1.0 EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "1.0 EXECUTIVE SUMMARY"

Transcription

1 1.0 EXECUTIVE SUMMARY S.No Particulars Details 1 Name of Project 2 Project Proponent 3 Village Proposed Granite Building Stone Quarry of Mr. Saji Sebastian Mr. Saji Sebastian Madeckal House, Kizhakkambalam P.O, Ernakulam District, Kerala State Arakuzha 4 Taluk Muvattupuzha 5 District Ernakulam 6 State Kerala 7 Co-ordinates 8 Topography N 09o E 76o Hilly Terrain 9 Topo Sheet No 58 C/4 10 Elevation 11 Mining Lease Area The highest elevation of the lease area is 117 m and lowest elevation is 87 m above MSL Ha 12 Production capacity TPA 13 Extent of mechanization Semi mechanized Opencast Mining 14 Bench Height Height 5m 15 Depth of Mining 62 m 16 Water requirement & source 17 KLD from open well 17 Man Power requirement Project Cost 19 Nearest Town a. Fixed Cost Rs. 24,00,000/b. Operational Cost Rs. 20,00,000/c. EMP Cost Rs 5,50,000/- 20 Nearest Railway Station Aluva- 35 Km 21 Nearest Airport Cochin International Airport 38 Km Muvattupuzha- 8 Km 1

2 2.0 INTRODUCTION 2.1 Identification of Project Proponent and project Proponent Applicant Details Phone Number Mr. Saji Sebastian Madeckal House, Kizhakkambalam P.O, Ernakulam District, Kerala State Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 3 years Name and Address Mr. M.D. Kuriakose, residing at Medeckal House, Kizhakkambalam Post, Ernakulam District has applied for grant of Environmental Clearance from the Hon ble DEIAA, Ernakulam District for the proposed Granite Building stone located in Survey No. 66/3 of Arakuzha Village,, Kerala. The mining lease applied for the quarry is for a period of 3 years. This mine has already worked in past years. The proponent has already obtained quarry lease for 10 years vide proceeding No. Rc. No. 709/ /786/M3/2010 dated from the DMG. The lease deed was executed on and the lease will expire on Now, applicant has Prepared and submitting the Mining Plan for a period of Three Years and is approved by the District Geologist, DMG. 2.2 Brief description of nature of the project The area applied for quarry lease is almost a hilly terrain with elevation ranges from 87117m above mean sea level. Water table is noticed at a depth of 21-38m from the surface in the adjacent open wells of the area. The Geological Reserves is estimated as M3 ( MT) and Mineable Reserves is estimated as are M3 ( MT) and recoverable reserves is estimated as M³ 2

3 ( MT) of Granite Building Stone after leaving necessary safety distance from the lease boundary as indicated in the precise area letter and relevant mining laws in force. The average proposed rate of production of Granite Building Stone is about M3 ( MT)/3 = M3 (47302 MT) per year for Applied Lease area. The Average proposed production of Granite Building Stone per day is about MT/260days = MT by truck load is /8= 22.7 MT. 2.3 Need for the project and its importance to the country and or region The major need of building stone is due to high compressive strength and durability (among the hardest, dimensional & structural stones) it can effectively withstand the vagaries of nature. Fine-grained granite is employed for ornamental and monumental. Works as well as for inscription purposes. The mineral rich colours, and the hardness & density, makes its useful for many applications. The proposed mining project will fulfill its end uses in buildings and constructions, bridges, paving, monuments and many other exterior projects. Polished slabs and titles are used in countertops, flooring, retaining walls and landscaping around a centre are used in countertops, flooring, retaining walls and landscaping around a centre fountain / pond, staircase and many other design elements (residential and commercial applications). It is also known as the maintenance free stone. The mining and associated activities in the mineral bearing areas bring about gains in gross domestic product, ie. There is though a minor contribution by the proposed project but will add to the gains in G.D.P (Gross Domestic Product). A total of 37 people will be employed in the mine. It will create employment (though marginally) for local population. Applicant will pay royalty for the mineral produced from the mine, direct and indirect taxes will be paid thereby contributing to the regional revenue. The public revenue will further be put for infrastructure development and other sectors like health, education and social welfare. 3

4 2.4 Demand Supply Gap Since it is main raw material in construction project. It is always in demand. So the proposed mining project will fulfill its end users in local market, as it is always in good demand in construction projects. 2.5 Imports / Exports Building stone explored from the mines will be used in the local areas in construction activities like roads, building and railways. The mineral produced from the proposed mine will be sent to the crusher plant located near the quarry site for crushing it to required size before dispatching it to the end use. 2.6 Export possibility No export businesses are taken in this project. 2.7 Domestic/ export markets The rough stone produced will be sold in local market, which is in turn used for construction purposes. 2.8 Employment Generation due to the project Around 23 employees will be engaged in the mines after the expansion and required manpower for mining operation is given in Table Skilled Operator Mechanic Blaster/Mat Driver 4 No. 2 No. 2 No. 4 Nos Musdoor / Labours Cleaners Office Boy 4. Management & Supervisory staff Total = 6 Nos 2. Semi skilled 3. Unskilled 2Nos 1No 2No. 23Nos 4

5 3.0 PROJECT DESCRIPTION 3.1 Type of Project including interlinked and interdependent projects, if any There is no interlinked project proposed along with this proposal. 3.2 Location (map showing general location, specific location, project boundary) with coordinates The mine lease area is covered under Survey of India (SOI) Topo sheet No 58 B/5 5

