BID AWARD: PROP. 39 YEAR 5 20 L.E.D. LIGHTING RETROFIT
|
|
- Joleen Griffith
- 5 years ago
- Views:
Transcription
1 SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting May 14, 2018 BID AWARD: PROP. 39 YEAR 5 20 L.E.D. LIGHTING RETROFIT Status: Presented by: Action Byron Woods Dean, Facilities Issue The District is requesting that the Board of Trustees award Clear Blue Energy Corp of San Diego, CA the bid for the Prop. 39 Year 5 L.E.D. Lighting Retrofit project. Background In November 2012, Proposition 39, the Clean Energy Jobs Act of 2012, was voted into law. This initiative provides the California Community Colleges and K-12 systems five (5) annual budget allocations to be used to develop energy savings and create energy related jobs. For , the District received $332,349 and was granted approval in February 2018 to proceed with the fifth year of energy efficiency improvement projects. The District has elected to pursue two separate projects: 1) Sequoia Building HVAC Upgrades and 2) LED Lighting Retrofit. Funds allocated to the Year 5 scope of work are required to be expended by the District by June 30, In addition to the Year 5 funds, an additional $156k is being carried forward from Year 4 due to lower than expected bid results. The total funds available for both Year 5 projects is $488,927. The Sequoia Building HVAC Upgrades project was awarded at the April 2018 board meeting total project cost is approximately $177k. This provides an estimated $312k available for the LED Lighting Retrofit project. The Prop. 39 Year 5 L.E.D. Lighting Retrofit project entails an L.E.D. lighting retrofit of interior and exterior lighting upgrades on the Visalia, Hanford and Tulare campuses. The base bid scope of work includes interior upgrades at the Ponderosa lecture hall and Hanford Education classrooms, as well as exterior upgrades at the Visalia track and field, pool complex, tennis courts and Tulare parking lot, walkways and buildings. TETER Architects & Engineers has been contracted by the District to prepare the bid documents and provide construction oversight for this project and will verify that new lighting conditions meet or exceed the existing lighting levels in all locations in the scope of work. This project is scheduled to be completed June through August A bid opening was conducted on March 27, Four (4) bids were received and
2 opened for this project, all of which exceeded the maximum allowable construction budget for this project ($285k). The District elected to reject all bids due to budgetary limitations. The scope of work was reduced, removing the Tulare exterior building lighting from the project, and the project was reissued to bidders. On May 3, 2018, four (4) bids were received and opened for this project. The lowest responsive bidder was Clear Blue Energy Corp of San Diego, CA with a Base Bid of $104, The Bid Tabulation sheet and Bid Proposal are attached for reference. The total bid amount for this project, including the Base Bid plus all Alternate Bid Items, is $303, Due to the significant range in bid amounts, the Dean of Facilities contacted three of the four bidders to discuss the results. It was determined that the two low bidders proposed a lighting manufacturer substitution request during bidding as permitted in the project specifications the request was approved by TETER A&E and information was issued to all bidders during the bidding period via Addendum No. 1. All bidders acknowledged receipt of Addendum No. 1 on their bid proposal forms, however, the two higher bidders elected not to get pricing from those manufacturers. The Dean of Facilities has communicated directly with Jim Kelly, COO of Clear Blue Energy Corp, and his supporting staff to confirm that their bid is valid and that they clearly understand the entire scope of work, including scheduling restrictions. No items of concern were presented in these and phone conversations. In addition, the bonding company was validated and expressed no concerns with the contractor s work history. To further reinforce the above information, the Dean of Facilities also reached out to Davis Joint Unified School District DJUSD experienced a similar situation with Clear Blue Energy Corp s bid being significantly lower than others. That project is in the project closeout phase and the district has experienced no complains related to the contractor s performance. Recommended Action It is recommended that the Board of Trustees award the Base Bid and Alternate Bid Items #1, #2 and #4 in the amount of $282,248.38, for the Prop. 39 Year 5 L.E.D. Lighting Retrofit project to Clear Blue Energy Corp of San Diego, CA.
