Facilities Construction

Size: px
Start display at page:

Download "Facilities Construction"

Transcription

1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction March 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION Harlan High School

2

3 2014 BOND PROJECTS

4 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor Joeris General Contractor GMP - $110,800, Construction Period October 2014 May 2017 Construction Status: 93% Complete Project Scope New 2800 Student High School Site grading, utilities and landscaping in progress. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC installation in progress. Window installation, interior painting, exterior brick veneer and roofing in progress. Concrete drives and parking areas in progress. Punch in progress.

5 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Feb. 20, 2017)

6 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

7 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)

8 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)

9 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)

10 KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY) Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor Guido Construction GMP - $24,640, Construction Period March 7, 2016 May 26, 2017 Construction Status: 60% Complete Project Scope New 800 Student Elementary School Masonry, brick, MEP ductwork and roofing are ongoing.

11 KALLISON ELEMENTARY SCHOOL Front Entrance

12 KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017)

13 KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017)

14 KALLISON ELEMENTARY SCHOOL (February 28, 2017)

15 KALLISON ELEMENTARY SCHOOL (February 28, 2017)

16 KALLISON ELEMENTARY SCHOOL (March 1, 2017)

17 KALLISON ELEMENTARY SCHOOL (March 1, 2017)

18

19 GROSENBACHER AREA ELEMENTARY (Prototype of Boldt ES and Cole ES) Architect Noonan Rittiman Project Architect John Rittiman NISD Project Manager Tom Curiel Contractor DL Bandy Construction Amount - $22,465,000 Tentative Construction Period March 2017 May 2018 Project Scope New 800 Student Elementary School (Prototype of Boldt ES and Coles ES) General Contractor approved at February Board. Contract negotiations ongoing.

20 ADDITIONS AND RENOVATIONS PROJECTS IN PROGRESS

21 GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor McGoldrick Construction Co. Construction Amount - $3,750, Construction Period June 2016 June 2017 Construction Status: 50% Complete Project Scope New Administration Building Installing roof, interior walls and masonry, HVAC, plumbing and electrical.

22 GLENOAKS ELEMENTARY (Rendering of Front Elevation)

23 GLENOAKS ELEMENTARY Administration Upgrades (February 2017)

24 GLENOAKS ELEMENTARY Administration Upgrades (February 2017)

25 GLENOAKS ELEMENTARY Administration Upgrades (February 28, 2017)

26 NORTHSIDE ACTIVITY CENTER RENOVATIONS Architect Richard Sanchez Architects, Inc. Project Architect Richard Sanchez NISD Project Manager Thomas Curiel Contractor O Haver Contractors Co. Construction Amount - $5,319, Tentative Construction Period February 2017 January 2018 Project Scope Addition/Renovation Notice to Proceed issued March 3, Contractor is mobilizing on site.

27 PAUL TAYLOR FIELD HOUSE RENOVATIONS Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Stoddard Construction Management, Inc. Construction Amount - $3,400, Tentative Construction Period February 2017 August 2017 Project Scope ADA Interior/Exterior Renovations Notice to Proceed issued. Site Mobilization and Demolition in Progress.

28 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)

29 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)

30 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)

31 2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor CGC General Contractors Construction Amount - $1,293, Tentative Construction Period June 2017 August 2017 Project Scope New Security Lobby for (9) Elementary Schools: Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES General Contractor approved at January Board Meeting. Contract negotiations ongoing.

32 2014 BOND PROJECTS IN BID/DESIGN PHASE SUMMER 2017

33 HOLMES HS FINE ARTS - AUDITORIUM Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor Bartlett Cocke Construction Budget - $27,000, Tentative Construction Period June 2017 December 2018 Project Scope Fine Arts Building Replacement Site and Demolition Construction Documents issued February 28, Portables relocation complete. Portable renovation in progress. MDF relocation in progress.

34 BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Jim Berg Contractor TBD Construction Budget - $4,040, Tentative Construction Period June 2017 May 2018 Project Scope Administration Upgrades, Bus/Student Walkway Canopy Modifications Construction Documents in progress.

35 COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work Architect Huckabee Architects Project Architect Jeff Rodriquez NISD Project Manager Chris Parker Contractor TBD Construction Budget - $2,000, Tentative Construction Period June 2017 October 2017 Project Scope Window Upgrades and ADA Work Proposal Opening February 21, Contractor submitted for March Board Approval.

