Site Committee Meeting #5

Size: px
Start display at page:

Download "Site Committee Meeting #5"

Transcription

1 PROJECT MEETING NOTES San Rafael City Schools Site Committee Meeting #5 Location: Project: Glenwood ES 25 W. Castlewood Drive, San Rafael, CA Glenwood ES New Multi-Purpose Room Meeting Date: 28 February :30 pm Attendees: Kim Goodhope, Glenwood Principal Natu Tuatagaloa, SRCS Board Member Jenni Conte, Glenwood Teacher Tami McCall, SRCS Board Member / Glenwood Parent John Dasher, GSF President / Glenwood Parent Adam Treewater, Glenwood Teacher Ramina Winton, Glenwood Parent Pete Norgaard, VPCS Program Manager Terese Sladowska, VPCS Program Design Manager Wally Gordon, Deems Lewis McKinley Scott Berge, Deems Lewis McKinley Distribution: Next Meeting Participants File 1. General: a. VPCS noted that the latest schematic drawings were presented at the Board Meeting on 27 February Program / Master Plan Discussion: a. Selected Master Plan Option: 1) DLM reviewed the site placement of the new building and noted that the existing warming kitchen location will remain and that no new restrooms will be needed as existing restrooms are located nearby. 2) DLM noted that a 3-D model is currently being developed. Blocked-out images were presented but refinement is still in process. The Principal asked when the design will be finalized, and DLM stated that window locations, etc. will be finalized in the upcoming weeks even though tweaks will be made during the construction document phase. b. DLM explained the summary of items included / cost / budget: 1) 4,656 sq ft MPR building with stage and storage rooms. 2) Walkway canopies will be provided in the design to connect the new building to the existing buildings. The Principal asked if the canopies can be larger than those shown. DLM stated that the canopy layout has yet to be fully worked out and that the canopies would be adjusted to line up with those currently on the site. 3) 8,000 SF of asphalt playground will be added to replace the asphalt removed for the building placement. The Principal suggested relocating this to adjacent to the new building. The existing baseball diamond is slated to be reconditioned in the next coming years by the Little League so the diamond could be relocated away to accommodate the new asphalt. DLM noted that the orientation of the field might need to be adjusted for the loss of outfield. The Board Member said that the afternoon sun could be an issue if the diamond is reoriented. VPCS noted that the asphalt section can be possibly decreased since the use is only for a playground and no vehicular traffic will use it. This could save cost and allow for more asphalt. 4) DLM noted that the estimate is complete, but features such as stage curtains and backboards are not included in the base estimate. Structural wall backing and electrical connections will be provided to allow for Page 1 of 3

2 easy future installation. The backboard at the stage would have an electric lift to tilt it away from the view of the stage. These items can be bid as alternates if the District desires. i. A teacher questioned if basketball backboards and striping are desired if the court is undersized. The Board Member said that it is important to add a provision for the basketball courts since some schools have regretted not including the option in planning their MPR s. ii. A parent asked if the GSF can start fundraising for the excluded features. VPCS noted that they can work on a schedule for when funds need to be obtained in order to get the work into the building construction. iii. It was asked if advertising could pay for a scoreboard. The Board Member stated that this has been done at the high schools, but the Board wants to see what it would look like first. The Principal would need to present any proposals for this to the Board. 5) DLM noted that the estimate includes resilient athletic flooring. An option discussed at the previous meeting was for Gerflor Teraflex flooring as used at Bel Aire ES MPR at RUSD. DLM visited this site and spoke with the facilities director. It was noted that the floor does dent with heavy items such as pianos, but the dents go away after a few days. The school is very happy with the product. A teacher noted that the piano at GES could be located on the stage to prevent dents. 6) The Principal asked if the building will be air-conditioned. DLM said there will only be heat and ventilation for this site. The Principal noted that the MPR gets very hot during Back-to-School night and a few times each year and that good ventilation is needed. DLM said that this will be reviewed during design. The Principal asked if air-conditioning can be added in the future. DLM said that Terra Linda HS will be retrofitted with air-conditioning this summer so it is possible to add it later, but loads on the existing utilities need to be verified to ensure that it is possible to add it without a major upgrade. 7) The Principal questioned if tables and chairs are included in the project. VPCS said that this is in the overall budget for the project (not construction budget). i. The Principal said that there are pros and cons if folding wall tables are used. One complaint is pinched fingers. It is important that storage is provided if portable tables and chairs are used. DLM said that understage storage is included in the estimate. c. DLM noted that the emergency vehicle access has been preliminarily approved by the fire department. d. The Principal asked about glare with the building orientation. DLM stated that this is currently being reviewed based on the sun angles, and window locations will be adjusted or sunshades added to avoid glare. e. The Principal asked if the building will have a flat roof as she does not prefer this. DLM said that the roof profile is being studied and that gluelaminated beams will be used, and they can have a camber so as to avoid a true flat roof. A teacher noted that it is preferred to slope the roof so that balls roll off the roof. f. The Board Member asked about the procurement status for the building. VPCS noted that modular companies have been interviewed, but the decision to build modular vs. site-built-framing is still pending. DLM noted that there are no DSA pre-checked MPR buildings so there might not be an advantage to build modular for this project. g. The Principal noted that the geotechnical borings were recently completed. h. The Site Committee agreed that the current layout and design looks good. The only question is the playground asphalt location, and the Principal will look into this with Little League. i. The Principal requested that the existing gaga pit be shown on the site layout and that the basketball court be shown on the new asphalt. j. The Board Member asked about technology. Principal said that she wants infrastructure for a projector and wireless access. Page 2 of 3