6 Table 3-1 Environmental Setting Description Details Site Location Survey Nos Arakuzha Village, Muvattupuzha Taluk, Ernakulam District Sy. No. 66/3 SOI Topo sheet 58 C/4 Elevation Nearest City (habitation) The highest elevation of the lease area is 117 m and lowest elevation is 87 m above MSL. Muvattupuzha 8.0 km, Nearest Highway NIL Nearest Railway Station Aluva 35.0 Km Nearest Airport Cochin International Airport 38 km, Nearest Water Bodies/River/Sea Thodupuzha River 2 km, NE Archaeologically important places None within the study area National parks/ Wildlife Sanctuaries None within the study area Reserved/ Protected Forests None within the study area Seismicity Zone-III, Moderate damage risk zone as par BMTPC, Vulnerability atlas Seismic zone of India IS Defence Installations None within the study area 6

7 Google Image showing Project Boundary 3.3 Details of alternate sites considered No alternative sites considered, the proposal is mining project and it is site specific. 3.4 Size of magnitude of operation Extent of the mining lease area is hectares. The Geological Reserves is estimated as M3 ( MT) and Mineable Reserves is estimated as are M3 ( MT) and recoverable reserves is estimated as M³ ( MT) of Granite Building Stone after leaving necessary safety distance from the lease boundary as indicated in the precise area letter and relevant mining laws in force. The average proposed rate of production of Granite Building Stone is about M3 ( MT)/3 = M3 (47302 MT) per year for Applied Lease area. The Average proposed production of Granite Building Stone per day is about MT/260days = MT by truck load is /8= 22.7 MT. 7

8 Table 3-2 Year Wise Production Plans 3.5 Project description with process details The proposed mining operations will be carried out by open cast semi- mechanized method. The process flow diagram given below depicts the mining process3.5.1 Proposed mining method Open cast method of mechanized mining will be adopted to extract rough stones of required size from the mine area. While opening a new mine, several long term aspects of mining should be considered like semi permanent roads, planning the development work, formation of working faces, approach roads to various benches for movement of dumpers, selection and recruitment of man power, machineries, construction of infrastructures, selection of dump sites, stacking yards for undressed blocks, finished products and other facilities Project Description with process a details (A Schematic Diagram / Flow Chart showing the Project Layout. Components of the Project etc should be given. The proposed mining operations will be carried out by open cast semi mechanised method. The process flow diagram given n below depicts the mining processquarry Drilling Transportation Blasting Loading Transportation 8

9 Drilling Drilling of shot-holes will be carried out using compressor and Jack Hammers combination. Depth of holes shall be 1-2m bench height the spacing shall be 0.75m and burden shall be 0.60m from the preface. To achieve a correct blasting geometry certain amount of trial blast is prerequisite to effect a perfect pre-determined fragmentation and fly rock control. In case of heavy blasting qualified Mine manager has to be appointed for proper calculation of powder factor and control blasting sequencing and arrangement of explosives etc. Details of Type No Dia of hole Size/Capacity Make Motive Power H.P Jack Hammer mm Hand held Atlas copco 2 Nos Diesel 60 drilling equipments are tabulated below Blasting The massive formation shall be broken into pieces of portable size by drilling and blasting using jack hammers and shot hole blasting. Powder factor of explosives for breaking such hard rock shall be in the order of 6 to 7 tonnes per Kg of explosives. Diameter of the hole Spacing Depth Charge / Hole Pattern of hole Inclination of hole Quantity of rock broken mm 60 Cms 1 to 1.5m D.Cord with water or 70gms of gun powder or Gelatin. ZigZag 700 from the horizontal x 2.6= 1.17 MT Blasting 90% Charge per hole Quantity of rock broken per day 1.17 x 90% = 1.05MT / hole 140gms of 25mm dia cartridge 9.0 Cum or 22.7 MT Loading Loading of waste and Granite Building stone shall be done by Excavator into 10 tonners tippers from the working place periodically. Such waste and Granite Building stones shall be 9

10 dumped in the site earmarked for dumping as shown in the Plates XIII. The applicant is proposed to engage one Hydraulic excavator and one hydraulic rock breaker with 1.20 M3 capacity and six tippers of 10 tonnes capacity for internal transport of rejects from the working face to the dumps. The details of the loading equipments are shown below. Type Power Hydraulic Excavator Nos. Bucket Capacity (MT) 1.20 M3 1 Make L&T or Ex200 Motive Diesel H.P. 120 Transportation Transportation of Rejects and waste shall be done by Tippers of 10 Tonnes capacity as shown in section 6.5 of Mining plan. Type Nos Size / Capacity Make Motive power H.P. Tipper 3 10 M.T Ashok Diesel 110 Leyland Open Cast Mining The mining will be done by open cast semi mechanized method. The bench height and width will be 5m. Shovel dumper combination is used for mucking, loading and hauling to the disposal points. Excavated material is conveyed to the stone crusher located inside the quarry site for further processing. The ultimate depth of the mine workings is estimated to reach up to 23 m Salient features of Mining Method The proposed mining operations will be carried out by open cast mechanized method. The salient features of proposed mining methods are listed below The height and width of the bench will be maintained at 5m. The exploitation of mineral is being done in average depth of 62 m at conceptual phase. 10

