1 Florida Department of Transportation DESIGN-BUILD PUSH BUTTON Contract (FEDERAL SAFETY AND STATE FUNDS) Presentation to FHWA EDC 3 Systemic Safety Implementation Peer Exchange, Nashville, TN September 15,
2 Jobs Creation Fast Response Saving Lives Customer Service 2
3 Presentation Content History of the Contract Reasons to create this Contract Contract Process Tasks issued in 6 years Tasks Evaluation Contract Pros & Cons How to start your own DBPB Contract 3
4 FDOT DESIGN-BUILD PUSH BUTTON Contract -- History Starting in Year 2004 questions from District Traffic Operations concerning developing a new type of contract that would significantly reduce the amount of time it took to get a project from concept to concrete. Florida DOT already utilizes two (2) innovative types of contracts that provide some time-savings over the traditional Design-Bid-Build methodology. But, those two (2) innovative types of contracts Design-Build and Push-Button still had their limitations. Therefore, during a moment of inspiration, we reasoned why not try to combine those two (2) contracting strategies into a single contract? Traffic Operations Design-Build Push-Button concept was born! (Similar to FHWA TOPICS ) THEN, OUR NEXT CHALLENGE WAS TO SELL THE PLAN FDOT DBPB Evaluation 4
5 FDOT DESIGN-BUILD PUSH BUTTON Contract History (Cont.) On February 11, 2004, District Seven began to correspond with the Central office about our proposal of combining the design-build contracting methodology with the push-button contracting methodology to marry the benefits of both of those contracting strategies into a single contract using both State funds and Federal safety funds. In September, 2007, Central office agreed to allow District Seven to proceed with a pilot program to test-fly this one-of-a-kind and totally unique contracting concept. While the District began developing the RFP for such a combined contract, District Seven worked with FHWA FL Division to gain approval to include federal safety money under this unique combined contract on June 30, With FHWA s concurrence, District moved forward with the concept by conducting an informational meeting with the consultant community and the contractor industry. And, after receiving input from that forum, we completed the RFP and advertised the contract on March 24, District shortlisted three teams, evaluated their technical proposals, opened their price proposals, calculated the resulting adjusted-scores, and finally posted our contract execution on December 17,
6 FDOT DESIGN-BUILD PUSH BUTTON What is FHWA TOPICS? FHWA policy in late 1960 s & continued to late 1970 s Original Memo dated 1/17/1969 with 2 nd memo on 12/18/1978 TOPICS (FHWA) = Traffic Operations Programs to Increase Capacity & Safety TOPICS (FDOT) = Traffic Operations Projects to Improve Capacity & Safety 6
7 FDOT DESIGN-BUILD PUSH BUTTON Reasons for this Contract Streamlined Process Quick Solutions to operational & safety problems Covering wide range of projects Faster results = Reduce crashes early Innovative Approach Biggest bang for the buck Time Factor Similar to the early 1970 s era FHWA TOPICS program 7
8 FDOT DESIGN-BUILD PUSH BUTTON -- Reasons for this Contract Why Design-Build Push Button? Time Factor Month LAP LAP Certification* LAP Agreement Evaluation/Selection of Firm/Design Letting/Select a Low Construction Bidder/ Prepare for Construction Construction Design/Bid/ Build Evaluation / Select a Design Firm Design/Review Process Construction Class 1/District Let Evaluation / Select a Design Firm Prepare 60% Plans 60% Review/Comments/Prepare Final Plans/Review Comments/Prepare Spec. Package Letting/Select a Low Construction Bidder/ Prepare for Construction Construction Push Button Evaluation / Select a Design Firm Task Work Order Design/Review Hand off Construction to Construction Design/Build-PB Evaluation / Select a Design/Build (DB) Firm Review/comments/Prepare Final Plans/DB Firm Procurement of Equipment Construction Project Type Lap certification (Months) LAP Agreement Selection of Design Firm Prepare 60% Plans Task Work Order Design/ Review Process Letting Hand Off to Construction Construction Total Timeline (Months) LAP Project N.A. N.A. Design / Bid / Build Class 1 / District Let Already included 9 N.A N.A. N.A. 6 N.A. N.A N.A N.A. N.A. 6 3 N.A. 9 9 N.A Push Button N.A. N.A. 6 N.A. 2 6 N.A Design Build / Push Button N.A. N.A. 6 N.A. N.A. 6 N.A. N.A. 3 (Overlap) 13 * Note : Multiple Tasks can be issued under DBPB versus one task under Design-Build or Design-Bid-Build Projects. 8
9 FDOT DESIGN-BUILD PUSH BUTTON What is Push Button? FDOT Push Button Contract is similar to the NYDOT Job Order Contracting (JOC) multiple tasks see FHWA 5/24/11 webinar NYDOT JOC can only handle Preventive Maintenance tasks using federal funds FDOT can only use State fund for Push Button construction contract multiple tasks! Current FDOT construction approach for federal safety funded projects Design/Bid/Build or Design/Build one project per contract! DBPB contract combines the beauty of Design-Build & Push Button contracts -- to be able to use federal safety funds to issue multiple safety projects during the contract period (two or three years)! 9