3 k. Principal asked about adding a cellular tower to the site. The Board Member said that this can be hard to add as neighbors often don t want these installed. l. The Board Member asked about solar panels for this building. DLM stated that providing structural capacity for future installations is now required per the building code. 3. Next Meetings: a. GSF Parent Meeting (8 March :00 pm) b. Site Committee Meeting 6 (14 March :30 pm) c. Board Meeting for Final Schematics (17 April 2017) d. Staff Presentation (19 April 2017) General: The meeting notes were generated by Scott Berge. If there are corrections, please call prior to the next meeting. In the absence of such corrections these notes will stand as the true and accurate record of the meeting. Page 3 of 3

4 GLENWOOD ELEMENTARY SCHOOL San Rafael City School District 28 February 2017 Multi-Purpose Room Master Planning Meeting # 5 SIGN IN SHEET: Name Association Initial 1. Kim Goodhope 2. TamiMcCall 3. John Dasher 4. Nicole Cibellis 5. Jenni Conte 6. Adam Treewater 7. Kyri McClellan 8. Dan Zaich kgoodhope@srcs.org tami@mccallandcompany.com jmdasher629@gmail.com ncibellis@icloud.com jeconte@srcs.org atreewater@srcs.org kyrimc@gmail.com dzaich@srcs.org SchoolPrincipal Board Member/Parent GSF PresidenUParent SSC/Parent Teacher Teacher Parent SRCS 9. Pete Norgaard pete@vpcsonline.com VPCS 10. Terese Sladowska terese.sladowska@vcpsonline.com VPCS 11. Wally Gordon 12. Scott Berge 13. David Carey wgordon@dlm.com sberge@dlm.com david.carey@vpcsonline.com DLM DLM VPCS 14. Ramina Winton raminamw@comcast.net Parent 15. N \C'.f!r.A<,-1-tL o+ NP5N q'\ & COMCAS\. " END

5 LIB AD K K CHILD CARE K

6 72'-0" 25'-0" 32'-0" STORAGE 61SF 64'x36' COURT LIFT STORAGE 50 SF 48'-0" 24'-0" STAGE 576 SF FUTURE ASSROOMS STORAGE 184 SF SCHEME - 4,656 SF N

7

Boynton High School & Blackford Site

Boynton High School & Blackford Site Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066

More information

SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA

SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA 25 August 2009 All meetings are at 3:15 p.m. unless otherwise noted. Meeting dates are scheduled in advance and dates without agendas may or may not be

More information

HIDDEN VALLEY ELEMENTARY SCHOOL

HIDDEN VALLEY ELEMENTARY SCHOOL SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802

More information

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through November 2010 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Franklin Pierce School District Capital Construction Bond Candidate Projects

Franklin Pierce School District Capital Construction Bond Candidate Projects Franklin Pierce School District 2016 Capital Construction Bond Candidate Projects 2016 Capital Construction Bond The following projects have been selected to be offered to 2030 Committee for consideration

More information

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

27 January 2011, 3:30 pm-5:00 pm

27 January 2011, 3:30 pm-5:00 pm PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES DATE: SUBJECT: ATTENDEES: 27 January 2011, 3:30 pm-5:00 pm ATHLETIC FIELD IMPROVEMENTS SUBCOMMITTEE MEETING NO. 6 Sign-in sheet (attached)

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ WINNER 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Ivey Lane Elementary