11 Considering the stability of rocks the final slope or say ultimate pit slope is proposed 600 from vertical. Haul road will be developed up to point of loading. Transportation of the mineral from pit-mouth to destination will be by tippers / Trucks (10MT capacity) Mode of Working It is a semi mechanized quarrying operation using shot hole drilling with the help of compressor and jack hammers, smooth blasting,block lifting and waste removal using Hydraulic excavator and loaded directly to the tippers and transported to the crushing plants into required size in the crushing plants from 75mm jelly to 10mm chips Bench design parameters and fencing While developing a top soil bench, a height of 5m and width not less than the height. The rough stone working benches shall be 5m height as equal to the height of the excavator boom and width more than 6m for safe movement of machineries and slope shall not be more than 600. The proposed bench dimensions are shown in section 6. 7 of mining plan. S2 fencing (without closing or gate) shall be constructed at the top of high benches from inadvertent entry of persons or cattle fields. In case of road closing or entry of pit G1 fencing (parapet) should be formed as a safe practice to control tress passes Proposed Bench Height and Width As per reg. 106 (2) (b) of MMR, 1961, the bench height is designed as 5m and width as 5m but in the case of non-moving permanent stable benches the width shall be less that 5m due to lack of space for development. The bench height is designed equal to height of boom of the excavator. In this connection, the applicant should obtain necessary permission from DGMS whenever he deviates from the standard norms of bench design. 3.6 Conceptual Mining Plan Conceptual plan is prepared with an object of systematic development of bench lay outs, selection of ultimate pit limit, depth of mining and ultimate pit slope, selection of sites for construction of infrastructures etc., 11

12 Ultimate Pit Dimension The ultimate pit size is designed based on certain practical factors such as the economical depth of mining, safety zones, permissible area etc., Ultimate pit Limit is up to 62 m from the top. However during extraction of blocks each bench will be of 5m height and 5m width for proper quarrying. The quantum of excavation is estimated as MT to a depth of 62 m from the surface. The overburden of the applied area is topsoil of 792 MT. The waste and rejects up to the ultimate pit limit is estimated as 7470 MT. Entire quantity of excavated soil and rejects shall either be back filled or used for plantation 3.7 Raw material required along with estimated quantity No raw material is required; project is for mining of rough stone. The extracted rough stone shall be sent to the crushed through tippers and from there to end uses. 3.8 Resource optimization / recycling and reuse envisaged in the project i. Availability of water its source, energy/ power requirement Water requirement for the project is mainly for maintaining the Domestic, Drinking Purpose, green belt and also for sprinkling on the haulage roads to mitigate dust emissions. Quantity for Drinking and utilities is 2.0KLD will be sourced from the open well which will be purified in mini RO plant. Dust suppression and Green belt of water is 12.0KLD and 3 KLD respectively. Total estimated requirement of water quantity is 17 KLD. Drinking water is obtained by Mineral water industries by water cans. Dust suppression and green belt is obtained from the open wells of proponent site. Table 3.3. Water requirements S.No Particulars Domestic and Drinking Purpose Dust Suppression & Water sprinkling Green Belt development Total Quantity in KLD The characteristics of water like flurosis. TDS, COD, BOD, Salinity, hardness etc have to be tested by the applicant within one year for consumption of water by the mine workers one 12

13 sample each from open and tube wells. Mean while mineral water shall be supplied in cans for drinking purposes. ii. Quantity of wastes to be generated and scheme for their management /disposal The overburden of the applied area is Topsoil of 396 M3 (792 MT). This topsoil is removed initially and Backfilled in Eastern Side of the lease area, this will be done only after obtaining permission and paying necessary seignior age fees to the Government. The wastes are generated during the mining plan period is about 2988M3 (7470 MT) will be proposed to Backfilling to the Eastern side of the lease area. Backfilling area Dimensions are given below Mineral Reject Dump 50.0m(L) X 7.5m(W) X 3.0(H) The Granite Building stones will be stacked at the entry of mine within the lease boundary for transport to crushing units. 13

14 4.0 SITE ANALYSIS 4.1 Connectivity Mine area is well connected with roads. District roads such as Arakuzha--Meenkunnam road road is at a distance of 0.70 kms and connects to the state highway SH1 MC Road is at a distance of 0.5 km from the project site. The nearest Railway station is Aluva Station at a distance of 35 Km. The nearest airport is Cochin International Airport at a distance of 38 kms. Infrastructure facilities like post & telegraph office, telephone, police station, hospital etc are nearby the vicinity. 4.2 Land Form, Land Use and Land ownership The Lease Area does not involve any forest, agriculture or grazing land. The land is Private patta land, the land is not viable for agricultural purpose. 4.3 Topography / Drainage Pattern The area applied for quarry lease is almost a hilly terrain with elevation ranges from 87117m above mean sea level. Water table is noticed at a depth of 21-38m from the surface in the adjacent open wells of the area. Annual temperature range between 20 C (68 F) and 39 C (102 F). The Ernakulam district received the rain under the influence of both southwest and northwest monsoons. The southwest monsoon chiefly contributes to the rainfall in the district. Most of the precipitation occurs in the form of cyclonic storms caused due to the depressions in Arabian Sea. The normal annual rainfall over the district varies from about 3432mm.It is the minimum around Ernakulam in the southeastern part of the district. The highest humidity is generally recorded in May with the value of 87%. The average daily wind speed in August has been around 8 km/h, that s the equivalent to about 5 mph, or 5 knots. In recent years the maximum sustained wind speed has reached 74 km/h, that s the equivalent of around 46 mph, or 40 knots. 14

