PRE- FEASIBILITY REPORT

Size: px
Start display at page:

Download "PRE- FEASIBILITY REPORT"

Transcription

1 PRE- FEASIBILITY REPORT (In terms of provision of EIA Notification 2006) For Expansion of Maton Rock Phosphate mines from 0.18 MTPA to.5 MTPA AT MATON MINES, DISTRICT UDAIPUR, RAJASTHAN By Hindustan Zinc Limited Rajasthan Submitted to Ministry of Environment & Forest (MoEF) New Delhi May 2012

2 1.0 EXECUTIVE SUMMARY industan Zinc is India s only integrated producer of Zinc and Lead and is among the world s leading zinc and lead producers with ore production capacity of 9.75 million tonnes per annum. Its metal production capacity is currently 1,064,000 tonnes per annum (879,000 tonnes per annum for Zinc metal and 185,000 tonnes per annum for Lead metal) and associated byproducts i.e. Cadmium, Silver, Sulphuric acid etc. Hindustan Zinc Limited (HZL) is Asia s largest non-ferrous metal producer of Zinc and Lead and is Head quartered at Udaipur, Rajasthan. HZL is world's second largest integrated producer with a global share of approximately 6.0% in Zinc. H ZL has its operations in exploration, mining, ore processing, smelting and refining of Zinc, Lead, Cadmium and Silver. It is also a major producer of sulphuric acid as a by-product of Lead-Zinc metal processing. HZL also has large investment in wind energy having capacity of 273 MW and thermal power generation of 474 MW. H HZL also has Rockphosphate mining with an annual capacity of 0.18 million tonnes. he Maton mine is an operating mechanized opencast mine located at Village Maton, Tehsil Girwa, District Udaipur, Rajasthan. It is located at about 12 km southeast of Udaipur at a latitude and longitude and falls in the Survey of India toposheet No. 45H/14. The Phosphate deposit of Maton is located in a hill, which trends NE-SW. Site is well connected from two sides by asphalt road from Udaipur. The nearest airport is at Dabok about 12 Km NW of the project site. The nearest railway station is Rana Pratapnagar which is 8 km to the NW of Maton. T

3 he instant proposal is for expansion from 0.18 million TPA to 0.5 million TPA of ore production from its Maton mine of Rock Phosphate. T nvironment Clearance was granted by MoEF for 0.18 million TPA ore production from Maton mechanized Opencast mine vide letter no.j /169/2009-IA.II (M) dated Consent to operate was granted by Rajasthan SPCB for establishment of mine and associated structure vide letter no. F(Mines)/Udaipur(Girwa)/13(1)/ / dated and F(Mines)/Udaipur(Girwa)/13(1)/ / dated The mining operations are being carried out as per the above permissions. E 2.0 INTRODUCTION OF PROJECT 2.1 Identification of Project and Project Proponent Identification of Project The deposit was discovered by the Geological Survey of India (GSI) in 1966/67. There after an exploration program for the assessment of the deposit was under taken. Based on the finding of GSI, HZL took over the lease on for a period of 20 years with a view to develop the deposit as a captive mine for meeting the in-house requirement of Rock Phosphate for the zinc smelter Debari Udaipur. Maton Rockphosphate mine have been engaged in the mining of Phosphorite ore since inception. The initial lease area of ha. was granted on Subsequently the lease was renewed after the first approval period for ten years w.e.f and thereafter was granted an extension as second approval over a reduced area of ha (due to surrendering of Forest land) for a further period of ten years w.e.f The application for further renewal has been applied for and is under process of renewal with state Govt.

4 The mine was non-operational during However, there has been an upsurge in the demand of rockphosphate since 2007 which encouraged the company to review the economics of reopening of the mine in The consent to operate under Air and Water Act is granted by Rajasthan SPCB. Clearance was granted by MoEF for 0.18 million TPA ore production from Maton mechanized Opencast mine vide letter no.j-11015/169/2009-ia.ii (M) dated Consent to operate was granted by Rajasthan SPCB for establishment of mine and associated structure vide letter no. F(Mines)/Udaipur(Girwa)/13(1)/ / dated Ever since, the mine is in operation and operating to its rated capacity. The instant proposal is for expansion from 0.18 million TPA to 0.5 million TPA of ore production from Maton mine. In India the economy being predominantly based on agriculture, the fertilizer application to the cultivable lands plays a pivotal role in getting desired crop production. To meet, the food requirements of ever increasing population, as per the Planning Commission, the utilization of NPK fertilizers is expected to increase at the rate of 4% till India is net importer of its Phosphate requirements to the extent of 90%. Indigenous sources are able to cater upto the extent of 10%. The imports inter alia includes Rock Phosphate, Phosphoric acid which is an inter-mediatory for production of DAP and NPK fertilizers, Mono Ammonium Phosphate and Triple super phosphates. Out of the above, India is importing about 7.5 MT of Rock Phosphate balance is met by indigenous resources to the extent of about 1.5 MT (of the different grades). Of the 1.5 MT, HZL is contributing 0.18 MT from Maton Mines. Considering the huge gap between Demand and Supply, HZL is proposing to increase / expand its capacity from 0.18 to 0.5 MT Project Proponent Hindustan Zinc Limited (HZL) is the only integrated Lead & Zinc manufacturer in India and owns captive Lead and Zinc mines that supply complete requirement of Lead and Zinc concentrate for its smelters. HZL operates mechanized open cast

5 mine at Rampura Agucha as well as underground Mines at Rajpura Dariba, Sindesar Khurd, and Zawar Mines in the state of Rajasthan with state of the art technology to meet the ore requirement of its smelting operation. The smelting capacity stands Mt of metal (0.879 Mt of Zinc and Mt of Lead) and associated by-products i.e. cadmium, silver, sulphuric acid etc. are located at its smelters at Debari, Vizag, Chanderiya and Dariba in Rajasthan and a Melting and Casting plant each at Pantanagar and Haridwar in Uttarakhand. The fiscal and financial performance of the company for the past five year has shown remarkable upsurge. The company has come a long way with technology upgradation, research and development activities, up keeping of environment, safety and ecological balance besides exploring new business opportunities. HZL is also having a Rock Phosphate Mine viz. Maton Mines operating at 0.18 MtPA capacity. HZL is also having Captive Power Plants and Wind Farms Growth The growth of HZL is shown below. TABLE-2.1 GROWTH PROFILE OF HINDUSTAN ZINC LIMITED Sr. No Description Installed Capacity, MTPA Zinc Lead Ore Mining and Beneficiation Zinc Metal Production Lead Metal Production Sulphuric Acid Production Captive Power Plant (MW) Nil Wind Power (MW) Nil Rock Phosphate NIL 0.18