3 BID TABULATION 5/3/2018 Prop 39 Year 5 L.E.D. Lighting Retrofit (Rebid) PROJECT NAME: Prop 39 Year 5 L.E.D. Lighting Retrofit (Rebid) Bidder Name Base Bid (determines low bidder) Alt Bid #1 Alt Bid #3 Alt Bid #3 Alt Bid #4 Total Bid Proposal Addendum Bid Alternates Bid Security Subcontractor List Non-Collusion Affidavit Worker's Comp Cert Prevailing Wage Cert Verification of DIR Clear Blue Energy Corp. Fluoresco Services, LLC $ 104, $ 85, $ 76, $ 20, $ 15, $ 303, x x x x x x x x x $ 168, $ 119, $ 113, $ 21, $ 21, $ 445, x x x x x x x x x Contra Costa Electric $ 223, $ 143, $ 134, $ 32, $ 25, $ 559, x x x x x x x x x American Incorporated $ 232, $ 147, $ 155, $ 36, $ 32, $ 605, x x x x x x x x x Recommended Contractor: Clear Blue Energy Corp. Recommended Contract Amount: Base Bid $ 104, Alt #1 $ 85, Alt #2 $ 76, Alt #3 $ - Alt #4 $ 15, TOTAL $ 282,248.38
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
BID AWARD: 16 COS HANFORD EDUCATIONAL CENTER MODULAR CLASSROOM (SITE WORK)
COLLEGE OF THE SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting July 10, 2017 BID AWARD: 16 COS HANFORD EDUCATIONAL CENTER MODULAR CLASSROOM (SITE WORK) Status: Presented by: Action Byron
More informationProject Delivery Method
Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect
More informationCONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553
ADDENDUM #4 CONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553 CLASSROOM NOTIFICATION DEVICE INSTALLATION - DISTRICTWIDE Contra Costa College / Diablo College / Los Medanos College Date: May
More informationDOCUMENT POST BID INTERVIEW
DOCUMENT 00 45 90 POST BID INTERVIEW PART 1 GENERAL 1.01 SUMMARY By request of the District, this Section requires the apparent low bidder to attend and participate in a Post Bid Interview with the Construction
More informationDISTRICT-WIDE PROP 39 INTERIOR LED LIGHTING UPGRADES BID NO
CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT DISTRICT-WIDE PROP 39 INTERIOR LED LIGHTING UPGRADES BID NO. 18-05 ADDENDUM NO. THREE DATE: November 20, 2017 CLIENT / PROJECT: Chabot-Las Positas Community
More informationA D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary
A D D E N D U M 1 TO All Plan Holders ISSUE DATE 20 January 2017 PROJECT # 15-028 REGARDING Switchgear Replacement NARRATIVE PAGES 1 15-02812 KVa Switchgear Replacement Project SPECIFICATION PAGES 10 DRAWING
More informationDOCUMENT INVITATION TO BID
DOCUMENT 00 11 16 INVITATION TO BID 1. Notice is hereby given that the governing board ( Board ) of the Oakland School District ( District or Owner ) will receive sealed bids for the following: Project
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1
SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: Longfellow ES Exit Balcony Addition DATE: March 4, 2019 755 Morse Street, SF, CA 94112 SFUSD Project No.12059
More informationDOCUMENT BID PROPOSAL
DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of
More informationNOTICE TO BIDDERS. Work done shall be in strict accordance with Plans and Specifications prepared by
NOTICE TO BIDDERS NOTICE IS HEREBY GIVEN that the Board of Trustees of the Campbell Union High School District of Santa Clara County, California, hereby invites and will receive sealed proposals for the
More informationPROPOSITION 39 ENERGY EFFICIENCY UPGRADES EEP3
PROPOSITION 39 ENERGY EFFICIENCY UPGRADES EEP3 793 North E St, San Bernardino, CA 92410 PHASE 2 & PHASE 3 ADDENDUM 05 February 26, 2019 Prepared By JOHN SERGIO FISHER & ASSOCIATES 5567 Reseda Blvd., Suite
More informationDISTRICT-WIDE PROP 39 INTERIOR LED LIGHTING UPGRADES BID NO
CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT DISTRICT-WIDE PROP 39 INTERIOR LED LIGHTING UPGRADES BID NO. 18-05 ADDENDUM NO. TWO DATE: October 25, 2017 CLIENT / PROJECT: Chabot-Las Positas Community College
More informationALLEGAN PUBLIC SCHOOLS
ALLEGAN PUBLIC SCHOOLS Bid Package 2 High School & Alternative High School Pre Bid Meeting November 15, 2012 The SKILLMAN Corporation Project Administration Construction Management Allegan Public Schools
