Capital Projects Update

Size: px
Start display at page:

Download "Capital Projects Update"

Transcription

1 Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being pulled in the building along with HVAC equipment. In the central classroom, building sprinkler, plumbing, electrical, and insulation is continuing in preparation for sheet-rock. The south classroom is not as far along as all workers are working from the north building to the south. This allows us to keep schedule while using workers who are familiar with the previous work. This also reduces the learning curves and adds to the quality of the work and completed project. Concrete is being prepped and poured for the connector corridor between the classroom buildings. Eastside of the site: Steel stud framing continues in the kitchen, gyms, and various classrooms and the exterior sheathing is being installed on various walls. Sprinkler, plumbing, and electrical are keeping pace with the framing. Roof installation proceeds as weather permits over the main gym and the upper floors with hopefully enough breaks to proceed to the central core by the holidays. This may be optimistic as only 4 days in November were dry enough to proceed with roofing. The current cold but dry weather is helping get the roofing completed. Site work: The retaining wall between the tennis courts and the softball fields is completed and once it's waterproofed it can be backfilled. The east fire road retaining walls are nearly complete and the generator enclosure should start soon. The retaining wall and seating around the north end of the track has been excavated and waiting for concrete forming. Earthwork and slab preparation has started on the east side of the grandstand by taking advantage of the season s end of the fall sports program. Capital Projects Department Steve Crawford Director Mike Archer Debbie Massaro Tom Mullins Royce Nourigat Ladd Stejskal Phone: Fax: Aerial view of Issaquah High School, November 2009.

2 Page 2 Issaquah High School Reconstruction View of three classroom wings and west stairwells. South wall of south classroom building. Two-level circulation corridor connecting the east end of the classroom wings. View of the south and central classroom wings from the east. Courtyard, classrooms on the left with Commons, Library and Gym to the right. North side of construction.

3 December 2009 Page 3 Issaquah High School Reconstruction Courtyard area between classroom wings. Attendance check-in hallway in north building has been partially primed. North wing classroom gyp board nearing completion. Painting has started in some rooms. North wing classroom. Central wing classroom ready for installation of gyp board. South wing classroom framing complete, installation of utilities underway.

4 Page 4 Issaquah High School Reconstruction Library Exterior masonry installation has begun. Main Gym with upper Auxiliary Gym in background. View from Weight Room. View of track and field from third floor classroom.

5 December 2009 Page 5 Skyline High School Expansion and Alteration Site: Asphalt for the driveway and drop-off/pick-up loop has been placed at the new entrance. Concrete walkway and plaza to main entrance is completed. Landscaping is underway. NW & SW Areas: Rooms are nearly complete. Cleaning company is in the process of cleaning all the spaces. Installation of stairway handrails is approximately 80 percent completed. HVAC units are in and the direct digital control system is approximately 85 percent. Scheduled start-up of the HVAC units is set the week of December 7 th. Fire alarm testing is scheduled for week of December 7 th. Punch list is scheduled for week of December 1 st. Commons: Rubber tile is completed at the upper floor. Ceiling grid, tiles and light fixtures are nearly complete at both floors. Stairwell handrails are going in. Casework in DECA store is complete. Punch list is scheduled for week of December 1 st. Gymnasium, Locker Room & Weight Room: Electrical and Mechanical rough-in is complete in the three areas. Windows for the gymnasium and weight room are installed. Interior sheetrock for the gymnasium is complete. Taping and mudding has begun. Ductwork is approximately 50 percent complete in the mechanical room. Roofing is 90 percent complete at the weight room. View of new drop-off/pick-up drive towards the main entrance. Classrooms, Admin and Counseling to the left and Weight Room to the right. Main entrance doors on left with entrance to new reception area nearing completion. Entrance to reception area. Reception desk complete. Store-front and doors nearly complete.

6 Page 6 Skyline High School Expansion and Alteration Expanded upper level Commons looking back into the existing Commons. View from existing Commons into the expanded area. Main floor expanded Commons with new DECA store to the rear. View from the expanded Commons showing the upper floor classroom corridor and new stair. Third floor corridor. Small group area to left with windows at the end of the corridor. Lower level, central area connection of new classroom wing and existing corridor. New stair extends up to the third floor.

