Energy Services Contract Award

Size: px
Start display at page:

Download "Energy Services Contract Award"

Transcription

1 Energy Services Contract Award East Side Union High School District Board Meeting of: October 16, 2014; Item 9.02 Linda da Silva, Facilities Director Emily Douglas, OpTerra Energy Services

2 Background November 17, 2011: Board of Trustees approved a site improvement / deferred maintenance plan to be funded by Measure G bond proceeds in the amount of $32.5 million. November 2012: California passed the Clean Energy Jobs Act (Proposition 39) to fund energy efficiency in schools. January 10, 2014: District staff solicited qualifications from firms to design and construct cost effective energy performance improvements at District sites. March 20, 2014: Board of Trustees approved Program Development Agreement with Chevron Energy Solutions, Board Item 9.06, to determine the specific energy conservation measures that will be used to support an Energy Services Contract. 2

3 Background March September 2014: Chevron Energy Solutions (CES) performed the work of the Program Development Agreement: Surveyed all District facilities Reviewed as built construction records Reviewed electricity, gas, water and garbage utility records to ascertain usage and costs Investigated possible energy conservation measures Solicited preliminary pricing bids from a number of trades contractors Numerous meetings with Facilities Planning and Maintenance staff for information and direction September 2, 2014: CES was sold to OpTerra Energy Services and CES assigned its interest in the Program Development Agreement to OpTerra per the contract terms; OpTerra has assumed and is performing all the rights, duties, and obligations of the Program Development Agreement. 3

4 Special Criteria Government Code Section authorizes public agencies to enter into agreements with qualified energy services contract providers. However, before awarding an energy services contract, the Governing Board must first determine and find in a public hearing that the net benefits of the energy conservation measures to be provided through the contract are greater than the expense of the contracted improvements. California Clean Energy Jobs Act Created with the approval of Proposition 39 in the November 2012 statewide General Election Allocates projected revenue to the Clean Energy Job Creation Fund for five fiscal years, beginning in fiscal year 2013/14 Allocations are made to schools and/or districts based on enrollment Identify and include energy work that captures Prop 39 funding allocated to ESUHSD and charter schools housed in East Side facilities 4

5 Result of Program Development Phase Energy Saving and Infrastructure Upgrades: A specific package of energy saving measures and energy infrastructure upgrades has been identified. The cost will be outweighed by the savings provided through the improvements, making it eligible for award as an Energy Services Contract under Government Code On top of the net savings, the District will realize these additional benefits: Improved indoor environmental comfort and function Decreased disruption to learning and working environments due to equipment failures Decreased maintenance burden Economic stimulus through creation of 52 green construction jobs Educational enrichment through internships and custom educational programming that supports common core implementation, enhances career pathways, and boosts professional development Continuation of East Side s leadership position in energy conservation Environmental benefits of avoiding more than 20,000 tons of greenhouse gas emissions 5

6 Program Goals Goal General Fund Savings Economic Stimulus Solar & Lighting Project $3 million in year 1, and $43 million in lifetime savings Employ over 85 local union contractors District-Wide Energy Services Project Net value over $38 million during project lifetime, leveraging state funds Create 52 regional, green union jobs Educational Enrichment Celebrating District Leadership Environmental Benefits Provide professional development workshops and solar kits to students at 13 schools Host groundbreaking ceremony in March 2010 and ribbon cutting in May 2011 Equivalent to planting 726 acres of pine forest Enhance educational program with internships and custom educational programming Continue community leadership with media strategy Avoid nearly 20,000 tons of greenhouse gas emissions 6

7 Energy Education Enhance Professional Development Inquiry-based and literacy-infused sessions reinforce skills critical to Common Core and NGSS (Next Generation Science Standards) implementation Supporting curriculum and hands-on components empower teachers to incorporate energy concepts into classroom learning Strengthen Career Pathways Internship through S4CA (Santa Clara County Construction Careers Association) offers real-world construction experience to East Side students Visits from OpTerra STEM (Science, Technology, Engineering, Math) experts help students explore potential career paths and support workforce development Cultivate Community Connections Analysis of past East Side energy consumption helps students understand their environmental impact and why it matters Student-led energy awareness activities help make energy efficiency upgrades more visible and connect facility modernization to campus life 7

8 Regional Labor OpTerra secured the best price for the District through competitive RFPs for labor & materials The project is expected to directly create 52 regional jobs and millions of dollars in economic growth Construction workers from local union halls will complete installations The construction work falls under the District s Project Labor Agreement The following companies were invited to bid and we plan to expand the pool to include additional local contractors during final engineering Energy Management System Syserco (Fremont) Electrical Upgrades / Solar PV Atlas Pellizzari Electric (Redwood City) BEI Construction (Alameda) Sprig Electric (San Jose) did not bid Lighting ABM Electrical (Pleasanton) Enlight (Pleasanton) Mechanical Airco Mechanical (Benicia) Comfort Dynamics (Alameda) did not bid ICOM Mechanical (San Jose) Western Allied (Menlo Park) Pool Services Knorr Systems (Livermore) Solar Pool Heating Aztec Solar (Rancho Cordova) Poco Solar (Santa Clara) Solar PV Structural Work MBL Energy (San Jose) 8

9 Energy Measures Recommended Energy Saving Measures Interior Lighting Exterior Lighting Solar Photovoltaic (PV) Pool Cover Portable Classroom Controls Infrastructure Upgrades Priority Electrical Infrastructure Priority HVAC Improvements Pool Boiler Replacements Energy Management System (EMS) Exterior Lighting Controls 9