6 TABLE-2.2 EXISTING MINING & SMELTING UNITS OF HZL A. Mining Units Name of the Unit State Main Products Zawar Group of Mines Rajasthan Lead Zinc Ore MtPA Rajpura Dariba Mine Rajasthan Lead Zinc Ore MtPA RampuraAgucha Mine Rajasthan Lead Zinc Ore MtPA Sindesar Khurd Mines Rajasthan Lead zinc Ore MtPA Maton Mines Rajasthan Rock Phosphate B. Smelting Units Debari Zinc Smelter VizagLead-Zinc Smelter Chanderiya Smelter Complex Dariba Smelter Complex Rajasthan Andhra Pradesh Rajasthan Rajasthan Unit Annual Capacity MtPA Zinc MT 59,000 88,000 Sulphuric Acid MT 104, ,000 Cadmium MT Zinc MT 40,000 56,000 Sulphuric Acid MT 72,000 72,000 Cadmium MT Zinc MT ,000 Lead MT 35,000 85,000 Sulphuric Acid MT 1,76, ,000 Silver MT Cadmium MT Zinc MT Nil 210,000 Lead MT Nil 100,000 Sulphuric Acid MT Nil 400,000 Pantnagar Melting and Uttrakahand Zinc MT NIL 400,000 Casting Plant Lead MT NIL 100,000 Silver MT NIL 350 Haridwar Zinc Plant Uttrakahand Zinc MT NIL 250,000

7 2.2 Brief Description of Nature of Project Nature of the Project The present proposal is for expansion of the existing mechanised open cast rock phosphate mine at Maton, Udaipur District, Rajasthan from the present capacity of 0.18 MTPA to 0.5 MTPA of ore. The project is a mechanised opencast rockphosphate mine and is classified as Category-A by Ministry of Environment & Forests, New Delhi as per the EIA notification dated on 14th September 2006 and further Amendments Size of the Project The proposed rockphosphate deposit lies within the lease area of ha with an estimated ore reserves and resource of approx. 5.2 million tons. The grades varying from % of P The target production capacity of mine proposed is 0.5 million TPA. The ore produced will have an average grade of 23-26% of P Location of the Project Maton Mine is located at about 12 km southeast of Udaipur, at a latitude and longitude , and falls in the Survey of India toposheet No. 45H/14. The nearest railway station is Rana Pratapnagar on Udaipur - Chittorgarh broad gauge line of North - Western Railway at about 8 km away. The area is connected by airways with the airport being at Dabok which is at about 12 km. NW on Udaipur-Chittorgarh National Highway No. 76. The Mine is well connected on two sides by metalled road from Udaipur Mining Method The deposit is being mined by mechanised open cast mining method with benches of 10 m width and 10 m height. The bench height and width parameters have been optimized after studies on geo-technical slope stability were carried out by CIMFR. Dhanbad. The study recommended a slope of 45 in footwall orthoquartzite upto a depth of 100 m from highest point. Beyond 100 m the overall pit angle along footwall is suggested to be revised according to local conditions. The mining of the deposit shall continue with the same method. The present working

8 is confined in E1-W1& E2 lens only. The heavy earth moving machineries deployed for mining are diesel operated. A crusher is installed for crushing the ore to a size of <12 mm prior to dispatch. The mine will continue to be operated as mechanized open cast mines with increase in the size of the machinery being used to cope up the proposed expanded mining / excavation requirements. The capacity of the existing crusher will be increased to match the production. A geotechnical study would also be carried out for optimum and safe bench parameters with depth Importance to the Country & Region Indian Fertilizer industry is one of the vital industries for Indian economy, since it manufactures a very critical raw material for agriculture.the main objective of the fertilizer industry is to ensure the supply of primary and secondary nutrients in the required quantities. The fertilizer industry in India has performed a vital role in enabling the necessary increase in the use of plant nutrients for achieving the objectives of self sufficiency in food grains production and accelerated and continuous agricultural growth. Rock phosphate constituets as a basic feed stock for manufacture of phosphatic fertiliser. 2.3 Need for the Project and its Importance to the Country The basis for success in the phosphate business is access to lower-cost phosphate rock, a resource that is geographically concentrated. China, the US and Morocco together account for approximately two-thirds of world rock production and Morocco alone typically supplies more than one-third of global exports. Approximately 30 percent of global phosphate producers are non-integrated, relying on imports or domestic purchases for their rock supply. India has limited indigenous supply of phosphate rock and is the world s largest importer, accounting for about 30 percent of global trade.

9 ('000 tonnes) The following graph shows the Projection of fertilizer nutrients for 12 th Five year Plan Year k P N Source: FAI, New Delhi 2.4 Import Vs Indigenous Production The present production of Rockphosphate in India is estimated at 1.5 MT whereas the imports are estimated as 7.4 MT. If we consider the likely increase in per year, the gap between Demand and supply is likely to increase further. Whereas, on accounts of limited resources available with RSMML (which is the main producer) and MP Mining Corp, the overall domestic production is likely to remain stagnant. The following graph clearly suggests the Demand of Rock Phosphate.

10 In Million Tonnes Demand Year Import Indegeneous Source: 1. Mineral and Metal Trading Corporation of India Ltd. 2. International Fertilizer Industry Association, Paris 2.5 Export Possibility As India is already having scarcity of rockphosphate for its domestic consumption, the chances of export do not exists in near future. 2.6 Domestic and Export Market India has very limited resources of Rock Phosphate as against the Demand. The major use of Rock Phosphate in India is for manufacture of SSP, DAP, MAP, TSP, Phosphoric acid, Di-calcium Phosphate and elemental phosphorus. The Rock Phosphate from proposed expansion is proposed to be supplied as a feed stock to SSP, Phosphoric Acid manufacturing either for standalone use or for blending purpose. There is no export market for rock Phosphate in India as per the reasons given above. 2.7 Employment Generation. The proposed expansion would provide direct employment opportunity for about 180 persons (30 Executives and supervisors and 150 skilled and unskilled manpower) besides indirect employment.

11 3.0 PROJECT DESCRIPTION 3.1 Type of Project The proposed project is a mechanized Open Cast mining project of Rock phosphate of Hindustan Zinc limited situated at Village Maton; Tehsil Girwa; Dist. Udaipur. 3.2 Location Maton Mine is located at about 12 km southeast of Udaipur, at a latitude and longitude and falls in the Survey of India toposheet No. 45H/14. The phosphate deposit of Maton is located in a hill, which trends NE- SW, rising nearly 100 m above valley level. The climate is semi-arid with an average annual rainfall of 600 mm. The temperature varies from 45C in summer to as low as 1C in winter. The area is drained by a nallah, which is a tributary of seasonal Ahar river draining to UdaiSagar Lake. Maton mine receives power at 33 KV from Aklingpura substation of AVVNL. The nearest railway station is Rana Pratapnagar on Udaipur - Chittorgarh broad gauge line of North - Western Railway at about 8 km away. Water requirement is met through rainwater stored in old mine workings and purchase from 3 rd party sources.. The area is connected by airways with the airport being at Dabok which is at a distance of 12km. The Mine is well connected on two sides by metalled road from Udaipur. The revenue map is attached for reference The general location map is as shown below.