15 4.4 Flora and Fauna The Site has 181 species of plants belonging to 64 families. It consists of Trees 62 Shrubs 34 Herbs 55 Climbers 21 Ferns 09 Acmella paniculata Hemidesmus indicus Hibiscus Acmella The following list of faunal elements were observed from the site Birds 45 species Mammals 12 species Butterflies 54 species Dragonflies 20 species Amphibians 7 species Reptiles 14 species Spiders 22 species Ants 6 species The district has a variety of plants including medicinal, spices, tuber crops and those yielding fruits and fibber. Aromatic plants and spices such as pepper, ginger, cardamom and turmeric are cultivated on a large scale. Trees such as timber, teak, rosewood, jack tree, manjakadambu, anjili, pala can be found in abundance. Vegetation in the applied area for quarry lease but the surrounding area is composed of rubber, oak trees. Density is about 1000 trees per Hectare. Further, neither flora of botanical interest nor fauna of zoological interest is noticed in this area 15

16 4.5 Infrastructure Since the scale of operation is very small and total employment is only 13 employs hence infrastructure are not required minimums infrastructure like rest shatter, toilet are provided at site. 4.6 Existing Infrastructure There is no existing infrastructure inside the proposed mining lease area 16

17 5.0 PLANNING BRIEF Year wise excavation plan of rough stone, are already provided in the earlier sections. 5.1 Planning Concept Not applicable 5.2 Population Projection About 23 workers will be employed; they will be from local area. 5.3 Land Use planning (breaking along with Greenbelt etc) Table 5.1 Existing Land Use pattern The Existing land use pattern is previews mining years given in a tabular form as below, Sl. Present Area Area in use during the quarrying Land Use (Hect) 1. Quarry Infrastructure Nil Nil 3. Mineral Reject Dump Nil Roads Area Under Plantation Nil Unutilized Nil Total Ha Ha. No. 5.4 Amenities / Facilities a. Drinking Water period (Hect) Whole some drinking water shall be provided as per the Mines Rules, Quantity for Drinking and utilities is 2 KLD will be sourced from the open well which will be purified in mini RO plant. Quantity required for dust suppression and Green belt is 12 17

18 KLD and 3 KLD respectively. Minimum quantity of 17 KLD is required. For dust suppression and green belt, water is obtained from the open wells/ storm water reservoir of proponent site. b. Sanitary Facilities Semi permanent latrines & urinals shall be maintained at convenient places for use of labors as per the provisions of Rule (33) of the Mines Rules, 1960 separately for males and females. Washing facilities shall also be arranged as per rules (36) of the Mines Rules, c. First Aid facility Being a small mine, First Aid station as per provisions under Rule (44) of the Mines Rules 1955 will be provided with facilities as per the third schedule as prescribed. Qualified First Aid personnel should be appointed or nominated to attend emergency first aid treatment. d. Labour Health As per Mines Rule, Periodic medical examination has to be arranged for occupational health once in a year in addition to attending medical treatment of occupational injuries under the Rule 45 (A). MR e. Precautionary safety measures to the Labourers Safety provisions like helmet, goggles, safety shoes, Dust mask, Ear, muffs etc have to be provided as per the circulars and amendments made for Mine labours under the guidance of DGMS being a mechanized operation. Necessary training will be conducted once in a year to all the employee with the help of qualified and experienced officers to train about the safe and system at quarrying operation. 18

19 6.0 PROPOSED INFRASTRUCTURE Infrastructure facilities are in the form of first aid room, drinking water will be provided in the mine. The building is semi permanent nature and there will not be any problem in dismantling them during the closure of mine. The mine roads are also semi permanent nature and hence will not be any impact after the closure of mine. 6.1 Residential Area No residential area is proposed at mine. 6.2 Green belt and Reclamation of land Trees like Rosewood, Jack tree, Manjakadambu, Anjili, Pala Oak, Teak, Rubber and Silver etc,, will be planted along the lease boundary and avenues as well as over non active dumps at a rate 100 trees per annum with an interval of 5m. The rate of survival expected to be 80% in this area. The present mining is proposed to an average depth of 23 m. The mined out area will be fenced on top of open cast working with S1 fencing. Low lying areas with water logging shall be used for fish culture. No immediate proposals for closure of pit as the Granite Building stone persist still at deeper level. 6.3 Social Infrastructure Employment generation Measures to improve the socio economic conditions of the area Local people (23) will be employed on priority basis as per their skills. Direct and indirect development of the society. As a part of corporate social responsibility, it is proposed to spend Rs.4.0 Lakhs (Recurring) and 5.0 Lakhs (Non Recurring) for various local development activities like conducting medical checkups for the local people, road development, improvisation or development of temples, providing scholar ships for the back ward and girl students, physically handicapped etc. Medical facilities to the workers employed at site. 19