10 Scope Items by Site ESUHSD All Sites Site Solar Photovoltaic Interior Lighting Exterior Lighting Exterior Lighting Controls HVAC Improvements EMS Installation Boiler Replacement Pool Cover Electrical Infrastructure Upgrade Andrew P. Hill High School X X X X X Evergreen Valley High School X X X Independence High School X X X X X X James Lick High School X X X X X Mt. Pleasant High School X X X X Oak Grove High School X X X X X Piedmont Hills High School X X X X X X X Santa Teresa High School X X X X X Silver Creek High School X X X X X William C. Overfelt High School X X X X X Yerba Buena High School X X X X X X Calero High School X Foothill High School X X X X X Independence Adult Center Overfelt Adult Center X Education Center 10

11 Scope Items by Site ESUHSD Charter Schools School Location Solar Photovoltaic Common Spaces Exterior Lighting ACE Charter High School Independence High School X X Downtown College Prep Alum Rock Independence High School X X KIPP San Jose Collegiate Independence High School X X Leadership Public Schools William C. Overfelt High School X Summit Public Schools: Rainier Mt. Pleasant High School X X Note: Prop 39 requires at least one year of ADA data for eligibility. Luis Valdez Leadership Academy (LVLA) began operations in , and will receive allocations in years 3-5. LVLA is excluded for now because the allocation amount is uncertain. 11

12 Additional Scope Evaluated Solar Thermal, 9 sites Comprehensive HVAC Replacement (~700 units audited) Portable Classroom Controls Pool Pump Controls Education Center Solar PV Electrical Infrastructure Interior and Exterior Lighting Priority electrical and HVAC replacements that will be bundled with their respective building modernizations 12

13 Project Funding and Cost Measure G Site Improvements, $8,991,900 Energy-Saving Measures, $9,981,211 Measure I Infrastructure, $4,610,000 Def. Maint., $324,575 Measure G Unallocated Interest Income, $5,131,188 Energy Infrastructure, $15,105,457 Prop 39, $5,712,886 Utility Rebates, Rebates, $316,119 $315,119 Funding Sources $25,086,668 Scope Type and Cost $25,086,668 13

14 Project Financial Benefit GUARANTEE PERIOD (Columns A and 95%) Energy Conservation Rebates Energy Conservation Savings 2 Year Net Solar Project Savings 1 Maintenance Savings District Prop 39 ($) 3 Charter Prop 39 ($) 3 Net Program Savings Cumulative Savings A B C D E F G =A+B+C+D+E+F H 1 $163,426 $316,119 $537,548 $1,874,260 $712,171 $3,603,524 $3,603,524 2 $170,143 $561,738 $772,360 $293,477 $1,797,717 $5,401,241 3 $177,133 $587,016 $772,360 $293,477 $1,829,986 $7,231,227 4 $184,408 $613,432 $720,869 $273,912 $1,792,621 $9,023,848 5 $191,980 $641,036 $170,000 $1,003,016 $10,026,864 6 $216,991 $669,883 $886,874 $10,913,738 7 $225,706 $700,027 $925,733 $11,839,471 8 $234,769 $731,529 $966,298 $12,805,769 9 $244,196 $764,447 $1,008,643 $13,814, $254,000 $798,847 $495,000 $1,547,848 $15,362, $264,197 $834,796 $1,098,993 $16,461, $274,803 $872,361 $1,147,164 $17,608, $285,833 $911,618 $1,197,451 $18,805, $297,305 $952,640 $1,249,945 $20,055, $309,236 $995,509 $170,000 $1,474,745 $21,530, $321,645 $1,040,307 $1,361,952 $22,892, $334,551 $1,087,121 $1,421,672 $24,314, $347,973 $1,136,041 $1,484,015 $25,798, $361,933 $1,187,163 $1,549,097 $27,347, $376,452 $1,240,586 $1,617,038 $28,964, $391,552 $1,296,412 $1,687,964 $30,652, $407,256 $1,354,751 $1,762,007 $32,414, $423,589 $1,415,714 $1,839,303 $34,253, $440,575 $1,479,422 $1,919,997 $36,173, $458,242 $1,545,995 $2,004,237 $38,177,839 Total $835,000 $4,139,848 $1,573,038 Capital Outlay $19,057,663 Net Benefit $19,120,176 1 Solar kwh guaranteed by OpTerra for Years Energy conservation savings guaranteed by OpTerra for Years Prop 39 funding values known for Year 1 & 2 and awarded together. Values conservatively estimated for Years

15 Savings Guarantee 15 Years Annual measurement and reporting on solar production One-time measurement of lighting savings Backed by dollar value in contract and payment from OpTerra Value rises with expected energy cost increases 15

16 Project Funding Measure G Site Improvements / Deferred Maintenance $8,991,900 (of Board approved $28.7M; September 15, 2011, Board Item 13.01) Measure I Infrastructure $4,610,000 (of Board approved $32.1M; June 11, 2013, Board Item 15.02) Deferred Maintenance Fund 14 $324,575 Measure G Unallocated Interest Income $5,131,188 Proposition 39 Clean Energy Jobs Creation $5,712,886 (Board approved March 20, 2014, Board Item 9.06) This is a projected allocation amount; actual allocations for FY2015/16 through 2017/18 are not known at this time Utility Rebates $316,119 16