12 Maton Mines

13 The details of environmental setting are given in Table-3.1. TABLE-3.1 ENVIRONMENTAL SETTING OF THE SITE Sr. No. Particulars Details 1 Latitude Longitude Elevation above MSL 568m 4 Climatic conditions (Based on IMD Ajmer) Annual Maximum Temp: 45 0 C Annual Minimum Temp: 1 0 C Annual Average Rainfall: 600 mm 5 Present land use of mine site Agriculture, grazing, and barren land 6 Nearest Highway NH-76 (6 km, NW) 7 Nearest Railway Station Rana Pratapnagar (8 Km,NW.) 8 Nearest Airport Dabok (12 km) 9 Nearest Village Maton, Khardadia 10 Nearest Town/City Udaipur (12 km NW) City and District 11 Hills/Valleys Aravalli Hills 12 Reserved/Protected forest Bara Mandra RF, Kantla RF, Panwari RF, Hinlashla RF, Segara RF, Hora RF, Umara RF, Bagdara RF, Amarbir RF, Sant RF. 13 List of Industries Major Industry RSMML at distance of 5 km and HZL s Debari Zinc Smelter at 8 Kms 14 Socio-economic factors No fresh land acquisition. 15 Seismicity Seismic Zone-II. 3.3 Alternate Sites Considered No alternate site is applicable since ore deposit is present at Maton. 3.4 Size of Operation

14 The project has been planned to produce 0.5 MTPA Rock phosphate Ore from the mechanized opencast mine by expanding from the present 0.18 MTPA. The salient features of the proposed project are given in Table 3.2 TABLE-3.2 SALIENT FEATURES OF THE PROJECT Sr. No. Description Details 1 Name of Mine Maton Rockphosphate Mine 2 Mine lease area ha 3 Mine Lease No ML-6/89 4 Ore mineral Rock Phosphate 5 Proved Reserves Probable and Possible reserves million Tonnes Approx million Tonnes 6 Average Grade 24-26% P Ore body Width 3 m to 15 m. 8 Overall Strike length & Direction 3.2 kms, N40ºE- S40ºW 1.2 Kms with in Surface Rights 9 Ore body Dip 50º - 80º towards N50ºW 10 Mineable Reserves 2.5 million Tonnes 11 Established Depth Upto 520 mrl (190 mtrs) 12 Mode of Entry Haul Road 13 Method of Mining Open Cast Mechanized Mine 14 Rated Ore Production 0.5 Million Tpa. 15 Transportation of Ore By Truck/ Dumpers 16 Waste Rock Generation Approx. 11.5MT/Year (Avg) 17 Power requirement 1.0 MW 18 Water requirement 500 KLD 19 Manpower requirement About 180 (30 executives & supervisors, 150 unskilled, semiskilled & skilled personnel) * The Reserves & Resources are estimated as detailed below in section 3.5.2

15 3.5 Project description with Process details Geology The rocks of Maton area belonging to Aravalli Super group of Proterozoic age, strikes N 40E-S40W and dips at degree s towards N50 W and display a synformal structure plunging moderately due NE. Dolomite and argillaceous dolomite is the oldest formation. Next in the stratigraphic column is orthoquartzite and jaspery-quartzite, which hosts stromatolitic rock phosphate. The rocks overlying rock phosphate are phyllite, which grid into mica-schist at places. Rock Phosphate in general is unconsolidated, soft to medium hard in nature, except in few patches where it is compact and cherty. The ore forming mineral is mainly Fluor-apatite (Ca 5 (P0 4 ) 3 F). The phosphorite horizon in the Maton area extends over a strike length of 1.2 km. Thickening and thinning of the horizon is quite common. The thickness of the horizon varies from 3.0 m to as high as 15.0 m Ore Reserves The reserve estimates are based on 1120 m strike length between S-14 to N-65 sections, width of the intersected ore zones and maximum depth up to 520mRL. The reserve has been estimated by Datamine Software using geo-statistical method and statistical analysis. Depletion of reserves: During the plan period of to , MT of ore reserves depleted up to the end of FY Additional reserves estimates: During the plan period no exploration drilling has been done due to access problem on hill slope. However Rock Phosphate has been exposed, during mine development, along the strike of E2 lens towards north, confirming its continuity along the strike up to B block. It can be thus assumed that the ore body exists along the strike, both at surface and subsurface which may add to the present reserves and resource. Resource estimation The resource estimation has been done by volume of each block * in situ density and krigged grades. Total estimated reserves and resource upto -520mRL are

16 3.327 MT of rockphosphate. Additional ore if considered will increase the Qty to 5.2 MT. The categorisation of the ore reserves is as under. The ore reserves at Maton Rockphosphate mine is as under - CATEGORY Mt %P 2 O 5 Proved A) RESERVES Probable Total Measured (M) - - B) RESOURCE Indicated (I) Total M & I Inferred - The in-situ geological reserves/resource as on is shown in the table below

17 Proved Probable Reserve Possible Reserves Av. Depth of Lens Qty Grade Qty Grade Qty Grade Qty Grade Total Res. Grade Estimation W S.Total Top to top E S.Total Top to top E S.Total Top to 520 B- Block Top to 520 W1, E1, E2 S.Total B- Block TOTAL Top to 520 Top to 520 Top to 520 As per United Nation framework of Classification (U.N.F.C), Reserve and Resources position as on is as follows: (in million T) BLOCK LENS Mineral reserve (111) Mineral reserve (121 & 122) Mineral resource (211) Mineral resource (221 & 222) Mineral resource (331) Mineral resource (332) Mineral resource (333) Location W1, E1, E2 A- BLOCK S.Total B- BLOCK B- Block Top to 520 Top to 520 TOTAL Top to 520

18 RESERVES AND ANTICIPATED LIFE OF MINE A total of million T of ore reserve and resources, 1.293MT Proved & MT probable reserves) and million T of resources have been estimated upto 520 mrl with average grade of % in A & B Blocks. At a production rate of 0.18 million TPAin the first year and million tonnes in the subsequent years, the present life of the mine upto 520 mrl will be about 8 years considering limits of practical mining open pit of reserves and resources. As explained previously, exploratory drilling done will further augment the reserves and resources which would increase the life of the mine beyond 10 years Mining Method of Mining: The deposit is being worked by mechanised open cast mining method with benches of 10 m minimum width and 10 m height. The bench height and width parameters have been optimized after studies on geo-technical slope stability were carried out by CIMFR. Dhanbad. They had recommended a slope of 45 in footwall ortho-quartzite upto a depth of 100 m from highest point. Beyond 100 m the overall pit angle along footwall has to be revised according to local conditions. The mining of the deposit is intended to continue with the same method. The present working is confined in E1-W1& E2 lens only. The entry to the benches below 600 mrl is by a ramp driven from south side. Hangwall overburden is removed first, then ore is mined out and then waste of Foot Wall is removed on the bench to reduce the dilution to the maximum possible extent and bench is formed. The heavy earth moving machineries deployed for mining are diesel operated. With expansion, there would be increase in the size of the machines viz. excavators and trucks to cope up the excavation requirements. The crusher capacity would also be increased to meet out the crushing requirements of expanded ore production. Drilling and Blasting: At Maton Mine the bench height in waste (Over Burden) and ore is 10 mtrs. The hole dia. for both ore and waste benches is 115/165 mm. The drilling is carried out with the help of track mounted diesel engine powered DTH (Down the Hole) drill machines of 115/165mm button bit. Drill machine