10 FDOT DESIGN-BUILD PUSH BUTTON - Contract Process Develop the Request for Proposal (RFP) by Traffic Operations office. Communicate with Contract, Design & Construction offices. Prepare the Contract package by Professional Service office. Obtain approval from Legal office & FHWA Division office. Allocate State and/or Federal fund for the Contract. Will need to decide the length of the contract (3 contract years in FL now) & Stipends (not allow in FL now). Develop the initial projects in the 1 st contract task for short listed teams. Advertise the contract. Select the short listed teams (3) to design those initial projects. Rank & Select the winning team using the adjusted scores approach. Execute the contract it is a 9+ months process!!! 10
11 FDOT DESIGN-BUILD PUSH BUTTON - Contract Process Technical proposal evaluation criteria: Contract selection formula: Team with the lowest Adjusted Score is selected 11
12 FDOT DESIGN-BUILD PUSH BUTTON - Task Process Conduct the thorough Feasibility (all funds) & Justification (Federal Safety Funds) Study - includes National Environmental Policy Act (NEPA) requirements. Generate Task Scopes with maximum task time and cost. Conduct the Task Scopes Review Coordination! Send Task Scopes with all supporting studies to FHWA for approval. Allocate the approved State or Federal fund for each DBPB task. District Construction office sends the task(s) Notice to Proceed (NTP) to the DBPB Prime firm. DBPB team starts to work on the task! Task time period is counted from NTP to end of the construction. Use SharePoint technology and weekly progress meetings to share the DBPB Plans & task Information Communication is the Key for Success! 12
13 FDOT DESIGN-BUILD PUSH BUTTON - Task Process Involvement with local agencies 3 times for each DBPB task: -- Task Scope Preparation Stage, Coordinates with MPOs & Local Agencies -- Task NTP Stage, Community Awareness Plans for Elected Officials -- Task Design Stage, Plan review with local engineering agencies Three (3) phases in FDOT DBPB contract: -- Constructability Analysis Phase -- Design-Build Phase -- Contract Tracking & Evaluation Phase 13
14 FDOT DESIGN-BUILD PUSH BUTTON How to select a Candidate Project? Is it Operational or Safety Related issue? NO END Design (Consultant) Scope (FDOT) Construction (Contractor) YES Work Program YES Right of Way (R/W) Apply State Funds NO YES State Project Qualified For Fed. Safety? Qualified for State Funded? Federal Guidelines YES Apply Fed. Safety Funds Safety Project Design Build Push Button Project FINAL PRODUCT Federal Guidelines 14
15 FDOT DESIGN-BUILD PUSH BUTTON Total Tasks + $ in 6 years DBPB Version I Year 2009 to Year 2012 DBPB Version II Year 2012 to Year 2015 DBPB Version III Year 2015 to Year 2018 $20.13M in 34 months in DBPB I contract -- $6.10M State fund + $1.8M state earmark fund and $12.23M Federal Safety fund. Issued 45 tasks/55 projects in DBPB I contract federal safety funded projects & 17 state funded projects. $20.98M in 36 months in DBPB II contract -- $7.39M State fund and $13.59M Federal Safety fund. Issued 70 tasks/83 projects in DBPB II contract federal safety funded projects & 28 state funded projects. $21.1M in 36 months in DBPB IIII contract -- $8.1M State fund and $13.1M Federal Safety fund. 13 tasks/projects were issued in July
16 Total task cost (D/B) varied between $33,000 and $1,000,000 Flexibility Federal safety funded projects covered Inverted profile marking/ Wet weather audible striping, Pedestrian safety improvement, Bike lanes, High friction pavement, Intersection turn lane improvement, Signal enhancement, Street lighting, Signing safety, Pavement marking safety, Curve safety, Guardrail installation, Access (median) revision Any project with high B/C to address severe crashes. State funded projects covered Signal re-builds, Intersection /interstate operational improvement, Intelligent Transportation System (ITS) projects. Any project with high operational priority (but low safety benefit) FDOT DESIGN-BUILD PUSH BUTTON Types & Sizes of Tasks Design Build Push Button contract can issue numerous tasks, covering various project types through the life of the contract (3 years in this case) 16
17 FDOT DESIGN-BUILD PUSH BUTTON Project Time Evaluation Total Project Time from Concept to Concrete historically for safety projects varies from 30 months to 58 months per types of projects. Typical Total Project Time for DBPB from 2 months to 9 months! Project Time Saving 28 months to 49 months! Reduce crashes early