More information

TWIN RIVERS UNIFIED SCHOOL DISTRICT 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015

TWIN RIVERS UNIFIED SCHOOL DISTRICT 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015 2015 LONG-RANGE FACILITY MASTER PLAN Steering Committee Meeting No. 4 \\ April 13, 2015 AGENDA I. LRFMP BRANDING UPDATE II. LRFMP FOCUS GROUP UPDATE III. ENROLLMENT PROJECTIONS / DEMOGRAPHICS IV. FINALIZE

More information

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community. SYLVAN MIDDLE SCHOOL The mission of Sylvan Middle School is consistent with that of the San Juan Unified School District, which is to inspire each student tosucceed and responsibly contribute to a radically

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Agenda (Items may be taken out of order)

Agenda (Items may be taken out of order) I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017

More information

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Modifications to the baseball field safety features related to the first base line, to prevent foul balls from entering neighboring properties. Delivery Method: Design Bid Build - CUPCCAA Infrastructure

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through June 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Easthampton High School Building Project. Public Information Forum #3

Easthampton High School Building Project. Public Information Forum #3 Building Project Public Information Forum #3 May 4, 2010 CAOLO & BIENIEK ASSOCIATES, INC. Architecture Planning Interior Design Presentation Agenda Introduction - Michael Buehrle, Chair EHS Building Committee

More information

Facility Improvements

Facility Improvements AL-SI-02 ASPHALT PLAY AREA UPGRADE AL-SI-09 CURB RAMP ADDITIONS Asphalt improvements needed around building and playshed to provide a safe play area. Curb ramps needed to provide wheelchair access and

More information

Davenport School District - Long Range Facilities Maintenance Plan

Davenport School District - Long Range Facilities Maintenance Plan Re-surface & stripe tennis Courts $42,000 Summer 0f 2009 @ a cost of $38,239 Timeline Within next five years? Projected Cracks repaired with floating system & courts were re-sealed and re-painted Sumer

More information

ZERVAS SCHOOL BUILDING COMMITTEE and DESIGN REVIEW COMMITTEE MEETING Zervas Elementary School Newton, MA June 26, 2014

ZERVAS SCHOOL BUILDING COMMITTEE and DESIGN REVIEW COMMITTEE MEETING Zervas Elementary School Newton, MA June 26, 2014 ZERVAS SCHOOL BUILDING COMMITTEE and DESIGN REVIEW COMMITTEE MEETING FEASIBILITY STUDY Site and General Layout Building Location/Orientation Site Program Building Program and Configuration 3-Story, L-Shaped

More information

SHEPHERD ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Frost Technical Center

Frost Technical Center Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera

More information

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening

More information

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report Moreno Valley Unified School District Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report November 19, 2015 District Long Term School Funding Program Revenue Sources

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

Thank you in advance for your support of PSA and area youth. Sincerely, Kim Wadley Sponsorship Director, PSA

Thank you in advance for your support of PSA and area youth. Sincerely, Kim Wadley Sponsorship Director, PSA Plano Sports Authority Inc. (PSA) is a 501 C(3) non-profit corporation established in 1970. The mission is to provide safe, quality, year-round recreational and competitive sports programs for the youth

More information

Laurel School Upper Campus Building Features

Laurel School Upper Campus Building Features Laurel School Upper Campus Building Features INTRODUCTION Laurel School Upper Campus is tucked into the Willows neighborhood in Menlo Park surrounded by residential housing on all sides. The oddly shaped

More information

DRAFT FY15/16. TBD Roof Repairs $50,000

DRAFT FY15/16. TBD Roof Repairs $50,000 FY15/16 Building Albemarle HS Design: Main Gym Floor Replacement $35,000 Burley MS Fieldhouse Restroom Facility Repairs $60,000 Burley MS Gym Partition Replacement with Curtain $30,000 CATEC Building Envelope

More information

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

CESAR CHAVEZ LANGUAGE ACADEMY

CESAR CHAVEZ LANGUAGE ACADEMY SCHOOL DAA Address: 2570 West Steele Lane Santa Rosa, CA 95403 Established: Campus - 1972, CCLA - 2013 Permanent Classrooms: 14 Portable Classrooms: 4 Building Area: Site Area: 17,000 sq. ft. 24.08 acres

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls

More information

1. Replace Elmira Elementary School on the Same Site $12,600, Enclose the Libraries at Fern Ridge Middle School and Veneta Elementary