20 6.3.2 CSR Activities As part of our Corporate Social Responsibilities (CSR) activity for this project, we plan to carry out some activities like renovation of existing buildings, sanitary facility, facilitation of drinking water, supply of books & journals, computer and etc, to nearby Govt. School Promotion of Education To improve the infrastructure facilities, the management will support Schools near to our project. PARTICULARS TOTAL AMOUNT TYPE OF EXPENSE Water Purifiers 50,000 Non Recurring Books for Library 60,000 Non Recurring Computers 75,000 Non Recurring Smart Classrooms 1,50,000 Non Recurring TOTAL 3,35,000 The project can start a scholarship & sponsorship programme for children of nearby Govt. Schools, who are from economically backward families. PARTICULARS CALCULATION TOTAL TYPE OF EXPENSE AMOUNT Scholarship for children from 5,000 X 20 1,00,000 Recurring economically back ward families School Kit (Bag, Uniform etc) 1,000 X 50 TOTAL 50,000 Recurring 1,50, Environmental Sustainability The project can plant 200 saplings in the region in association with various schools and clubs. This will help to aware children and public about the importance of nature Particulars Calculation Total Amount Type of Expense Saplings 50 X200 10,000 Non Recurring Protection Net 100 X ,000 Non Recurring Maintenance 25 X 200 5,000 Recurring Working cost 10,000 Non Recurring TOTAL 45,000 20

21 Health Care The project will support the people from economically backward families to construct toilets. This initiation will help them to lead a safe and secure life. PARTICULARS CALCULATION TOTAL AMOUNT TYPE OF EXPENSE Toilet 50,000 X 2 1,00,000 Recurring TOTAL 1,00,000 The project can conduct medical camp in association with nearby Hospital Particulars Total Amount Type of Expense Medical camp 20,000 Recurring TOTAL 20, Social Aspects The renovation of village Road. This initiation will improve the basic infrastructure of the area Particulars Total Amount Type of Expense Road Renovation 1,25,000 Recurring TOTAL 1,25,000 Construction of waiting shed at the nearest Bus stop. Particulars Bus Stop Total Amount 1,25,000 TOTAL 1,00,000 Type of Expense Non-Recurring 21

22 Utilities The list of machineries proposed to deploy in rough stone mine is given as below Table 6-1 List of Machineries S.No Machine Type Required Nos Size / Capacity 1 Jack Hammer mm Dia 2 Hydraulic Excavator L&T or M3 Ex200 3 Tippers / Trucks 3 10 M.T 6.4 Waste Management Liquid Effluents Domestic effluent sent to septic tanks followed by soak pit Air Pollution Periodically air samples will be collected and tested in the laboratory. Control measures like suppression of dust by water sprinkling and developing green belt along the periphery of the pit will be carried out for controlling the dust Solid Waste The wastes are generated during the mining plan period is about M.T, will be proposed to Dumping to the lease area. Dumping area Dimensions are given below Dump Dimensions Mineral Reject Dump 50.0m(L) X 7.5m(W) X 3.0(H) 22

23 7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN The quarry location is a non agricultural hilly terrain and there is no any human settlement within the quarry area. The nearest public buildings / settlements is at Meenkunnam which is at a distance of 1.0 kms towards west of the quarry area. Hence there is no rehabilitation and resettlements are required. 23

24 8.0 PROJECT SCHEDULE & COST ESTIMATE Infrastructure facilities are in the form of first aid room, labour sheds, sanitary facilities etc,. The mine roads are also developed as semi permanent nature. No major construction activity involves. 8.1 Estimated project cost along with analysis in terms of economic viability of the project The estimated cost of the project is approximately Rs Lakhs a) Fixed Asset Cost i) Land Cost Rs 20,00,000 ii) Laborers Shed Rs1,00,000 iii) Sanitary facility Rs2,00,000 iv) Fencing cost Rs1,00,000 v) Total Rs 24,00,000/- b) Operational Cost i) Machinery cost Rs. 20,00,000/- c) EMP Cost i) Drinking water facility for the laborers Rs1,00,000 ii) Water Sprinkling Rs1,00,000 iii) Safety kits, Rs1,00,000 iv) Dust control Rs50,000 v) Afforestation etc. Rs 50,000 vi) Water quality test Rs 50,000 vii) Air quality test Rs 50,000 viii) Noise/vibration test Rs 50,000 ix) Cost towards charity Rs 50,000 Total Total Project Cost Rs 5,50,000/ Rs 49,50,000/24

25 9.0 ANALYSIS OF PROPORSAL ( FINAL RECOMMENDATION) The Building Stone quarry plan has been approved by Department of Mines and Geology for a proposed total capacity of MT of Granite Building stone for 3 years. The financial estimates reveal high rate of returns. The project is economically viable. The estimates have also taken into consideration the occupational health and safety expenses, environmental protective measures, social welfare activities etc., Considering all the above aspects, we request you to accord Environment Clearance for this project at the earliest. Duly filled Form-1 M, Pre Feasibility Report, District Survey Report and Approved Mining Plan are prepared and annexed with this document. Project Proponent (Along with name and address) Mr. Saji Sebastian Madeckal House, Kizhakkambalam P.O, Ernakulam District, Kerala State

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT 1 MCDR INSPECTION REPORT General SN Particulars Details Date of Inspection 18.10.2016 1 Name of the Mine Dhobitola Titaniferous Iron Ore Mine 2 Total Lease Area (Ha) 2.61 Ha (Entire Forest Land) with breakup

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED HALF YEARLY PROGRESS REPORT ON IMPLEMENTATION OF ENVIRONMENTAL CLEARANCE CONDITION BY MoEF (PERIOD FROM OCTOBER 13 TO MARCH 14) HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED SIX MONTHLY

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 31/05/2012 TO PIRABHAI VALABHAI NANDASANIYA LOCATED

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

THE RAMCO CEMENTS LIMITED

THE RAMCO CEMENTS LIMITED 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE JAYANTHIPURAM NORTH BAND MINING LEASE 2.0 MILLION TPA CAPACITY EC Lr. No. : J-11015/377/2006-IA.II

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH FORM I (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri K. Ravi Shankar Door No. 39/49/39, Krishnadevaraya

More information

STONE CRUSHER. Profile No.: 60 NIC Code: INTRODUCTION: 2. PRODUCT & ITS APPLICATION:

STONE CRUSHER. Profile No.: 60 NIC Code: INTRODUCTION: 2. PRODUCT & ITS APPLICATION: Profile No.: 60 NIC Code: 08106 STONE CRUSHER 1. INTRODUCTION: Crushed stone is also known as metal jelly. Crushed stone is segregated into various sizes viz. 35mm, 20mm, 12mm etc. for different uses.