17 Project Cash Flow Strategy Proposition 39 California Clean Energy Creation Fund Funding allocations over 5 fiscal years (2013/ /18) Applications for eligible projects are submitted to the California Energy Commission the agency responsible for Proposition 39 oversight. Upon completion of the approved projects, including any required Measurement & Verification (M&V) processes, funds are disbursed. OpTerra will provide Prop 39 program administration on East Side s and charter schools behalf. Utility Rebates Applications, M&V, and claims processes with PG&E will be administered by OpTerra. Cash Flow Strategy School Facilities Fund 35 will be used to bridge the funding gap until East Side receives Prop 39 and utility rebate proceeds. 17

18 Project Funding Bond Measure G Unallocated Interest Income $5,131,188 of interest income remains unallocated (as of June 30) District s best interest to allocate the remaining interest income to this project (including interest earned after June 30) With so many competing school modernization needs, why? Maximize previously cited project benefits (improved learning and working environments, reduction in energy and maintenance costs, economic stimulus through creation of green construction jobs, customized educational enrichment and professional development, continued environmental leadership) Maximize modernization benefit with no additional project soft costs Close out Measure G Bond Program administrative burden (program management, annual audits, Citizens Bond Oversight Committee efforts, Measure G financial and accounting oversight) 18

19 Program Development Assessment Fee The terms of the Program Development Agreement between the District and OpTerra provide that OpTerra shall receive a $60,000 Assessment Fee for their work of the Program Development Phase. The terms further provide that if the District enters into an Energy Services Contract with OpTerra, this Assessment Fee shall be incorporated into the total contract amount payable under the Energy Services Contract. 19

20 Recommendation It is recommended that, pursuant with Government Code and on the basis of the foregoing and the materials and analysis presented, the Board of Trustees finds and determines: (i) that the anticipated cost to the District for thermal or electrical energy or conservation services provided by the energy conservation facility under the proposed contract with OpTerra will be less than the anticipated marginal cost to the District of thermal, electrical, or other energy that would have been consumed by the District in the absence of those purchases, (ii) authorize the Associate Superintendent of Business Services to execute an Energy Services Contract with OpTerra Energy Services in an amount not to exceed $25,086,668, to provide energy saving measures and energy infrastructure upgrades, administer Proposition 39 Clean Energy Jobs Act and utility rebate funding processes, administer an associated educational enrichment program, and provide support and assistance with an energy conservation media campaign; (iii) that the Board allocate $5,131,188 of Measure G interest income earned through June 2014, as well as all Measure G interest income accrued after June 2014, to partially fund this Energy Services Contract; and (iv) that the Board approve use of approximately $6 million of School Facilities Fund 35 to bridge the funding gap until the District receives Proposition 39 Clean Energy Jobs Creation fund and utility rebate proceeds. 20

DOCUMENT PROPOSAL FORM (Modified)

DOCUMENT PROPOSAL FORM (Modified) To be submitted by the time and date specified in Document RFI 01 (Request for Information), paragraph 5. TO THE HONORABLE BOARD OF TRUSTEES OF THE EAST SIDE UNION HIGH SCHOOL DISTRICT: THIS MODIFIED PROPOSAL

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Independence High School Building B1 Modernization Modernization repurposes the building for the Visual Arts academic program. The building will be converted to six visual arts classrooms with a curriculum

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Security Camera Upgrades The project will take the existing multiple security camera systems currently used throughout the District and replace them with a single integrated Districtwide,

More information

Santa Teresa High School

Santa Teresa High School Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew

More information

Independence Adult Center

Independence Adult Center Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus

More information

James Lick High School

James Lick High School James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being

More information

Policy Leadership Education & Engagement Smart Energy Solutions. Irvine Los Angeles Oakland San Diego

Policy Leadership Education & Engagement Smart Energy Solutions. Irvine Los Angeles Oakland San Diego Policy Leadership Education & Engagement Smart Energy Solutions Irvine Los Angeles Oakland San Diego Green CA Schools & Community College Summit Making Schools Energy Efficient - How One No-Cost Program

More information

DESERT COMMUNITY COLLEGE DISTRICT RESOLUTION NO

DESERT COMMUNITY COLLEGE DISTRICT RESOLUTION NO DESERT COMMUNITY COLLEGE DISTRICT RESOLUTION NO. 121914-1 FINDINGS RE: ENERGY CONSERVATION PROJECT AND AUTHORIZATION TO ENTER INTO ENERGY SERVICES AGREEMENT WITH JACKSON ELECTRIC (GOVERNMENT CODE 4217.10

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Security Camera Upgrades The project will take the existing multiple security camera systems currently used throughout the District and replace them with a single integrated Districtwide,

More information

The Board of Governors of the California Community Colleges

The Board of Governors of the California Community Colleges The Board of Governors of the California Community Colleges PRESENTED TO THE BOARD OF GOVERNORS DATE: November 13, 2017 SUBJECT: Board of Governors Energy and Sustainability Award Program CATEGORY: Recommended

More information

PITTSBURG UNIFIED SCHOOL DISTRICT CONSTRUCTION AND MODERNIZATION PROGRAM SEPTEMBER 2016

PITTSBURG UNIFIED SCHOOL DISTRICT CONSTRUCTION AND MODERNIZATION PROGRAM SEPTEMBER 2016 PITTSBURG UNIFIED SCHOOL DISTRICT CONSTRUCTION AND MODERNIZATION PROGRAM SEPTEMBER 2016 DATE OF ELECTION ELECTION TYPE PROPOSED BOND APPROVAL RATE VOTE REQUIRED NOV 2014 MEASURE N GENERAL OBLIGATION BONDS