More informationLEVEL I PREQUALIFICATION DOCUMENTS
Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,
More informationInformation for Contractors Regarding Public Works Projects
Information for Contractors Regarding Public Works Projects Page 1 Table of Contents 1. INTRODUCTION...3 WHAT IS CUPCCAA?...3 BENEFITS OF CUPCCAA...3 2. TRADITIONAL BIDDING VS. MCC IMPLEMENTED CUPCCAA...4
More informationMaintenance and Operations 1302 Service Road Tustin, California (714) CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20
Maintenance and Operations 1302 Service Road Tustin, California 92780 (714) 730-7515 CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 The Tustin Unified School District ( District ) has determined that
More informationJim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide
Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,
More informationBerryessa Union School District Measure L Bond Construction Program
Berryessa Union District Measure L Bond Construction Program Board of Trustees Update Introduction The following presentation is intended to provide the Board of Trustees with an update on Measure L Construction
More informationSAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL
DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of
More informationBID DOCUMENTS COVER SHEET CONTRACT DOCUMENTS FOR. Backup Generator Projects. Diablo Valley College. 321 Golf Club Road, Pleasant Hill, CA 94523
BID DOCUMENTS COVER SHEET CONTRACT DOCUMENTS FOR Backup Generator Projects AT Diablo Valley College 321 Golf Club Road, Pleasant Hill, CA 94523 DVC San Ramon Campus 1690 Watermill Rd, San Ramon CA 94583
More informationHillsborough City School District Window Covering Projects At 6 District Sites. Bid #19-01 ADDENDUM NO. 1
Window Covering Projects At 6 District Sites Bid #19-01 ADDENDUM NO. 1 February 13, 2019 Owner: Project Manager: 300 El Cerrito Avenue Hillsborough, CA 94010 Capital Program Management, Inc. 1851 Heritage
More informationADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No Addendum #1 May 17, 2017
ADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No. 17-016 Addendum #1 May 17, 2017 To All Prospective Bidders: The Fieldbrook Elementary School
More informationSAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop
SAN DIEGO COMMUNITY COLLEGE DISTRICT SDCCD Design/Build Subcontracting Plan Preparation Workshop April 7, 2015 Welcome Chris Manis Vice Chancellor, Facilities Management Purpose To share information useful
More informationState Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund
State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous
More informationFarmington Public Schools 2015 Bond Issue Bid Package 9- Beechview & Kenbrook Elementary School Remodeling Project Wednesday, January 24, 2018
Farmington Public Schools 2015 Bond Issue Bid Package 9- Beechview & Kenbrook Elementary School Remodeling Project Wednesday, January 24, 2018 POST-BID ADDENDUM 1 CONSTRUCTION MANAGEMENT PACKAGE - Bidding
More informationMain Building Auditorium
Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform
More informationADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION)
ADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION) Subject to conditions prescribed by the University of California, San Francisco (the University or UCSF ), bids for a Construction Manager at Risk Agreement
More informationProposition 39 Sole Source Requirement
Proposition 39 Sole Source Requirement Presented by Aaron Jobson, Principal Kevin Wang, Associate Quattrocchi Kwok Architects Best Best & Krieger LLP Getting Started with Prop 39 Set Goals and Process
More informationPREQUALIFICATION OF PROSPECTIVE BIDDERS
Subcontractor* Prequalification for Fullerton College Building 3000 HVAC Equipment Replacement North Orange Coast Community College District, Fullerton California BID #1819-09 PREQUALIFICATION OF PROSPECTIVE
More informationCHAs ensure that workers are trained, skilled, and qualified. CHAs set goals for hiring local workers.
