Volume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737

Size: px
Start display at page:

Download "Volume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737"

Transcription

1 Volume 7 November 2009 Additions and Alterations to: Tinicum Elementary School Palisades School District Monthly Progress Report T&W Project 0737

2 Additions and Alterations to Tinicum Elementary School Palisades School District Table of Contents Section Page(s) 1. Executive Summary 1 2. Progress Summary Phasing Summary 4 4. Analytics 5 5. Budget Report Photos Thomas & Williamson Table of Contents

3 Additions and Alterations to Tinicum Elementary School Palisades School District Let s Talk Turkey The new addition is nearly complete and the teachers and staff are already in the process of rapidly moving in and unpacking. Everyone, especially the students, are anxious to occupy their new digs. This is the first official move of students to their new classrooms; we have phased the project so that no class or group of students will be required to move more than once during the duration of the project. Since the last report the building has morphed from a completed shell to an architecturally complete school building. The installation of the interior finishes is complete, the architectural punch list has been issued and the trades are following on miscellaneous touch-ups and fine tuning. The mechanical systems have been completed and are operating under the A.T.C. system, although not completely tied into the PSD system at this time. Condensed versions of operation and maintenance trainings for the MEP systems were held for the owner s maintenance staff, once the overall building systems are complete and tied to the PSD monitoring programs formal training on the systems will be initiated. The General Contractor, although somewhat delayed by mother nature, has completed the finishes on the building and is nearing completion of the finish grading and seeding. Overall, Phase II the classroom addition, has been completed and is ready for class. In our first monthly report we discussed the importance of setting up the project right, establishing the project procedures and protocols, and building a positive team approach from the beginning. It has been evident through the duration of the project that this was in fact the case and was essential to the success of the project. At this point in the project, completing Phase II and preparing for Phase III, we are seeing the product of the relationships the contractors have established and the team approach they have adopted since May with the successful completion and turnover of Phase II one month ahead of schedule. Issues and concerns are discussed and coordinated between trades to arrive at the best and most advantageous outcome for both the owner and the contractors. This is carrying into the next phase as the coordination between trades to begin the demolition work, along with the removal and installation of the exterior walls systems, is complete and the contractors are ready to mobilize. With the majority of the submittals completed during the previous phases, the procurement and fabrication of materials is well underway with several of the long lead items already in storage or on site: i.e. mechanical and electrical equipment and fixtures, Kalwall panels, as well as floor coverings. There will be challenges and opportunities during the next couple of months, the team is anxious and ready to begin on this next phase. With the holiday coming up on the 24 th of November the 4 th and 5 th grade students will pack up their belongs and make the walk down the hall to their new slice of the Tinicum Elementary School. Once the TV s are installed, the books stowed away, the new desks moved in and the students in the building we will consider Phase II to be a success. Have a great Thanksgiving Holiday. Thomas & Williamson Executive Summary - Page 1

4 Additions and Alterations to Tinicum Elementary School Palisades School District Planned Work this Period The work planned for this period encompassed all of the activities to complete the architectural, mechanical and exterior work as scheduled to achieve the team goal of the November turnover. It was planned to complete and energize the completed building operations systems including all associated owner trainings. The remainder of the interior finishes were scheduled to be completed which included the installation of the floor coverings, white boards, lighting systems, and miscellaneous trims. The planned work for the exterior areas included: the completion of the site work and the exterior building finishes, including the standing seam roof fascia, gutters and down spouts. The site work encompassed completing the hardscape, all final topsoil and grading, and the hydro seeding. Also planned for the end of this period was the mobilization and beginning of the demolition work for the Phase 3 work. Work Accomplished this Period Much like the last period, the project maintained its momentum this month and the progress of the work during this period has been outstanding once again. The trades coordinated their installations and finishes in an organized strategy and are intended to meet the three goals established when the project team accelerated the schedule; substantial completion on November 9th, turnover on November 20th and begin Phase III on November 25th. The targets for the work plan put in place for this period were all accomplished as expected and the building is ready for occupancy. The mechanical systems are online and operating under the building automation system. The life safety systems consisting of the fire alarm and emergency generator are tested, tied into the existing building systems and have been activated and put on line. The architectural finishes are now complete and the punchlist is in progress with expected completion before occupancy. The completion of the work on the exterior of the building has lagged a bit from the projected schedule due to the weather but we are expecting all of the work to be completed prior to occupancy. The only exterior item that is still questionable at the writing of this report is whether the contractor manages to final grade and seed, a temporary solutions would be to lay hay and seed, this is weather dependant as the soils have to be dry to properly rock hound and grade prior to seeding. The first coordination meeting for Phase III was held this month and the prime contractors are scheduled and ready to begin the work as scheduled on November 25th. As areas become available early miscellaneous material removals, measurements for shop drawings and MEP reviews are proceeding as the team is ready to fully mobilize to attack this next area. Thomas & Williamson Progress Summary Page 2