More information

BID AWARD: PROP. 39 YEAR 5 20 L.E.D. LIGHTING RETROFIT

BID AWARD: PROP. 39 YEAR 5 20 L.E.D. LIGHTING RETROFIT SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting May 14, 2018 BID AWARD: PROP. 39 YEAR 5 20 L.E.D. LIGHTING RETROFIT Status: Presented by: Action Byron Woods Dean, Facilities Issue The District

More information

K-12 Proposition 39 Update. Jillian Rich March 23, 2015

K-12 Proposition 39 Update. Jillian Rich March 23, 2015 K-12 Proposition 39 Update Jillian Rich March 23, 2015 Agenda Time Category 1 PM Welcome and Introductions (All) 1:05 PM State of Prop 39 Implementation (Jillian) 1:10 PM New Prop 39 Guidelines: What s

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being

More information

Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education

Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education Session Purpose Help to design holistic school energy initiatives including facility upgrades, conservation, and student

More information

CUMMING. Firm Overview

CUMMING. Firm Overview CUMMING Firm Overview Owner s Representatives Cumming has ranked in Engineering News Record Magazine s Top 40 listing of Top 50 CM-for-Fee Firms in the US; Top 4 of strictly Owner s Representatives. 20

More information

CITY COUNCIL STAFF REPORT

CITY COUNCIL STAFF REPORT CITY COUNCIL STAFF REPORT DATE: December 17, 2014 CONSENT SUBJECT: FROM: BY: ADOPT A RESOLUTION ENDORSING THE CITY OF PALM SPRINGS GREEN FOR LIFE PROGRAM INCLUDING GREENHOUSE GAS INVENTORY, ENERGY ACTION

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being

More information

Navigating the Prop 39 Maze Part 2

Navigating the Prop 39 Maze Part 2 Navigating the Prop 39 Maze Part 2 February 6, 2014 Presented by: Rick Brown, President TerraVerde Renewable Partners, LLC Tyler B. Dockins, Attorney at Law Lozano Smith Table of Contents 1. Proposition

More information

Proposition 39 Sole Source Requirement

Proposition 39 Sole Source Requirement Proposition 39 Sole Source Requirement Presented by Aaron Jobson, Principal Kevin Wang, Associate Quattrocchi Kwok Architects Best Best & Krieger LLP Getting Started with Prop 39 Set Goals and Process

More information

Financing Energy Operations in Schools. Peter Lindstrom Summer Institute for Climate Change Education June 17, 2015

Financing Energy Operations in Schools. Peter Lindstrom Summer Institute for Climate Change Education June 17, 2015 Financing Energy Operations in Schools Peter Lindstrom Summer Institute for Climate Change Education June 17, 2015 CERTs: Minnesotans Building a Clean Energy Future Mission: We connect individuals and

More information

Procuring and Financing Energy Efficiency. September 20, 2011

Procuring and Financing Energy Efficiency. September 20, 2011 Procuring and Financing Energy Efficiency September 20, 2011 Oro Valley, Arizona Located just a few miles north of Tucson, Arizona Incorporated in 1974 with 1,500 residents Over 41,000 residents today

More information

LEED It Green: County Design/Build Projects

LEED It Green: County Design/Build Projects LEED It Green: County Design/Build Projects Solano County Kanon Artiche County Architect Alameda County Jim Kachik Deputy Director, TSD July 19-21, 2006, GSA Academy IV LEED Design-Build County Projects

More information

Novato Unified School District

Novato Unified School District Novato Unified School District Novato Unified School District Solar Master Plan Prepared by KyotoUSA April 2015 The purpose of this analysis is to assess the current feasibility of solar projects in the

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Projects Projects Security Camera Upgrades Digital cameras and software will be installed throughout the District. Delivery Method: Design-Bid-Build Swimming Pool Upgrades Modernization and/or

More information

Preparing Your Prop 39 Application: The TerraVerde Energy Report Card

Preparing Your Prop 39 Application: The TerraVerde Energy Report Card CASBO Members Rick Brown, PhD, President, TerraVerde Prop 39 Application/Energy Best Practices 1/27/14 Preparing Your Prop 39 Application: The TerraVerde Energy Report Card Background Passage of Proposition

More information

APPENDIX E. Sector Specific Objectives

APPENDIX E. Sector Specific Objectives APPENDIX E Sector Specific Objectives 2018-2019 Each Sector Navigator, in collaboration with Sector Deputy Sector Navigators, has developed Sector Specific Objectives as the first step in fiscal year planning.

More information

APPENDIX E. Sector Specific Objectives

APPENDIX E. Sector Specific Objectives APPENDIX E Sector Specific Objectives 2018-2019 Each Sector Navigator, in collaboration with Sector Deputy Sector Navigators, has developed Sector Specific Objectives as the first step in fiscal year planning.