CHAs ensure that workers are trained, skilled, and qualified. CHAs set goals for hiring local workers. CHAs can set targets for securing local business participation. CHAs create career opportunities for
More informationInformation for Contractors Regarding Public Works Projects
Information for Contractors Regarding Public Works Projects Table of Contents INTRODUCTION...2 WHAT IS CUPCCAA?...2 BENEFITS OF CUPCCAA...2 TRADITIONAL BIDDING VS. MCC IMPLEMENTED CUPCCAA...3 ADOPTION
More informationADDENDUM #1. for the. Physical Security (Phase II), #31336 Bid #G San Jose City College
ADDENDUM #1 for the Physical Security (Phase II), #31336 Bid #G2010.0179 at San Jose City College San Jose Evergreen Community College District San Jose, California September 8, 2017 SAN JOSE EVERGREEN
More informationMorgan Hill Unified SCHOOL DISTRICT SEMI-ANNUAL PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS
Morgan Hill Unified SCHOOL DISTRICT SEMI-ANNUAL PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS The Morgan Hill Unified School District ( District ) has determined that contractors on future projects
More informationRequest for Bid Questions and Responses. December 29, 2017
Bid: Janitorial Cleaning Services Bid Due Date: January 5, 2018 Request for Bid Questions and Responses December 29, 2017 All Prospective Bidders: In reference to the bid solicitation, the following questions
More informationThe Bid Date has changed to 03/16/2010 at 2:30 PM.
, Chinatown / North Beach Campus Main Building & Annex Building Curbs Gutters and Sidewalk CCSF Project No. 107 A 1. Summary DOCUMENT 00900 Bid Package 7.20 Curbs Gutters and Sidewalk ADDENDUM NO. 4 (02/22/2009)
More informationLABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES
LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES 1 of 15 CS & ASSOCIATES EXPERIENCE & BACKGROUND Established in 2003 by Charla Curtis, Former LCP Director for LAUSD Certified MBE/
More informationDOCUMENT ADDENDUM
ADDENDUM NO. [6] Date: May 22, 2018 DOCUMENT 00 90 00 ADDENDUM RE: FROM: WESTERN TECHNICAL COLLEGE INDOOR SHOOTING RANGE 11177 COUNTY RD A SPARTA, WI 54656 HSR Associates, Inc 100 Milwaukee Street La Crosse,
More informationSANTA PAULA UNIFIED SCHOOL DISTRICT 201 S. Steckel Drive Santa Paula, California (805)
SANTA PAULA UNIFIED SCHOOL DISTRICT 201 S. Steckel Drive Santa Paula, California 93060 (805) 933-3908 Annual Pre-Qualification for MEP Contractors per Public Contract Code 20111.6 License Classifications:
More informationThe Housing Authority of the County of Marin ( MHA ) 4020 Civic Center Drive. San Rafael, CA Addendum #1. Released October 3, 2016
The Housing Authority of the County of Marin ( MHA ) 4020 Civic Center Drive San Rafael, CA 94903 Addendum #1 Released October 3, 2016 Addendum #1 to IFB MHA-010-2016 Re-Roofing, HVAC Unit Replacements
More informationEL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN
EL CAMINO COLLEGE Facilities Master Plan Report November 2008 PROJECTS IN DESIGN I. Math, Business & Allied Health Building (MBA) The scope of this building is the construction of a new building at the
More informationPeralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department
Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department Date: March 30, 2011 ADDENDUM No. 3 BID NO.: 10-11/27 PCCD Smart
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationNOTTAWASEPPI HURON BAND of the POTAWATOMI
NOTTAWASEPPI HURON BAND of the POTAWATOMI Widoktadwen New Government Center Bid Pkg #2 Pre Bid Meeting October 4, 2012 The SKILLMAN Corporation Project Administration Construction Management Nottawaseppi
More informationCONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student Quad
COLLEGE OF THE SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting December 14, 2015 CONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student
More informationAll bidders shall indicate in their bid/proposal that this Addendum has been received and considered in their bid proposal.