5 Work Planned for Next Period The work planned for the next period is focused on quickly completing the demolition of the next phase, both architecturally and mechanically to begin to coordinate and install the new systems. The work completed during the first month of this phase is very important. In order to be successful we have to quickly complete the demolition and analyze the existing building and provide plans for unforeseen conditions. We have planned to complete the abatement and MEP disconnects over the Thanksgiving holiday so the demolition contractor can fully mobilize to knock out the demolition. It is planned to complete the structural modifications, required to complete the demolition of the interior walls, while beginning to install the new headers and openings for the revised door frames and wall openings. Also planned is the phased removal and replacement of the exterior panelized wall system with the new Kalwall system. Our goal and our plan are to be completely into an installation phase by the end of the first period. Thomas & Williamson Progress Summary Page 3

6 Additions and Alterations to Tinicum Elementary School Palisades School District Phase 2 & 3 The exterior site work is substantially complete, the rough grading, sidewalks, curbs and pavement patching have completed; final grading and seeding remain. The exterior building and site punchlist has been issued and work is ongoing. The interior finishes are substantially complete; all white boards, lockers, casework, DFH, carpeting and floor coverings have been installed. The Architectural punchlist has been issued and is nearing completion with a few items to follow-up on. The school has begun moving in and is going to begin classes in the new space following the Thanksgiving Holiday. The mechanical systems are in operation and under automated control. The owner operating and maintenance training was reviewed in a condensed version, a more thorough training will be completed when the whole system on line and a formal session can be held. Phase III coordination is underway and the contractors will mobilize to begin abatement and demolition beginning November 25 th. Thomas & Williamson Phasing Summary- Page 4

7

8 Additions and Alterations to Tinicum Elementary School Palisades School District Project Budget Summary Hard Costs Original Contract Value Change Orders Pending Ratification Approval Approved Chg Orders Current Contract Value Prime Contractors Haz. Material Construction $154, $0.00 $0.00 $ $155, General Construction $4,689, $0.00 $0.00 $33, $4,722, Plumbing Construction $618, $0.00 $0.00 $0.00 $618, HVAC Construction $1,986, $0.00 $0.00 $0.00 $1,986, Electrical Construction $1,094, $0.00 $0.00 $30, $1,124, Telephone/Data Wiring $123, $0.00 $0.00 $5, $128, Summary of Hard Cost $8,665, $0.00 $0.00 $70, $8,735, Basic Contingency $399, $0.00 $0.00 ($70,357.71) $329, Summary of Hard Cost Plus Basic Contingency $9,065, Thomas & Williamson Budget Report - Page 6