More information

EAST BAY COMMUNITY ENERGY BUSINESS TOOLKIT

EAST BAY COMMUNITY ENERGY BUSINESS TOOLKIT EAST BAY COMMUNITY ENERGY BUSINESS TOOLKIT East Bay Community Energy (EBCE) is Alameda County s new local provider of cleaner, greener electricity at lower rates. As a not-for-profit public agency, EBCE

More information

Smart Schools Symposium

Smart Schools Symposium Smart Schools Symposium September 2013 2013 CLEAResult All rights reserved. 1 INTRODUCTION David Casentini, Resource Solutions Group VP of California Programs 2013 CLEAResult All rights reserved. 2 2013

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

MUNDELEIN ELEMENTARY SCHOOL DISTRICT 75. Job Description

MUNDELEIN ELEMENTARY SCHOOL DISTRICT 75. Job Description MUNDELEIN ELEMENTARY SCHOOL DISTRICT 75 Job Description JOB TITLE: QUALIFICATIONS: Business Manager 1. Master s degree in educational administration or business administration 2. Minimum of five years

More information

Building Careers in Sustainable Facilities Design and Management

Building Careers in Sustainable Facilities Design and Management Building Careers in Sustainable Facilities Design and Management November 29, 2017 11:15 am 12:15 pm Presented By Robert T. Mejia, Executive Director, Economic, Resource, and Community Development, San

More information

2015 Quarter 3 Butte County Climate Action Plan Monitoring Report

2015 Quarter 3 Butte County Climate Action Plan Monitoring Report MEMO To: From: Cc: Butte County Jennifer Venema Jeff Henderson, Tammy Seale Date: November 13, 2015 Re: 2015 Quarter 3 Butte County Climate Action Plan Monitoring Report We are pleased to provide the 2015

More information

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT. Discussion of Community Choice Aggregation and Recommendation to Join the Marin Energy Authority

CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT. Discussion of Community Choice Aggregation and Recommendation to Join the Marin Energy Authority CITY OF ALBANY CITY COUNCIL AGENDA STAFF REPORT Agenda Date: November 18, 2013 Reviewed by: Pat O SUBJECT: REPORT BY: Discussion of Community Choice Aggregation and Recommendation to Join the Marin Energy

More information

Sweetwater Union High School District. Proposition O Performance Audit. March 20, 2012 Board of Education and Citizens Bond Oversight Committee

Sweetwater Union High School District. Proposition O Performance Audit. March 20, 2012 Board of Education and Citizens Bond Oversight Committee Sweetwater Union High School District Proposition O Performance Audit Board of Education and Citizens Bond Oversight Committee Outline of Performance Audit Presentation All parties, District staff and

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Projects Upgrades in Multipurpose Building 1300 In order to meet the needs of the building s three distinct uses administrative gatherings, recreational program space, and as a general venue and event

More information

MT. SAN ANTONIO COLLEGE BOARD OF TRUSTEES SELF-EVALUATION 2014 COMPILED

MT. SAN ANTONIO COLLEGE BOARD OF TRUSTEES SELF-EVALUATION 2014 COMPILED MT. SAN ANTONIO COLLEGE BOARD OF TRUSTEES SELF-EVALUATION 2014 COMPILED Just as Boards are concerned with the effectiveness of the institutions they govern, so they should be concerned with their own effectiveness

More information

Bundled Energy Solutions to Lower Operating Costs and Maximize ROI. Harvey Katzen Director of Bundled Energy Services ABM Building and Energy

Bundled Energy Solutions to Lower Operating Costs and Maximize ROI. Harvey Katzen Director of Bundled Energy Services ABM Building and Energy Bundled Energy Solutions to Lower Operating Costs and Maximize ROI Harvey Katzen Director of Bundled Energy Services ABM Building and Energy Association of California Water Agencies Anaheim, CA November

More information

Energy Savings Programs August 23, 2012

Energy Savings Programs August 23, 2012 Energy Savings Programs August 23, 2012 p-p2s7-56g Energy Savings Programs Peter Berger Eric Rehm www.energy.mn.gov 2 Public Building Enhanced Energy Efficiency Program (PBEEEP) Newer buildings Make existing

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Swimming Pool Modernization This project reconstructs the swimming pool complexes and infrastructure including pool pumps, motors, water heaters, filtration and disinfection systems. The new

More information

Division of Administration & Finance Strategic Plan

Division of Administration & Finance Strategic Plan Division of Administration & Finance 2017-2022 Strategic Plan Mission: The Administration & Finance Division s mission is to provide efficient, effective, value-added service that contributes to the achievement

More information

Emerging Zero Net Energy School Retrofit Case Study NEWCASTLE ELEMENTARY SCHOOL OVERVIEW. Planning and Design Approach

Emerging Zero Net Energy School Retrofit Case Study NEWCASTLE ELEMENTARY SCHOOL OVERVIEW. Planning and Design Approach Emerging Zero Net Energy School Retrofit Case Study Credit: Tricia Casper, Auburn Journal OVERVIEW Location: Newcastle, CA Size: 31,536 SF Original Construction: 1950s Retrofit: 2017 School District: Newcastle

More information

San Jose Evergreen Community College District Strategic Goals 2013 to 2016

San Jose Evergreen Community College District Strategic Goals 2013 to 2016 San Jose Evergreen Community College District Strategic Goals 2013 to 2016 SJECCD Vision: By the year 2017, SJECCD becomes the premier institution for advancing opportunity, equity, and social justice

More information

of programs qualifies the organization uniquely; there is no other similar organization that we are aware of in the state.

of programs qualifies the organization uniquely; there is no other similar organization that we are aware of in the state. Director s Letter Implementors of Change It was a time of transition at CCSE during 2012, marking the retirement of longtime leader Irene Stillings, closing of the San Diego Energy Resource Center, moving

More information

Operational Plan

Operational Plan 2013-2014 Operational Plan Goal 1 Student learning and Success: Ensure student learning and success by promoting an innovative and supportive learning environment. 1.1 Offer and promote a variety of programs

