1 Arlington Independent School District Board of Trustees Communication Meeting Date: September 21, 2017 Consent Item Subject: Bids Purpose: To provide the Board of Trustees the opportunity to review the purchase of goods and services prior to final Board approval. Background: Bids presented on the consent agenda: CSP for Berry, Rankin & Roark Elementary Schools Renovations Projects Maintenance Supplies and/or Services - Supplemental Recommendation: The Administration recommends approval of the bids. Submitted to: Board of Trustees Arlington Independent School District Submitted by: Prepared by: Tammy Craig Date: 9/13/2017

2 TO: FROM: Cindy Powell Chief Financial Officer Tammy Craig Director of Purchasing DATE: September 21, 2017 RE: CSP Berry, Rankin & Roark Elementary Schools Renovations Project Competitive Sealed Proposal is for the construction services of Berry, Rankin and Roark Elementary Schools Renovations Project funded from the 2014 Bond Program. Three proposals were received in response to the CSP. Attached is a recommendation letter from William Kelly Horn, Executive Director of Plant Services, a letter from VLK Architects and an evaluation summary. It is recommended that the contract be awarded per the recommendation. cc: Tony Drollinger Executive Director of Finance

3 MEMORANDUM TO: FROM: Cindy Powell, Chief Financial Officer Wm. Kelly Horn, Executive Director of Plant Service DATE: September 13, 2017 SUBJECT: Competitive Sealed Proposal for Addition, Renovation, Condition Deficiency, and Life Cycle Improvements for Berry, Rankin, and Roark Elementary Schools The District approved an addition, renovations, condition deficiency, and life cycle improvements for Berry, Rankin, and Roark Elementary Schools as a part of the 2014 Bond program. Additionally, the Board of Trustees approved VLK Architects as the design professional and approved Competitive Sealed Proposal (CSP) as the method of construction procurement. The project architect, VLK Architects, completed the construction documents and the District requested proposals. Notification of the request for CSP was sent to local contractors, area chambers of commerce and contractors on a list supplied by the DFW Minority Business Council. Notice of the request for CSP was also advertised in accordance with state law. Proposals were received from three general contractors: Reeder General Contractors, Inc. Phillips May Corporation ICI Construction, Inc. Competitive Sealed Proposals received from the proposers were evaluated based criteria published in the CSP document: Price 40% Qualifications 40% HUB Participation 10% Interviews 10% An evaluation committee consisting of the Chief Financial Officer, Executive Director of Plant Services, Director of Facility Planning and Construction, the District s Senior Project Manager and Staff Architect, and the Design Architect completed evaluations and interviews. Reeder General Contractors, Inc., ranked highest amongst all proposers at points. District staff worked with Reeder General Contractors, Inc., to ensure that the intended project scope is

4 being addressed, identify opportunities to reduce the proposed cost and verify the project budget. The architect s letter of recommendation for construction contract award for addition, renovation, condition deficiency, and life cycle improvements for Berry, Rankin, and Roark Elementary Schools is attached. Pending approval of the CSP, work on this project will begin in the fall of 2017 with substantial completion expected in the summer of Based on the evaluation process, the committee recommends the Competitive Sealed Proposal as submitted by Reeder General Contractors, Inc., in the amount of $9,094,420. This CSP is over the original construction budget by $356,349.

5 September 13, 2017 Wm. Kelly Horn, RTSBA Executive Director of Plant Services Arlington Independent School District 1201 Colorado Lane Arlington, Texas Reference: Renovations to Berry, Rankin, and Roark Elementary Schools Dear Mr. Horn: VLK Architects has reviewed the Schedule of Values (SOV), provided by Reeder General Contractors for the above mentioned project. We believe the CSP amount of: $9,094, accurately reflects the scope of work documented in the Issue for Permit + Bid Contract Documents dated June 30, 2017 and the subsequent work sessions with Reeder General Contractors and Arlington ISD. It is our recommendation that Arlington ISD approve the proposed CSP at this time. Sincerely, Angela Mitchell, AIA cc: Javier Fernandez, AISD File