18 FDOT DESIGN-BUILD PUSH BUTTON Safety Benefit Evaluation Potential crash reduction and actual reduction for safety Case Studies in the DBPB 5.01 vs /Year Corresponding potential crash reduction benefit for Case Studies $18.5M (Total Safety Project Cost: $4.5M) Project Types Locations Projected Crash Reduction per Year Traditional Const. Time (Months) DB PB Const. Time (Months) Time Savings (Months) Potential Crash Reduction DBPB Cost Per Crash Potential Crash Reduction Correctable Crashes Before Construction (Per Year) Actual Correctable Crashes After Construction (Per Year) Reduction Factor Percent of Initial Projected Crash Reduction Achieved Inverted Profile Pavement Markings (Task #1) & Wet Weather Audible Pavement Markings (Task #5) Inverted Profile Pavement Markings Installation of 702 Inverted Profile Pavement Markings to reduce Nighttime/ Wet Weather/ Lane Departure Crashes US $200,834 $2,416, % % US $211,613 $2,009, % % SR 35 (US 301) $102,305 $1,154, % % SR 686 (Roosevelt Blvd) SR 686 (Roosevelt Blvd) SR 50 (Cortez Blvd) SR 50 (Cortez Blvd) $118,319 $165, % % $118,319 $284, % % $118,319 $258, % % $371,295 $227, % % US $371,295 $438, % % SR $371,295 $373, % % US $371,295 $1,332, % % Safety Improvement (Task #14) New Traffic Signal SR 582 (E. Fowler Ave) $128,668 $803, % % Traffic Operations / Safety (Task #15) Roadway SR $108,240 $7,488, % %
19 FDOT DESIGN-BUILD PUSH BUTTON Design/CEI Cost Evaluation Design & Survey Fee % in the DBPB contract 16%, 18% or 20% of the total project construction cost per the level of project difficulty. Design & Survey Fee % for the traditional design-bid-build projects shown in the Florida DOT system depends on the size of the projects varies from 8% (mega $100+ million projects) to 150+% (small operational projects). DBPB projects are usually in the small operational project (30% to 150+%) category. Construction Engineering Inspection Fee % in the DBPB contract funded and conducted by FDOT average 9%. Construction Engineering Inspection Fee % for the traditional design-bid-build projects shown in the Florida DOT system average 10% - 15%. Huge Cost Saving in the Design & CEI Cost -- at least 30% saving! 19
20 FDOT DESIGN-BUILD PUSH BUTTON Construction Cost Evaluation State Wide Unit Price vs. DBPB Unit Price Project Type Description Corresponding Task Numbers Average % Difference vs. Statewide Unit Price District Wide High Emphasis Crosswalk Enhancements 2, 32, 39, 43, 44 & % District Wide Inverted Profile Markings 5 & % District Wide Wet Weather Audible Pavement Markings 1(6), 1(9), 1(10), 5, 17, 28, 29 & % District Wide Pedestrian Signal & Pedestrian Features 1(2), 13, 16 & % Bicycle Lanes Signing & Pavement Markings 25, 26, 36, 37 & % New Signal / Signal Rebuild 14, 40, 46 & % Offset Left Turn Lanes 41 & % Miscellaneous Signing & Pavement Markings 1(7) & % Overhead Sign Structure 1(8) % Installation of Advanced Flashers 1(4) -3.24% Quick Curb to Concrete Median % Intersection Improvements % District Wide High Friction Surface Treatment % Installation of Traffic Separator % 20
21 FDOT DESIGN-BUILD PUSH BUTTON Before & After Pictures
22 FDOT DESIGN-BUILD PUSH BUTTON Evaluation Binder DBPB Contract & Process Details Everything you want to know! 22
23 FDOT DESIGN-BUILD PUSH BUTTON Pros Customer Service -- Florida DOT can finish operational or safety improvements to better meet public expectations on al public roads. Saves Time -- the shortest project time is 2 months for design & build. Minimum project time reduction: 28 months! Saves Lives Reduce project time = Obtain crash reduction early! Flexibility Can issue small or large projects (samples from $33K to $1M). Created/Saved Jobs 88 in FDOT case. Fast plan review process Enforced by the District Design Engineer. Weekly Progress Meetings between FDOT & DBPB teams help -- Communication! Innovative Technology to enhance Communication SharePoint & ERC (Electronic Review Comment System). Teamwork between FDOT offices is amazing! 23
24 FDOT DESIGN-BUILD PUSH BUTTON Cons Administration Issues -- requires a higher level and constant communication between all offices to streamline process. Tasks need to have good feasibility study & clear project scopes. Technology is good. However, if system breaks, time lost! NEPA is needed even for state funded projects. Traffic Operations DBPB contract is designed to address traffic operational or safety issues, not roadway improvements higher unit price for roadway items. Limited pay items. There are issues to be resolved when adding pay items. Potential backlog due to numerous tasks need to plan work force well. Limited staff to review multiple tasks concurrently. Difficult to address safety along local roadways if locals are not stepping up. 24
25 FDOT DESIGN-BUILD PUSH BUTTON What is this DBPB Contract? Saves Time & Money! Reduces Congestion! Creates Jobs! Saves Lives! Every Day Counts when it comes to Safety!