Addendum #1 Window Replacements at [4] Buildings Desoto Bass Court, OH5-2A, AMP 7 IFB #13-02 May 6, 2013 Greater Dayton Premier Management 400 Wayne Ave. Dayton, Ohio 45410 This Addendum modifies and shall
More informationADVERTISEMENT FOR SUBCONTRACTOR QUALIFICATION AND ADVERTISEMENT FOR PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS)
ADVERTISEMENT FOR SUBCONTRACTOR QUALIFICATION AND ADVERTISEMENT FOR PROPOSALS OF DESIGN BUILD SUBCONTRACTORS (DB SUBCONTRACTORS) PROJECT NOTICE DPR Construction, hereinafter called DPR, intends to award
More informationEnergy Services Contract Award
Energy Services Contract Award East Side Union High School District Board Meeting of: October 16, 2014; Item 9.02 Linda da Silva, Facilities Director Emily Douglas, OpTerra Energy Services Background November
More informationMEMORANDUM MIKE LINN, CAPITAL PROJECTS ENGINEER
MEMORANDUM TO: FROM: BY: SUBJECT: CITY COUNCIL GEOFF ENGLISH, PUBLIC WORKS DIRECTO~ MIKE LINN, CAPITAL PROJECTS ENGINEER CONSIDERATION TO REJECT ALL BIDS FOR THE CORPORATION YARD ADMINISTRATION BUILDING
More informationOttawa Elementary. Buchanan Middle Schools Additions and Remodels. Pre-Bid Meeting February 13, and
Ottawa Elementary and Buchanan Middle Schools Additions and Remodels Pre-Bid Meeting February 13, 2014 The SKILLMAN Corporation Project Administration Construction Management Buchanan Community Schools
More informationLOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department
Addendum 1 Text 5-9-17 LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA 95825 Phone (916) 568-3071 FAX (916) 568-3145 Purchasing Department Sacramento City College American River College
More informationBID PROPOSAL FORM C.I.P. NO PROJECT: VETERANS PARK SHOOTING RANGE LEAD ABATEMENT/DEMO
Bid Proposal Form C.I.P. NO. 2016-012 PROJECT: BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND ATTACHMENTS AS REQUIRED SUBMITTED BY: (Bidder s Name) In accordance with the City of Commerce s Notice
More informationADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION
ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build
More informationADDENDUM NUMBER 02 TO THE BID DOCUMENTS
SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT ADDENDUM NUMBER 02 TO THE BID DOCUMENTS To all general contract bidders of record on the Bid Proposal: BID NUMBER: G2010-0145 #25103 Energy Efficiency-Clean
More informationJOB ORDER CONTRACTING INFORMATIONAL PRESENTATION
JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS March 2, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) SANDAG s JOC Program SANDAG
More informationLEVEL I PREQUALIFICATION DOCUMENTS COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION
Project No. 4863/A4L-396 LEVEL I PREQUALIFICATION DOCUMENTS for COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North
More informationADDENDUM NO. 3. Item 3 NOTICE OF OPPORTUNITY - REPLACE in its entirety with the attached ***REVISED 08/03/2018
Construction Contracts Administration, Procurement Contracts & Materials Management (PCMM) Oregon State University 644 SW 13 th Ave. Corvallis, Oregon 97333 P 541-737-4261 F 541-737-5546 oregonstate.edu
More informationMIRACOSTA COLLEGE. [X] MiraCosta College Bid Opportunities Website /FAX
MIRACOSTA COLLEGE BID ADDENDUM MiraCosta Community College District Distribution: One Barnard Drive [X] Owner [X] Architect Oceanside, California 92056 [X] MiraCosta College Bid Opportunities Website 760.795.6691/FAX
More informationREVISED BID FORM WILLIAM PATERSON UNIVERSITY OF NEW JERSEY. PROJECT NAME: Renovations & Addition to Hunziker Hall & Wing
REVISED BID FORM WILLIAM PATERSON UNIVERSITY OF NEW JERSEY PROJECT NUMBER: WP-14-14-8/14 PROJECT NAME: Renovations & Addition to Hunziker Hall & Wing Bids are to be returned to The Office of Associate
More informationADDENDUM NO. B. TO THE BID DOCUMENTS, dated 1/5/16 FOR THE
ADDENDUM NO. B TO THE BID DOCUMENTS, dated 1/5/16 FOR THE CVUSD M&O/WAREHOUSE/PRINTING SERVICES TENANT IMPROVEMENT 667 Building & 750 Building #DO-15C1024 & #DO-15C1026 CONEJO VALLEY UNIFIED SCHOOL DISTRICT
More informationOhlone Community College District
Bond Measure G February 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Schedule
More informationThis Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.