6 Request for Competitive Sealed Proposals #18-12 Proposer's Qualifications Evaluation CSP Proposal Budget $ 8,738,071 PROPOSAL SELECTION CRITERIA Price 40% HUB Commitment 10% 0.5 Qualifications 40% Interview 10% Total 100% PRE INTERVIEW PROPOSAL EVALUATION Proposer Price Price HUB Commitment % HUB Qualifications Qualifications Total Ranking 40 Score 10 Score 40 Score Score Reeder General Contractors, Inc. $9,200, Phillips/May Corporation $9,361, ICI Construction, Inc. $12,399, POST INTERVIEW PROPOSAL EVALUATION Proposer Price Price HUB Commitment % HUB Qualifications Qualifications Interview Total Ranking 40 Score 10 Score 40 Score Score Score Reeder General Contractors, Inc. $9,200, Phillips/May Corporation $9,361, PH3-BP07 Berry, Rankin, Roark Elementary Schools Renovations Project CSP Proposer Evaluation Matrix FINAL/Summary Facility Planning and Construction Page 1 of 1

7 TO: FROM: DATE: RE: Cindy Powell Chief Financial Officer Tammy Craig Director of Purchasing September 21, 2017 Bid Maintenance Supplies and/or Service - Supplemental Bid Number is a supplemental to the annual contract for maintenance supplies and/or services. The bid asked for a discount from the vendor s catalog, price list or shelf price. This will allow the District to purchase items which are not identified at this time. It is recommended that all vendors meeting specifications be approved for catalog purchasing. cc: Tony Drollinger Executive Director of Finance

8 ARLINGTON INDEPENDENT SCHOOL DISTRICT Bid # Maintenance Supplies and/or Services - Supplemental Effective Date: September 22, 2017 through May 31, 2018 VENDOR: VENDOR ID NUMBER: RESIDENT VENDOR: AC Supply Company Ashcraft Company Binswansger Glass Brazos Forest Products Central Poly Corp ChemsearchFE Not Set Up Texas District Texas District Texas District Texas District Texas District HUB VENDOR: NO NO NO NO NO NO DESCRIPTION PRICE PRICE PRICE PRICE PRICE PRICE Labor Charge per Regular Time Hour NA Varies $105/hr Catalog Discount 0% Varies Varies Varies 5% 10% Texas District Classification of Services HVAC supplies Boiler tech, HVAC tech, pipefitter,project manager Glass, materials and installation Distributor of quality hardwood, plywood and custom moulding Plastic materials such as bags and liners Certified green jan-san chemicals, drain technology and water treatment VENDOR: City Electric Supply Cowtown Materials H.A. Gray & Associates Hancock Sign Co. Irrigators Supply Johnstone Supply VENDOR ID NUMBER: Not Set Up RESIDENT VENDOR: Texas District Texas District Texas District Texas District Texas District HUB VENDOR: NO NO NO NO YES NO DESCRIPTION PRICE PRICE PRICE PRICE PRICE PRICE Labor Charge per Regular Time Hour Varies Varies $75/hr Catalog Discount Varies 15% Varies 0% Varies 50% Texas District Classification of Services Electrical supplies, tools and maintenance supplies Drywall, acoustical ceilings, steel framing, insulation & tools Cooling towers, evaporators, steam condensors, thermals ice coolers Signage, marquee, lettering, LED message signs Irrigation supplies HVAC parts, plumbing, refrigeration

9 ARLINGTON INDEPENDENT SCHOOL DISTRICT Bid # Maintenance Supplies and/or Services - Supplemental Effective Date: September 22, 2017 through May 31, 2018 VENDOR: Martin Locksmith NovaCopy Phillips Welding PPG Architectural Finishes Precision Landscape Management Regency Lighting VENDOR ID NUMBER: Not Set Up Not Set Up RESIDENT VENDOR: Texas District Texas District Texas District Texas District Texas District Texas District HUB VENDOR: NO NO NO NO NO NO DESCRIPTION PRICE PRICE PRICE PRICE PRICE PRICE Labor Charge per Regular Time Hour $65/hr $195/hr $95/hr NA Catalog Discount Varies Varies Varies Varies Varies 85% Classification of Services Locksmith, keys, safes Software consultation, copiers, printer and other output devices Welding equipment, steel and pipe sales, steel building components, structural steel and pipe Paint and supplies Landscape maintenance, arbor care and irrigation management Lighting design, retrofit, lamp recycling, bulbs VENDOR: Seal Tex State Chemical Solutions TFE Tech Plan, Inc Tower Tech Services Trugreen Lawncare VENDOR ID NUMBER: Not Set Up Not Set Up RESIDENT VENDOR: Texas District Texas District Texas District Texas District Texas District Texas District HUB VENDOR: NO NO YES NO NO NO DESCRIPTION PRICE PRICE PRICE PRICE PRICE PRICE Labor Charge per Regular Time Hour Varies Varies $107/hr Varies Varies Catalog Discount 10% Varies 0% Varies Varies Classification of Services Commerical kitchen repair Certified green jan-san chemicals, drain technology and water treatment IP communications, structured cabling, data center Data center parts and service Cooling tower repair and upgrade contractor Lawn care, shrubs, pest control

