montgomery college rockville student services center student services center Pre-Bid Meeting October 5, 2016 montgomery college rockville campus
|
|
- Loraine Wheeler
- 5 years ago
- Views:
Transcription
1 montgomery college rockville October 5, 2016
2 campus context with project scope
3 new construction campus plan with project scope
4 maintain fire access to the site at all times submit phasing plan for Owner approval existing utility lines to remain operational until new lines installed limited to April-May or September-October existing Student Services Building to remain fully operational until completion of new prior to beginning excavation, complete items 1-4 water line completed by august 15, 2017 maintain access for deliveries at all times FDR alternate at end of construction phasing project phasing summary of requirements
5 phasing phase 1
6 phasing phase 2
7 phasing phase 3 (alternate)
8 access diagram
9 owner: Montgomery College owner consultants: Envelope Consultant: Wiss Janney Elstner (WJE) Systems Commissioning: Facility Dynamics Engineering (FDE) - relatively extensive testing and commissioning requirements design team: Architect: Cho Benn Holback + Associates (CBH) Associate Architect: Bohlin Cywinski Jackson (BCJ) Civil: A Morton Thomas & Associates (AMT) Landscape: Michael Vergason Landscape Architects (MVLA) Geotechnical: Schnabel Engineering Structural: A+F Engineers Mechanical/Electrical/Plumbing: James Posey Associates (JPA) AV/IT and Acoustics: The Sextant Group (TSG) Foodservice Consultant: Culinary Advisors Hardware Consultant: Frank Erbschloe (ECSI) project data - team
10 code authority (AHJ): City of Rockville construction type: IIA, fully sprinklered - primary structural frame = 1HR - bearing walls, int and ext = 1HR - floors and associated members: 1HR - roofs and associated members: 1HR - interior partitions: 0HR - smoke barriers at Lobby perimeter - non-combustible construction occupancy / use: non-separated mixed - Business (B), Assembly (A-3), Storage (S) total gross square footage: 127,275gsf - 23,000gsf to 27,500gsf per floor sustainability target: - LEED Silver required (50 points minimum) - LEED Gold possible (60 points minimum) - current potential point total: 63 - we will operate as if we are going for Gold project data - code and general construction Exterior construction: - cast-in-place and concrete masonry back-up cavity walls - brick masonry veneer (2 types) - curtainwall with fixed louver sunshading - operable casement windows within curtainwall - roofing: torch applied sbs modified bitumen - green roof: approximately 2,300 square feet - metal roof: limited at canopies - loading dock - custom rooftop AHU - high performance envelope - waterproofing coordination with concrete important - plantings, paving, site walls and site lighting Interior construction: - cementitious and intumescent spray fireproofing - metal framing with drywall primarily - acoustic requirements - smoke barrier requirements (Lobby only) - epoxy terrazzo (Lobby / corridors 1+2 and restrooms only) - wood ceiling (Lobby only) - special architectural steel and terrazzo stair (Lobby only) - carpet tile, bio-based composition tile and stained concrete - millwork (p-lam) - non-proprietary elevators - mechanical system oversized for campus usage
11 floor plan basement
12 floor plan level 1 (ground floor)
13 floor plan level 2
14 floor plan level 3
15 floor plan level 4
16 roof plan
17 view from North (North Campus Drive)
18 view from West (existing Humanities Building hidden)
19 view from East
20 view from South
21 view from South - campus connection and lawn
22 interior main entry and lobby space
23 interior 2 nd floor corridor / lounge
24 interior 3 rd / 4 th floor corridor / lounge / conference
25 B(uilding) I(nformation) M(odeling) Montgomery College + Autodesk 360
Fundamentals of Building Construction: Materials and Methods
Fundamentals of Building Construction: Materials and Methods Allen, Edward ISBN-13: 9780470074688 Table of Contents Preface. Chapter 1: Making Buildings. Learning to Build. Sustainability. The Work of
More informationTABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS
AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding
More informationInitial Design & Size
Want to Save time and money on your next building project? Careful planning will help you to anticipate problems, make the right decisions, and to speed construction. If you don t know the answers to all
More informationMANHATTAN COLLEGE STUDENT COMMONS
MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons
More informationUNC Charlotte Science Building Project. Informational Meeting: May 3, 2018
UNC Charlotte Science Building Project Informational Meeting: May 3, 2018 Project Team Owner and Designers UNC Charlotte Donia Schauble Senior Project Manager - Design Jennifer Price Senior Construction
More informationTABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE
TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders
More informationCONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS
CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationJMU Capital Projects SWaM Outreach Event Presentations
JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom
More informationSTRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC
CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION
More informationUniversity of Illinois Business Instructional Facility LEED Gold Design. University of Illinois. University of Illinois
Keys to success: Sustainable design strategies included early. Clear and early benchmarking choice. Integrated design process. Consensus building. Keys to success: Sustainable design strategies considered
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #161 Douthit Hills Student Community, Clemson University Project Tony Greene
March 9, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Final Paint in Building B Electrical Rooms. Completed Final Clean in C1 Units. Completed Installing Carpet/Base in Building D Corridors.