NORTHWEST-SHOALS COMMUNITY COLLEGE CARPENTRY SHOP EXPANSION ADDENDUM #1 PART 1 - GENERAL Project: Carpentry Shop Expansion B.C. # 2015573 Owner: Northwest-Shoals Community College Architect: Aho Architects,
More informationNotice Inviting Informal Bids
Notice Inviting Informal Bids Construction Services for SBVC Trane Chiller CH-1 Adaptive Frequency Drive Replacement Project NIB RELEASED: 6/11/2018 SITE WALK AND CONFERENCE (MANDATORY): 9:00 A.M. PST
More informationPITTSBURG UNIFIED SCHOOL DISTRICT CONSTRUCTION AND MODERNIZATION PROGRAM SEPTEMBER 2016
PITTSBURG UNIFIED SCHOOL DISTRICT CONSTRUCTION AND MODERNIZATION PROGRAM SEPTEMBER 2016 DATE OF ELECTION ELECTION TYPE PROPOSED BOND APPROVAL RATE VOTE REQUIRED NOV 2014 MEASURE N GENERAL OBLIGATION BONDS
More informationREQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES Memorial Ballpark Renovation
REQUEST FOR PROPOSALS FOR CIVIL ENGINEERING SERVICES Memorial Ballpark Renovation The Mandan Park District, Mandan, ND (Owner) is seeking proposals from qualified Civil Engineering firms to provide professional
More informationMustang Substation Bank I Replacement Project MAJ 15-SP5054
CALIFORNIA POLYTECHNIC STATE UNIVERSITY FACILITIES PLANNING & CAPITAL PROJECTS San Luis Obispo, CA 93407-0690 p 805/756-2581 f 805.756.7566 http://www.afd.calpoly.edu/facilities/ Mustang Substation Bank
More informationMISSOURI DEPARTMENT OF CONSERVATION DESIGN & DEVELOPMENT ADDENDUM NO. 1
MISSOURI DEPARTMENT OF CONSERVATION DESIGN & DEVELOPMENT ADDENDUM NO. 1 TO THE SPECIFICATIONS, PROPOSAL, CONTRACT AND BOND FOR THE CONSTRUCTION OF SALEM MAINTENANCE CENTER REPLACE WINDOWS AND INSULATE
More informationADDENDUM NO. 1 CONTRACT NO. TU-191 SALT STORAGE BUILDING FOR THE TOWN OF ULSTER ULSTER COUNTY, NEW YORK. January 25, 2019
DENNIS M. LARIOS, P.E. CHRISTOPHER J. ZELL, L.L.S. Lic. No. 58747 Lic. No. 49629 BRINNIER and LARIOS, P.C. PROFESSIONAL ENGINEERS & LAND SURVEYORS 67 MAIDEN LANE DESIGN KINGSTON, NEW YORK 12401 SUBDIVISIONS
More informationBOARD OF TRUSTEES OCTOBER 13, 2014
Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property
More informationPREQUALIFICATION DOCUMENTS FOR SUBCONTRACTORS FOR
1. PROJECT TICE PREQUALIFICATION DOCUMENTS FOR SUBCONTRACTORS FOR York Hall Biology/Chemistry Renovation UNIVERSITY OF CALIFORNIA SAN DIEGO a) BNBuilders, Inc. (BNB) intends to award lump sum contracts
More informationFebruary Significant reduction in delays, unexpected costs and disputes between the parties arising during construction.