10 ARLINGTON INDEPENDENT SCHOOL DISTRICT Bid # Maintenance Supplies and/or Services - Supplemental Effective Date: September 22, 2017 through May 31, 2018 VENDOR: Unipak USA Bluebook Voss Lighting Walker Tools Western BRW Wexford Labs VENDOR ID NUMBER: Not Set Up RESIDENT VENDOR: HUB VENDOR: NO NO NO NO NO NO DESCRIPTION PRICE PRICE PRICE PRICE PRICE PRICE Labor Charge per Regular Time Hour Catalog Discount Varies 3% 86.5% 0% Varies 5% Classification of Services Texas District Texas District Texas District Texas District Texas District Texas District Bags and can liners Clearning and maintenance products Interior and exterior lighting, and energy services Tools Printing Disinfectant and cleaning solutions Estimated Total: $ 225,000.00

Arlington Independent School District Board of Trustees Communication

Arlington Independent School District Board of Trustees Communication Arlington Independent School Board of Trustees Communication Meeting Date: February 4, 2016 Consent Item Subject: Bids Purpose: To provide the Board of Trustees the opportunity to review the purchase of

More information

The Architectural and Engineering professional services RFQ identified the qualifications for the professional service providers as follows:

The Architectural and Engineering professional services RFQ identified the qualifications for the professional service providers as follows: For: Fort Bend ISD Board of Trustees Date: December 17, 2018 Action: Consent: Consideration and Approval: Professional Service Firms: Architectural and Engineering (A/E) Design Firms for 2018 Bond Program

More information

Arlington Independent School District Board of Trustees Communication

Arlington Independent School District Board of Trustees Communication Arlington Independent School Board of Trustees Communication Meeting Date: January 19, 2017 Consent Item Subject: Bids Purpose: To provide the Board of Trustees the opportunity to review the purchase of

More information

SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis Rouse

SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis Rouse SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, 2018 Members Present: Members Absent: Others Trustees Present: Others Present: Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis

More information

REQUEST FOR COMPETITVE SEALED PROPOSALS HEAT PUMP PIPING UPGRADE PROJECT FOR CSP HVAC

REQUEST FOR COMPETITVE SEALED PROPOSALS HEAT PUMP PIPING UPGRADE PROJECT FOR CSP HVAC REQUEST FOR COMPETITVE SEALED PROPOSALS HEAT PUMP PIPING UPGRADE PROJECT FOR CSP 12-20 HVAC Piping Rework at POWELL ELEMENTARY SCHOOL GRAND PRAIRIE INDEPENDENT SCHOOL DISTRICT Proposals are requested by

More information

This Addendum consists of~ Pages and. Attachments. NOTE THAT ITEMS APPLY TO ALL CAMPUSES UNLESS SPECIFICALLY NOTED OTHERWISE.