9 Soft Cost Budget Budget Adj Amts Less Expended Remaining Budget Design Fees Architect's Fees on Structure $682, $6, $689, $0.00 Asbestos Abatement Designer $39, ($29,631.00) $9, $0.00 Consultant - Extra work for township $0.00 $23, $23, $0.00 Total Design Fees $721, $ $722, $0.00 Movable Fixtures & Equipment Movable Fixtures and Equipment $228, $0.00 $24, $203, Architect's Fees on MF&E $0.00 $0.00 $0.00 $0.00 Total Movable Fixtures & Equipment $228, $0.00 $24, $203, Site Cost Sanitary Sewage Disposal $0.00 $0.00 $0.00 $0.00 Tap-In Fees or Excess Capacity Fee $0.00 $0.00 $0.00 $0.00 Real Estate Appraisal Fees $0.00 $0.00 $0.00 $0.00 Total Site Cost $0.00 $0.00 $0.00 $0.00 Construction Related Cost Geotech Rpt/Borings & Sub Surface $4, $0.00 $4, $0.00 Construction Testing $13, $0.00 $2, $11, Non-ACM Air Monitoring $7, $0.00 $0.00 $7, Building Permits/Approval Fees $17, $33, $51, $0.00 Attorney Fees $10, $14, $25, $0.00 Advertising $5, ($3,848.92) $1, $0.00 Asbestos Abatement Monitoring $26, ($8,777.13) $1, $16, Construction Manager Fee $387, $0.00 $214, $172, Construction Manager Fee for Rebid $0.00 $19, $19, $0.00 Traffic Study $ $6, $6, $0.00 Blueprinting $15, ($1,299.68) $11, $1, Land Survey $6, $0.00 $6, $0.46 Building Survey $0.00 $0.00 $0.00 $0.00 Moving and Rentals $19, $0.00 $14, $4, Miscellaneous Non-Budgeted Cost $0.00 $13, $13, $0.00 Total Construction Related Cost $514, $73, $374, $213, Financing Cost Total Financing Cost $183, $0.00 $0.00 $183, Total Financing Cost $183, $0.00 $0.00 $183, Summary Soft Cost $1,647, $73, $1,120, $600, Additional Contingency $74, ($67,126.67) $0.00 $7, Summary of Soft Cost + Contingency $1,722, $6, $1,120, $608, Total Project Value (Hard + Soft Cost) : $10,787, Thomas & Williamson Budget Report - Page 7

10 Project Contingency Spending The charts below illustrate the impact of the change order spending on the Project Contingency. The Project Contingency was established at $399,854 within the total Project Budget of $10,787,927. Upon receipt of bids and the placement of contracts, T&W apportioned the available Project Contingency to the individual prime contracts on the following pages. The amount shown above the highest blue "Projected" bar is calculated by dividing the original value of the contract by the total original value of all contracts and by multiplying the Project Contingency by that percentage. That amount (for each contract) is then allocated in uniform increments in order to form a Baseline to measure the solvency of the Project Contingency by comparing the Actual Change Orders placed (red bars) versus the Baseline. $420,000 $399,000 $378,000 $357,000 $336,000 $315,000 $294,000 $273,000 $252,000 $231,000 $210,000 $189,000 $168,000 $147,000 $126,000 $105,000 $84,000 $63,000 $42,000 $21,000 $0 All Contracts Projected Actual Thomas & Williamson Budget Report - Page 8

11 $220,000 General Contract $198,000 $176,000 $154,000 $132,000 $110,000 Projected Actual $88,000 $66,000 $44,000 $22,000 $0 $7,200 $6,480 $5,760 $5,040 $4,320 $3,600 $2,880 $2,160 $1,440 $720 $0 -$720 Asbestos Abatement Projected Actual $30,000 $27,000 $24,000 $21,000 $18,000 $15,000 $12,000 $9,000 $6,000 $3,000 $0 Plumbing Contract Projected Actual Thomas & Williamson Budget Report - Page 9

12 $92,000 $82,800 $73,600 $64,400 $55,200 $46,000 $36,800 $27,600 $18,400 $9,200 $0 HVAC Contract Projected Actual $51,000 $45,900 $40,800 $35,700 $30,600 $25,500 $20,400 $15,300 $10,200 $5,100 $0 Electrical Contract Projected Actual $5,800 $5,220 $4,640 $4,060 $3,480 $2,900 $2,320 $1,740 $1,160 $580 $0 Telephone/Data Wiring Contract Projected Actual Thomas & Williamson Budget Report - Page 10

13 Change Orders Pending Board Ratification The Administration has approved the issue of the following change orders to the construction contracts for the following school projects. The complete change order document is attached to the Official Minutes. None Pending Board Approval The Administration recommends approval of the following change orders to the construction contracts for the following school projects. The complete change order document is attached to the Official Minutes. None Thomas & Williamson Budget Report - Page 11

14 Additions and Alterations to Tinicum Elementary School Palisades School District Beginning of classroom casework installation. Casework and finishes nearing completion, ready for carpet. Classroom complete for occupancy. Classroom complete for occupancy. Thomas & Williamson Photos Page 12

15 Drywall complete, locker bases in place. Lockers, MEP, & sills complete, ready for carpet. Corridor finishes complete and ready for occupancy Corridor finishes complete and ready for occupancy Thomas & Williamson Photos Page 13

16 Sub grade in progress for beginning of curb installation South elevation of building exterior East elevation of substantially complete exterior trades. West elevation of substantially complete exterior trades. Thomas & Williamson Photos Page 14