19 with dust extractor system is being used for controlling Air Borne Dust. ANFO (Ammonium Nitrate Fuel Oil) is used as the column charge along with Primary charge in the form of PETN cast booster or cartridge slurry explosive. The initiation of the explosive is being done by down the hole delay Non Electric shock tubes (NONEL). For interhole delay the trunk line delay detonators are used on surface tie up for improved blast performance, reduced ground vibration and noise level. The max. charge is kept within limit to minimize environmental impact of blasting. The no. of blasts required in ore and waste clubbed together are approx per month. However by increasing the size of the blast, number of blasts would be reduced to 14 to 15 per month. Depending upon the strata condition, bench height and rock type, spacing and burden is being varied. Typical Drill & Blast design parameters are as under. Spacing : 4 to 5 m Burden : 3 to 4 m Depth of holes : 10.5 to 11m Sub grade drilling : 0.5 to 1.0 m Primary charge/booster charge : 250 gm PETN Booster / Cap sensitive slurry cartridge of 83/125 mm dia (12.5 to 25 Kgs) Column charge : Non cap sensitive (ANFO/Slurry Cartridge) Charge Length : 50-60% of hole depth Powder factor : 4 to 5 T/Kg of explosive Pattern of holes : Staggered or Square Pattern Detonators : Millisecond delay detonators. Av. No. of holes in a blast : 60 to 70 nos. Av.Quantity of explosive/hole : 100 Kg. (Approx.) Quantity of explosive/blast. : 6-7 T (Approx) Safe storage of explosive : Explosive is being sourced from licensed magazines.

20 Secondary breaking: Oversize boulder s (Boulder of size more than 1 mtr.) size reduction is done by Hydraulic Rock Breaker. Secondary Blasting i.e. Pop Shooting or Plaster shooting is avoided. With proposed expansion, additional rock breaker would be put in to use to cope up the breaking of boulder. Efforts would be made with improved blasting techniques as described above to keep generation of boulders below 1% of total blasted volume. Presplitting: To achieve stable slopes and control the blast damage to walls, presplitting techniques would be adopted at final pit limits.. The technique would involve, drilling small dia holes ( mm) at a close spacing of 1.0 to 1.2 mtrs. along the final bench profile line at an angle of 70 to 80 degrees as per the recommended slopes. These holes would be then charged lightly with mm cartridges which are suspended in to holes axially tied with a detonating fuse. A charge factor of 0.40 to 0.60 Kg / sq meter would be maintained depending upon the strata conditions. The holes are then fired instantaneously and are normally fired prior to the production blast in front of limit line. The final production blast is called Trim Blast. In Trim blast in front of Pre-Split, one or two small dia production hole line is drilled at a standoff of 1.0 to 1.5 mtrs to reduce the charge concentration near final wall. The trim blast is fired with inter hole delay of 42 ms or 65 ms with inter row delays of 100 ms so as to have proper burden relief for holes and reduced vibrations on wall. The excavation is then done maintaining the slope. However exact parameters of pre-splitting can only be established after a number of trial blasts with varying spacing and/or explosive charge and the most appropriate pattern would be adopted. The machinery to be deployed for expanded capacity would be as tabulated below. TABLE 3.6 DETAILS OF MACHINERIES

21 Equipment Capacity Existing (Nos.) Proposed (Nos.) 2.0 cum 4 2 Excavator 6.7 cum - 2 Rock Breaker MT 25 3 Dumper 50 MT mm 1 2 Drill 115 mm KL 2 - Water Sprinkler 20 KL - 2 D65 E 2 - Track Dozer D275 A 2 Motor Grader - 1 The expanded production (ore and overburden) requirement is to T of rock per day. The capacity of machinery has been arrived at after considering the availability and utilization of the equipments. Four excavators (2 of 6.7 m3 & 2 of 2.0 m3 for ore) and twenty dumpers of 50 T are planned Conceptual Mine Plan The present working is confined to E1-W1& E2 lens only. The present entry is through a ramp along the hill on FW side. Hangwall overburden is being removed first, then ore is mined and then FW is excavated thereby forming the bench and reduced dilution. The ore body is proven up to 520 mrl and the pit will be economical up to this depth of approx 190 meters from the top. It is proposed to keep a pit slope of 45 in footwall ortho-quartzite upto a depth of 100 m from highest point and beyond 100 m the overall pit angle along footwall has to be made flatter according to local conditions. A detailed Geotechnical study would also be conducted to arrive at optimal bench slopes and overall angles and depth of pit. The mine operation is planned on three shifts per day of 8 hours duration basis. The mine is scheduled to work for 300 days/ year after keeping margin for weekly day of rest, public holidays and days lost due to weather conditions like rain, fog & storm. Ore Production Schedule for Mining Plan period five years after grant of EC would be as follows

22 Plan period Ore Production ,80, ,00, ,00, ,00, ,00,000 Production in Year 1 has been considered as per existing plan considering the time required for development of the ore for 0.5 MTPA capacity Selection of Dumping Site The overburden generated from mines will be stacked at earmarked Dump locations which are at north east of strike direction and East of the strike direction. These sites have been selected as the area doesn t bear any mineralisation and is within the acquired land. 3.6 Raw material required along with estimated quantity likely source, marketing area of final product/s, Mode of transport of Raw material and finished. Maton being a purely mining Project and there wouldn t be any other process involved like beneficiation. So no significant raw material requirement is there except consumable like fuel for equipments and explosive / Ammonium Nitrate for blasting purpose. The final product would be ROM and/or crushed Rockphosphate. The mode of transport of material would be through trucks. 3.7 Resource optimization / recycling and reuse envisaged in the project, if any Not envisaged 3.8 Water & Power Availability & Source Water Availability

23 An additional 300 KLD of water will be required, as compared to the present 200 KLD for the present capacity of 0.18 MTPA. The additional requirement is proposed to be extracted from ground from within or outside the mine lease through bore wells after obtaining requisite approvals and also from the rain water collection in the pit area, water collection pond is also proposed to be constructed Power Availability Energy requirement will be 1.0 MW after expansion. Power will be wheeled from captive power plant at Hindustan Zinc s Zawar mines located 45 kms away through AVVNL grid. 3.9 Waste Generation and its Management Solid Waste The waste rock generated from the mining will be systematically dumped at earmarked overburden dumps with proper stabilization and plantation. The physico-chemical analysis of the waste rock indicates that the waste is nonhazardous in nature and not likely to cause any adverse impacts. Waste generated by mining will be dumped at pre decided sites in ultimate dump configuration of 10 x 10 meters or 5 x 20 m lifts after obtaining necessary approval. Each lift would have slope angle of 40 0 and overall final slope of There is no sub grade mineral available as such there would not be need for stacking of sub grade mineral separately. The proposed excavation of overburden for five year is as follows. Year Qty(T) Total Liquid Waste, effluents

24 No Liquid effluents / waste generation would be there as beneficiation plant is not proposed. 4.0 Site Analysis 4.1 Connectivity Maton Mine is located at about 12 km southeast of Udaipur, at a latitude and longitude and falls in the Survey of India toposheet No. 45H/14. The nearest railway station is Rana Pratapnagar on Udaipur - Chittorgarh Broad gauge line of North - Western Railway at about 8 km away. The area is connected by airways with the airport being at Dabok which is at about 12 km. (NW) on Udaipur Chittorgarh NH 76. The Mine is well connected from two sides by asphalt road from Udaipur. The revenue map is attached for reference. 4.2 Land Form, Land use and land ownership Land Form The general topography of the Mining Lease area is flat to undulated. The mineralization is within a hillock. HZL has the surface rights over the land where mining and related activities are being carried out Land Use Total Mine lease area is of ha, out of which ha is acquired within mining lease area for carrying out mining and related support activities. Additionally Ha has been acquired outside the ML area for OB storage, crusher, offices etc. The pre operational land use pattern of mining lease is as follows: The present land use detail of acquired land is as per following table.