This Addendum consists of~ Pages and. Attachments. NOTE THAT ITEMS APPLY TO ALL CAMPUSES UNLESS SPECIFICALLY NOTED OTHERWISE. Estes, McClure & Associates, Inc. Engineering and Consulting BID PACKAGE #527 ADDENDUM NO. 1 September 23, 2015 EMA PROJECT NUMBER: 1-001-0069-028 ENGINEER: ESTES, McCLURE & ASSOCIATES, INC. 3608 WEST

More information

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:

More information

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA 2700 Judge Fran Jamieson Way

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications During the review of the application materials submitted with the Bishop Place Economic Hardship

More information

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015 FACILITIES PROJECTS UPDATE BOARD OF EDUCATION August 11, 2015 AGENDA Measure R Bond Projects Fund 40 Capital Projects Maintenance Projects MEASURE R BOND PROJECTS KINDERGARTEN MODERNIZATIONS PROGRAM BUDGET:

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS

PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS Urban infill on a previously developed site. The new building was built over an existing parking lot. Landscaping is composed of all native plants

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Water Conservation Program FY Activities. Quality of Life Committee April 9, 2007

Water Conservation Program FY Activities. Quality of Life Committee April 9, 2007 Water Conservation Program FY 06-07 Activities Quality of Life Committee April 9, 2007 Briefing Purpose Provide water conservation program update Highlight 2006 activities Highlight 2007 planned activities

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

DALLAS INDEPENDENT SCHOOL DISTRICT. BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations

DALLAS INDEPENDENT SCHOOL DISTRICT. BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations DALLAS INDEPENDENT SCHOOL DISTRICT PROCUREMENT SERVICES CONSTRUCTION SERVICES DOCUMENT DISTRIBUTION CONSTRUCTION SERVICES BID PACKAGE # 209 ORG 056 E. D. Walker Middle School Addition & Renovations 1.

More information

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA 2700 Judge Fran Jamieson Way

More information

Historic Courthouse Restoration: Window Replacement and Painting & Caulking Bids # RFP & # RFP WORK SESSION DECEMBER 10, 2015

Historic Courthouse Restoration: Window Replacement and Painting & Caulking Bids # RFP & # RFP WORK SESSION DECEMBER 10, 2015 Historic Courthouse Restoration: Window Replacement and Painting & Caulking Bids #259-15 RFP & #260-15 RFP WORK SESSION DECEMBER 10, 2015 Project Background Historic Courthouse built in 1870 & is the oldest

More information

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES I. PURPOSE REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES The Greensboro Housing Authority (GHA) invites qualifications for the Architectural/Engineering Services for RAD Renovations at

More information

Approved Vendor Lists. Food Service

Approved Vendor Lists. Food Service Big Spring Independent School District Approved Vendor Lists December 1, 2016 through November 30, 2017 Food Service Labor and Contracted Services Supplies and Equipment Big Spring Independent School District

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE

TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE TECHNICAL QUESTIONS FOR ITB-DOT-17/18-7004LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE Question 1: Question 2: Question 3: Question 4: Question 5: Question 6: When area configurations

More information

Welcome. Anaheim Union High School District Local Contractor Outreach Event

Welcome. Anaheim Union High School District Local Contractor Outreach Event Welcome Anaheim Union High School District Local Contractor Outreach Event Introductions: Lease-Leaseback General Contractor Jason Howarth*Speaker- Dale Jr. High School & TCC Bid Opportunities Project

More information

CITY OF NORTH RICHLAND HILLS

CITY OF NORTH RICHLAND HILLS CITY OF NORTH RICHLAND HILLS PURCHASING DIVISION P.O. BOX 820609 NORTH RICHLAND HILLS, TX, 76182-0609 817/427-6150 Fax: 817/427-6151 VENDOR INFORMATION FORM Complete the information below and check the

More information

April 16 th Linda Morrison Jesse Stanley

April 16 th Linda Morrison Jesse Stanley April 16 th 2010 Linda Morrison Jesse Stanley Energy efficiency Renewable energy Net zero buildings Envelope HVAC systems Water efficiency and metering Rating system, codes, best practice LEED-NC Version

More information

DISTRICT SERVICES BUILDING

DISTRICT SERVICES BUILDING DISTRICT SERVICES BUILDING BUILDING DATA DISTRICT SERVICES BUILDING 1100 Longhorn Dr., Weatherford, TX 76086 Year Built 1993 No. of Buildings 1 No. of Portables 0 Approx. Total Square Footage Grades Served

More information

August 2018 PROGRESS REPORT. Cobb County PARKS 2011 SPLOST Program

August 2018 PROGRESS REPORT. Cobb County PARKS 2011 SPLOST Program August 2018 Cobb County PARKS 2011 SPLOST Program September 11, 2018 Mr. Tom Bills Senior Project Manager, Construction Cobb County PARKS 1772 County Services Parkway Marietta, Ga.30008-4026 RE: 2011 PARKS