36 GLASS ELEMENTARY Window Upgrades / ADA Work Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,500, Tentative Construction Period June 2017 August 2017 Project Scope Window Upgrades and ADA Work Schematic Design and Master Plan in progress.

37 GLENOAKS ELEMENTARY - Window Upgrades / ADA Work Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $1,100, Tentative Construction Period June 2017 December 2017 Project Scope Window Upgrades and ADA Work Schematic Design approved by Board in January. Construction Documents issued March 6, Proposals to be received on March 29, 2017.

38 GLENOAKS ELEMENTARY Library and Classroom Building Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $10,000, Tentative Construction Period June 2018 December 2018 Project Scope Library and Classroom Building Schematic Design in progress.

39 GLENN ELEMENTARY School Building Replacements / Security Lobby Architect LPA Project Architect Mark Oppelt / Lowell Tacker NISD Project Manager Jim Berg Contractor TBD Construction Budget - $4,800, Tentative Construction Period June 2017 August 2018 Project Scope Replacement of Buildings Proposal Documents issued February 13, Proposals to be received March 23, 2017.

40 KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition Architect Pfluger Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor TBD Construction Budget $2,200, Tentative Construction Period June 2017 November 2017 Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Schematic Design approved by Board October 25, Proposal Opening February 28, Contractor submitted for March Board Approval.

41 TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor TBD Construction Budget $2,200, Tentative Construction Period June 2017 November 2017 Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Schematic Design approved by Board October 25, Proposal Documents issued February 20, Proposal opening March 22, 2017.

42 2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS Architect Chesney Morales Project Architect Richard Morales NISD Project Manager James Evans Contractor TBD Construction Budget $117, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Door Hardware for Accessibility Construction Documents in progress.

43 2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary Architect CWS Architect Project Architect Robert Watts NISD Project Manager Chris Parker Contractor TBD Construction Budget $230, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Flooring Proposal Documents issued February 27, Proposal opening March 22, 2017.

44 2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS Architect Huckabee Architects Project Architect Jeff Rodriguez NISD Project Manager Chris Parker Contractor TBD Construction Budget $325, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Flooring Proposals received February 15, Contractor submitted for March Board Approval.

45 NEFF MS COMPETITION GYM FLOORING AND BLEACHERS Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Chris Parker Contractor TBD Construction Budget $200, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Flooring and Bleachers Proposals Opening March 8, Contractor submitted for March Board Approval.

46 2016 GROWTH & IMPROVEMENT

47 CHILD NUTRITION WAREHOUSE Warehouse Renovation Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Henry Acosta Contractor Workman Commercial Contract Amount - $5,726, Construction Period July 2016 January 2017 Construction Status: 89% Complete Project Scope Warehouse Renovation Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings. Demo complete, rough-ins in progress. Walk in cooler/freezer floor complete. Office area drywall complete, tape & float (finishes in progress), new switch gear being installed, new CPS transformer on its way. Walk-in cooler/freezers, walls, racks and ceilings being installed. Condensers set.

48 CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)

49 CHILD NUTRITION WAREHOUSE Warehouse Renovation (March 3, 2017)

50 CHILD NUTRITION WAREHOUSE Warehouse Renovation (March 3, 2017)

51 CHILD NUTRITION WAREHOUSE Warehouse Renovation (Feb 16, 2017)

52 CHILD NUTRITION WAREHOUSE Warehouse Renovation (Feb 16, 2017)

53 2017 GROWTH & IMPROVEMENT

54 2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Chris Parker Contractor TBD Construction Budget $920, Construction Period June 2017 August 2017 Construction Status: 0% Complete Project Scope Installation of Athletic Storage Units and Interior Renovations. Proposals received February 7, Contractor submitted for March Board Approval.

55 JORDAN MIDDLE SCHOOL Interior Painting Project Architect Noonan Rittimann Project Architect Noonan Rittimann NISD Project Manager James Evans Contractor TBD Contract Amount $325, Construction Period June 2017 August 2017 Construction Status: 0% Complete Project Scope Paint Interior of the School. Construction Documents issued for IDQ March 6, 2017.