25 Land Use Area(ha.) Built up 4.42 Mine pit Waste Dump Green Belt Others Total No additional acquisition of land is proposed for expansion from 0.18 million TPA to 0.5 million TPA of ore production at Maton Rockphosphate Mine Land Ownership Village wise details of total land acquired from within the mine lease and outside the mine lease area for the mining project is as below. Village Govt Land Private Land Total Maton Umra Lakadwas NIL Karbadia NIL Total Topography Topography of the area is shown in attached map. TOPOGRAPHICAL FEATURES OF THE AREA

26 4.4 Land Use Pattern of Mining Lease Details of the land is as given in sec and above 4.5 Existing Infrastructure and Amenities Existing Infrastructure viz. Office building, Crusher, and quarters for the security personnel are available at site. As Udaipur, a major city is nearby from the project site; all basic amenities like school, hospital, recreational facilities, electrical lines are available. 4.6 Soil Classification The texture of soil is mostly sand and silty sand in the study area. The PH of the soil in the study area ranged from The soil is neutral to slightly alkaline. Details of soil sampling locations:

27 Station Code Location Distance wrt. Boundary of Direction wrt Centre of ML Present Land Use ML Area (km) Area S1 Umra Village 2.2 S Agri. Land S2 Lakadwas 2.4 E Barren Land Village S3 Nr UdaiSagar 3.0 NE Barren S4 Maton Village 0.5 N Barren Land S5 Kharbadia 0.6 NW Barren Land Village S6 ML area Core Zone - Industrial area The soil analysis parameters as per recent monitoring report Dec 2011 are as shown below: PARAMETER UNIT RESULTS S 1 S 2 S 3 S 4 S 5 S 6 ph Ca 2+ % Mg 2+ % SODIUM as Na % POTASSIUM as K % AVAILABLE N % CHLORIDE as Cl % SULPHATE as So 4 % IRON as Fe % MANGNESE as Mn % ZINC as Zn % ALUMINUM as Al % LEAD as Pb % PHASPHATE as Po 4 % PHOSPHOURS as P % ORGANIC MATTER % ORGANIC CARBON % WATER SOLUBLE CHLORIDE %

28 4.7 Climatic data and secondary sources The meteorological data recorded during the monitoring period is very useful for proper interpretation of the baseline information as well as for input prediction models for air quality dispersion. Historical data on meteorological parameters will also play an important role in identifying the general meteorological regime of the region. The year may broadly be divided into four seasons: Winter season : December to February Pre-monsoon season : March to May Monsoon season : June to September Post-monsoon season : October to November Onsite monitoring was undertaken for various meteorological variables in order to generate the site specific the data was collected at site every hour continuously from 1 st march 2009 to 31 st March 2009 covering pre-monsoon season. The generated data then compared with the meteorological data generated by nearest Indian meteorological Department (IMD) station located at Udaipur at a distance of (12 km NW) 4.8 Social Infrastructure available The location is very near to the city of Udaipur and all the basic social infrastructure as listed below are available. Hospitals Banks Post Office Railway Station Bus Station Schools Police Station Shopping Complexes Sports Infrastructure

29 Cinema Hall 5.0 PLANNING BRIEF 5.1 Planning Concept The industry is mining. It is proposed for expansion of mine from 0.18 MTPA to 0.5 MTPA of ore production. The mining will be through open cast method by conventional Shovel Dumper combination and Drilling and Blasting. The operations will be fully mechanised. The ore excavated will be stacked at ore yard from where will be loaded in dumpers and will be crushed to <12 mm size. Separate stock yards of crushed ore will be maintained as per the grade. The ore will be sold to the parties which shall be transported through trucks by road. All required infrastructure is already available. 5.2 Population Projection As per 2001 census, persons inhabited in 10 villages around Maton Mine. The distribution of population in the study area is as per the table below. TABLE 5.1 DISTRIBUTION OF POPULATION IN STUDY AREA Sl. No. Village Total Family Population 1 Maton Kharbadia Lakadwas Kaladwas Eklingpura Umra DhuniMata Boiki Pancholi Kanpur Kamlod Grand Total

30 . 5.3 Land use planning The land use pattern of the total acquired land is as given in Sec above. 5.4 Amenities and Facilities i) Education: There exists Primary, Secondary and Senior Secondary Schools and colleges ii) Social Infrastructure like Hospitals, Post Office, Bank, Police Station, Bus Station, Facility Exists iii) Telecommunication, LPG services, Marketing stalls, Sports infrastructure exists iv) Recreation- Existing Recreation facilities such as cinema hall, Sports infrastructure 6.0 PROPOSED INFRASTRUCTURE 6.1 Industrial Area Infrastructure is already available for 0.18 MTPA capacity. The same infrastructure will be shifted within the mine premises / acquired land on expanding to 0.5 MTPA if needed. Road Network two way road along the mine. Power transmission 4 kms of 33 KV transmission line installed through AVVNL. Internal roads within mine boundary Office buildings The following would be developed as part of the proposed expansion Truck parking facility Residential Area: No residential Area shall be developed as HZL is already having the residential colony at Udaipur. 6.2 Green Belt HZL has planted 5500 plants saplings from to in an area of ha. Thick vegetation will be developed along acquired land boundary to

31 attenuate the dust and noise. The plantation will be carried out along the roads within the boundary to arrest dust. The plantation will also be carried out on the waste dumps slopes as and when they mature i.e. reach to final limits after their stabilization. Plantation will also be done on the top of waste dump benches. Around 33% acquired area shall be developed with plantation. 6.3 Social Infrastructure The Maton Mines is very near to the city of Udaipur and its suburbs and all the social infrastructures as listed below are available. Education: There exists Primary, Secondary and Senior Secondary Schools and colleges Social Infrastructure like Hospitals, Post Office, Bank, Police Station, Bus Station facility exists Telecommunication, LPG services, Marketing place exists Recreation- Cinema hall, Sports infrastructure exists Looking to above, company doesn t propose for creation / construction of any Social Infrastructure. However the company would continue its CSR activities in surrounding villages of Maton. 6.4 Connectivity The project site is located 12 Km South East of Udaipur city and is well connected by Jhamarkotra road from Udaipur. The nearest Airport is Dabok about 12 Km NW of the Maton Mine. The nearest railway station Rana Pratapnagar is 8 Km NW of Maton Mine. NH 76 is at 6 km NW from the ML area. As site is well connected, there is no requirement for any additional infrastructure except strengthening of internal roads. 6.5 Drinking water management 15 cum/day of drinking water would be required during the operations. Same shall be purchased from external sources in the same way as being done at present.