More information

The Board of Governors of the California Community Colleges

The Board of Governors of the California Community Colleges The Board of Governors of the California Community Colleges AVE BLANK PRESENTED TO THE BOARD OF GOVERNORS DATE: January 14, 2019 SUBJECT: Board of Governors Energy and Sustainability Award Program Item

More information

AGENDA REPORT SUMMARY. Community Greenhouse Gas (GHG) Inventory Report ATTACHMENTS. Environmental Commission Report

AGENDA REPORT SUMMARY. Community Greenhouse Gas (GHG) Inventory Report ATTACHMENTS. Environmental Commission Report AGENDA REPORT SUMMARY MEETING DATE: May 25, 2010 SUBJECT: Community Greenhouse Gas (GHG) Inventory Report RECOMMENDATION: A. Receive Community GHG Survey Los Altos Environmental Commission; and B. Approve

More information

Sellwood Bridge Replacement Slayden Sundt JV. Diversity Plan

Sellwood Bridge Replacement Slayden Sundt JV. Diversity Plan Sellwood Bridge Replacement Slayden Sundt JV Diversity Plan A. Diversity Plan Objectives Slayden-Sundt shares in the County s commitment to diversity in all aspects of the Sellwood Bridge Replacement project.

More information

MCE A local, not-for-profit electricity provider

MCE A local, not-for-profit electricity provider MCE A local, not-for-profit electricity provider About MCE 2008 2010 2016 MCE formed Service launched Serving 255,000 accounts California Community Choice 2010 2014 2015 2016 2017 Local Control 27 Board

More information

Energy Savings Performance Contracting Southwest CERT April 2, 2012

Energy Savings Performance Contracting Southwest CERT April 2, 2012 Energy Savings Performance Contracting Southwest CERT April 2, 2012 Energy Services Coalition, Minnesota Chapter Madonna Rykken, Ben Glynn Agenda What is Performance Contracting (PC)? How does it work?

More information

DOCUMENT BID PROPOSAL

DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

January 17, 2017 Investment Grade Audit Mid-Term Update

January 17, 2017 Investment Grade Audit Mid-Term Update City of Lawrence Energy Efficiency & Facility Improvement Project January 17, 2017 Investment Grade Audit Mid-Term Update Agenda Review of project goals and process history Performance contract and the

More information

N IO T C U D PRO Y G ER EN

N IO T C U D PRO Y G ER EN ENERGY PRODUCTION This page is intentionally left blank Energy Production The use of fossil fuels, including coal, oil, and gas, for energy production contributes significantly to greenhouse gas emissions.

More information

Skilled Trades Training Funds Frequently Asked Questions

Skilled Trades Training Funds Frequently Asked Questions These FAQs were developed as a supplement to the Skilled Trades Training Fund (STTF) Program Overview and Application Guidelines. Questions regarding this document can be directed to skilled@michigan.gov.

More information

NOTICE TO BIDDERS. Work done shall be in strict accordance with Plans and Specifications prepared by

NOTICE TO BIDDERS. Work done shall be in strict accordance with Plans and Specifications prepared by NOTICE TO BIDDERS NOTICE IS HEREBY GIVEN that the Board of Trustees of the Campbell Union High School District of Santa Clara County, California, hereby invites and will receive sealed proposals for the

More information

Ohio Energy. Workshop A. Best Practices & Case Study Model for Integrated Energy Solutions at The Ohio State University

Ohio Energy. Workshop A. Best Practices & Case Study Model for Integrated Energy Solutions at The Ohio State University Ohio Energy Workshop A Best Practices & Case Study Model for Integrated Energy Solutions at The Ohio State University Tuesday, February 20, 2018 10:45 a.m. to Noon Biographical Information Ken Cowan, Vice

More information

BOND MEASURE E COMMUNICATIONS PLAN

BOND MEASURE E COMMUNICATIONS PLAN FREMONT UNIFIED SCHOOL DISTRICT BOND MEASURE E COMMUNICATIONS PLAN Citizens Bond Oversight Committee February 4, 2015 COMMUNICATIONS PLAN GOALS & OBJECTIVES To report and inform on the Bond Measure E program

More information

EPA chief leads dedication of Hayward solar landfill conversion

EPA chief leads dedication of Hayward solar landfill conversion \\ EPA chief leads dedication of Hayward solar landfill conversion By Rebecca Parr rparr@bayareanewsgroup.com POSTED: 05/13/2015 12:54:54 PM PDT Guests walk around the West Winton Landfill on May 13, 2015,

More information

City of Oak Grove, Missouri. Economic Development Incentives Policy

City of Oak Grove, Missouri. Economic Development Incentives Policy City of Oak Grove, Missouri Economic Development Incentives Policy March 2008 TABLE OF CONTENTS Policy Introduction 3 Page Tax Increment Financing (TIF) 4 Chapter 100 Industrial Development Bonds 6 Chapter

More information

Human Resources RECOMMENDED BUDGET & STAFFING SUMMARY & BUDGET PROGRAMS CHART. Operating $ 8,511,700 Capital $0 FTEs 25.25

Human Resources RECOMMENDED BUDGET & STAFFING SUMMARY & BUDGET PROGRAMS CHART. Operating $ 8,511,700 Capital $0 FTEs 25.25 RECOMMENDED BUDGET & STAFFING SUMMARY & BUDGET PROGRAMS CHART Operating $ 8,511,700 Capital $0 FTEs 25.25 Lori Gentles Department Director Administration Employee Relations/Benefits Recruiting & Classification