26 How to start your agency own DBPB contract? Identify any roadblocks in your State laws or guidelines! Get your agency management support for this innovation contract! Work with your FHWA Division office to obtain their support! Make sure all agency offices will support the team work effort! Obtain budget and fund to program your own DBPB contract! Assign energetic contract manager and supporting staff! FDOT DBPB contract information can be a good reference Get help from 26
27 Answer your questions FDOT DBPB Contract information: Peter Hsu, P.E. District Traffic Services Engineer Florida Department of Transportation District N. McKinley Drive Tampa, FL (813) ping.hsu@dot.state.fl.us 27
Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract
Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract (FEDERAL SAFETY AND STATE FUNDS) Contract Evaluation June 2013 06/18/13 FDOT DBPB Evaluation 1 Jobs Creation
More informationDesign-Build and Design-Bid-Build
Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build
More informationDesign-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection
DESIGN-BUILD Design-Build Authorization Project Selection Criteria Selection/Award Process Warranties Design-Build Construction Engineering and Inspection Materials Acceptance DESIGN-BUILD AUTHORIZATION
More informationFDOT PROJECT INFORMATION APPLICATION FORM
THIS FORM SHALL BE SUBMITTED FOR ALL PROJECTS NOT CURRENTLY IN THE FDOT WORK PROGRAM. FDOT PROJECT INFORMATION APPLICATION FORM DATE: APPLICANT: FDOT LIAISON: 1. MPO/TPO Project Priority Number: 2. Contact
More informationThe Gateway Expressway FTBA Conference. February 2-3, 2017
The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north
More informationALTERNATE TECHNICAL CONCEPTS Missouri Department of Transportation
Missouri Department of Transportation INNOVATIVE CONTRACTING PROCESS Table of Contents Introduction... 1 Description... 2 General Conditions... 3 Submittal Process... 5 Evaluation Procedure... 7 Design
More informationPresented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013
PROJECT MANAGEMENT IN A DOT ENVIRONMENT Presented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013 Mission Safe Transportation
More informationNOTICE TO DESIGN PROFESSIONALS / CONTRACTORS REQUEST FOR LETTERS OF INTEREST S.R. 408/ S.R. 417 INTERCHANGE IMPROVEMENTS PHASE 2 PROJECT NO.
NOTICE TO DESIGN PROFESSIONALS / CONTRACTORS REQUEST FOR LETTERS OF INTEREST S.R. 408/ S.R. 417 INTERCHANGE IMPROVEMENTS PHASE 2 PROJECT NO. 253G, CONTRACT NO. 001266 The Central Florida Expressway Authority
More informationSR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.
Palm Beach County, Florida Palm Beach Metropolitan Planning Organization April 217 Project Study Area LIMITS: SR 9/I-95: from S of 45th Street to N of 45th Street 45th Street: From Village Boulevard to
More informationJoe Santos Transportation Safety Engineer Florida Department of Transportation
Joe Santos Transportation Safety Engineer Florida Department of Transportation D7 Safety Summit, June 8, 2011 D7 Safety Summit Purpose & Goals: Despite significant progress, crash rates in the Tampa Bay
More informationTAMPA - HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Committee / Board Meeting January 17, E. Twiggs Street, Suite 300 Tampa, FL AGENDA
TAMPA - HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Committee / Board Meeting January 17, 2017 1104 E. Twiggs Street, Suite 300 Tampa, FL 33602 AGENDA I. Operations & Maintenance Committee Bennett Barrow,
More informationSouth Carolina DOT Data Driven Intersection Safety Improvements
South Carolina DOT Data Driven Intersection Safety Improvements Intersection Safety Data Nationwide: 21 % of all fatalities occur at or near intersections, as well as 52 % of all injuries 45 % of all
More informationDale Mabry Pedestrian Overpass Technical Feasibility Analysis. March 2017
Dale Mabry Pedestrian Overpass Technical Feasibility Analysis March 2017 Overview Two Part Study: 1. Feasibility of Alternatives for a Pedestrian Overpass Across Dale Mabry Hwy Near I 275 2. Walk/Bike
More informationStatewide Acceleration Transformation (SWAT)
Presented to: AASHTO SCOE/SCOD Presented by: Marjorie Kirby Paul Hiers, P.E. Statewide Acceleration Transformation (SWAT) July 2017 PD&E Study Comply with the National Environmental Policy Act (NEPA) and
More informationPWC Neighborhood Services Conference. February 20, 2016 Aleksandra Tuliszka Assistant Transportation and Land Use Director
PWC Neighborhood Services Conference February 20, 2016 Aleksandra Tuliszka Assistant Transportation and Land Use Director www.virginiadot.org Overview: VDOT s primary Function The Virginia Department of
More informationFROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07
TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07 SUBJECT: APPROVAL OF A CONTRACT WITH BOND BLACKTOP, INC., IN THE AMOUNT OF $556,812 FOR PHASE 1 AND
More informationFDOT and NTPEP Pavement Marking Materials Test Decks
FDOT and NTPEP Pavement Marking Materials Test Decks Project Overview FDOT Office State Materials Office Report Number EXP-I-4 Authors Nikita L. Reed Date of Publication March 2017 About NTPEP The National
More informationEXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES
EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID 432430-1-32-13 TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES DISTRICT TWO November 27, 2017 Page 1 EXHIBIT A SCOPE
More informationLOCATION AND DESIGN DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form
More informationState Road (S.R.) 12 (Florida Arts Trail PD&E)
State Road (S.R.) 12 (Florida Arts Trail PD&E) from North Corry Street to S.R. 63 (U.S. 27) Gadsden County, Florida FPID Number: 433380-1-32-01 CRTPA Briefing September 2015 Today s Presentation Evolution
More informationNCHRP UPDATE AASHTO Highway Subcommittee on Construction. Timothy Hess National Cooperative Highway Research Program
NCHRP UPDATE AASHTO Highway Subcommittee on Construction Timothy Hess National Cooperative Highway Research Program National Cooperative Highway Research Program State DOTs support -Problems -Funds Applied
More informationLPA Stewardship and Oversight A Louisiana Perspective
LPA Stewardship and Oversight A Louisiana Perspective A Little History FY 2007 FHWA HQ LPA Comprehensive Oversight Program Determination Results (HINT: RED = NOT GOOD) Yes No Yes/No Undetermined NA Getting
More informationTraffic & Safety Engineering Project Selection Process
Traffic & Safety Engineering Project Selection Process By Neil E. Boudreau State Traffic Engineer MassDOT Highway Division 1 Leading the Nation in Transportation Excellence www.mass.gov/massdot Traffic
More informationBoster, Kobayashi & Associates NEVIN Q. SAMS, P.E., T.E., P.T.O.E.