56 ATHLETIC STORAGE BUILDING AT TAFT HS AND JOHN JAY HS Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager James Evans Contractor TBD Contract Amount $90, Construction Period June 2017 July 2017 Construction Status: 0% Complete Project Scope Installation of Athletic Storage Units. Construction Documents to be issued March 8, 2017.

57 ROOFING PROJECTS

58 BOONE ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Raba Kistner Contractor Samuel Dean Sheet Metal Inc. Contract Amount $336, Construction Period June August 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project Closeout in Progress.

59 CABLE ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Austech Engineering Contractor Cram Roofing Contract Amount $199, Construction Period June 2016 August 2016 Construction Status: Complete Project Scope Roof Repairs & Waterproofing Project Closeout Complete.

60 HOWSMAN ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Raba Kistner Contractor Beldon Contract Amount $692, Construction Period June 2016 August 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project Closeout in Progress.

61 LEWIS ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Austech Contractor Empire Roofing Contract Amount $190, Construction Period June 2016 August 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project Closeout in Progress.

62 LINTON ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Raba Kistner Contractor ATC Contractors, Inc. Contract Amount $208, Construction Period June 2016 August 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project Closeout in Progress.

63 MAY ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor Port Enterprise Contract Amount $1,678, Construction Period June 2016 October 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project closeout in progress.

64 TAFT HIGH SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor Port Enterprise Contract Amount $1,632, Construction Period June 2016 December 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project closeout in progress.

65 VILLARREAL ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Austech Contractor Samuel Dean Sheet Metal Inc. Construction Budget $97, Construction Period June 2016 August 2016 Construction Status: 98% Complete Project Scope Roof Repair & Waterproofing Project Closeout in Progress.

66 2016 HAIL DAMAGE ROOFING PROJECTS

67 BEARD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Hollon & Cannon Contractor TBD Contract Amount $566, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration Project in Design. Bids Received. Approved at February Board.

68 CARNAHAN ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Hollon & Cannon Contractor TBD Contract Amount $2,125, Construction Period June 2017 December 2017 Project Scope Roof Replacement Project in Design. Bids Received. Approved at February Board.

69 CLARK HIGH SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Hollon & Cannon Contractor TBD Contract Amount $2,490, Construction Period June 2017 December 2017 Project Scope Roof Replacement Project in Design. Bids Received. Approved at February Board.

70 SOUTH TRANSPORTATION HAIL DAMAGE ROOFING PROJECT Roofing Consultant Raba Kistner Contractor TBD Contract Amount $261, Construction Period June 2017 December 2017 Project Scope Roof Replacement Project in Design. Submitted for March Board Approval.

71 STEVENSON MIDDLE SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Raba Kistner Contractor TBD Contract Amount $1,904, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration Project in Design. Approved at February Board.

72 CARLOS COON ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Austech Contractor TBD Contract Amount $1,409, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration Project in Design. Submitted for March Board Approval.

73 ELROD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Austech Contractor TBD Contract Amount $784, Construction Period June 2017 December 2017 Project Scope Roof Restoration Project in Design. Bids Received. Approved at February Board.

74 FERNANDEZ ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT Roofing Consultant Austech Contractor TBD Contract Amount $1,102, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration Project in Design. Submitted for March Board Approval.

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

Crockett Elementary School Renovations

Crockett Elementary School Renovations We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ WINNER 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Ivey Lane Elementary

More information

Facilities Planning & Construction

Facilities Planning & Construction Facilities Planning & Construction Weekly Report Goose Creek CISD Week of June 10 June 16, 2017 Technology Center In This Issue: GCM Wing Addition Cover Security Vestibules Cover Transportation Center

More information

Dilley ISD 2013 Bond Program Project Update Report March 11, 2015

Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going o Architect BWA: Executed 2/20/13 Work on-going

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

Building Construction Occupations

Building Construction Occupations Job Ready Assessment Blueprint Building Construction Occupations Test Code: 2011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge

More information

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath Trade Package Base Bid P and P BOND Alternate #1: drop off canopy Alternate #2: bike rack canopies Alternate #3: courtyard Alternate #4 Unit Door Alternate #5 Solid Surface Alternate #6A Bath Alternate

More information

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form. Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