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Will County Justice Center Trade Contractor Outreach Session May 3, 2017

Will County Justice Center Trade Contractor Outreach Session May 3, 2017 Will County Justice Center Trade Contractor Outreach Session May 3, 2017 Replace Cover Image on Master Slide Gilbane Building Company May 2017 1 Trade Contractor Outreach Session Agenda Meet and Greet

More information

UNC Charlotte Science Building Project. Informational Meeting: May 3, 2018

UNC Charlotte Science Building Project. Informational Meeting: May 3, 2018 UNC Charlotte Science Building Project Informational Meeting: May 3, 2018 Project Team Owner and Designers UNC Charlotte Donia Schauble Senior Project Manager - Design Jennifer Price Senior Construction

More information

Voorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06

More information

OPERATION SERVICES DIVISION. Supporting the Journey

OPERATION SERVICES DIVISION. Supporting the Journey OPERATION SERVICES Supporting the Journey Presented by, Wanda Paul Chief of Operations DIVISION Presentation Date: 7 29-30 - 2013 Operation Services Organizational Chart Chief of Operations Wanda Paul

More information

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL

More information

DOCUMENT BID DOCUMENT

DOCUMENT BID DOCUMENT DOCUMENT 00 40 00 BID DOCUMENT 1 Submit bids in compliance with Document 00 21 00Instructions to Bidders. Fill in blanks which pertain to the project or indicate N/A. The Owner reserves the right to reject

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

Ameren Illinois Energy Efficiency Programs and Incentives. Helping public sector buildings and communities save energy and money.

Ameren Illinois Energy Efficiency Programs and Incentives. Helping public sector buildings and communities save energy and money. Ameren Illinois Energy Efficiency Programs and Incentives Helping public sector buildings and communities save energy and money. 1 Why Energy Efficiency? Save money Reduce environmental impact Increase

More information

wattsmart Business Utah

wattsmart Business Utah Incentives for lighting system retrofits Measure Category Eligibility Requirements Incentive Full fixture replacement Advanced controls $0.15/kWh annual Basic controls $0.12/kWh annual Interior lighting

More information

A. Remove Table of Contents and insert new attached Table of Contents.

A. Remove Table of Contents and insert new attached Table of Contents. ADDENDUM NO. 01 PROJECT Colby Glass E.S. Window Upgrades and ADA Work PROJECT NO. 16043 DATE February 07, 2018 TO: All Prime Contract Bidders and all others to whom Drawings and Specifications have been

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

Architectural Services Consultant Registration Form

Architectural Services Consultant Registration Form Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,

More information

YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects

YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects WORKING DOCUMENT YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects The Tendering Capital Construction and Maintenance Projects policy

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Dat e: August 2018 March Update Lemm restoration contract awarded to ICI Construction on March 2nd Contractor began mobilization on March 5th

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Crockett Elementary School Renovations

Crockett Elementary School Renovations We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.

More information

Moonlight Architecture, Inc. Architecture Interior Design Site Planning

Moonlight Architecture, Inc. Architecture Interior Design Site Planning Moonlight Architecture, Inc. Architecture Interior Design Site Planning 22 May 2018 18057 Mr. Michael J. Petit de Mange, County Administrator Kent County Levy Court 555 Bay Road Dover, DE 19901 RE: Facilities

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Lesky, Superintendent of Schools Board of School Directors Lewis F.

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

DALLAS INDEPENDENT SCHOOL DISTRICT

DALLAS INDEPENDENT SCHOOL DISTRICT DALLAS INDEPENDENT SCHOOL DISTRICT PROCUREMENT SERVICES CONSTRUCTION SERVICES DOCUMENT DISTRIBUTION CONSTRUCTION SERVICES BID PACKAGE # 008 Org 017 H. Grady Spruce High School 1. DOCUMENT DISTRIBUTION:

More information

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations

More information

LAS VEGAS - CLARK COUNTY LIBRARY DISTRICT

LAS VEGAS - CLARK COUNTY LIBRARY DISTRICT (Range 117) DEFINITION Performs a variety of fundamental and skilled work in the building and mechanical trades, with an emphasis in heating, ventilation and air conditioning (HVAC) equipment, in order

