Review Templates Review Sundt Templates for Headworks Project Introduction to Project Management Scope
More informationAPPLICATION AND CERTIFICATE FOR PAYMENT
AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationBUILDING PERMIT CHECKLIST FOR THE TOWN OF GRAND LAKE
BUILDING PERMIT CHECKLIST FOR THE TOWN OF GRAND LAKE Please Note: No construction, including site preparation (grading, excavating, vegetation removal, etc.), will be allowed until a building permit or
More information1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.
City of Goshen Instructions for Residential Permit Application Why do you need a building permit? Your home is a large investment, and if your construction project does not comply with the codes adopted
More informationVillage of Orland Hills COMMERCIAL Building Permit Application S. 94th Avenue, Orland Hills, IL
COMMERCIAL Building Permit Application 16033 S. 94th Avenue, Orland Hills, IL. 60487-4623 (PRINT or TYPE to complete this form only) Construction Address: {Construction Cost } Owner's Name: Applicant:
More informationProud of its Heritage, Preparing for its Future
TUSTIN Proud of its Heritage, Preparing for its Future Revised August 2013 USER GUIDE FOR THE INSTALLATION OF RESIDENTIAL ROOM ADDITIONS OR ALTERATIONS PURPOSE This guide describes the City of Tustin s
More informationDelco Activity Center Site Summary
1 Site Summary Address 4601 Pecan Brook Austin, TX 78724 Number of Permanent Campus Facilities 1 Original Year of Construction 2003 Total Campus Building Area (combined) 60,294 SF Introduction The is located
More informationEXPANSION & RENOVATION
ISSUE 06 JANUARY 2012 SAN JOSE CONVENTION CENTER EXPANSION & RENOVATION MONTHLY PROGRESS REPORT CONTENTS Project Summary Expansion & Renovation Update Central Utility Plant Update Schedule of Subcontractors
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationInspection of New One- and Two- Family Dwellings
Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Inspection of New One- and Two- Family Dwellings Planning and Development
More informationFleet Elementary School
Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project
More informationSTATE UNIVERSITY CONSTRUCTION FUND
STATE UNIVERSITY CONSTRUCTION FUND The following checklist show the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the Schedule B of the Consultant
More informationProject #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50
Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed
More informationCommercial Remodel Permit
Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each
More informationMONTHLY PROGRESS REPORT
Report Date: Prepared By: Prepared For: MONTHLY PROGRESS REPORT 04 SEPTEMBER REPORT LISTING Project Description 1 S OUTHBOROUGH, MASSACHUSETTS Project Information 1 Payment Status 2 Damages / Claims 2
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:
ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan
More informationConstruction Update. April 2016
Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor
More informationCity Of Mendota Construction Procedures
City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time
More informationAPPENDIX E APPLICATIONS
APPENDIX E APPLICATIONS Schedule of Fees ACC Meeting Calendar Foundation Survey & As Built Plan Checklist Application for New Construction Landscape Review Submittal Sheet Elevation Verification/Foundation
More informationItem # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities
ADDENDUM NO. 1 Proposed Residence 422 Hickory Street Buffalo, New York 14204 February 15, 2019 Long Associates, Architects 189 Kenmore Avenue Buffalo, New York 14223 This addendum is issued to amend the
More informationCOMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018
COMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018 CONSTRUCTION CODES The City of Colleyville has adopted and enforces the following codes which are applicable to building construction activities within the
More informationPermit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:
Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,
More informationTHE CONSTRUCTION SUPERVISOR
City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor
More informationSWPPP Inspection Procedures and Form 247 Instructions
SWPPP Inspection Procedures and Form 247 Instructions 1. Pre-Construction Conference a. A stormwater pollution pre-construction conference shall be held prior to beginning work on each project. b. The
More informationApplication for Commercial Plan Review and Building Permit. Address:
City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial
More informationC ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)
C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) 353-8115 Fax: (630) 852-4709 BUILDING PERMIT INFORMATION PACKET Revised: October 2018 Building Codes: International Residential
More informationSERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS
SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,
More informationCity of Lorena 107-A S. Frontage Road Lorena, Texas Phone: (254) Fax: (254)
Residential New Home Building Requirements This document is not meant to modify any Federal or State laws or City Ordinances. It is intended to be informative and to be used as a guideline. Where circumstances
More informationCommercial and Residential Projects (after appropriate Board approvals have been made if necessary):
Village of Lansing Office: 2405 N. Triphammer Rd. Hours: 9:00-1:00 Telephone: 257-0424 Ext. # 3 Email: codeofficer2@vlansing.org Commercial and Residential Projects (after appropriate Board approvals have
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationPAULDING COLLEGE & CAREER ACADEMY
PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE
More informationCOMMERCIAL PROJECT INFORMATION
Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org COMMERCIAL PROJECT INFORMATION The Community
More informationCity of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements
Table of Contents City of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements General Requirements Application & Processing Procedures o Plan Requirements
More informationWatercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS
Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING
More information3.0 Planning and Submittal Requirements
October 2003, Revised February 2005 Chapter 3.0, Planning and Submittal Requirements Page 1 3.0 Planning and Submittal Requirements 3.1 Drainage Studies and Drawings The City of Greenwood Village (Village)
More informationCITY of COLDWATER. Requirements for Obtaining Building Permits City of Coldwater, Michigan
Requirements for Obtaining Building Permits City of Coldwater, Michigan Any owner, owner s builder, architect or agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy
More informationINSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST
Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING
More informationBasement Build-Out Guidelines
Community Development Department Five Plaza Drive Woodridge, IL 60517-5014 (630) 719-4750 FAX (630) 719-2900 Basement Build-Out Guidelines The Village of Woodridge requires that a building permit be submitted
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationPort KC RFP NORTHLAND PARK BUILDING V
Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?
More informationMITTERSILL WARMING HUT
STATE OF NEW HAMPSHIRE DEPARTMENT OF RESOURCES AND ECONOMIC DEVELOPMENT DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1786 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE DRAWING LIST: COVER SHEET
More informationINSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.
INSPECTION REQUIREMENTS Page 1 of 5 JOB SITE ADDRESS posted during entire construction process. JOB PLACARD POSTED IN PLAIN SIGHT: GREEN Placard - Building, ORANGE Placard Electrical, BLUE Placard - HVAC,
More informationPrequalification Form
1.0 General Information Date: 1.1 Name of Firm _ County Telephone Toll Free Fax Website _ for Bid Purposes: Name Phone 1.2 Legal Identity: Sole Proprietorship Partnership Corporation Limited Liability
More informationSECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationShow how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality
Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge
More informationGood Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions
September 18, 2018 Good Housekeeping Phones Weather related emergencies Breaks and facilities Introductions Goals and Objectives 1. Plan Review Process 2. Land Disturbance Permitting 3. Erosion and Sediment
More informationSECTION PAYMENT PROCEDURES
SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply
More informationSafety Update Crossing study is in final review stages. Facilities Update Construction Progress
Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene
February 16, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed 1 ST Coat of Paint in C5 Corridors. Completed Test & Balance in Building C. Completed Final Paint in B1 Corridors. Completed
More informationCITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS
CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS Update April 29, 2013 12 Permit application forms and contact information can be found on our website under Inspection Department
More informationCity of Meadowlakes Builder s Packet for New Construction Builder/Contractor or Property Owner
City of Meadowlakes Builder s Packet for New Construction Builder/Contractor or Property Owner PERMIT APPLICATION Plans must be submitted fourteen (14) business days prior to the next regularly scheduled
More informationSECTION GREEN BUILDING POLICY IMPLEMENTATION