More informationProject Information Session / Meet and Greet # 3
ATL WEST DECK COMPONENT Project Information Session / Meet and Greet # 3 Holder-Austin-Moody-Bryson, a Joint Venture October 10 th, 2017 Agenda 1. HAMB, a JV Company Overview 2. ATL West Deck Project Description
More informationDESIGN & CONSTRUCTION GUIDELINES
DESIGN & CONSTRUCTION GUIDELINES EDITION: USF FACILITIES MANAGEMENT - DC 5 DCG FACILITIES MANAGEMENT DESIGN & CONSTRUCTION PHONE: (813) 974-2845 4202 E. FOWLER AVENUE, OPM 1000 TAMPA, FLORIDA 33620-7550
More informationFRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6
PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA
More informationNOTTAWASEPPI HURON BAND of the POTAWATOMI
NOTTAWASEPPI HURON BAND of the POTAWATOMI Widoktadwen New Government Center Bid Pkg #2 Pre Bid Meeting October 4, 2012 The SKILLMAN Corporation Project Administration Construction Management Nottawaseppi
More informationSimcoe County District School Board. 5yr Condition Assessment 2006/07 to 2010/11. Hillcrest PS (Barrie), 9205
5yr Condition Assessment 2006/07 to 2010/11 Construction Year Area 1951 3,813 Page 1 of 25 1. Architectural / Structural & Site Exec Summary Hillcrest Public School is a two storey structure of masonry
More informationCOPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31
Contents Preface to the Sixth Edition xi 1 Making Buildings 3 Learning to Build 4 Buildings and the Environment 5 The Work of the Design Professional 11 The Work of the Construction Professional 19 Trends
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene
October 6, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Hardscapes East of Building C. Completed Building D Dumpster Pad. Completed Brick on Site Wall North of Building D. Completed
More informationAGILITAS Property Development
Hartmann Commons offered by For Infomation and Leasing Mr. Seth T. McDowell 1614 16th Avenue South Nashville, Tennessee 37212 Voice 615-327-8788 Fax 615-327-8789 Hartmann Commons Agilitas Property Development
More informationNYC Department of Education
Building Assessment Survey 2017-2018 Asset: SAINT FRANCIS COLLEGE - BROOKLYN, 180 REMSEN STREET, New York, 11201 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-02-05
More informationBVSC BVSC. Midwest Technical Inspections Survey Worksheet. Account / Account Code: Insured: Policy #: Building Data - Section 1
Midwest Technical Inspections Survey Worksheet BVSC BVSC Account / Account Code: Agency: Insured: Policy #: Telephone: Alt. Phone: Building Data - Section 1 Building Name (Entire Valuation) Section Name
More informationAIR CRE Industrial Building Standards
AIR CRE Industrial Building Standards Established March 1993 AIR CRE 500 N Brand Blvd, Suite 900, Glendale CA, 91203 AIR CRE INDUSTRIAL BUILDING STANDARDS TABLE OF CONTENTS SECTION 1 Introduction P. 1
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 370 - BROOKLYN, 3000 WEST 1 STREET, New York, 11224 Inspection Id Inspection Type Time In Last Edited Asset Data Architectural
More informationSubject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3
MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape
More informationAPPLICATION AND CERTIFICATE FOR PAYMENT
AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in
More informationLEED TM POINT DOCUMENTATION
LEED TM POINT DOCUMENTATION 1100 SUMMARY LEED PROGRAM 1101 REQUIREMENTS 1125 SUMMARY OF MULTIPLE CONTRACTS WORK 1140 RESTRICTIONS 1210 ALLOWANCES 1230 ALTERNATES 1250 CONTRACT MODIFICATION PROCEDURES 1270
More informationSubcontractor Pre-Qualification Statement Hunt / Moss, A Joint Venture
Subcontractor Pre-Qualification Statement Hunt / Moss, A Joint Venture 1. SUBMITTED BY: DATE: Name of Firm: Street Mailing Address (If different): Primary Fax: E-mail: Website: Address of the office that
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: I.S. 364 AX (POOL&GYM)-BROOKLYN, 1540 VAN SICLEN AVE, New York, 11239 Inspection Id Inspection Type Time In Last Edited SA : Architectural
More informationMaterial Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5
Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene
February 16, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed 1 ST Coat of Paint in C5 Corridors. Completed Test & Balance in Building C. Completed Final Paint in B1 Corridors. Completed
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationPRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016
PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 WORK LEGEND OVERALL WORK TO BOTH BUILDINGS 1 2 3 4 Existing corridors will receive new
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene
August 25, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Turned All East Zone Parking Lots Over to Clemson. Completed Trench Drain on Bradley Road. Completed Pouring Walls for Building D
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More informationNAME OF PROJECT Design Development. General Objectives of Phase. Phase Task Checklist. Quality Management Phase
General Objectives of Phase Drawings and other documents to fix and describe the size and character of the project as to architectural, structural, mechanical and electrical systems, materials and such
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Pate Elementary School Observed By: Creed/Carter Principal: Grade
More informationBUILDING STATISTICS PART 1
BUILDING STATISTICS PART 1 UNIVERSITY OF MARYLAND BALTIMORE HEALTH SCIENCES FACILITY III 666 W. BALTIMORE ST. BALTIMORE, MD KENNETH MOORE LIGHTING / ELECTRICAL THESIS ADVISOR: SHAWN GOOD TABLE OF CONTENTS
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #168 Douthit Hills Student Community, Clemson University Project Rush Dunaway
April 27, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Continued Installing Wireless Access Points in Bldg C. Continued Signing Off Punch List Items in the West Zone. Continued Cleaning Interior
More informationTABLE OF CONTENTS Public Safety Building
DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More information1200 Oakman Blvd INDUSTRIAL INVESTMENT/ USER OPPORTUNITY. Building A 85,999 SF. Building D. Building C 11,495 SF 15,046 SF.
1200 Oakman Blvd A 85,999 SF Detroit, MI 48238 C D 15,046 SF A C Below (4) Grade Level Replacement Cost Doors Shop Floor Height: Zoning M4-Intensive 18 3 Industrial District Immediate HVAC - 6 Ton Unit
More informationAllison M. Clarke Construction Management Capital One Headquarters McLean, VA Executive Summary Overall Existing Conditions Summary
Executive Summary Overall Existing Conditions Summary The results of my researching the topics requested for the Overall Existing Conditions Summary, ended up helping me to learn more about the items I
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene
January 19, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Carpet & Base in B6 Corridor. Completed 1 ST Coat of Paint in B4 Corridor. Completed 2 ND Coat of Paint in C3 Units Completed
More informationdate: 10 july 2012 the pennsylvania state university: burrowes building
the pennsylvania state university: burrowes building. faculty/staff committee project overview introductions goals of the renovation critical considerations exterior envelope mechanical systems interior
More informationCAMPUS STANDARDS HANDBOOK
CAMPUS STANDARDS HANDBOOK OFFICE OF PHYSICAL PLANNING AND CONSTRUCTION UNIVERSITY OF CALIFORNIA, SANTA CRUZ Italics indicate recent revisions. THESE STANDARDS ARE PROVIDED TO UCSC CONSULTANTS FOR GUIDANCE
More informationFleet Elementary School
Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 Y DATE: December 6-8, 2016 ****************************************************************************** SUBJECT: SDSU Student Wellness
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationMidwester State University Health Science Center
Bid Proposal For: Bid Due: Bids Received At: Email Bid to: Midwester State University Health Science Center 8-Aug-17 Midwestern State University Attn: Steven Shelley - Director of Purchasing/Contract Management
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationFire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II
Fire Inspection and Code Enforcement, 7 th Edition Chapter 6 Building Construction: Components Today we will Discuss fire walls, party walls, fire partitions, and curtain walls Discuss roof types and coverings
More informationSTATE UNIVERSITY CONSTRUCTION FUND Concept Phase Checklist
STATE UNIVERSITY CONSTRUCTION FUND Concept Phase Checklist The following checklist shows the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the
More informationSTATE UNIVERSITY CONSTRUCTION FUND
STATE UNIVERSITY CONSTRUCTION FUND The following checklist show the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the Schedule B of the Consultant
More informationINNOVATIVE OFFICE SPACE AT A PREMIER LOCATION.