7 December 2009 Page 7 Skyline High School Expansion and Alteration Large windows at the new north stairwell brighten the interior and open up views. Mid-level of new central stair. Small group area beyond stair and science lab to right. Newly installed carpet in new rectangular classroom. New Science Lab New Main Gym Weight Room

8 Page 8 May Valley Service Center A Pod Replacement Building E basement walls have been poured and walls framed. Backfilling of large walls is underway. Building F is fully framed, weathered-in and ready for slab pour. Storm pond expansion and liner work to begin shortly. Maywood Middle School Design development is over 50% complete. Design team met with King County and completed the Voluntary Pre- Application Meeting. Design team is now following the direction of King County in preparation of the formal Pre- Application Meeting which is scheduled in early January Elementary #15 The contractor continues to make good progress with the work. The north classroom wing is now dried in with electrical rough-in nearly complete. Drywall is slated to start in the next week. In comparison, drywall started on the Grand Ridge project the beginning of April. Mechanical rough-in has begun. The south classroom wing is framed and rough-in work has started. Steel floor framing is complete at the library core of the building. Metal will go down in the next week with the concrete deck to follow. Hot mop and metal roofing are proceeding to allow insulation and sheetrock in dry conditions. Roof beams for the commons and gym are scheduled to arrive next week. Masonry work in these areas is complete and ready for the roof structure. View of north classroom wing to right with elevator masonry core work proceeding left. Library and central core area with north classroom wing beyond.

9 December 2009 Page 9 Elementary #15 View from the southeast with gym to left and classroom wings beyond. View from upper floor, north wing classroom. Rain garden will be located where the temporary pond (ice rink) is located with forested background. View from upper floor, south wing activity areas. North wing, lower floor classrooms. Utility work complete, ready for insulation and drywall. Second floor, south wing view toward playfield. Sand playfield

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

Applying for Permits to build a new house in Linn County

Applying for Permits to build a new house in Linn County Planning & Development Linn County, Iowa Building Division Linn County Building Code Residential Guidelines Single Family Dwellings Page 1 of 4 Applying for Permits to build a new house in Linn County

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene March 2, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Final Paint in B6 Corridors. Completed Final Clean in CL1 Units. Continued Signing Off Punch List Items in the West Zone. Continued

More information

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No Laker Hall Program Study Intercollegiate Athletics Preferred Concept & Project Phasing SUCF Project No. 101009 26 January 2017 Agenda Preferred Concept - Existing Site Plan - Existing Floor Plans - Space

More information

Yardmen Arena Expansion & Renovation Project Update

Yardmen Arena Expansion & Renovation Project Update For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

The Homeowner s Building Application Checklist for Constructing a Residential Addition

The Homeowner s Building Application Checklist for Constructing a Residential Addition The Homeowner s Building Application Checklist for Constructing a Residential Addition This checklist provides homeowners a summary of the Building Permit submission requirements for constructing a residential

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri

More information

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER SUMMARY OGDENSBURG, NY The New York Main Street program (NYMS) is administered by the Office of Community Renewal (OCR) under the direction of the New York State Housing Trust Fund Corporation (HTFC).

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

BuildingAdvisor.com Estimating Checklist

BuildingAdvisor.com Estimating Checklist BuildingAdvisor.com Estimating Checklist GENERAL REQUIREMENTS Plans and specifications Plan review Permits: Zoning, building, environmental, other Survey Impact fee Administrative costs Financing costs

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

St. Germain Facility Study

St. Germain Facility Study Prepared for: Town of St. Germain Presented on: April 4, 2107 Prepared by: Funktion Design Studio, LLC 207 Windtree Drive Wausau, WI 54401 207 Windtree Drive Wausau, WI 54401 Melody 715-571-8122 Rick 920-379-7133

More information

Morehouse School of Medicine

Morehouse School of Medicine /0/00 Print /0/00 00 Campus General Building ID Built 7098 98 Renovated Gross Square Feet Building Type Current Replace Value 00 - ACADEMIC FALITIES $ FC/QI (%) > 00.00 Electrical Lighting upgrades/retrofits

More information

Section 4 - Design and Construction Overview

Section 4 - Design and Construction Overview Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene January 19, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Carpet & Base in B6 Corridor. Completed 1 ST Coat of Paint in B4 Corridor. Completed 2 ND Coat of Paint in C3 Units Completed

More information

LOVEJOY Independent School District

LOVEJOY Independent School District Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $

More information

Toronto Community Housing Executive Summary 2016/2017. BCA Report. Sample House High FCI

Toronto Community Housing Executive Summary 2016/2017. BCA Report. Sample House High FCI BCA Report Porfolio Development Size Construction TCHC - All Op Units Scattered Units (CHU 20),005 Sq.Ft. 925 Floor Above Grade 2 Divisional Units Page of 43 Description This dwelling unit is a detached

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

Residential Building Inspections

Residential Building Inspections Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved

More information

Detached Garages and Building Permits. 1 and 2 Family Dwellings

Detached Garages and Building Permits. 1 and 2 Family Dwellings Detached Garages and Building Permits 1 and 2 Family Dwellings Why do I need a permit? The City of Minneapolis adopts the State of Minnesota Building Code (MNSBC) and its associated state statutes and

More information

Successful Home Contracting

Successful Home Contracting Successful Home Contracting How to save thousands of dollars and get a better quality home by acting as your own contractor. Return to Home-Building-Answers.com Lesson Two An Overview of the Home Building

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved. Sri Ganesha Temple HTNT Construction Update (June, 2016) With Lord Ganesha s Blessing We start everything Architect View of the Ganesha Temple at Finish Sri Ganesha Temple HTNT Construction Milestones

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule C OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS Schedule "C" Building Code All Ready To Move (RTM) Homes are built according to the Alberta Building Code and National Building Code. Please note that

More information

M-DCPS DESIGN CRITERIA Table of Contents

M-DCPS DESIGN CRITERIA Table of Contents M-DCPS DESIGN CRITERIA Table of Contents TITLE Page No. Division 0: General Considerations 1.1 General... 0-1 1.2 Sustainability... 0-2 1.3 Site (Rev. 6/20/16)... 0-3 1.4 Buildings (Rev. 1/29/16)... 0-6

More information

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER THE CORPORATION OF THE MUNICIPALITY OF SOUTH HURON 322 Main Street South, P.O. Box 759, Exeter, Ontario N0M 1S6 PHONE: (519) 235-0310 FAX: (519) 235-3304 TOLL FREE: 1-877-204-0747 WEBSITE: www.southhuron.ca

More information

Application for Commercial Plan Review and Building Permit. Address:

Application for Commercial Plan Review and Building Permit. Address: City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT SECTION 00510 CONTRACTOR S REQUISITION FOR PAYMENT 1.1 The Standard Monthly Contractor s Requisition for Payment,

More information

Davis Frame Co., Inc. Construction Budget Considerations

Davis Frame Co., Inc. Construction Budget Considerations Davis Frame Co., Inc. Construction Budget Considerations ITEM BID 1 BID 2 BID 3 MISCELLANEOUS COSTS Surveying Building Permit Engineering Fees Interest on Construction Loan Property Taxes Hazard & Liability

More information

The Inspection Process. Waxhaw N.C.

The Inspection Process. Waxhaw N.C. The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"

More information

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form. Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene October 6, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Hardscapes East of Building C. Completed Building D Dumpster Pad. Completed Brick on Site Wall North of Building D. Completed

More information

Structural Inspection

Structural Inspection General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

STRUCTURAL ASSESSMENT OBSERVATION REPORT

STRUCTURAL ASSESSMENT OBSERVATION REPORT Consulting Engineers THORSON BAKER & Associates, Inc. 3030 West Streetsboro Road (330) 659-6688 phone Richfield, Ohio 44286 (330) 659-6675 fax www.thorsonbaker.com STRUCTURAL ASSESSMENT OBSERVATION REPORT

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST This list is provided as a guide to help you understand the information that must be contained on the construction drawings. This list is not all-inclusive of all building codes but is used as a general

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

Built to Order. Stile. Frames. Section Contents. Profiles. Elevations. Double Egress Frames Pocket Frames

Built to Order. Stile. Frames. Section Contents. Profiles. Elevations.  Double Egress Frames Pocket Frames Frames Section Contents General Frame Construction Profiles F-1.0 Typical Jamb & Sill Profiles F-2.0-2.1 Frame Welding Elevations F-3.0 Frame Elevations F-4.0-4.2 Custom Frame Elevations Panel Types +

More information

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS STANDARD FEATURES LIST Foundation Concrete walls 4 concrete floor slab Interior basement unfinished Standard nine foot foundation walls

More information

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210)

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210) Quality Inspection 8618 London Heights San Antonio, TX 78254 Phone: (210) 240-0476 PRE DRYWALL INSPECTION REPORT Prepared For: DELETED (Name of Client) Concerning: DELETED, San Antonio, TX 78258 (Address

More information

PROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California

PROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California PROGRAM COST MODEL for PEER Tall Buildings Study Concrete Structural Option Los Angeles, California March 8, 2010 PEER Tall Buildings Study Concrete Structural Option March 8, 2010 CONTENTS Page Nos. Overall