More information

Update on LEED v3. All projects registered after June 26, 2009 must be under the guidelines of LEEDv3. A LEEDv3 summary of changes:

Update on LEED v3. All projects registered after June 26, 2009 must be under the guidelines of LEEDv3. A LEEDv3 summary of changes: Update on v3 September 9, 2009 GP #7 The Green Building Rating system was recently updated and re-introduced April 27, 2009 as v3. This Green Piece will outline the major changes to the rating system and

More information

Proposition E Independent Citizens Oversight Committee. Report to the Board of Education June 21, 2017

Proposition E Independent Citizens Oversight Committee. Report to the Board of Education June 21, 2017 Proposition E Independent Citizens Oversight Committee Report to the Board of Education June 21, 2017 Ballot Proposition November 6, 2012 Repair, renovate, construct, and upgrade classrooms and school

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

ADDENDUM #2 REQUEST FOR COMPETITIVE SEALED PROPOSALS FOR A GENERAL CONTRACTOR. The University of Texas Health Science Center at San Antonio

ADDENDUM #2 REQUEST FOR COMPETITIVE SEALED PROPOSALS FOR A GENERAL CONTRACTOR. The University of Texas Health Science Center at San Antonio ADDENDUM #2 REQUEST FOR COMPETITIVE SEALED PROPOSALS FOR A GENERAL CONTRACTOR The University of Texas Health Science Center at San Antonio Renovate Floor 1 and Floor 2 of the PARC Bldg. RFP No.: 745-16-9935

More information

LUFacilities Policy Service Level Agreement v1.1

LUFacilities Policy Service Level Agreement v1.1 PURPOSE The Service Level Agreement (SLA) for University provides a detailed list of services offered by the LU Department. The SLA identifies which services are funded by the approved Lehigh University

More information

AZUSA UNIFIED SCHOOL DISTRICT

AZUSA UNIFIED SCHOOL DISTRICT AZUSA UNIFIED SCHOOL DISTRICT BOARD STUDY SESSION June 9, 2014 EVALUATION OF STATUS OF FACILITES AND FUTURE NEEDS NEEDS vs. FUNDING SETTING PRIORITIES 5) OTHER ADDITIONAL IMPROVEMENTS 4) OTHER ARCHITECTURAL

More information

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Agenda EWaS Overview History Who is EWaS? Mission EWaS Standards & Tools Energy Efficiency HVAC equipment

More information

ENERGY AND ENVIRONMENT DESIGN AND CONSTRUCTION STANDARDS ENERGY AND ENVIRONMENT

ENERGY AND ENVIRONMENT DESIGN AND CONSTRUCTION STANDARDS ENERGY AND ENVIRONMENT ENERGY AND ENVIRONMENT The University has committed to approaching new building construction and major renovations with an emphasis on Life Cycle Cost (LCC). Part of this approach is a focus on maximizing

More information

CONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student Quad

CONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student Quad COLLEGE OF THE SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting December 14, 2015 CONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student

More information

National EPA SUSTAINABLE COMMUNITIES CONFERENCE March 2009

National EPA SUSTAINABLE COMMUNITIES CONFERENCE March 2009 National EPA SUSTAINABLE COMMUNITIES CONFERENCE March 2009 Presenter: Theresa Townsend, AIA LEED AP, Senior Architect State of California Department of General Services Division of the State Architect

More information

Exhibit A Program Descriptions, Historical Changes and Proposed Changes

Exhibit A Program Descriptions, Historical Changes and Proposed Changes Exhibit A Program Descriptions, Historical Changes and Proposed Changes Exhibit A Program Descriptions, Historical Changes and Changes Reflected in Forecasts Home Energy Savings The Home Energy Savings

More information

Full-Scope Commissioning for High-Quality Buildings

Full-Scope Commissioning for High-Quality Buildings Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building

More information

Berryessa Union School District Measure L Bond Construction Program

Berryessa Union School District Measure L Bond Construction Program Berryessa Union School District Measure L Bond Construction Program Board of Trustees Update December 8, 2015 Introduction The following presentation is intended to provide the Board of Trustees with an