500 North Hurstbourne, Louisville, Kentucky 40222 INNOVATIVE OFFICE SPACE AT A PREMIER LOCATION. 4 Floors 120,000 Square Feet Class AA+ Office Building A Paramount And Landmark Location On Hurstbourne
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More informationCALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3%
CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE EXAM ID: I6 80 multiple-choice questions 3-1/2-hour time limit Open book 01. GENERAL ADMINISTRATION 3 % 0101. Project Administration 3% Verify that plans,
More informationSchool Assessment Report
School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report
More informationADDENDUM NO. 2 Consisting of 3 pages and Attachments
10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta
More informationNYC Department of Education
Architectural Inspection Asset: Building Assessment Survey 2017-2018 NYC SCHOOL CONSTR. AUTHORITY - QUEENS, 30-30 THOMSON AVE, New York, 11101 Inspection Id Inspection Type Time In Last Edited SA : Architectural
More informationPACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS
PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS Urban infill on a previously developed site. The new building was built over an existing parking lot. Landscaping is composed of all native plants
More information5.0 BUILT FEATURES 5.5 AUDITORIUM (ASSEMBLY ROOM)
5.5 AUDITORIUM (ASSEMBLY ROOM) auditorium for presentations, seminars with projection room behind east wall access behind west wall (stage wall) to basement stairs and exterior 6 rubber base 1/4 mahogany
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Cain Elementary School Observed By: Creed/Carter Principal: Grade
More informationNYC Department of Education
NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 81 ANNEX (OLD 75) - QUEENS, 511 SENECA AVENUE, New York, 11385 Inspection Id Inspection Type Time In
More informationNYC Department of Education
Building Assessment Survey 2017-2018 Asset: P.S. 65 - BROOKLYN, 158 RICHMOND STREET, New York, 11208 Inspection Id Inspection Type Time In Last Edited Architectural - Senior 2018-05-15 11:22 AM 2018-06-12
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationMargaret Batts Tobin Laboratory
Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of
More informationADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:
ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan
More informationNYC Department of Education
NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 234 ANNEX - MANHATTAN, 200 CHAMBERS STREET, New York, 10007 Inspection Id Inspection Type Time In Last
More informationDIVISION 7 - THERMAL AND MOISTURE PROTECTION
07100 WATERPROOFING 07150 DAMPPROOFING 07175 Water Repellent Coatings 07190 VAPOR AND AIR RETARDERS 07192 Vapor Retarders 07200 INSULATION 07240 Exterior Insulation and Finish Systems 07250 FIREPROOFING
More informationHARLEY CLARKE MANSION Condition Assessment
HARLEY CLARKE MANSION Condition Assessment 2603 Sheridan Road Evanston, Illinois 60201 Final Report August 24, 2016 WJE No. 2016.5003 Prepared for: Ms. Lisa DiChiera Landmarks Illinois 30 North Michigan
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: SECOND OPPORTUNITY SCHOOL - K, 797 BUSHWICK AVENUE, New York, 11221 Inspection Id Inspection Type Time In Last Edited SA : Architectural
More informationSTRUCTURAL ASSESSMENT OBSERVATION REPORT
Consulting Engineers THORSON BAKER & Associates, Inc. 3030 West Streetsboro Road (330) 659-6688 phone Richfield, Ohio 44286 (330) 659-6675 fax www.thorsonbaker.com STRUCTURAL ASSESSMENT OBSERVATION REPORT
More informationCEFPI Monthly Meeting
CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type
More informationCSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP
VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 21
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 12 - QUEENS, 42-00 72 STREET, New York, 11377 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-09-26
More informationIn the design development phase, submit finish and material selections to Facilities Management Planning Group for review.
09 00 00 FINISHES 09 01 00 Maintenance of Finishes 09 01 20 Maintenance of Plaster and Gypsum Board 09 01 20.91 Plaster Restoration 09 01 30 Maintenance of Tiling 09 01 30.91 Tile Restoration 09 01 50
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationSERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS
SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,
More informationLEAD DESIGN PROFESSIONAL:
2009 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of Project: Address:
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S./I.S. 266 - QUEENS, 74-10 COMMONWEALTH BLVD, New York, 11426 Inspection Id Inspection Type Time In Last Edited SA : Architectural
More informationEvansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data
Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationHERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School
HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has
More informationSimcoe County District School Board. 5yr Condition Assessment 2006/07 to 2010/11. Warnica PS, 9283
5yr Condition Assessment 2006/07 to 2010/11 Construction Year Area 1964 3,035 Page 1 of 27 1. Architectural / Structural & Site Exec Summary Warnica Public School is a one storey structure of masonry construction
More informationNOTE: For construction other than new commercial or additions (renovations), only those areas below describing the scope of work will be applicable.
Applicant s Name: New Commercial - Commercial Additions Renovations Permit Plan Submittal Check List Applicant s Phone Number (s): Project Address: Project Type: _New Commercial or Commercial Addition
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More informationDivision 00 Procurement and Contracting Requirements
SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationWatercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS
Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING
More informationMarch 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT
March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationPRELIMINARY STRUCTURAL INVESTIGATION REPORT
124 E. Broadway Tucson, AZ Prepared for: CBRE Brokerage Services 3719 N. Campbell Ave. Tucson, AZ 85719 BACKGROUND: The Tucson Veterans of Foreign Wars building, located at 124 E. Broadway, Tucson, AZ
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 290 - MANHATTAN, 311 EAST 82 STREET, New York, 10028 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior
More information