More information

INCUMBENT WORKFORCE DEVELOPMENT TRAINING POLICY EFFECTIVE DATE: SEPTEMPTER 1, 2015

INCUMBENT WORKFORCE DEVELOPMENT TRAINING POLICY EFFECTIVE DATE: SEPTEMPTER 1, 2015 version 7-29-15 INCUMBENT WORKFORCE DEVELOPMENT TRAINING POLICY EFFECTIVE DATE: SEPTEMPTER 1, 2015 A. OVERVIEW As part of its ongoing commitment to established businesses and their existing workers, the

More information

2017 PARTICIPANT HANDBOOK

2017 PARTICIPANT HANDBOOK 2017 PARTICIPANT HANDBOOK POLICIES AND PROCEDURES FOR PARTICIPATION IN THE STATEWIDE SAVINGS BY DESIGN PROGRAM Last Revised: January 20, 2017 www.savingsbydesign.com This program is funded by California

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Projects Projects Mechanical, Electrical and Controls Equipment Upgrades This project replaces aged mechanical, electrical and controls equipment that have reached the end of their service

More information

Business Engagement and Services RFP

Business Engagement and Services RFP Business Engagement and Services RFP Goals of the RFP The City of Oakland, Office of Economic and Workforce Development / Oakland Workforce Investment Board (OWIB) seeks experienced organizations to provide

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G February 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Schedule

More information

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS March 2, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) SANDAG s JOC Program SANDAG

More information

General Rate Case Application Information

General Rate Case Application Information General Rate Case Application Information I. About San Jose Water Company II. III. IV. General Information About Rates Summary of San Jose Water Company s 2015 General Rate Case Application Frequently

More information

Overall Strategic Plan Dashboard

Overall Strategic Plan Dashboard 07-9 Overall Strategic Plan Dashboard Thought Leadership Be the local go-to organization on workforce development. Increase visibility and understanding of Partner4Work regionally and nationally through

More information

Proposals must be received in the Office of the City Manager no later than 2:00 p.m. on December 3, 2018.

Proposals must be received in the Office of the City Manager no later than 2:00 p.m. on December 3, 2018. REQUEST FOR PROPOSAL Proposals are now being accepted in the Office of the City Manager, 745 Forest Parkway, Forest Park, Georgia 30297 for: COMPREHENSIVE CLASSIFICATION & COMPENSATION STUDY FOR THE CITY

More information

CONTRACTORS: Things you should know about the East Side Union High School District Project Labor Agreement.

CONTRACTORS: Things you should know about the East Side Union High School District Project Labor Agreement. CONTRACTORS: Things you should know about the East Side Union High School District Project Labor Agreement. 1. Project Labor Agreements Project Labor Agreements are a legally recognized form of pre hire

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Mechanical, Electrical and Controls Equipment Upgrades This project replaces aged mechanical, electrical and controls equipment that have reached the end of their service lives with modern

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Districtwide Mechanical, Electrical and Controls Equipment Upgrades This project replaces aged mechanical, electrical and controls equipment that have reached the end of their service lives with modern

More information

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,

More information

PARTICIPANT HANDBOOK

PARTICIPANT HANDBOOK 2017-2018 PARTICIPANT HANDBOOK POLICIES AND PROCEDURES FOR PARTICIPATION IN THE STATEWIDE SAVINGS BY DESIGN PROGRAM Last Revised: February 23, 2018 www.savingsbydesign.com This program is funded by California

More information

Addendum 6 to the Northeast Regional Plan Area #2 Local Workforce Plan Medina County and Summit County, Ohio

Addendum 6 to the Northeast Regional Plan Area #2 Local Workforce Plan Medina County and Summit County, Ohio Addendum 6 to the Northeast Regional Plan Area #2 Local Workforce Plan Medina County and Summit County, Ohio Area 2 Local Workforce Plan Effective Period: May 1, 2017 - January 31, 2017 Introduction This

More information

Solar Projects in Indian Country. PRESENTED BY: Josh Simmons Principal Consultant / Attorney October 28, 2015

Solar Projects in Indian Country. PRESENTED BY: Josh Simmons Principal Consultant / Attorney   October 28, 2015 Solar Projects in Indian Country PRESENTED BY: Josh Simmons Principal Consultant / Attorney www.prospersustainably.com October 28, 2015 Solar Projects in Indian Country Please sign-in and provide contact

More information

PROGRESS ON THE COMMUNITY COLLEGES SYSTEM ERP PLAN, DESIGN AND IMPLEMENTATION PROGRAM. A Report to the:

PROGRESS ON THE COMMUNITY COLLEGES SYSTEM ERP PLAN, DESIGN AND IMPLEMENTATION PROGRAM. A Report to the: PROGRESS ON THE COMMUNITY COLLEGES SYSTEM ERP PLAN, DESIGN AND IMPLEMENTATION PROGRAM A Report to the: Joint Legislative Oversight Committee on Information Technology Submitted By NC Community College

More information

WIA Communication No

WIA Communication No MASSACHUSETTS STEERING COMMITTEE WIA Communication No. 00-15 10 Policy 0 Information To: Chief Elected Officials Regional Employment Board Chairs Regional Employment Board Directors Service Delivery Area

More information

St. Louis Park Green Building Policy

St. Louis Park Green Building Policy St. Louis Park Green Building Policy One of the Strategic Directions listed within Vision St. Louis Park is that the City is committed to being a leader in environmental stewardship. To that end the City