BOYERTOWN AREA SENIOR HIGH SCHOOL

BOYERTOWN AREA SENIOR HIGH SCHOOL BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 10 November / December 2015 Construction Manager D Huy Engineering, Inc. Architect

More information

BOYERTOWN AREA SENIOR HIGH SCHOOL

BOYERTOWN AREA SENIOR HIGH SCHOOL BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 11 January 2016 Construction Manager D Huy Engineering, Inc. Architect KCBA Architects

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

PAULDING COLLEGE & CAREER ACADEMY

PAULDING COLLEGE & CAREER ACADEMY PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

Application for Commercial Plan Review and Building Permit. Address:

Application for Commercial Plan Review and Building Permit. Address: City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350

More information

TRIAD ENGINEERING CONSULTANTS, INC.

TRIAD ENGINEERING CONSULTANTS, INC. TRIAD ENGINEERING CONSULTANTS, INC. 2638 Willard Dairy Rd Providing High Point, NC Suite 100 Plumbing, Mechanical and 27265 (336) 454-0225 Electrical Engineering Services Since 1984 admin@triadengmep.com

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Home Building Planner

Home Building Planner Home Building Planner Created by PHO For YOU! Please accept this guide with our compliments. We have developed this planner based upon prior projects we have completed. While every situation will have

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

LLANO ISD SCHOOL BOARD MEETING. January 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016 LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS

More information

Owen County School District

Owen County School District Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Building & Grounds Committee Meeting Tuesday, 13 September Minutes

Building & Grounds Committee Meeting Tuesday, 13 September Minutes Building & Grounds Committee Meeting Tuesday, 13 September 2016 Minutes Present: Johnson, Laverghetta (joined at 8:00 am) and McCarthy. Also present: Kettrich, Koch, Prior, Crolius, Marsenison. Mrs. Johnson

More information

New Hall High School Project Summary Report to the Board of Education June 3, 2015

New Hall High School Project Summary Report to the Board of Education June 3, 2015 New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

Project Update. Facilities Committee Meeting

Project Update. Facilities Committee Meeting Lower Merion School District Project Update Close-Out Phase for Gladwyne Elementary School (Temp. CR s and Add ns/ Renov s) Penn Valley Elementary School (Add ns/ Renov s) Bala Cynwyd Middle Schools (Add

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM GH Phipps Construction Co. OAC 17D5780 - Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, 2017 10:00 AM Meeting ID 003 Subject Weekly OAC Meetings Location 6000 Spine Rd #101,

More information

NEW NORWOOD HIGH SCHOOL

NEW NORWOOD HIGH SCHOOL TOWN OF NORWOOD NEW NORWOOD HIGH SCHOOL MONTHLY PROGRESS REPORT MARCH 2010 Prepared by: 266 Main Street Suite 31A Medfield, MA 02052 www.compasspminc.com Table of Contents: I. Executive Summary II. III.

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

ADDENDUM #1 TO ALL PROSPECTIVE BIDDERS: SUBJECT: IFB # \ Science Labs Conversions Luther Jackson Middle School, Falls Church, VA

ADDENDUM #1 TO ALL PROSPECTIVE BIDDERS: SUBJECT: IFB # \ Science Labs Conversions Luther Jackson Middle School, Falls Church, VA TO ALL PROSPECTIVE BIDDERS: ADDENDUM #1 SUBJECT: IFB # \17-020 Science Labs Conversions Luther Jackson Middle School, Falls Church, VA BID DUE DATE: May 17, 2017 May 15, 2017 THIS ADDENDUM IS SUPPLEMENTARY

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2 OMAHA BASEBALL STADIUM May 21, 2009 Report No. 2 METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

Procedure Yes; No; greater than

Procedure Yes; No; greater than Procedure 1. Project manager (PM) notifies facilities information coordinator of forecasted substantial completion date one month prior to reaching substantial completion. 2. PM completes the project information

More information

Board Report. Bond Program Update:

Board Report. Bond Program Update: March 2014 Bond website: www.pcc.edu/bond Bond Program Update: Winter term is quickly coming to an end and as spring term approaches we have more buildings and areas opening for use for students and staff.