February 2014 The major benefits to the Owner in a design and construction program carried out by employing the Bridging method are listed and discussed below along with the benefits to the Owner s Design
More informationDESERT COMMUNITY COLLEGE DISTRICT RESOLUTION NO
DESERT COMMUNITY COLLEGE DISTRICT RESOLUTION NO. 121914-1 FINDINGS RE: ENERGY CONSERVATION PROJECT AND AUTHORIZATION TO ENTER INTO ENERGY SERVICES AGREEMENT WITH JACKSON ELECTRIC (GOVERNMENT CODE 4217.10
More informationSweetwater Union High School District. Proposition O Performance Audit. March 20, 2012 Board of Education and Citizens Bond Oversight Committee
Sweetwater Union High School District Proposition O Performance Audit Board of Education and Citizens Bond Oversight Committee Outline of Performance Audit Presentation All parties, District staff and
More informationDestructive Testing for the following location(s): Daniel Webster Elementary School 465 Missouri Street, San Francisco, CA
Facilities Prop A 2011 Bond Program San Francisco Unified School District 135 Van Ness Avenue, Room 207 San Francisco, CA 94102 October 9, 2007 DESCRIPTION OF WORK FOR INFORMAL BID PROPOSAL RE: Destructive
More informationADDENDUM NO. 2. PROJECT: Request for Submittal of Qualifications DATE: June 1, 2012 Willie L. Brown, Jr. Middle School 2055 Silver Avenue, SF CA
SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM REQUEST FOR SUBMITTAL OF QUALIFICATIONS Pre-Qualification Questionnaire for Prospective Design Build Entities Willie L. Brown, Jr.
More informationSB 854 DIR CONTRACTOR REGISTRATION DLSE PREVAILING WAGE RATE ENFORCEMENT & MONITORING
SB 854 DIR CONTRACTOR REGISTRATION DLSE PREVAILING WAGE RATE ENFORCEMENT & MONITORING T: 310-640-0800 F: 310-640-0818 Sherman Wong KEY CHANGES DIR REGISTRATION DLSE PWR MONITORING & ENFORCEMENT All public
More informationBERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA OFC FAX
BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA 95132 408-923-1871 OFC 408-926-8329 FAX PREQUALIFICATION PACKAGE INSTRUCTIONS FOR PROSPECTIVE MEP SUBCONTRACTORS FEBRUARY
More informationCENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program. MONTHLY REPORT March 31, 2009
CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program MONTHLY REPORT March 31, 2009 Construction Management 414 W. 4 th Street, Suite L Santa Ana, CA. 92701 Table of
More informationWATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018
SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 Types of Public Construction Delivery Methods Available: Design-Bid-Build (DBB) under M.G.L Ch. 149 Overview Pros Cons Construction Management at Risk
More informationMAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS:
ADDENDUM NO. 1 CITY OF PORT ARANSAS ELLIS MEMORIAL EXISTING LIBRARY RENOVATIONS AND REPAIRS CSP #2016-22 700 W. AVE A PORT ARANSAS, TX 78373 Issue Date: 01/07/2019 The following additions, deletions, modifications,
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM RAPHAEL WEILL EARLY EDUCATION SCHOOL STRUCTURAL STRENGTHENING ADDENDUM NO.
SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM RAPHAEL WEILL EARLY EDUCATION SCHOOL STRUCTURAL STRENGTHENING ADDENDUM NO. PROJECT: Raphael Weill Early Education DATE: March, 208
More informationNOTICE INVITING BIDS
NOTICE INVITING BIDS NOTICE IS HEREBY GIVEN that the City of Long Beach, California, acting by and through the City s Board of Harbor Commissioners ( City ) will receive, before the Bid Deadline established
More information1. Pre-Bid Meeting: The Meeting was held on July 15, 2013 at 1:30PM at Kiser Middle School.
ADDENDUM #1 Date: 7/24/2013 Project: Window-Door Replacement/Repair Kiser Middle School 716 Benjamin Parkway, Greensboro, NC Number of Pages: The following corrections, changes, additions, deletions, revisions,
More informationI. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards
I. INTRODUCTION The Los Angeles Community College District is currently undertaking the largest public sector sustainable building effort in the United States, funded by its Proposition A/AA and J Bond
More informationIRVINE UNIFIED SCHOOL DISTRICT CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20
CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 The Irvine Unified School District ( District ) has determined that bidders on an annual basis must be prequalified prior to submitting a bid on a project
More informationREVISED BID FORM. To Procurement Services, Room 1104, 900 East Broad Street, Richmond, Virginia:
REVISED BID FORM SEALED BIDS WILL BE RECEIVED at the Department of Procurement Services, City Hall, 900 E. Broad Street, Rm. 1104, Richmond, Virginia 23219, UNTIL BUT NOT LATER THAN 2:30 P.M. ON February
More informationDEPARTMENT OF FINANCE & OPERATIONS Wilmette Public Schools INFORMATION ITEM. Date: February 22, Raymond E. Lechner, Ph.D.