Creative Performing Media Arts Middle School

Creative Performing Media Arts Middle School Dawne St Kilkee St Enelra Pl Creative Performing Media Arts Middle School 5050 Conrad Ave. San Diego, CA 92117 Sub-district: A Cluster: Madison Year School Opened: 2002 Grades: 6-8 Arlene Pl 3 2 Conrad

More information

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

LOVEJOY Independent School District

LOVEJOY Independent School District Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene January 19, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Carpet & Base in B6 Corridor. Completed 1 ST Coat of Paint in B4 Corridor. Completed 2 ND Coat of Paint in C3 Units Completed

More information

Madison School District. Strategic Five-Year Facility Maintenance Plan

Madison School District. Strategic Five-Year Facility Maintenance Plan Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since

More information

Operational Services Facility Innovation & Readiness Stakeholder Team

Operational Services Facility Innovation & Readiness Stakeholder Team Operational Services Facility Innovation & Readiness Stakeholder Team A great place for kids to learn. A great place for employees to work. A place our community can be proud of. 21 st Century School District!

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene March 2, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Final Paint in B6 Corridors. Completed Final Clean in CL1 Units. Continued Signing Off Punch List Items in the West Zone. Continued

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

MIAMI-DADE COUNTY PUBLIC SCHOOLS OFFICE OF ECONOMIC OPPORTUNITY PREQUALIFICATION FORUM

MIAMI-DADE COUNTY PUBLIC SCHOOLS OFFICE OF ECONOMIC OPPORTUNITY PREQUALIFICATION FORUM MIAMI-DADE COUNTY PUBLIC SCHOOLS OFFICE OF ECONOMIC OPPORTUNITY PREQUALIFICATION FORUM THURSDAY, May 4, 2017 OVERVIEW OF M-DCPS CONTRACTOR PREQUALIFICATION 2 GENERAL CONTRACTING ELECTRICAL BUILDING ROOFING

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

PRELIMINARY STRUCTURAL INVESTIGATION REPORT

PRELIMINARY STRUCTURAL INVESTIGATION REPORT 124 E. Broadway Tucson, AZ Prepared for: CBRE Brokerage Services 3719 N. Campbell Ave. Tucson, AZ 85719 BACKGROUND: The Tucson Veterans of Foreign Wars building, located at 124 E. Broadway, Tucson, AZ

More information

DSA Inspectors. Arcadia USD. Arcadia HS Campus Enrichment. Inspection Report Apr 2014

DSA Inspectors. Arcadia USD. Arcadia HS Campus Enrichment. Inspection Report Apr 2014 DSA Inspectors Arcadia USD Arcadia HS Campus Enrichment Inspection Report Apr 2014 Architect DSA Application No. A03-111889 33 Narcissa Drive, Rancho Palos Verdes, CA 90275 (626) 786-4331 Info@KnowlandInc.com

More information

CITY OF NOVI. Police Department

CITY OF NOVI. Police Department CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

Easthampton High School Building Project. Public Information Forum #3

Easthampton High School Building Project. Public Information Forum #3 Building Project Public Information Forum #3 May 4, 2010 CAOLO & BIENIEK ASSOCIATES, INC. Architecture Planning Interior Design Presentation Agenda Introduction - Michael Buehrle, Chair EHS Building Committee

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Office of Planning, Design and Construction. Capital Program Update April 10, 2017

Office of Planning, Design and Construction. Capital Program Update April 10, 2017 Office of Planning, Design and Construction Capital Program Update April 10, 2017 Projects Under Construction Translational Research Center Translational Research Center Phase I Site work Completed - June

More information

CATAMARAN TOWER - 1 Seef Area Plot 19, 20

CATAMARAN TOWER - 1 Seef Area Plot 19, 20 STATUS REPORT NO 18 [As on September 30, 2017] This report is intended as a status report and covers only the activities completed till date, non-completed works and work-in-progress. A. Project Details

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene October 6, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Hardscapes East of Building C. Completed Building D Dumpster Pad. Completed Brick on Site Wall North of Building D. Completed

More information

PeachStone Capital, Inc. Atlanta s Hard Money Lender When timing is everything, we close! Hard Money Loan Property Worksheet Checklist

PeachStone Capital, Inc. Atlanta s Hard Money Lender When timing is everything, we close! Hard Money Loan Property Worksheet Checklist Hard Money Loan Property Worksheet Checklist Please complete ALL requested information. Incomplete applications will NOT be reviewed! Fully executed purchase and sale agreement including all exhibits,