Boster, Kobayashi & Associates 59 Rickenbacker Circle Office: (925) 447-6495 P.O. Box 2049 Fax: (925) 447-6589 Livermore, CA 94551-2049 NEVIN Q. SAMS, P.E., T.E., P.T.O.E. Curriculum Vitae EDUCATION: B.S.
More informationAny discussions or marketing activities related to this specific project.
04-11-19 Posting Date South Sandusky Street Widening and Relocation PID No. Not Assigned City of Mount Vernon Response Due Date: 04-24-19 Communications Restrictions Please note the following policy concerning
More informationPRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT
PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT RFQ No. 21-9SDP5001 601CT0000003698 November 19, 2018 Safety Minute Purpose of Meeting
More informationEng. Benjamín Colucci-Ríos, PhD, PE, PTOE, FITE, API, JD
An Overview of Innovative Safety Initiatives to Create Awareness and Save Lives on Puerto Rico Highways & Local Road Safety Checklist Eng. Benjamín Colucci-Ríos, PhD, PE, PTOE, FITE, API, JD benjamin.colucci1@upr.edu
More informationEXHIBIT "A" SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO.
EXHIBIT "A" SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO. 443787 1 72 01 Revised: 07/05/18 06/29/18 TABLE OF CONTENTS PAGE NO. I. PURPOSE...
More informationConnected and Automated Vehicles and the Future of Transportation. Dean Gustafson, P.E., PTOE State Operations Engineer April 25, 2017
Connected and Automated Vehicles and the Future of Transportation Dean Gustafson, P.E., PTOE State Operations Engineer April 25, 2017 Why Connect? What Benefits Can We Expect? National Timeline for Application
More informationSelection of Contractor Step 5. June 2013
Selection of Contractor Step 5 June 2013 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement of Contractor
More informationOverview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations
Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overall Project Development Process The time it takes to produce a project varies significantly
More informationRIDOT S Statewide Roadway and Asset Data Collection Project
RIDOT S Statewide Roadway and Asset Data Collection Project ESRI User Conference 2017 Rafiq Basaria, DTS; Daniel Behnke DTS, Shane White, RIDOT Accent image here Primary Image here What is MIRE? Recommended
More informationEngineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida
Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South
More informationConclusions & Lessons Learned
What is a DDI Recommended Practices Traffic Operations Analysis Geometric Design FHWA Review Conclusions & Lessons Learned It s not about you, it s about the public Developed by Access Utah County
More informationAlternatives Evaluation Methodology
Alternatives Evaluation Methodology www.vision54 56.com B 1 Phase 2 Alternatives Evaluation Methodology PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph
More informationStatus of Highway Safety Manual Implementation. October 2015
Status of Highway Safety Manual Implementation October 2015 Agenda NCHRP Project 17-50 Overview Project Objective Panel members and support states Project Deliverables to Date Status of HSM Implementation
More informationThe Essential Elements of a SMARTZONE Contract
AASHTO (TIG) Workshop St. Louis, MO September 12-13 13 The Essential Elements of a SMARTZONE Contract Steve Kite, PE NCDOT Work Zone Traffic Control Project Engineer How do I start? http://tig.transportation.org
More informationINNOVATIVE CONTRACTING GUIDELINES
Office of Construction and Innovative Contracting INNOVATIVE CONTRACTING GUIDELINES A+B Bidding Lane Rentals Incentives/ Disincentives Liquidated Savings Design-Build Warranties Pay for Performance No
More informationUtilizing Transportation Data for Low Cost Safety Improvements
Utilizing Transportation Data for Low Cost Safety Improvements Samuel Sturtz Transportation Planner Iowa Department of Transportation samuel.sturtz@dot.iowa.gov Photo Credits: Ken West- Kenneth G. West
More informationProject Location. Pensacola Bay Bridge Replacement Design Build 03/02/16. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer
Pensacola Bay Bridge Replacement Design Build Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Project Location 2 1 GENERAL PROJECT INFORMATION Replacement of the structurally deficient
More informationALTERNATIVE CONTRACTING METHODS
ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional
More informationPalm Coast-Daytona Beach-Port Orange Transportation Management Area (TMA) River to Sea TPO. TMA Federal Certification Review Closeout Presentation