More information

Measure YY. Approved by the Board of Education

Measure YY. Approved by the Board of Education Measure YY Approved by the Board of Education July 10, 2018 San Diego Unified has 226 educational facilities with over 1,400 permanent buildings and more than 2,000 portable classrooms. In 2008, a study

More information

Ordinance establishing a Community Choice Aggregation Program in accordance with

Ordinance establishing a Community Choice Aggregation Program in accordance with FILE NO. ORDINANCE NO. 1 [Ordinance establishing a Community Choice Aggregation Program to allow San Francisco to aggregate the electrical load of San Francisco electricity consumers and to accelerate

More information

Request for Qualifications: Solar Service Provider Questions and Answers and Addendum #1

Request for Qualifications: Solar Service Provider Questions and Answers and Addendum #1 Request for Qualifications: Solar Service Provider Questions and Answers and Addendum #1 Issue Date: February 17, 2016 1.0 PURPOSE OF THIS ADDENDUM The Association for Energy Affordability Inc. (AEA) is

More information

ADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No Addendum #1 May 17, 2017

ADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No Addendum #1 May 17, 2017 ADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No. 17-016 Addendum #1 May 17, 2017 To All Prospective Bidders: The Fieldbrook Elementary School

More information

NCWorks:Workforce Solutions. for Your Business

NCWorks:Workforce Solutions. for Your Business NCWorks:Workforce Solutions for Your Business North Carolina Business Climate and Workforce Development 2 What is the NCWorks Commission? Overarching Goal Statewide workforce development goal that by 2025,

More information

Notice Inviting Informal Bids

Notice Inviting Informal Bids Notice Inviting Informal Bids Construction Services for SBVC Trane Chiller CH-1 Adaptive Frequency Drive Replacement Project NIB RELEASED: 6/11/2018 SITE WALK AND CONFERENCE (MANDATORY): 9:00 A.M. PST

More information

NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST

NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST The New Haven Unified School District will use bonds funds to provide up to date classrooms, renovate athletic fields and related facilities, replace

More information

Kalispell School District Energy Savings Performance Project Review

Kalispell School District Energy Savings Performance Project Review Kalispell School District Energy Savings Performance Project Review Gwyn Andersen Business Director Kalispell Public Schools Brian Solan, P.E. Montana Business Leader Ameresco, Inc. Overview The Process

More information

The Department of Public Works invites applications for the position of

The Department of Public Works invites applications for the position of The Department of Public Works invites applications for the position of The Position The Chief of Plant and Engineering, Medical Center is responsible for the operations and maintenance of all County Health

More information

COMMUNITY ACTION PARTNERSHIP OF STAUNTON, AUGUSTA AND WAYNESBORO (CAPSAW) INTRODUCTION

COMMUNITY ACTION PARTNERSHIP OF STAUNTON, AUGUSTA AND WAYNESBORO (CAPSAW) INTRODUCTION INTRODUCTION The Economic Opportunity Act of 1964 created Community Action Agencies as a strategy to impact its mission to eliminate poverty and to foster opportunity for individuals, families and communities

More information

Operational Plan

Operational Plan 2014-2015 Operational Plan Goal 1 Student learning and Success: Ensure student learning and success by promoting an innovative and supportive learning environment. 1.1 Offer and promote a variety of programs

More information

2011 Sustainability Summary

2011 Sustainability Summary SAN DIEGO COMMUNITY COLLEGE DISTRICT 2011 Sustainability Summary Presented to SDCCD Board of Trustees February 9, 2012 1 Waste Diversion The District continues to divert a significantly higher percentage

More information

QUARTERLY REPORT. (July 1, 2013 September 30, 2013) December 18, 2013

QUARTERLY REPORT. (July 1, 2013 September 30, 2013) December 18, 2013 QUARTERLY REPORT (July 1, 2013 September 30, 2013) December 18, 2013 Closed CCC NBLC Lease Revenue Bond Retirement Completed DIST Help Desk Software OCC Gym Acoustic Retrofit OCC Large Lecture Hall Seating

More information

Community Choice Energy for Alameda County

Community Choice Energy for Alameda County Community Choice Energy for Alameda County Status Update Put Name of City and Date of Session Here What is Community Choice Energy? CCE enables local governments to procure and/or develop power on behalf

More information

Energy Savings Performance Contracting

Energy Savings Performance Contracting Energy Savings Performance Contracting Achieving Corporate Financial and Environmental Sustainability Presented By Jorge G. Quintana Energy Solutions Account Executive Johnson Controls, Inc. Executive

More information

Preliminary Solar Photovoltaic Assessment for Gavilan College

Preliminary Solar Photovoltaic Assessment for Gavilan College Preliminary Solar Photovoltaic Assessment for Gavilan College by Clyde Murley, Solar Program Manager, Community College League of California, October 18, 2016 This preliminary assessment of the potential

More information

REB Strategic Plan July 1, 2017-June 30, 2020 Summary Scoreboard. Quarterly Progress Report Year 1, QTR 3 Progress January 1, 2018 March 30, 2018

REB Strategic Plan July 1, 2017-June 30, 2020 Summary Scoreboard. Quarterly Progress Report Year 1, QTR 3 Progress January 1, 2018 March 30, 2018 REB Strategic Plan July 1, 2017-June 30, 2020 Summary Scoreboard Quarterly Progress Report Year 1, QTR 3 Progress January 1, 2018 March 30, 2018 KPI Metric Key: KPI Metric Trend between Quarters: 1. Changing

More information