32 6.6 Sewerage System As there will be no township facility developed within the boundary so no sewerage waste would be there and need for Sewerage System would not be there. 6.7 Industrial Waste Water management Since the Ore beneficiation Plant is not proposed, there would not be generation of any industrial waste water and effluents. The rain water collected in mine pit area, will be used in wet drilling and water sprinkling for dust suppression on haul roads. Zero discharge of water shall be maintained from mining premises. Storm water generated shall be allowed to flow naturally ensuring no contamination to it. Garland drains and de-silt pit will be constructed around the OB dump to ensure de- silting of rain water. The rainwater will be collected in suitable sump pits and will also be used in mining operations and dust suppression. 6.8 Solid Waste Management About 521,80,000 T waste rock (Over Burden) would be generated from the mine proposed Mining Plan period of five year. Waste rock from the development heading would consist of quartzite, phyllite, Jaspery quartzite, etc. Mine waste from development areas shall be transported and dumped in a specifically assigned area i.e. waste dump area. The waste is non-hazardous in nature and not likely to cause any adverse impacts. The dumps will be stabilized by plantation of trees. The following mitigation measures for solid waste management shall be adopted: Adequate slope will be maintained to give proper stability to the dump. Waste will be stacked & leveled systematically in layers. After reaching the benches to their ultimate height and location, plantation shall be done on slopes and top. Construction of garland drains around the Waste dump so that surface run off from the dump is collected in a sump. Regular maintenance of the garland drains constructed around the solid waste dump to collect the surface run off. 6.9 Energy requirement

33 Presently Maton mine receives Power at 33 KV from Aklingpura substation of AVVNL. Energy requirement will be approx 1.0 MW after expansion. Power will be wheeled from captive power plant at Hindustan Zinc s Zawar mines located 45 kms away through AVVNL grid. 7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN There will not be any additional acquisition of land due to proposed expansion from 0.18 million TPA to 0.5 million TPA. All the mining operation will continue within the and acquired land within and outside ML. 8.0 PROJECT SCHEDULE AND COST ESTIMATES 8.1 Project Schedule The current production of rockphosphate ore of Maton mine is 0.18 MTPA.It is proposed to increase its production of ore from 0.18 to 0.5 MTPA. The mine will reach to the expanded capacity of 0.5 MT in Year 2 / year Capital Cost Estimates As the project is going to be completely outsourced so there will be no capital cost on machineries. The only cost comprise of crusher, office infrastructure, shifting of power line, small warehouse etc. The total Capital cost has been estimated at INR 120 million (12 crores) The calculation below indicates that the project is robust and is economically viable at a high stripping ratio of 24 considering average sale price of the product at Rs 2500 per Tonne. TABLE 8.1

34 ECONOMICAL VIABILITY Description Ore prod (Lac tons) Tentative Total Excavation (in Lac Tons) Capex (Crusher and Offices) (Av price) Operating Profit Depreciation Tax (30%) Net Cash Flow All Amounts are in Lacs. 9.0 ANALYSIS OF PROPOSAL (Final Recommendations) 9.1 Financial Benefit The proposed project will reduce import of rockphosphate and phosphoric acid thus saving of foreign exchange. It will boon for the fertilizer industry and agriculture. This will also generate revenue to the state Government as well as central government. The people around the region will get direct and indirect employment thus improves the financial status. HZL will also get benefited. 9.2 Social Benefits The proposed project shall proactively participate in the upliftment of socio economic index of the communities around the project site by way of financial and administrative support. The project will open up employment opportunities, directly and indirectly. There shall be opportunities for entrepreneurs to engage in many service sectors directly or indirectly associated with the project. The CSR approach of the company continues to be towards sustainable livelihood management of the community around. on the present focus areas shall be continued in education, health, sanitation, drinking water, agriculture, water shed management, culture identity preservation, tribal welfare, welfare of socially weaker sections and marginalized people.

35

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA

PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA 21-07-2107 INTRODUCTION The Sandur Manganese & Iron Ores Ltd. (SMIORE) are operating

More information

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The groups cement facilities are located

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT 1 MCDR INSPECTION REPORT General SN Particulars Details Date of Inspection 18.10.2016 1 Name of the Mine Dhobitola Titaniferous Iron Ore Mine 2 Total Lease Area (Ha) 2.61 Ha (Entire Forest Land) with breakup

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal 1.0 SUMMARY OF THE PROJECT PRE-FEASIBILITY REPORT Project Name of Company / Mine Location Village Taluka District State Sand mine Gram Panchayat Tarrighat, Sand mine Tarrighat Tarrighat Patan Durg Chhattisgarh

More information

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED HALF YEARLY PROGRESS REPORT ON IMPLEMENTATION OF ENVIRONMENTAL CLEARANCE CONDITION BY MoEF (PERIOD FROM OCTOBER 13 TO MARCH 14) HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED SIX MONTHLY

More information

PRE FEASIBILITY REPORT (PFR)

PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 27 PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 28 INDEX S. No. Contents Page No. 1.0 EXECUTIVE SUMMARY 30 2.0 INTRODUCTION OF THE PROJECT / BACKGROUND

More information

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited EXECUTIVE SUMMARY A. INTRODUCTION : M/s Jayaswal Neco Industries Limited (JNIL) belongs to the wellknown industrial group of Central India viz. NECO GROUP having annual turnover exceeding Rs. 3500 Crores.

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

MAJHIGAWAN LIMESTONE MINE Mine Lease area ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.

MAJHIGAWAN LIMESTONE MINE Mine Lease area ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M. MAJHIGAWAN LIMESTONE MINE Mine Lease area 362.68 ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

THE RAMCO CEMENTS LIMITED

THE RAMCO CEMENTS LIMITED 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE JAYANTHIPURAM NORTH BAND MINING LEASE 2.0 MILLION TPA CAPACITY EC Lr. No. : J-11015/377/2006-IA.II

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN HALF YEARLY REPORT FOR THE PERIOD OCTOBER, 2011 to MARCH 2012 V. S. Lignite Power Pvt. Ltd. Name of the Project : 1x 135 MW Lignite

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 31/05/2012 TO PIRABHAI VALABHAI NANDASANIYA LOCATED

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi PRE FEASIBILITY REPORT For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS Of M/s. M.K. DRUGS F-10, Industrial Area, Focal Point, Tehsil: Derabassi Dist: Mohali, Punjab INTRODUCTION M/s. M.K. Drugs is

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT JAYPEE NIGRIE SUPER THERMAL POWER PROJECT (A Unit of M/s Jaiprakash Power Ventures Limited) Villages: Nigrie, Tehsil :Sarai District: Singrauli 2014 2015 SUBMITTED M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

More information

N.H. 6 is 50 km away from the proposed plant boundary; in N direction;

N.H. 6 is 50 km away from the proposed plant boundary; in N direction; 1.1 INTRODUCTION Godawari Power & Ispat Limited (GPIL) has an existing Iron Ore Crushing plant of 12,00,000 MTPA capacity at Gidhali, Village Kusumkasa, Tehsil - Balod, District - Durg (Chhattisgarh) and

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

Schedule Of Works. 35 Konkan Railway Corporation Limited Signature of Tenderer

Schedule Of Works. 35 Konkan Railway Corporation Limited Signature of Tenderer Schedule Of Works 35 Konkan Railway Corporation Limited Signature of Tenderer Schedule of Works (Package II, Chainage 5/400 to 7/800 = 2400 mtrs SCHEDULE - A (CUTTING) Name of work: Limited tender for