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal 1.0 SUMMARY OF THE PROJECT PRE-FEASIBILITY REPORT Project Name of Company / Mine Location Village Taluka District State Sand mine Gram Panchayat Tarrighat, Sand mine Tarrighat Tarrighat Patan Durg Chhattisgarh

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

Quarry, Mobile asphalt plant, Equipment Yard and Storage Garage

Quarry, Mobile asphalt plant, Equipment Yard and Storage Garage Quarry, Mobile asphalt plant, Equipment Yard and Storage Garage Trans Canada Highway, 8.5 KM west of Springdale Jct, NL. Department of Environment and Conservation File Ref No. 200.20.2475 Prepared for.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN HALF YEARLY REPORT FOR THE PERIOD OCTOBER, 2011 to MARCH 2012 V. S. Lignite Power Pvt. Ltd. Name of the Project : 1x 135 MW Lignite

More information

4. PROFILE ON GRANITE CUTTING

4. PROFILE ON GRANITE CUTTING 4. PROFILE ON GRANITE CUTTING 4-2 TABLE OF CONTENTS PAGE I. SUMMARY 4-3 II. PRODUCT DESCRIPTION & APPLICATION 4-3 III. MARKET STUDY AND PLANT CAPACITY 4-4 A. MARKET STUDY 4-4 B. PLANT CAPACITY & PRODUCTION

More information

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary TABLE OF CONTENTS Title page Table of contents List of tables List of figures Non- technical summary Page i ii vii viii ix CHAPTER 1: INTRODUCTION 1 1.1 Project Background 1 1.2 Aims and Objectives 3 1.3

More information

PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA

PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA 21-07-2107 INTRODUCTION The Sandur Manganese & Iron Ores Ltd. (SMIORE) are operating

More information

The mine is opened on The reasons for delay for starting mining operations are:

The mine is opened on The reasons for delay for starting mining operations are: 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly known as Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE BUDAWADA LIMESTONE MINE - 1.10 MILLION TPA CAPACITY EC Lr. No : J-11015/150/2008-IA.II

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

ToR Letter No. SEIAA/AP/ANT/ Dated Monitoring Period : October 2016 to December Applicant

ToR Letter No. SEIAA/AP/ANT/ Dated Monitoring Period : October 2016 to December Applicant EXECUTIVE SUMMARY of Proposed Quartz Mine (30.667 Ha.) with a Production of 91,125 TPA at Sy. No. 410, D.Cherlopalli Village, Bathalapalli Mandal, Anantapur District, Andhra Pradesh. ToR Letter No. SEIAA/AP/ANT/2015-3568

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment A brief discussion Presented by: Apekshit Solanki Kirti Neetu Yadav Sameera Vishakha Shankar Introduction EIA is a formal process to predict the environmental consequences

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

BASIC INFORMATION QUESTIONNAIRE

BASIC INFORMATION QUESTIONNAIRE Application No. Central Environmental Authority BASIC INFORMATION QUESTIONNAIRE Essential information to determine the environmental approval requirement of projects (Note Use separate sheets as and when

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests Paryavaran Bhavan, C.G.O. Complex, Lodi Road, New Delhi-110 003. Dated the 28th June, 2013 To, M/ s Arbind Kumar Singh

More information

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17.

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17. STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. SURVEY NO.81/2, NEAR VILLAGE - KODIDRA, TALUKA- VERVAL, DISTRICT GIRSOMANATH, (GUJARAT) PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE

More information

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR Near Village Tehsil District State Capacity Lease Area Category of Project Project Cost KANTBARA BIJOLIYA Bhilwara Rajasthan 36561 TPA of

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any; TERMS OF REFERENCE 1.0 PROPOSED SCOPE OF WORK FOR EIA STUDY The components of the EIA study include: Determination of baseline data using primary data generation and secondary data available from various

More information

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The groups cement facilities are located

More information

Outline for. Protected Areas Management Planning

Outline for. Protected Areas Management Planning Outline for Protected Areas Management Planning Level One: Community-based protected area management organizations and Level Two: Conservation organizations / Non-governmental organizations Outline for

More information

Pre-Feasibility Report. for. Proposed Construction project of Santnagari

Pre-Feasibility Report. for. Proposed Construction project of Santnagari Pre-Feasibility Report for Proposed Construction project of Santnagari at Survey No. 1439, Near Dharoi Dam, Village Mahor, Taluka Vadali, District Sabarkantha, Gujarat By Gujarat Pavitra Yatradham Vikas

More information

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres ) PRE FEASIBILITY REPORT FOR Mining of Riverbed Sand From Darakeswar River Area : 8.09 Ha ( 20 Acres ) AT Mouza: Kunjapur, Plot No: 2227 (P), 2269 (P), 2603 (P),JL: 112, Village: Kunjapur, Block : Indus,,