DEPARTMENT OF FINANCE & OPERATIONS Wilmette Public Schools INFORMATION ITEM Date: February 22, 2016 To: From: Subject: Raymond E. Lechner, Ph.D. Superintendent Gail F. Buscemi Business Manager Summer 2016
More informationPre-Bid Conference Agenda
West Valley-Mission Community College District Mission College - Main Building Replacement Phase II - Sign In Sheets - Introductions (Appendix A) - Master Plan - Project Description - Delivery Method -
More informationFACILITIES Summer Projects. September 8, 2015 Board Meeting
FACILITIES 2015 Summer Projects September 8, 2015 Board Meeting On January 27, 2015 the Laguna Beach Unified School District Board of Education approved a 10-year facilities plan. The plan identified numerous
More informationPublicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build
1 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Mark Kelley, Dannis Woliver Kelley Deidree Sakai, Dannis Woliver Kelley 2 1 Publicly Bid: Design-Bid-Build Multiple-Prime
More informationPeralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department
Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department ADDENDUM No. 2 DATED JULY 2, 2013 TO THE PROJECT MANUAL and PLANS
More informationADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4
ADDENDUM #3 GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4 Please address inquiries to: Aaron R. Nickerson GRW, Inc. anickerson@grwinc.com TO ALL PROSPECTIVE BIDDERS:
More informationTHE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732)
THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ 08904 PHONE (732)572-4420 February 10, 2017 Window Replacements at Samuel J Kronman Building and Park Terrace
More informationSECTION BIDDING AND CONTRACT REQUIREMENTS ADDENDUM NUMBER (1) January 25, 2017
SECTION 00 90 0 BIDDING AND CONTRACT REQUIREMENTS ADDENDUM NUMBER () January 5, 07 Demonica Kemper Architects 5 N. Halsted Street, Suite 30 Chicago, IL 6066 3.96.0000 To: Prospective Bidders Re: ADDENDUM
More informationJOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference
JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation
More informationLSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3
LSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3 PART 1 - GENERAL Project: Open-End Agreement for Misc. Projects Package D Millsap Building [B.C. # 2018332] Owner: Lawson State
More informationWaterford Unified School District
Waterford Unified School District 219 Reinway Avenue, Bldg 2 P.O. Box 270 Waterford, CA. 95386 (209) 874-1809 Bid # 01/12 School Buses Opening date: October 19, 2011 Opening time: 2:00 p.m. GENERAL CONDITIONS,
More informationBIDDERS HANDOUT Please provide to all bidders who inquire about the City of Granite Shoals Quarry Parks Projects
IN IN ORDER ORDER TO TO SUBMIT SUBMIT COMPLETE COMPLETE BID, BID, FULL FULL BID BID PACKAGE PACKAGE MUST MUST BE BE REQUESTED REQUESTED FROM FROM CITY CITY HALL HALL BIDDERS HANDOUT Please provide to all
More informationADDENDUM #2. Several questions below refer to bids and bidders. This RFP is a solicitation for proposals, not for bids.
CONTRA COSTA COMMUNITY COLLEGE DISTRICT RFP Mechanical Engineering Services for Mechanical and Controls Improvements and Upgrades Design Build Performance Specification Development At Diablo Valley College,
More informationOAKLAND UNIFIED SCHOOL DISTRICT FOR NON-LOCAL PRIME CONTRACTORS PREQUALIFICATION QUESTIONNAIRE FOR CURRENTLY QUALIFIED FIRMS RENEWAL
OAKLAND UNIFIED SCHOOL DISTRICT FOR N-LOCAL PRIME CONTRACTORS PREQUALIFICATION QUESTIONNAIRE FOR CURRENTLY QUALIFIED FIRMS RENEWAL OAKLAND UNIFIED SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR CURRENTLY
More informationNotice to Bidders Page 1 of 6
Page 1 of 6 COYOTE CREEK LEVEE RODENT DAMAGE REPAIR DOWNSTREAM OF SR 237 Project No. 62084001, Task No. 5171 Contract No. C0637 1. Notice. Notice is hereby given that sealed Bids will be accepted by the
More information