More information

Strategic mine planning of surface mining projects incorporating sustainability concepts

Strategic mine planning of surface mining projects incorporating sustainability concepts 6th International Conference on Sustainable Development in the 645 Strategic mine planning of surface mining projects incorporating sustainability concepts C. Roumpos and E. Papacosta Public Power Corporation

More information

INTERNATIONAL O&M CONFERENCE

INTERNATIONAL O&M CONFERENCE INTERNATIONAL O&M CONFERENCE COAL SUPPLY CHALLENGES & WAY FORWARD 14 TH FEB 2012 - BY DK SAHA, DGM(FM) & JANARTHAN C. DGM(FM) Electricity Per Capita consumption India Egypt China Brazil World Average Russia

More information

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests Paryavaran Bhavan, C.G.O. Complex, Lodi Road, New Delhi-110 003. Dated the 28th June, 2013 To, M/ s Arbind Kumar Singh

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

MANGANESE ORE, CHROME ORE, FERRO ALLOYS

MANGANESE ORE, CHROME ORE, FERRO ALLOYS MANGANESE ORE, CHROME ORE, FERRO ALLOYS GLOBAL STEEL PRODUCTION In 2011 World Crude Steel Production reached 1527 million tonnes and showed a growth of 6.8% over 2010 and China remained the World s largest

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF HPCL, LPG BOTTLING PLANT Capacity: 3 X 500 MT At Plot No.499 Kota-Jhalawar Road (NH-12) Village- Mandana, Tehsil-

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System HNPCL, (2X520 MW). VIZAG THERMAL POWER PROJECT TECHNICAL ENQUIRY SPECIFICATION FOR MS ERW 45O NB POLYURETHANE COATED PIPE FOR ASH WATER RECOVERY SYSTEM Prepared By Checked by Approved by Ashok Kumar Ashok

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

URANIUM MINING IN MALAWI BY PATRICK MEDIUS NYIRENDA ENVIRONMENTAL AFFAIRS DEPARTMENT, MINISTRY OF NATURAL RESOURCES, ENERGY AND MINING, MALAWI

URANIUM MINING IN MALAWI BY PATRICK MEDIUS NYIRENDA ENVIRONMENTAL AFFAIRS DEPARTMENT, MINISTRY OF NATURAL RESOURCES, ENERGY AND MINING, MALAWI URANIUM MINING IN MALAWI BY PATRICK MEDIUS NYIRENDA ENVIRONMENTAL AFFAIRS DEPARTMENT, MINISTRY OF NATURAL RESOURCES, ENERGY AND MINING, MALAWI OUTLINE Introduction History of Mining in Malawi Operations

More information

Sr.No Condition Status A. SPECIFIC CONDITIONS:

Sr.No Condition Status A. SPECIFIC CONDITIONS: J.K. CEMENT WORKS, MANGROL (RAJ.) Compliance report of Mangrol Lime stone mine (For the period from April 2011 to September 2011) Sub:- Conditions of Environment Clearance from MOEF, New Delhi Letter No.

More information

Base Metal and Iron Ore Mining

Base Metal and Iron Ore Mining Multilateral Investment Guarantee Agency Environmental Guidelines for Base Metal and Iron Ore Mining Industry Description and Practices This document addresses the mining of base metal ores (copper, lead

More information

White Dam Gold Project Dump Leach

White Dam Gold Project Dump Leach ALTA 2015 White Dam Gold Project Dump Leach A division of Midas Engineering Group Mineral Engineering Technical Services PO Box 5778 St Georges Tce WA 6831 P: (+61 8) 9421 9000 F: (+61 8) 9325 8311 ABN

More information

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 1 Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 2 COAL RESOURCE Indonesia has large resources of lower heating value subbituminous coal the resources are

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH FORM I (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri K. Ravi Shankar Door No. 39/49/39, Krishnadevaraya

More information

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102. JAIPRAKASH ASSOCIATES LTD. (CEMENT DIVISION) EXECUTIVE SUMMARY FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.983 Ha) APRIL, 2008

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

BENEFITS RELATED TO THE APPLICATION OF MASS BLASTS IN OPEN CUT MINING

BENEFITS RELATED TO THE APPLICATION OF MASS BLASTS IN OPEN CUT MINING BENEFITS RELATED TO THE APPLICATION OF MASS BLASTS IN OPEN CUT MINING José Vergara, Carlos Muñoz, Natalia Ortega. Advanced Technology Solutions, Orica Mining Services Latin America jose.vergara@orica.com,

More information

Research Compendium. Coal Sector in India 2013 A comprehensive data and information update

Research Compendium. Coal Sector in India 2013 A comprehensive data and information update Research Compendium Coal Sector in India 2013 A comprehensive data and information update Release Date : August 2013 Background About the report Coal is the only major conventional source of energy that

More information

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres ) PRE FEASIBILITY REPORT FOR Mining of Riverbed Sand From Darakeswar River Area : 8.09 Ha ( 20 Acres ) AT Mouza: Kunjapur, Plot No: 2227 (P), 2269 (P), 2603 (P),JL: 112, Village: Kunjapur, Block : Indus,,

More information

Environmental Monitoring Results Summary

Environmental Monitoring Results Summary Environmental Monitoring Results Summary Quarter 1 2016 Name of Mine: CSA Mine Environment Protection Licence: EPL 1864 Licensee Name and Operator: Cobar Management Pty Ltd Licensee Address: PO Box 31,

More information

PRE FEASIBILITY REPORT. This is a proposal of running mining lease for which CTO has been issued by Regional officer, Jaipur.

PRE FEASIBILITY REPORT. This is a proposal of running mining lease for which CTO has been issued by Regional officer, Jaipur. Masonry Stone Mining Project (2,11,000 TPA), M.L. No. 82/97, ML Area 1.0 ha Near Village: Beri Tehsil Kotputali District 1.0 EXECUTIVE SUMMARY PRE FEASIBILITY REPORT This is a proposal of running mining

More information

Bisha Mining Share Company

Bisha Mining Share Company Bisha Mining Share Company Asmara Mining Conference 2014 Bisha Mine Geology Activities Samson Ephrem Mine Geologist October 2014 Forward Looking Statements This Presentation contains forward-looking statements

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY S.No Particulars Details 1 Name of Project 2 Project Proponent 3 Village Proposed Granite Building Stone Quarry of Mr. Saji Sebastian Mr. Saji Sebastian Madeckal House, Kizhakkambalam

More information

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:

More information

ScienceDirect. Wirtgen drives the development of surface mining

ScienceDirect. Wirtgen drives the development of surface mining Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 138 (2016 ) 30 39 SYMPHOS 2015, 3rd International Symposium on Innovation and Technology in the Phosphate Industry Wirtgen drives

More information

Indian Copper Industry February 2018

Indian Copper Industry February 2018 Indian Copper Industry February 2018 Introduction Copper is the oldest known metal to man. It is an essential non ferrous metal and an excellent conductor of heat and electricity as well as being corrosion

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

FEASIBILITY REPORT FOR NARAYANPOSHI IRON & MN ORE MINE-AMTC (EXPANSION OF MINE CAPACITY FROM 3.0 MTPA TO 6.0 MTPA (ROM) FOR IRON ORE & EXISTING 0.