More information

COMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018

COMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018 COMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018 CONSTRUCTION CODES The City of Colleyville has adopted and enforces the following codes which are applicable to building construction activities within the

More information

SOLICITATION ADDENDUM

SOLICITATION ADDENDUM CITY OF PALM BEACH GARDENS PURCHASING DEPARTMENT SOLICITATION ADDENDUM Addendum No. 1 DATE: January 30, 2018 TO: SOLICITATION NO.: TITLE: OPENING DATE: All Potential Bidders ITB2018-097GF Prefabricated

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal # Issued: May 23, 2011

ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal # Issued: May 23, 2011 ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal #43-11 Issued: May 23, 2011 This Addendum forms part of the original document marked: Portsmouth City Hall Boiler Plant

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

Project Status Report Property and Finance Committee Meeting August 6, 2013

Project Status Report Property and Finance Committee Meeting August 6, 2013 Westmont Hilltop School District Project Status Report Property and Finance Committee Meeting August 6, 2013 S. Dwight Knouse II, AIA, LEED AP Russell D. Greaser, Project Manager Matthew T. Filan, PE,

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge

More information

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School

Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School ADDENDUM No. 002 For Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School DALLAS INDEPENDENT SCHOOL DISTRICT September 24, 2014 The following items modify the Project

More information

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings

More information

CRC Item No. 6 - February 16, Construction Update

CRC Item No. 6 - February 16, Construction Update CRC Item No. 6 - February 16, 2018 Construction Update Project Overview Western Zone Grid Line 1-10 Central Zone Grid Line 10-20 Eastern Zone Grid Line 20-35 2 Recent Activity 3 Recent Activity 4 Construction

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

EcoSteel Pre-Engineered Steel Buildings provide the world s most advanced Eco friendly construction systems.

EcoSteel Pre-Engineered Steel Buildings provide the world s most advanced Eco friendly construction systems. System Overview EcoSteel Pre-Engineered Steel Buildings provide the world s most advanced Eco friendly construction systems. In our ever extensive product line, we offer solutions for Commercial, Residential,

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

PROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction

More information

PROJECT STATUS REPORT Coronado Elementary School - - Reconstruction Period Ending: 5/31/2015 Scope: Reconstruction Project Construction Status: Architect: WLC Architects Project Manager: Project Engineer:

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Longmeadow High School Section 12.1

Longmeadow High School Section 12.1 Longmeadow High School Section 12.1 Schematic Design 12 Total Project Budget and MSBA Form 3011 The attached Total Project Budget and Form 3011 includes all costs associated with Administrative, Architecture

More information

Ubuildit. Construction Project Budget for Date Prepared wholesale retail

Ubuildit. Construction Project Budget for Date Prepared wholesale retail Ubuildit Construction Project Budget for Date Prepared wholesale retail Buyer: Address: City/St: Living Area SF Frame Ground Floor 170 Living Area SF Frame 2nd Floor 0 189.666667 total veneer total veneer

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single

More information

Saginaw Historic Preservation Benefits, Requirements and Guidelines

Saginaw Historic Preservation Benefits, Requirements and Guidelines Saginaw Historic Preservation Benefits, Requirements and Guidelines The Corning Mansion Saginaw, Michigan Purpose of Historic Preservation The Purpose of historic preservation in the city of Saginaw is

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

FREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018

FREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018 FREMONT UNIFIED S C H O O L D I S T R I C T Thornton Middle School Conversion Quattrocchi Kwok Architects Sept 26, 2018 1 Transforming Thornton Incoming 6 th graders in year 2021/22 Student population

More information

Facilities and Planning Department Measure E Update March 2017

Facilities and Planning Department Measure E Update March 2017 State Seismic Mitigation Program (SSMP) The District s application for SSMP funds for Horace Mann Building A will be reviewed for approval by the State Allocation Board at its next scheduled meeting on

More information

Capital Projects Progress Report. September Presented by

Capital Projects Progress Report. September Presented by Capital Projects Progress Report September 2018 Presented by October 5, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York

More information

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages TABLE OF CONTENTS VOLUME 1 DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages SCHEDULE OF DRAWINGS...... 1 PROJECT PERSONNEL & DIRECTORY......

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

Facilities Planning & Management

Facilities Planning & Management Facilities Planning & Management 1100 North Grand Avenue Walnut, CA 91789 909-274-4850 www.mtsac.edu CONSTRUCTION QUARTERLY UPDATE 9/1/2016 PROJECT MANAGER: Gary Gidcumb / Fernan Siocon September 1, 2016

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information