1. Replace Elmira Elementary School on the Same Site $12,600, Enclose the Libraries at Fern Ridge Middle School and Veneta Elementary 2013 Proposed Capital Improvement Plan Presented October 21, 2013 Prepared By Fern Ridge School District Long Range Facility Planning Committee DLR Group The Fern Ridge Long Range Facility Planning Committee

More information

GALT JOINT UNION HIGH SCHOOL DISTRICT May 24, 2017 MEASURE E BOND UPDATE BIWEEKLY REPORT Report No: 001

GALT JOINT UNION HIGH SCHOOL DISTRICT May 24, 2017 MEASURE E BOND UPDATE BIWEEKLY REPORT Report No: 001 GALT JOINT UNION HIGH SCHOOL DISTRICT May 24, 2017 MEASURE E BOND UPDATE BIWEEKLY REPORT Report No: 001 SUMMARY May 2017 marks a busy month of master planning refinement and continued substantial progress

More information

Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report

Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Kirk Elementary

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

MAPLE GROVE PUBLIC SCHOOL FACILITY INFORMATION. East and South Lincoln Elementary Schools Accommodation Review

MAPLE GROVE PUBLIC SCHOOL FACILITY INFORMATION. East and South Lincoln Elementary Schools Accommodation Review MAPLE GROVE PUBLIC SCHOOL FACILITY INFORMATION East and South Lincoln Elementary Schools Accommodation Review October 2012 EAST AND SOUTH LINCOLN ELEMENTARY SCHOOLS ACCOMMODATION REVIEW Maple Grove Public

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

COMPREHENSIVE SIGN CODE UPDATE. City of Topeka Planning & Development Dept. 2/26/19

COMPREHENSIVE SIGN CODE UPDATE. City of Topeka Planning & Development Dept. 2/26/19 COMPREHENSIVE SIGN CODE UPDATE City of Topeka Planning & Development Dept. 2/26/19 1 WHY Reed vs. Town of Gilbert and content neutrality ruling 45% rated community s aesthetics/appearance below average

More information

Orange Education Center Project Update. Board Of Trustees Meeting November 9, 2015

Orange Education Center Project Update. Board Of Trustees Meeting November 9, 2015 Orange Education Center Project Update Board Of Trustees Meeting November 9, 2015 1 PROJECT BACKGROUND Existing building is 85,130 g.s.f., concrete tilt-up industrial building on 6.37 acres of land. Built

More information

Report No. 404-F Meeting Date: October 11, 2011 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA

Report No. 404-F Meeting Date: October 11, 2011 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Report No. 404-F Meeting Date: October 11, 2011 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Topic: AMENDMENT NO.1 TO INCREASE CONTRACT WITH CARMICHAEL-KEMP, ARCHITECTS FOR

More information

Report No F Meeting Date: June 22, 2017 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA

Report No F Meeting Date: June 22, 2017 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Report No. 1203-F Meeting Date: June 22, 2017 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Topic: APPROVAL OF MTT PRIORITY LIST OF PROJECTS RECOMMENDATION: The Board of Education

More information

Field House Proposal

Field House Proposal Field House Proposal For Experienced Dependable Resourceful 5802 Akron Cleveland Rd. Hudson, OH 44236 Table Of Contents Cost Projection 3 Funding Summary 4 Site Plan 5 Field House Layout 6 Field House

More information

Crockett Elementary School Renovations

Crockett Elementary School Renovations We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

Repair & Replacement Study

Repair & Replacement Study Donald Lum Elementary School Repair & Replacement Study 23 January 2018 ALAMEDA UNIFIED SCHOOL DISTRICT 1495.05 1 PROJECT BACKGROUND Overview of Engineering Studies Miller Pacific Geotechnical Report -

More information

Energy Projects to Increase Safety, Comfort & Performance

Energy Projects to Increase Safety, Comfort & Performance Energy Projects to Increase Safety, Comfort & Performance Learn how Inter-lakes School District began a 10-year journey toward energy efficiency. With school board and community support, the district teamed

More information

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST March 10, 2018 TABLE OF CONTENTS PROJECT SUMMARY LIST AND COST PROJECT DESCRIPTIONS MISSION COLLEGE PROJECT DESCRIPTIONS WEST VALLEY COLLEGE PROJECT DESCRIPTIONS

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T DEFINED: Measure T is a local ballot measure on the November 2014 ballot seeking voter authorization

More information

Meeting 6 December 14, 2016

Meeting 6 December 14, 2016 Meeting 6 December 14, 2016 TONIGHT'S AGENDA 6:00-6:30 6:30-6:35 6:35-6:40 6:40-6:45 6:45-7:00 7:00-7:15 7:15-7:25 7:25-7:35 7:35-7:50 7:50-7:55 Dinner Welcome / Agenda for tonight Review of scenarios