More information

HOW TO DO BUSINESS WITH FAYETTEVILLE PUBLIC WORKS COMMISSION

HOW TO DO BUSINESS WITH FAYETTEVILLE PUBLIC WORKS COMMISSION HOW TO DO BUSINESS WITH FAYETTEVILLE PUBLIC WORKS COMMISSION Fayetteville Public Works Commission Procurement Department 955 Old Wilmington Road Fayetteville, North Carolina 28301 Getting Started Your

More information

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number:

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number: Capital Projects Office Request For Qualifications for Architectural Design Services University of Washington Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR UW Fluke Hall Labs and Building

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Energy and Utility Management Plan and Procedures. Updated September 7, 2018 by: Danny Helm Energy Manager

Energy and Utility Management Plan and Procedures. Updated September 7, 2018 by: Danny Helm Energy Manager Energy and Utility Management Plan and Procedures Updated September 7, 2018 by: Danny Helm Energy Manager Purpose In accordance with Texas Education Code Section 44.902, the school board must establish

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System

REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System Issued by the City of Montpelier, Vermont Department of Planning and Community Development Responses Due: August 12, 2011,

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information.

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information. City of Boulder Residential Building Guide Green Building & Green Application Resource Conservation Ordinance 7565 www.bouldergeenpoints.com FOR ADDITIONS and REMODELS Before filling out this application,

More information

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS:

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS: ADDENDUM NO. 1 CITY OF PORT ARANSAS ELLIS MEMORIAL EXISTING LIBRARY RENOVATIONS AND REPAIRS CSP #2016-22 700 W. AVE A PORT ARANSAS, TX 78373 Issue Date: 01/07/2019 The following additions, deletions, modifications,

More information

Lealman Community Redevelopment Area Non-Residential Improvement & Demolition Grant Program Application Package

Lealman Community Redevelopment Area Non-Residential Improvement & Demolition Grant Program Application Package Lealman Community Redevelopment Area Non-Residential Improvement & Demolition Grant Program Application Package Applications & supporting documents may be submitted electronically to LealmanCRA@pinellascounty.org

More information

38% 62% Project Funding. TPS Systems and Infrastructure needs

38% 62% Project Funding. TPS Systems and Infrastructure needs TPS Systems and Infrastructure needs Project Funding Roof replacements (BGP, TMS) Plumbing upgrades Boiler replacements Code compliant systems, PA, Fire Alarm, Area of Refuge Concrete repair Floor repair

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Executive Summary. Overview: Louis Brier Home and Hospital Carbon Neutral Action Report

Executive Summary. Overview: Louis Brier Home and Hospital Carbon Neutral Action Report Executive Summary The Louis Brier Home and Hospital is a 218 Intermediate and Extended Care facility located at 41 st and Oak street in Vancouver. The 9,676 square meter (104,152 square feet) was constructed

More information

Connecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2018

Connecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2018 Connecticut Housing Finance Authority Construction Guidelines: Energy Conservation 2018 These Guidelines are effective January 1, 2018 I. Energy Conservation Guidelines Construction Guidelines: Energy

More information

Request for Qualifications. for. Seattle Public Schools Miscellaneous Consultants and Professional Services Roster

Request for Qualifications. for. Seattle Public Schools Miscellaneous Consultants and Professional Services Roster Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Qualifications for

More information

Basic renewal/restoration and safety projects

Basic renewal/restoration and safety projects Basic renewal/restoration and safety projects Board Update September 9, 2013 Bond Team Support Team Agenda Program Management Goals Program Budget Status 2013 Project Updates Labor Distribution Study 2014

More information

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO.