Palm Coast-Daytona Beach-Port Orange Transportation Management Area (TMA) River to Sea TPO TMA Federal Certification Review Closeout Presentation MPO Board Meeting January 27, 2016 Federal Highway Administration
More informationFDOT D7 Local Agency Traffic Safety Academy September 21, FHWA - Kevin Burgess, Chimai Ngo, Esther Strawder, and Jim Thorne
FDOT D7 Local Agency Traffic Safety Academy September 21, 2016 FHWA - Kevin Burgess, Chimai Ngo, Esther Strawder, and Jim Thorne Presenters Kevin Burgess FHWA Florida Division Safety Engineer Chimai Ngo
More informationProject Name: Corridor Studies, Sub-area Studies and Special Transportation Studies. City: Tampa State: Florida Zip: 33604
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PROFESSIONAL SERVICES LETTER OF RESPONSE 375-030-22 Page 1 Advertisement No.: 15721 DOT FM Number: 259109-1-12-23 Project Name: Corridor Studies, Sub-area
More informationGloucester Parkway Extension RFQ Information Meeting
Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information
More informationPAVEMENT DESIGN MEMORANDUM
PAVEMENT DESIGN MEMORANDUM FOR SR 70 (15TH STREET EAST) ROUNDABOUT MANATEE COUNTY FINAL SUBMITTAL FPID 435090-1-52-01 PREPARED FOR: FLORIDA DEPT. OF TRANSPORTATION DISTRICT 1 FEBRUARY 16, 2018 PREPARED
More informationODOT ADA Program 10/31/2017. Recent ADA outcomes. What you need to know. Settlement Agreement approved. Updated Transition Plan
Recent ADA outcomes What you need to know ODOT ADA Program Lisa Strader, ODOT ADA Program Manager Settlement Agreement approved Updated Transition Plan What does it mean? Public Transportation Advisory
More informationDerry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing
Derry-Londonderry 13065 - I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing July 25, 2018 Purpose of Meeting Purpose and Need Current Project Status Alternatives Overview
More informationCASE STUDY. Frampton Construction GENERAL CONTRACTOR CLIENT: FRAMPTON CONSTRUCTION
GENERAL CONTRACTOR CASE STUDY Frampton Construction CLIENT: FRAMPTON CONSTRUCTION CHALLENGE: After a company re-branding in early 2015, Frampton Construction started looking for a project management system
More informationFlorida Department of TRANSPORTATION. FDOT Update. Florida Urban Traffic Engineering Council (FLUTEC) Florida Section ITE (FSITE) October 30, 2018
Florida Department of TRANSPORTATION FDOT Update Florida Urban Traffic Engineering Council (FLUTEC) Florida Section ITE (FSITE) October 30, 2018 Agenda Traffic Services Speed Zone Manual Intersection Control
More informationADAPTIVE SIGNAL CONTROL - When is it the right choice? JOINT TSITE/ITS TN FALL MEETING Clarksville, TN. October 7, 2014
ADAPTIVE SIGNAL CONTROL - When is it the right choice? JOINT TSITE/ITS TN FALL MEETING Clarksville, TN October 7, 2014 Agenda What is adaptive signal control? Benefits Is adaptive signal control the right
More informationWork Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
More informationNATMEC June 30, 2014 Anita Vandervalk, PE, PMP
NATMEC June 30, 2014 Anita Vandervalk, PE, PMP Agenda 1. Florida s MPM Program 2. Research Efforts and Progress 3. Source Book 4. Transitioning to Real Time Data 5. Next Steps Importance of Mobility Providing
More informationEnhancing Sustainability with INVEST
Enhancing Sustainability with INVEST Connie (Hill ) Galloway Federal Highway Administration June 17, 2016 Texas DOT Transportation Planning Conference Today s Agenda 1. What is INVEST? 2. INVEST Usage
More informationProject Performance Measurement
Project Performance Measurement The Key to Measuring Non-monetary Value Improvement Mike Pearsall, P. Eng., AVS Topic Overview Why Measure Performance? Adjusted Job Plan Using Performance Measures Defining
More informationTSM Limited Scope Project Delivery Process Activity Descriptions November 2017
TSM Limited Scope Project Delivery Process Activity Descriptions November 2017 Procedures are subject to change without notice. Check the NJDOT website to ensure this is the current version. 1 Table of
More informationEXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES
EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY
More informationAdvanced Construction Techniques
Alaskan Way Viaduct Replacement Program Organization University of Washington Date October 20, 2011 Presentation Overview SR 99 south end viaduct replacement. Design-build contracting. SR 99 tunnel project.
More informationDESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD
OWNER OWNER OWNER DESIGNER GC DESIGNER DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD Contracts Communications
More informationHERNANDO COUNTY BOARD OF COUNTY COMMISSIONERS JOB DESCRIPTION
HERNANDO COUNTY BOARD OF COUNTY COMMISSIONERS JOB DESCRIPTION Job Title Traffic Engineering Coordinator Pay Grade 221 Class Code P233 Department Public Works Salary Range $51,521.60 - $83,449.60 Annually
More informationEXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD
Scope of Services 12/08/2008 EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD TABLE OF CONTENTS Section Pace I. 0 PROJECT DESCRIPTION........................,............................................................
More information295 Project Showing Meeting Minutes
295 Meeting Minutes Project: (FO)0295-964-264,N501 FHWA: IM-295-3(080) County: Henrico, Chesterfield, Hopewell, and Prince George UPC: 104467 August 29, 2013 / 10:00 a.m. Richmond District Auditorium Shane
More informationState DOT Procedures for the Evaluation of Materially Unbalanced Bids
State DOT Procedures for the Evaluation of Materially Unbalanced Bids On April 30, 2004 the AASHTO Subcommittee on Construction, Contract Administration Section initiated a survey concerning the evaluation
More information2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM
2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM A. District: 1 2 3 4 5 6 7 TPK C.O. B. Nomination Category: (Select only one category) Outstanding Major Project Outstanding
More informationMISCELLANEOUS PAVING PROJECTS & SIGNAL INSTALLATION
TAMPA-HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY LETTER OF CLARIFICATION NO. 1 REQUESTS FOR PROPOSALS FOR MISCELLANEOUS PAVING PROJECTS & SIGNAL INSTALLATION RFQ No. O-01616 THEA Page 1 of 6 LETTER OF CLARIFICATON
More informationRIDOT S Statewide Roadway and Asset Data Collection Project
RIDOT S Statewide Roadway and Asset Data Collection Project GIS-T Conference 2017 Shane White Rhode Island DOT; Daniel Behnke DTS Accent image here Primary Image here RDIP Technical Assistance Started
More informationFlorida Department of Transportation. Lane Elimination
Florida Department of Transportation Lane Elimination FDOT D6 Lane Elimination Review and Approval Process Developed to assure consistency in FDOT D6 s handling of the Lane Elimination Review and Approval
More informationPerformance Based Practical Design (PBPD)
Performance Based Practical Design (PBPD) 2016 ODOT D08 LPA Day John R. Kasich, Ohio Governor Jerry Wray, ODOT Director PBPD PBPD Presenter Katherine DeStefano, P. E. District 08 Design Engineer ODOT D08
More informationTAMPA BAY NEXT MAJOR PROJECTS UPDATE
TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023
More informationI-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY)
I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY) TO WEST OF SR 435 (KIRKMAN ROAD) ORANGE COUNTY, FLORIDA Financial Project
More information(Online Procurement Initiative)
Internet Negotiations (Online Procurement Initiative) Objective Share Intel s present findings in the application of Internet negotiations (I-NEG) for construction services and facilities equipment. Specifically,
More informationFLORIDA DEPARTMENT OF TRANSPORTATION
FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 1 DATE: 2/18/2011 RE: BID #: ITB-DOT-10/11-9027-GB BID TITLE: GADGET GRIPS OPENING DATE: 3/1/2011 Notice is hereby given of the following changes to the
More informationMaintenance, Construction & Secondary Roads. Terry Gibson, PE Chief Engineer February 20, 2013
Maintenance, Construction & Secondary Roads Terry Gibson, PE Chief Engineer February 20, 2013 State versus local responsibility Division structure Allocations Flexibility in funding Implications of not
More informationJob Order Contracting (JOC) ITB JE Overview August 2016
Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.
More informationInfrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey
Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey Maintain transportation system in state of good repair 1. Increase focus on maintenance of existing infrastructure in poor
More informationI-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge
I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge Client: AJR or IJR? This is a TO-MAY-TO This is a TO-MAH-TO Practical Design PRACTICAL
More informationRequest for Letter of Interest (Electronic Submittal Required)
Request for Letter of Interest (Electronic Submittal Required) Skyline Drive Engineering Design and Right-of-Way Acquisition October 2017 Page 1 of 10 Overview: Consultant selection is a Qualification-Based
More informationAASHTO Subcommittee on Traffic Engineering. June 19, John Conrad
AASHTO Subcommittee on Traffic Engineering June 19, 2012 John Conrad What is SHRP2? Save lives. Save money. Save time. $218 million, federally funded research program to address critical transportation
More informationPublic Building Commission of Chicago Terms and Tools for Public Capital Development and Financing
Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan
More informationThe Basics of Temporary Traffic Control What Every Contractor Should Know
The Basics of Temporary Traffic Control What Every Contractor Should Know James E. Bryden, PE jbryden@nycap.rr.com Federal Highway Administration, USDOT Work Zone Safety and Mobility Final Rule Updates
More informationDesign-Build Selmon West Extension
TAMPA-HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Letter of Clarification No. 1 FOR REQUESTS FOR PROPOSALS Design-Build Selmon West Extension Page 1 of 8 Letter of Clarification No. 1 ~ Date of Letter of
More informationREQUEST FOR PROPOSALS (RFP) MUNICIPAL TRAFFIC ENGINEERING SERVICES. Borough of Phoenixville. May 17, 2016
REQUEST FOR PROPOSALS (RFP) MUNICIPAL TRAFFIC ENGINEERING SERVICES Borough of Phoenixville 351 Bridge Street Second Floor Phoenixville, PA 19460 Chester County, Pennsylvania May 17, 2016 Borough of Phoenixville
More information40TH AVENUE NE BRIDGE REPLACEMENT
Is this Project funded? The City plans to use approximately $22 million of Penny for Pinellas funds to rebuild this and other bridges in the near future. The Federal Department of Transportation (FDOT)
More informationI-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017
I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479),
More informationAlternative Project Delivery Status Update 2013
Alternative Project Delivery Status Update 2013 Eric Kahlig Division of Construction Management Alternative Project Delivery Innovative Contracting Manual Separate from Division of Innovative Delivery
More information448 INNOVATIVE BIDDING TOOLKIT
Publication 448 INNOVATIVE BIDDING TOOLKIT 2013 Edition, Change 2 Bureau of Project Delivery, Highway Delivery Division Project Schedules, Specifications and Constructability Section PUB 448 (05-16) This
More informationMINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No T-02 October 30, 2014
MINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No. 14-11-T-02 To: From: Subject: Electronic Distribution Recipients Jon M. Chiglo, P.E. Division Director, Engineering
More informationLOCATION HYDRAULIC REPORT
Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID
More informationMaterial Transfer Device Effect on Pavement Smoothness Widening Joint Design & Construction
Florida Department of TRANSPORTATION Material Transfer Device Effect on Pavement Smoothness Widening Joint Design & Construction 2016 FTBA Construction Conference Florida Department of TRANSPORTATION Factors
More informationConstruction Project Delivery Methods
Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031
More informationIII. Regional TSM&O Overview from the 2040 Regional Transportation Plan (Jessica Josselyn, Kittelson & Associates, Inc.)
Regional Transportation Technical Advisory Committee (RTTAC) Transportation System Management & Operations (TSM&O) Subcommittee Meeting Agenda June 23, 2015 1:30 PM FDOT District Four Headquarters Auditorium
More informationPensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer
Pensacola Bay Bridge Replacement Design Build Industry Forum Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Project Location 2 GENERAL PROJECT INFORMATION Replacement of the structurally
More informationADAPTIVE SIGNAL CONTROL - When is it the right choice? ITS 3C SUMMIT Mobile, AL. September 15, 2014
ADAPTIVE SIGNAL CONTROL - When is it the right choice? ITS 3C SUMMIT Mobile, AL September 15, 2014 Agenda What is adaptive signal control? Benefits Is adaptive signal control the right choice, then Things
More informationCONSTRUCTION CONFERENCE
CONSTRUCTION CONFERENCE - 2010 Concrete Paving Session February 23, 2010 Greg Schiess 1 2 3 CHANGE 4 TOPICS OF DISCUSSION Implementation of the new Design Guide and related software Pavement Type Selection
More informationDISTRICTWIDE MODAL DEVELOPMENT OFFICE (MDO) RAIL CONSULTANT SERVICES SCOPE OF SERVICES FM# Ad # 19627
DISTRICTWIDE MODAL DEVELOPMENT OFFICE (MDO) RAIL CONSULTANT SERVICES SCOPE OF SERVICES FM# 433056-4-12-01 Ad # 19627 Qualification Requirements for Type of Work 99.0 I. Purpose II. Rail Services III. Administration
More informationADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012
ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle
More informationData Knowledge and Knowing What To Do Next. 11th National Conference on Transportation Asset Management
Data Knowledge and Knowing What To Do Next 11th National Conference on Transportation Asset Management July 11th, 2016 Rob Zilay Objectives Session - Explore ways that data have been collected, managed,
More informationPROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA
PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily
More information-1- Intermodal Parking Facilities And Enhancements Design-Build Project
-1- Intermodal Parking Facilities And Enhancements Design-Build Project Presentation Foothill Extension Phase 2A Pasadena to Azusa Three Design-Build Projects Intermodal Parking Facilities and Enhancements
More informationScope of Services Traffic Signal Retiming Contract FM NO Florida Department of Transportation District Four
Scope of Services Traffic Signal Retiming Contract FM NO. 230017-8-32-01 Florida Department of Transportation District Four A-1 Contents 1. Background... 3 2. Summary of Services... 3 3. Consultant Requirements...
More information