More information

Schematic Design D ecember 2018

Schematic Design D ecember 2018 Hey wor th CUSD #4 - Gymnasium Addition Schematic Design D ecember 2018 Prepare d by: It s more than a school, it s your future. Hey wor th CUSD #4 - Gymnasium Addition Schematic Design D ecember 2018

More information

Superintendent Proposed Capital Improvements Program. Fiscal Years

Superintendent Proposed Capital Improvements Program. Fiscal Years Superintendent Proposed Capital Improvements Program Fiscal Years 2019-2024 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-7 Capital Projects Description Pages 8-12 SUPERINTENDENT PROPOSED CAPITAL

More information

September 28, Measure TT Un-Prioritized Projects Nelson Cayabyab, Chief of Facilities

September 28, Measure TT Un-Prioritized Projects Nelson Cayabyab, Chief of Facilities September 28, 2017 Measure TT Un-Prioritized Projects Nelson Cayabyab, Chief of Facilities UN-PRIORITIZED MASTER PLAN SITES September 28, 2017 Priority # Location Project Construction cost 60/40 contribution

More information

BERKELEY UNIFIED SCHOOL DISTRICT (BUSD) Chapter 3. Structural Evaluations

BERKELEY UNIFIED SCHOOL DISTRICT (BUSD) Chapter 3. Structural Evaluations BERKELEY UNIFIED SCHOOL DISTRICT (BUSD) Chapter 3 Structural Evaluations Solar Master Plan November 2011 Chapter Three Structural Evaluations Once a school district has identified the buildings that it

More information

The Waldinger Corporation Office & Production Building

The Waldinger Corporation Office & Production Building The Waldinger Corporation Office & Production Building Scout Trail Des Moines, IA 50321 SVPA Project No 18036 U.D.R.B. PROJECT NARRATIVE September 19, 2018 The Waldinger Corporation Office & Production

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Modifications to the baseball field safety features related to the first base line, to prevent foul balls from entering neighboring properties. Delivery Method: Design Bid Build - CUPCCAA Infrastructure

More information

Lisbon School Department. 5 Year Plan-Buildings, Grounds, Equipment, & Technology. April 2016

Lisbon School Department. 5 Year Plan-Buildings, Grounds, Equipment, & Technology. April 2016 April 2016 Following is a list of items that the Lisbon School Department deems necessary for Capital Improvements for the next 5 years. Capital Improvements shall mean any construction project exceeding

More information

WATKINS ELEMENTARY SCHOOL

WATKINS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

Report No F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA

Report No F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Report No. 1203-F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Topic: APPROVAL OF MTT PRIORITY LIST OF PROJECTS RECOMMENDATION:

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

(11/17/2009) Adam Lid - Public Works Committee meeting Wed Page 1

(11/17/2009) Adam Lid - Public Works Committee meeting Wed Page 1 (11/17/2009) Adam Lid - Public Works Committee meeting Wed Page 1 From: To: Date: Subject: Attachments: Adam, diana nave 11/14/2009 1:27 PM Public Works

More information

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting:

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting: a contract within the Total Project Cost budget of $123.2 million, and to proceed with project construction not to exceed a Total Project Cost of $62.6 million. This motion is effective September 27, 2012.

More information

PROJECT LIST ALTERNATIVE #1

PROJECT LIST ALTERNATIVE #1 PROJECT LIST ALTERNATIVE #1 TEMECULA VALLEY UNIFIED SCHOOL DISTRICT BOND PROJECT LIST To protect the quality of education in schools within the Temecula Valley Unified School District ( School District

More information

Bond Referendum: Proposed Capital Project

Bond Referendum: Proposed Capital Project BRONXVILLE UNION FREE SCHOOL DISTRICT Building for the next 100 years Bond Referendum: Proposed Capital Project Overview Process started several years ago Review of 100 year old building needs: Five Year

More information

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

Facilities Feasibility Study Frederick Douglass HS Condition Assessment Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies

More information

William Paca / Old Post Road Elementary School

William Paca / Old Post Road Elementary School William Paca / Old Post Road Elementary School Scope Study Presentation Submitted to: Harford County Public Schools 102 South Hickory Avenue Bel Air, Maryland 21014 Prepared by: 11415 Isaac Newton Square

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions Sherwood Elementary School resides in a quiet residential neighborhood with a shared parking area adjacent to the community league on the north and a generous play