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT Annexure B Land Possession letters & N.A. permission letters Annexure C Photograph of the Site Annexure D Details of Buildings Area Calculation Annexure 1 Topo Sheet Annexure 2 Soil Analysis Report Annexure

More information

AGENDA ITEM NO. F. No. 8-20/2015-FC

AGENDA ITEM NO. F. No. 8-20/2015-FC AGENDA ITEM NO. F. 8-20/2015-FC Sub: Proposal for according permission for use of 2.0001 ha of forest land within total forest land of 400 ha (out of total prospecting lease area of 816 ha) in Meenakshi

More information

.in Dated 9th August, Sharma ;

.in Dated 9th August, Sharma  ; F. No. J-11011/151/2010-IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi -110 003.. To, Ankleshwar E-mail: pb.rastoai@nic.in

More information

SCHOOL SITE SELECTION GUIDE

SCHOOL SITE SELECTION GUIDE SCHOOL SITE SELECTION GUIDE Ministry of Education Province of British Columbia 7 Preface The Ministry of Education School Site Selection Guide has been developed by the School Finance and Capital Planning

More information

Forest (Conservation) Rules, 1981

Forest (Conservation) Rules, 1981 Forest (Conservation) Rules, 1981 (as amended up to May 1992) G.S.R. 719... in exercise of the powers conferred by sub-section (i) of section 4 of the Forest (Conservation) Act, 1980 (69 of 1980), the

More information

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (Gazette No. 23922, Notice No. 1273 dated 10 October 2002. Commencement date: 1 May 2004 [Proc. No. R25, Gazette No. 26264])

More information

Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623)

Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623) Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623) 1 Contents Background Objective EIA of Hydroelectric plants Tools and Techniques used

More information

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1 White Clay/China Clay Mining Project (3,250 TPA), M.L. No.3/01, ML Area 4.80 ha, Index INDEX 1 EXECUTIVE SUMMARY... 1 2 INTRODUCTION OF THE OBJECT/ BACKGROUND INFORMATION... 4 2.1 IDENTIFICATION OF PROJECT

More information

FORM-1, PRE FEASIBILITY REPORT ENVIRONMENT MANAGEMENT PLAN FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE

FORM-1, PRE FEASIBILITY REPORT ENVIRONMENT MANAGEMENT PLAN FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE FORM-1, PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. SURVEY NO.81/2, NEAR VILLAGE - KODIDRA, TALUKA- VERVAL, DISTRICT GIRSOMANATH, (GUJARAT) PROPOSED

More information

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server. Environmental Clearance Point Wise Half Yearly Compliance Report (October 2014 to March 2015) Cement Plant - EC No: F.No. J-11011/450/2007-IA II(I) Dated: 24 th March 2008 A. SPECIFIC CONDITIONS : S.NO.

More information

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi PRE FEASIBILITY REPORT For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS Of M/s. M.K. DRUGS F-10, Industrial Area, Focal Point, Tehsil: Derabassi Dist: Mohali, Punjab INTRODUCTION M/s. M.K. Drugs is

More information

SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION

SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION CITY OF GENEVA, NEW YORK The purpose of the site plan and architectural review process is to secure compliance with the City s Zoning Ordinance and to promote

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

File No Supplemental November Geotechnical and Environmental Consulting Engineers

File No Supplemental November Geotechnical and Environmental Consulting Engineers Supplemental Information & Geotechnical Recommendations Proposed New Solar Valley Location B (East of Building No. 7) Cañada Community College 4200 Farm Hill Boulevard Submitted to: Mr. Peter Hempel Construction

More information

INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office

INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office Mine file No HP/BLS/LST-9 (i) Name of the Inspecting Officer and ID No. (ii) Designation

More information

Photographic Processing Facility Sector Control Policy

Photographic Processing Facility Sector Control Policy Photographic Processing Facility Sector Control Policy Persigo Wastewater Treatment Plant Industrial Pretreatment Division 2145 River Road Grand Junction, CO 81505 970-256-4180 I. INTRODUCTION The United

More information

1. (I)Name of the applicant & company name. (II)Father s / Husband s Name in the case of individuals. (III)Complete Postal Address

1. (I)Name of the applicant & company name. (II)Father s / Husband s Name in the case of individuals. (III)Complete Postal Address APPLICATON FOR ISSUE OF GROUND WATER CLEARANCE / NO OBJECTION CERTIFICATE FOR INDUSTRY / CONSTRUCTION / HORTICULTURE / COMMERCIAL / INFRA STRUCTURES / OTHER USERS 1. (I)Name of the applicant & company

More information

Research Compendium. Coal Sector in India 2013 A comprehensive data and information update

Research Compendium. Coal Sector in India 2013 A comprehensive data and information update Research Compendium Coal Sector in India 2013 A comprehensive data and information update Release Date : August 2013 Background About the report Coal is the only major conventional source of energy that

More information

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY EXECUTIVE SUMMARY 1. PREAMBLE Minerals are the chief source of present phase of industrialization, and play an important role in the present phase of the national economy and overall development of the

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

RECLAMATION OF COAL MINE VOID

RECLAMATION OF COAL MINE VOID RECLAMATION OF COAL MINE VOID Reclamation of Coal Mine Void with Fly Ash Filling of mine voids with fly ash in an environmental sound process is the most viable option of bulk utilisation. This not only

More information

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited EXECUTIVE SUMMARY A. INTRODUCTION : M/s Jayaswal Neco Industries Limited (JNIL) belongs to the wellknown industrial group of Central India viz. NECO GROUP having annual turnover exceeding Rs. 3500 Crores.