SECTION 01390 [Note: The intent of this section is to identify Contractor specific work required for achievement of the University Green Building Policy. The policy applies to all new facilities, and partially
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationHome Modification Loan Program Guide and Bid, Scope of Work and Contract Form
Home Modification Loan Program Guide and Bid, Scope of Work and Contract Form PART I: Guide and General Terms and Conditions The Home Modification Loan Program (HMLP) provides funding for necessary home
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Quantity Estimated Mobilization 1 LS
010100-01 Mobilization 1 LS 010500-01 Construction Surveying 1 LS 015000-01 Temporary Construction Fence 1 LS 029100-01 Tree Retention and Protection 1 LS 015150-01 Erosion and Sediment Control 1 LS Division
More informationEquine Barn LLC 213 Crescent Moon Way Canton, Ga Proposal
Equine Barn LLC 213 Crescent Moon Way Canton, Ga 30114 Proposal 2014 We hereby propose to provide all the materials and labor necessary to build a custom barn located in, Ga for. What is included in the
More informationBuilding Permit Submittal Requirements
CITY OF MONTE SERENO 18041 Saratoga-Los Gatos Road Monte Sereno, CA 95030 Phone (408) 354-7635 Fax (408) 395-7653 www.cityofmontesereno.org Building Permit Submittal Requirements NOTE: Submit three (3)
More informationRESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS
RESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS New Construction, Addition, or Alteration All plans submitted must be prepared, sealed, and signed by a Registered Nebraska Design Professional
More informationVolume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737
Volume 7 November 2009 Additions and Alterations to: Tinicum Elementary School Palisades School District Monthly Progress Report T&W Project 0737 Additions and Alterations to Tinicum Elementary School
More informationResidential Building Permits
Central Saanich Residential Building Permits When is a Building Permit Required? No person shall commence or continue any construction, alteration, reconstruction, demolition, removal, relocation, excavation
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationWater Damage on Construction Sites. A guide to loss prevention
Water Damage on Construction Sites A guide to loss prevention Water damage is the second most frequent cause of loss during building projects and represents a large percentage of Construction All Risk
More informationResidential Construction Minimum Required Inspections
Residential Construction Minimum Required Inspections The permit which you have been issued gives authority for work to commence. The stamped, approved plans, returned with this permit, shall be retained
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 21450» Total Man Hours on Project: 669792» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 7, 20 Page 1 CURRENT CONSTRUCTION ACTIVITIES East
More information2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationFRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6
PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationCITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS
CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS COMPLETE THROUGH REVISION #18 April 2009 CITY STANDARD DETAILS REVISIONS Revision No. Revision Date Effective Date 2 August
More informationCITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application
CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY
More informationCity of Roanoke. Commercial Permit Submittal Guidelines
City of Roanoke Commercial Permit Submittal Guidelines These guidelines are for information purposes only. The contractor is obligated to comply with all adopted codes and ordinances BUILDING INSPECTIONS
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationCITY STATE ZIP CODE TELEPHONE NUMBER (include area code) B. Owner or Lessee
CODE ENFORCEMENT SERVICES, INC. 215 West Main Street Phone: (248) 449-9902 Northville, MI 48167 Fax: (248) 349-9244 Authority: 1972 PA 230 Completion: Mandatory to obtain permit Penalty: Permit cannot
More informationConstruction Update. May 2016
Construction Update May 2016 Project Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor Statistics
More informationBYRON TOWNSHIP BUILDING PERMIT APPLICATION 8085 Byron Center Ave SW., Byron Center, MI /Fax
BYRON TOWNSHIP BUILDING PERMIT APPLICATION 8085 Byron Center Ave SW., Byron Center, MI 49315 616-878-9155/Fax 616-878-0699 Applicant to complete all items in Section I, II, III, IV, V Note: Separate applications
More informationOWNER-BUILDER? A HOMEOWNER S GUIDE TO BUILDING PERMITS AND INSPECTIONS FOR PROJECTS IN ARROYO GRANDE, CALIFORNIA
OWNER-BUILDER? A HOMEOWNER S GUIDE TO BUILDING PERMITS AND INSPECTIONS FOR PROJECTS IN ARROYO GRANDE, CALIFORNIA PREPARED BY: CITY OF ARROYO GRANDE BUILDING AND LIFE SAFETY DIVISION Under the Direction
More information