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO. BERKELEY DAVIS IR VINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SAN!' A BARBARA SANT A CRUZ OFFICE OF THE ASSIST ANT VICE CHANCELLOR CAMPUS ARCHITECT - FACILITIES DESIGN & CONSTRUCTION TEL:

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

Summary of Greening of State Government Executive Orders

Summary of Greening of State Government Executive Orders Summary of Greening of State Government Executive Orders Energy Management By Fiscal Year 2011-2012 achieve at least a 20% reduction in energy consumption of state facilities below fiscal year 2005-2006

More information

Construction Defects and Contract Breach 1

Construction Defects and Contract Breach 1 Construction Defects and Contract Breach 1 Presented by: David Hansen Eichelbaum, Wardell, Hansen, Powell, and Mehl P.C. 1 Copyright 2015, Eichelbaum, Wardell, Hansen, Powell, and Mehl P.C. 1 Construction

More information

Electric Association Annual Conference January 25, 2018

Electric Association Annual Conference January 25, 2018 Electric Association Annual Conference January 25, 2018 Teri Lewand CEM, LEED AP ComEd, Business Programs Mgr. C O N F I D E N T I A L Origin of Energy Efficiency Programs Illinois energy legislation passed

More information

SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut

SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut DATE: January 30, 2018 TO: FROM: RE: Karen Berasi Bill Hoff Board Approval of Final Spaulding Roof Cost Estimates and Plans The Board of Education approved

More information

A1.01 SITE PLAN 394 W OLENTANGY ST POWELL, OH BUILDING TO BE RENOVATED SITE PLAN. P F www. archa ll.

A1.01 SITE PLAN 394 W OLENTANGY ST POWELL, OH BUILDING TO BE RENOVATED SITE PLAN. P F www. archa ll. N O R T H F I F T H S T R E E T C O L U M B U S O H I O P.. 00 F.. 000 www. archa ll. com W OLENTANGY ST POWELL, OH 0 DRAWING SET 0 0 0 preliminary check bid permit construction REVISIONS BUILDING TO BE

More information

VILLAGE OF BOSTON HEIGHTS 45 E. Boston Mills Road Hudson, OH REGULAR COUNCIL MEETING OF July 14, :00 PM

VILLAGE OF BOSTON HEIGHTS 45 E. Boston Mills Road Hudson, OH REGULAR COUNCIL MEETING OF July 14, :00 PM VILLAGE OF BOSTON HEIGHTS 45 E. Boston Mills Road Hudson, OH 44236 REGULAR COUNCIL MEETING OF July 14, 2010-8:00 PM AGENDA ROLL CALL PLEDGE OF ALLEGIANCE APPROVAL OF AGENDA MINUTES PRESENTED FOR CHANGE

More information

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

Bids and Contracts. Pre-Board Meeting Workshop Discussion with Bob Parker

Bids and Contracts. Pre-Board Meeting Workshop Discussion with Bob Parker Bids and Contracts Pre-Board Meeting Workshop Discussion with Bob Parker BP 6340 Revised 01-15-15 Proposed minor revisions resulting from CCLC analyst review AP 6340 Bids and Contracts Legally required

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011

Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011 Energy Audit Report Lee Recycling Center Office and Facility 11 Recycling Center Rd, Lee NH August 16 & 17, 2011 S D E S G r o u p 2 W a s h i n g t o n S t r e e t S u i t e 2 0 6 D o v e r, N H 0 3 8

More information

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Facilities Advisory Committee (FAC) AGENDA FAC focus and framework FPCS Preliminary Design and Construction Schedule Meet our

More information

Nation Environmental Policy Act (NEPA)

Nation Environmental Policy Act (NEPA) COMPLIANCE WITH AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) PROVISIONS In an effort to let ARRA SECO Sub-recipients know what the major federal contract requirements will be, SECO Stimulus is providing

More information

MARYLAND STADIUM AUTHORITY

MARYLAND STADIUM AUTHORITY MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS Warehouse at Camden Yards Construction Manager for Warehouse Improvements Project MSA Project No. 18-070 ISSUE DATE: April 13, 2018 Contents A. Instructions...

More information

THE FOLLOWING PROPOSAL, SUBMITTED BY JARED B. GARDNER, DIRECTOR OF PURCHASING, IS RECOMMENDED FOR BOARD APPROVAL.

THE FOLLOWING PROPOSAL, SUBMITTED BY JARED B. GARDNER, DIRECTOR OF PURCHASING, IS RECOMMENDED FOR BOARD APPROVAL. THE FOLLOWING PROPOSAL, SUBMITTED BY JARED B. GARDNER, DIRECTOR OF. Superintendent Martin Bates RE: Lawn Mowing at 25 locations Across the District $74,256.00 The Purchasing Department was requested to

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information