More information

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along Wall Face Option 5 - Steps In Wall; 10 (25cm) Tread Option

More information

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Wall - Option 4 Steps and Stairs Q & A E CONSTRUCTION

More information

Schedule Of Works. 35 Konkan Railway Corporation Limited Signature of Tenderer

Schedule Of Works. 35 Konkan Railway Corporation Limited Signature of Tenderer Schedule Of Works 35 Konkan Railway Corporation Limited Signature of Tenderer Schedule of Works (Package II, Chainage 5/400 to 7/800 = 2400 mtrs SCHEDULE - A (CUTTING) Name of work: Limited tender for

More information

Application for Gas Exploration and Production

Application for Gas Exploration and Production 1800 Washington Blvd. Suite 655 Baltimore Maryland 21230 Application for Gas Exploration and Production This application is to be used to obtain a permit to Drill and Operate a well, within the State for

More information

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings G U I D E L I N E S F O R L A N D O W N E R S, D E V E L O P E R S A N D C O N T R A C T O R S T A B L E O F C O N T E N T S 1 Introduction 2 Office Locations/Map 3 General Requirements 4 Structures and

More information

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE. LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE. LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON 09.08.2016 Ecological Impact of Mining *334. SHRI JANARDAN SINGH SIGRIWAL state:

More information

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No Serial Number FORM 1 (Application for Environment Clearance Certificate) Item 1. Name of the project/s 2. S. No. in the schedule 3. Proposed capacity/ area/ length/ tonnage to be handled/ command area/lease

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Building from the ground up in West Africa. The Hatch approach to projects in a developing country

Building from the ground up in West Africa. The Hatch approach to projects in a developing country Building from the ground up in West Africa The Hatch approach to projects in a developing country 2 Agenda 1. Hatch Contribution to West Africa Development 2. Three Recent Projects on Which We Worked 3.

More information

Minutes of Meeting ( )

Minutes of Meeting ( ) Minutes of Meeting (5.9.2017) Meeting Details Project Supplementary ESIA for Shwe Taung Cement () Cement Plant & Associated Facilities in Myanmar Office/ Department/ Organization Kalewa GAD office Region/

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT TABLE OF CONTENTS Sr. No. Content Page No. 1.0 Executive Summary 24 2.0 Introduction of Project / Background Information 25 3.0 Project Description 27 4.0 Site Analysis 34 5.0 Planning

More information

PRE FEASIBILITY REPORT. This is a proposal of running mining lease for which CTO has been issued by Regional officer, Jaipur.

PRE FEASIBILITY REPORT. This is a proposal of running mining lease for which CTO has been issued by Regional officer, Jaipur. Masonry Stone Mining Project (2,11,000 TPA), M.L. No. 82/97, ML Area 1.0 ha Near Village: Beri Tehsil Kotputali District 1.0 EXECUTIVE SUMMARY PRE FEASIBILITY REPORT This is a proposal of running mining

More information

Bishunpur Small Hydro Power Project

Bishunpur Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102. JAIPRAKASH ASSOCIATES LTD. (CEMENT DIVISION) EXECUTIVE SUMMARY FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.983 Ha) APRIL, 2008

More information

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE APPENDIX VIII Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (I) Basic Information S.No. Particulates Details 1. Name of the Mining Lease site

More information

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from  METS is not the copyright owner. Disclaimer This unofficial translation of Ministerial Decision No 421/1998 was downloaded from www.mets-oman.com. METS is not the copyright owner. METS is not responsible for the content of this document.

More information

HEADQUARTERS WEST LTD. FARM, RANCH, AGRIBUSINESS REAL ESTATE SALES & SERVICES

HEADQUARTERS WEST LTD. FARM, RANCH, AGRIBUSINESS REAL ESTATE SALES & SERVICES Offered For Sale HUNT VALLEY RANCH Apache County, Arizona Exclusively Listed By: Traegen Knight Headquarters West, Ltd. P.O. Box 1980 St. Johns, Arizona 85936 Ph. 928 524-3740 Fx. 928 563-7004 Hunt Valley

More information

PUFFED RICE Introduction Market Packaging Production capacity 5. Sales revenue 6. Production process outline.

PUFFED RICE Introduction Market Packaging Production capacity 5. Sales revenue 6. Production process outline. PUFFED RICE 1. Introduction Puffed Rice is a commonly consumed commodity as a pastime snack. It can be used in combination with nuts such as groundnut or roasted and salted cashews; with fried gram; with

More information

PRECAST CEMENT PRODUCTS

PRECAST CEMENT PRODUCTS Profile No.: 30 NIC Code: 23959 PRECAST CEMENT PRODUCTS 1. INTRODCUTION: Reinforced cement concrete products are becoming popular as modular house and apartment buildings are based on standard designs.

More information

Section 2 Proposal Description

Section 2 Proposal Description Section 2 Proposal Description 2. PROPOSAL DESCRIPTION 2.1 Overview The Proposal comprises the construction, operation and closure of mining at the J5 and Bungalbin East iron ore deposits and associated

More information

Cut and fill productivity. Operating procedures. Introduction. 1. Approach of the model

Cut and fill productivity. Operating procedures. Introduction. 1. Approach of the model Model: Level: Cut and fill productivity Micro Operating procedures Introduction The goal of the model is to calculate realistic productivity from data collected on site and to estimate the effect when

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information