More information

7663 N. San Fernando Rd. Burbank Airport Commerce Center Burbank, CA 91505

7663 N. San Fernando Rd. Burbank Airport Commerce Center Burbank, CA 91505 7663 N. San Fernando Rd. Burbank Airport Commerce Center Property Features 15,053 Sq. Ft. Fully Air-Conditioned Warehouse SALE PRICE: $3,010,600 ($200.00/SF) LEASE RATE: $0.98/SF NNN Estimated Building

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

Darien Public Schools. Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018

Darien Public Schools. Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018 Darien Public Schools Master Plan Discussion Review of Elementary Schools Board of Education Meeting March 14, 2018 BACKGROUND MASTER PLAN REPORT SUBMITTED DECEMBER 2016 DOCUMENTED DISTRICT-WIDE INFRASTRUCTURE

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 X DATE: December 6-8, 2016 ****************************************************************************** SUBJECT: South Dakota State University

More information

Background to why Transition Bath objects of the design of the building

Background to why Transition Bath objects of the design of the building Summary Transition Bath formally objects to the planning application to build a new classroom block for 180 pupils on the grounds that the proposed building has not been designed sustainably and is likely

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets

More information

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District

More information

PROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction

More information

County of Santa Cruz %

County of Santa Cruz % County of Santa Cruz % PROBATION DEPARTMENT P.O. BOX 1812, SANTA CRUZ, CA 95061-1812 (831) 454-2150 FAX: (831) 454-3035 JOHN P. RHOADS CHIEF PROBATION OFFICER December 3,1999 Agenda: December 14, 1999

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

Cold Spring School District

Cold Spring School District Cold Spring School District Deferred Maintenance & Capital Facilities Program July 9, 2018 Deferred Maintenance District Fund 14 School Facilities Maintenance in General Three types of maintenance projects

More information

Architectural Services Consultant Registration Form

Architectural Services Consultant Registration Form Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,

More information

HOOVER. Hoover High School Practice Field Lighting Project

HOOVER. Hoover High School Practice Field Lighting Project REVISED JUNE 21, 2012 Hoover High School Practice Field Lighting Project 06/20/12 Community Presentation: 6:30pm to 7:30pm Hoover High School, Parent Meeting Room 12101 Agenda Introductions Project Needs

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

Field Report. Background Projects programmed for Madison High School include:

Field Report. Background Projects programmed for Madison High School include: SDUSD Prop. S ICOC Prop. S ICOC Subcommittee Construction September 2, 2010, Exhibit 7.1 Field Report School District: SDUSD ICOC Location/School: Madison High School Project: Automotive Repair & Multi-Media

More information

CENTRAL EASTSIDE INDUSTRIAL CO-OP ENERGY PROGRAM

CENTRAL EASTSIDE INDUSTRIAL CO-OP ENERGY PROGRAM CENTRAL EASTSIDE INDUSTRIAL CO-OP ENERGY PROGRAM Scott Grbavac University of Oregon Architectural Programming Fall 2007 CENTRAL EASTSIDE INDUSTRIAL CO-OP ENERGY PROGRAM Company towns of the Industrial

More information

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely

More information

TRANSFORMING ROOFS, TRANSFORMING HOMES

TRANSFORMING ROOFS, TRANSFORMING HOMES TRANSFORMING ROOFS, TRANSFORMING HOMES TRANSFORMING ROOFS, TRANSFORMING HOMES Delta Roof Systems range of products offer customers a truly unique and innovative roofing solution that is supported with

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive

More information

THE ACCELERATED BUILDING SYSTEM FOR YOUR EDUCATION FACILITY NEEDS

THE ACCELERATED BUILDING SYSTEM FOR YOUR EDUCATION FACILITY NEEDS THE ACCELERATED BUILDING SYSTEM FOR YOUR EDUCATION FACILITY NEEDS ABOUT RAMTECH S ince our founding as a design-build construction company in 1982, Ramtech has provided multiple building solutions for

More information

Juanita High School Modernization vs. New-in-lieu of Modernization Report

Juanita High School Modernization vs. New-in-lieu of Modernization Report Juanita High School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Juanita High School

More information

SCARSDALE PUBLIC SCHOOLS Bond Project Planning

SCARSDALE PUBLIC SCHOOLS Bond Project Planning SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning October 23, 2017 2017 Bond Project Planning - Overview 1) December 2014 Bond (2013-2014) Work in this bond included for Heathcote, Edgewood, Middle School,

More information