More information

DAT MEETING NOTES # 3

DAT MEETING NOTES # 3 DAT MEETING NOTES # 3 MOA ARCHITECTURE Design Advisory Team 821 17 th Street, Suite 400 Denver, Colorado 80202 303.308.1190 Phone 303.308.1197 Fax Project: Superior Elementary School Date: 16 December

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY 1.1 Campus Program Summary There are five (5) projects in pre-design and programming; four (4) are in design; and five (5) in construction. A summary of the Trade-Tech construction

More information

Projects Currently in Planning, Design and Construction. April 12, 2017

Projects Currently in Planning, Design and Construction. April 12, 2017 Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space

More information

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER SUMMARY OGDENSBURG, NY The New York Main Street program (NYMS) is administered by the Office of Community Renewal (OCR) under the direction of the New York State Housing Trust Fund Corporation (HTFC).

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA 2700 Judge Fran Jamieson Way

More information

Mount Vernon Elementary School Grades PK 5

Mount Vernon Elementary School Grades PK 5 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

Building Services. Experienced Professionals. Reliable Service. Quick Response.

Building Services. Experienced Professionals. Reliable Service. Quick Response. Building Services Experienced Professionals. Reliable Service. Quick Response. What We Offer Leopardo s Building Services group offers general maintenance, emergency service and light construction work.

More information

POC: John Roberts, or (843)

POC: John Roberts, or (843) NAVAL FACILITIES ENGINEERING COMMAND, MID-ATLANTIC FACILITIES ENGINEERING AND ACQUISITION DIVISION (FEAD) PARRIS ISLAND 62 ATSUGI STREET (BUILDING 852) PARRIS ISLAND, SC 29905 POC: John Roberts, john.b.roberts@navy.mil

More information

Fayetteville Public School Facilities

Fayetteville Public School Facilities Fayetteville Public School Facilities Asbell Asbell Elementary School Principal: Ms. LaTayna Greene Capacity: 504 Enrollment: 399 Date Constructed: 1961 Square Feet: 39,166 Acres: 19.93 Major Renovations:

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

BoardDocs Pro http://www.boarddocs.com/fla/leon/board.nsf/public 1 of 2 3/9/2015 12:39 PM Agenda Item Details Meeting Mar 10, 2015 - Business Meeting Category Subject Type Budget Source 18. Items for Consideration

More information

PANERA BREAD BAKERY-CAFE # EAST EAU GALLIE BLVD. INDIAN HARBOUR BEACH, FL BREVARD COUNTY

PANERA BREAD BAKERY-CAFE # EAST EAU GALLIE BLVD. INDIAN HARBOUR BEACH, FL BREVARD COUNTY SHEET INDEX. CONSTRUCTION DOCUMENTS (DRIVE-THRU ADDITION) GENERAL G-CS COVER SHEET G-ADA ACCESSIBILITY GUIDELINES G-SL SYMBOLS, LEGEND, & ABBREVIATIONS LSP-1 LIFE SAFETY PLAN ARCHITECTURAL SP-1.0 SITE

More information

BOWIE LEARNING CENTER

BOWIE LEARNING CENTER BOWIE LEARNING CENTER Bowie Learning Center BUILDING DATA BOWIE LEARNING CENTER 900 North Elm St., Weatherford, TX 76086 Year Built 1936 No. of Buildings No. of Portables 0 Approx. Total Square Footage

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved. Sri Ganesha Temple HTNT Construction Update (June, 2016) With Lord Ganesha s Blessing We start everything Architect View of the Ganesha Temple at Finish Sri Ganesha Temple HTNT Construction Milestones

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

FACILITY NEEDS ASSESSMENT CURRENT PRIORITY ONE PROJECTS

FACILITY NEEDS ASSESSMENT CURRENT PRIORITY ONE PROJECTS 9 - MARCH - 2015 Professional Team TMP Architecture, Inc. Peter Basso Associates, Inc. Integrated Design Solutions SUMMARIES SUMMARIES District Totals ELEMENTARY SCHOOLS Beverly Bingham Farms Greenfield

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN. CONSTRUCTION UPDATE June THIS IS AUBURN. RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Lobby of the Risk Management and Safety

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

New Homes Forestbrook Road. Yes, it s INCLUDED!