More information

EVALUATION AND ASSESSMENT TROY ELEMENTARY SCHOOL 44 SCHOOL STREET TROY, NEW HAMPSHIRE

EVALUATION AND ASSESSMENT TROY ELEMENTARY SCHOOL 44 SCHOOL STREET TROY, NEW HAMPSHIRE FINAL REPORT EVALUATION AND ASSESSMENT TROY ELEMENTARY SCHOOL 44 SCHOOL STREET TROY, NEW HAMPSHIRE FOR MONADNOCK SCHOOL DISTRICT SAU #93, SWANZEY, NEW HAMPSHIRE JUNE 30, 2017 Monadnock School District

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

Home Building Planner

Home Building Planner Home Building Planner Created by PHO For YOU! Please accept this guide with our compliments. We have developed this planner based upon prior projects we have completed. While every situation will have

More information

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017 Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (05/15) 02050 Demolition (Create for each existing building)

More information

1 AND 2 FAMILY DWELLING REQUIREMENTS

1 AND 2 FAMILY DWELLING REQUIREMENTS PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Budget Estimate Basic Tenant Improvement

Budget Estimate Basic Tenant Improvement Building work rules, conditions and insurance: 1. Review the work rules. If they are not available no budget should be provided. 2. Hours available for construction 3. Insurance requirements 4. Entities

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

TERMINAL BUILDING EVALUATION

TERMINAL BUILDING EVALUATION TERMINAL BUILDING EVALUATION 1.0 INTRODUCTION This report evaluates the existing Terminal Building at Frederick Municipal Airport (FDK) to determine the suitability of the building for continued use as

More information

FLOORPLAN /ELEVATION SQ.FT. BDRM BATHS GARAGE BASE PRICE

FLOORPLAN /ELEVATION SQ.FT. BDRM BATHS GARAGE BASE PRICE FLOORPLAN /ELEVATION SQ.FT. BDRM BATHS GARAGE BASE PRICE PROVIDENCE Prairie 1713 2 + Den 2 2 $341,400 Country Cottage 1713 2 + Den 2 2 $343,400 Craftsman 1713 2 + Den 2 2 $349,400 2 bedrooms + den or optional

More information

MADISON HIGH SCHOOL // Executive Summary

MADISON HIGH SCHOOL // Executive Summary MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN. CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS AUBURN. GARDEN OF MEMORY AUBURN MEMORIAL STUDENT AFFAIRS HOLCOMBE NORTON PARTNERS LANDSCAPE SERVICES The Auburn Memorial wall includes excerpts from the Auburn

More information

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50 Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (01/04) 02050 Demolition (Create for each existing building)

More information

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC. 320-226.5189 www.101developmentresources.com While every attempt has been made to insure the correctness of this handout, no guarantees are made to its accuracy

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

Building Construction Occupations

Building Construction Occupations Job Ready Assessment Blueprint Building Construction Occupations Test Code: 2011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge

More information

UPPER ARLINGTON SCHOOLS 2015 FACILITIES ASSESSMENT. Windermere Elementary School Physical Assessment

UPPER ARLINGTON SCHOOLS 2015 FACILITIES ASSESSMENT. Windermere Elementary School Physical Assessment 2015 FACILITIES ASSESSMENT Windermere Elementary School Physical Assessment December 8, 2015 2015 FACILITIES ASSESSMENT WINDERMERE ELEMENTARY SCHOOL Executive mary The Moody Nolan/Korda/EMH&T/Turner team

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Single Family Detached home submittal Workbook

Single Family Detached home submittal Workbook 1880 Main Street, Centerville, Minnesota 55038 (651) 429-4750 Fax (651) 792-7949 Single Family Detached home submittal Workbook Site Address: Contractor Name: (print) Contractor Phone #: Contractor E-mail:

More information

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath Trade Package Base Bid P and P BOND Alternate #1: drop off canopy Alternate #2: bike rack canopies Alternate #3: courtyard Alternate #4 Unit Door Alternate #5 Solid Surface Alternate #6A Bath Alternate

More information

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements 700 Paris Ave. PO Drawer 9 Port Royal, SC 29935 Application for Permit - P O Drawer 9, Port Royal South Carolina Permit

More information

BUILDING PERMIT APPLICATION PACKAGE

BUILDING PERMIT APPLICATION PACKAGE BUILDING PERMIT APPLICATION PACKAGE NOTICE TO BUILDING PERMIT APPLICANTS In addition to completed applications forms, the following documentation is required to accompany all building permit applications

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

SANDTOWN CROSSING PROFESSIONAL OFFICE PARK Atlanta, GA

SANDTOWN CROSSING PROFESSIONAL OFFICE PARK Atlanta, GA Atlanta, GA LOCATED AT CAMP CREEK PARKWAY AND CAMPBELLTON ROAD For Sale or Lease Single units start at 1,176sf and can be combined to exact specification Custom Designed Medical and Professional finishes

More information