New Homes Forestbrook Road. Yes, it s INCLUDED! Sugar Mill is a Covenant Restricted Community. New Homes Forestbrook Road Yes, it s INCLUDED! Granite Countertops Ceramic Tile Kitchen Floors Front Brick Accents Upgraded Kitchen Cabinets Ceramic Tile

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

FACILITIES OPERATIONS PARKING SERVICES COMPLEX BUILDING PHASE - CERTIFIED BID TABULATION

FACILITIES OPERATIONS PARKING SERVICES COMPLEX BUILDING PHASE - CERTIFIED BID TABULATION BID PACKAGE: 07B ROOFING ALTERNATES 2B Washrack - CMU walls and roof AAR of North Carolina Carolina Commercial Roofing $ 563,000.00 X X X B X Davco Roofing and Sheet Metal Eastern Corporation Grieme Roofing

More information

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT:

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT: REV 2 CONCEPTUAL ESTIMATE FOR: Interior Architects, P.C Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY AT: BY: GARDINER AND THEOBALD INC Issued: 6/20/2013 BROOKLYN HEIGHTS LIBRARY, BROOKLYN

More information

Northside ISD 5900 Evers Road San Antonio, Texas 78238

Northside ISD 5900 Evers Road San Antonio, Texas 78238 Northside ISD 59 Evers Road San Antonio, Texas 78238 Prepared by: Texas Energy Engineering Services, Inc. 131 S. Capital of Texas Highway Capital View Center Suite B 325 Austin, Texas 78746 (512) 328 2533

More information

AVID Intelligent Home Plans

AVID Intelligent Home Plans Home Builder Rental Equipment Landscaping, Sprinklers Gutters & Downspouts Insulation, Rough electrical, lighting, appliances Engineered lumber, Joist Trusses, Sheathing Plywood, Lumber Roofing, siding,

More information

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS 1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225 GENERAL NOTES DESIGN NOTES (CONTINUED) FOUNDATION NOTES STRUCTURAL ABBREVIATIONS CONCRETE MASONRY NOTES DESIGN NOTES S-001 CONCRETE NOTES COLD-FORMED STEEL FRAMING NOTES PRE-ENGINEERED METAL BUILDING NOTES

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

PROFESSIONAL DESIGN MANUAL INDEX

PROFESSIONAL DESIGN MANUAL INDEX PROFESSIONAL DESIGN MANUAL INDEX DIVISION A--GENERAL PROJECT REQUIREMENTS... A2-A15 A.1 INTRODUCTION... A-2 A.2 CODES COMPLIANCE (VERIFY CITY REQUIREMENTS)... A-5 A.3 SPECIAL SUBSURFACE AND LAND CONDITIONS...

More information

MADISON HIGH SCHOOL // Executive Summary

MADISON HIGH SCHOOL // Executive Summary MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*

More information

NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES EXTERIOR RESTORATION & WATERPROOFING.

NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES EXTERIOR RESTORATION & WATERPROOFING. EXTERIOR RESTORATION & WATERPROOFING NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES www.janbarinc.com Janbar Inc is a general contracting company located in Brooklyn NY. Started originally in 2002

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

MANHATTAN COLLEGE STUDENT COMMONS

MANHATTAN COLLEGE STUDENT COMMONS MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons

More information

CARL E. SCHLUTER ELEMENTARY SCHOOL

CARL E. SCHLUTER ELEMENTARY SCHOOL CARL E. SCHLUTER ELEMENTARY SCHOOL Carl E. Schluter Elementary School Campus Data CARL E. SCHLUTER ELEMENTARY SCHOOL 1220 Mesa Crest Drive, Haslet, Texas 76052 Year Built 2011 Approx. Total Square Footage

More information

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater

More information

Design Advisory Committee Meeting #1. December 6, 2016

Design Advisory Committee Meeting #1. December 6, 2016 Design Advisory Committee Meeting #1 December 6, 2016 1 Meeting Agenda 1. Agenda / Attendance Sheet 5 minutes 2. Introductions - 10 minutes 3. Meeting Norms 5 minutes 4. Project Schedule 5 minutes 5. Buildings

More information