FEASIBILITY REPORT FOR NARAYANPOSHI IRON & MN ORE MINE-AMTC (EXPANSION OF MINE CAPACITY FROM 3.0 MTPA TO 6.0 MTPA (ROM) FOR IRON ORE & EXISTING 0. 1 CHAPTER I EXECUTIVE SUMMARY 1.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION 1.1 BACKGROUND INFORMATION OF PROJECT: Narayanposhi Iron & Manganese Ore Mines of Aryan Mining & Trading Corporation

More information

MEMORANDUM OF UNDERSTANDING BETWEEN HINDUSTAN COPPER LIMITED AND MINISTRY OF MINES FOR

MEMORANDUM OF UNDERSTANDING BETWEEN HINDUSTAN COPPER LIMITED AND MINISTRY OF MINES FOR i.exe MEMORANDUM OF UNDERSTANDING BETWEEN HINDUSTAN COPPER LIMITED AND MINISTRY OF MINES FOR 2010-2011 MEMORANDUM OF UNDERSTANDING (MOU) BETWEEN HINDUSTAN COPPER LIMITED AND MINISTRY OF MINES FOR 2010-2011

More information

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2014 Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations Daniel

More information

Topic: Site Formation

Topic: Site Formation Topic: Site Formation Presentation prepared by Raymond Wong February 2006 Purpose of site formation is to prepare a piece of land in order to: Accommodate building/s or other facilities which will be placed

More information

Marine Phosphate Project Namibia

Marine Phosphate Project Namibia Marine Phosphate Project Namibia Windhoek Mining Expo - April 2016 1 Introduction: General Phosphate uses in brief Phosphate: Crucial element in food security required by the growing world population:

More information

Forward Looking Statement

Forward Looking Statement Olympias Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation

More information

Page 1 of 26 (www.unapcaem.org)

Page 1 of 26 (www.unapcaem.org) Farm Mechanization in Punjab: Social, Economic and Environmental Implications Gurharminder Singh Sr. Scientific Officer, Punjab State Council for Science & Technology, INDIA Page 1 of 26 () Page 2 of 26

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment A brief discussion Presented by: Apekshit Solanki Kirti Neetu Yadav Sameera Vishakha Shankar Introduction EIA is a formal process to predict the environmental consequences

More information

Pre-Feasibility Report. for. Proposed Construction project of Santnagari

Pre-Feasibility Report. for. Proposed Construction project of Santnagari Pre-Feasibility Report for Proposed Construction project of Santnagari at Survey No. 1439, Near Dharoi Dam, Village Mahor, Taluka Vadali, District Sabarkantha, Gujarat By Gujarat Pavitra Yatradham Vikas

More information

(this cover page left intentionally blank)

(this cover page left intentionally blank) 4. Siting the Well (this cover page left intentionally blank) 4. Siting the Well Chapter Table of Contents Chapter Table of Contents Chapter Description... 4 Regulatory Requirements Well Siting... 4 Relevant

More information

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY EXECUTIVE SUMMARY 1. PREAMBLE Minerals are the chief source of present phase of industrialization, and play an important role in the present phase of the national economy and overall development of the

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

PRE-FEASIBILITY REPORT ON DRILLING OF ONE EXPLORATORY WELL PDAL (RPD-11) IN SIVASAGAR DISTRICT, ASSAM.

PRE-FEASIBILITY REPORT ON DRILLING OF ONE EXPLORATORY WELL PDAL (RPD-11) IN SIVASAGAR DISTRICT, ASSAM. PRE-FEASIBILITY REPORT ON DRILLING OF ONE EXPLORATORY WELL PDAL (RPD-11) IN SIVASAGAR DISTRICT, ASSAM. NORTH ASSAM SHELF A&AA BASIN ONGC, JORHAT Assam &Assam Arakan Basin, ONGC 1 1. Introduction Pre-Feasibility

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1 White Clay/China Clay Mining Project (3,250 TPA), M.L. No.3/01, ML Area 4.80 ha, Index INDEX 1 EXECUTIVE SUMMARY... 1 2 INTRODUCTION OF THE OBJECT/ BACKGROUND INFORMATION... 4 2.1 IDENTIFICATION OF PROJECT

More information

HELLENIC COPPER MINES LTD. History of the Company

HELLENIC COPPER MINES LTD. History of the Company HELLENIC COPPER MINES LTD History of the Company Hellenic Copper Mines (HCM) was formed in 1994 by Hellenic Mining Co Ltd a Cypriot company and Oxiana NL an Australia company, later renamed to Oz Minerals.

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

ASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT

ASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT ABN 46 006 045 790 14 th December 2010 ASX ANNOUNCEMENT Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA Cullen Resources Limited (ASX:CUL) (Cullen) is pleased to report the maiden JORC

More information

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE APPENDIX VIII Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (I) Basic Information S.No. Particulates Details 1. Name of the Mining Lease site

More information

Bishunpur Small Hydro Power Project

Bishunpur Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

Monitoring and analysis of production waste blasts at the Cadia Hill Gold Mine

Monitoring and analysis of production waste blasts at the Cadia Hill Gold Mine Monitoring and analysis of production waste blasts at the Cadia Hill Gold Mine Dr. Sedat Esen Metso Minerals Process Technology (Asia-Pacific) Dr Italo Onederra Senior Research Engineer - Mining Research

More information

INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office

INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office INDIAN BUREAU OF MINES MINES CONTROL AND CONSERVATION OF MINERAL DIVISION MCDR INSPECTION REPORT Dehradun regional office Mine file No HP/BLS/LST-9 (i) Name of the Inspecting Officer and ID No. (ii) Designation

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

Page# The Top soil generation is very less and it is being simultaneously utilized.

Page# The Top soil generation is very less and it is being simultaneously utilized. Page# 1 Name of Project : Belkapahar Mine of Wolkem Industries Ltd. Project Code: 226/336/-2005 Clearance Letter No. : J-11015/23/2004-IA.II (M) dated 31.03.2005 Period of Compliance Report : October,

More information

Bench terraces on loess soil China - 土坎梯田, 梯地

Bench terraces on loess soil China - 土坎梯田, 梯地 Bench terraces on loess soil China - 土坎梯田, 梯地 A Terrace is a structural SLM practice with a raised flat platform built on the slope to reduce soil loss and runoff on the slope, increase the rainfall infiltration

More information

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any; TERMS OF REFERENCE 1.0 PROPOSED SCOPE OF WORK FOR EIA STUDY The components of the EIA study include: Determination of baseline data using primary data generation and secondary data available from various

More information

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE ASX RELEASE 11 December 2012 NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE Independently prepared JORC Ore Reserve for Nolans Bore to support a 22 year mine life; 95% of Measured and Indicated Resources

More information

Towards Sustainable Mining Industries in India Challenges

Towards Sustainable Mining Industries in India Challenges Towards Sustainable Mining Industries in India Challenges 1. Introduction Dr. Sukumar Devotta Director National Environmental Engineering Research Institute Nagpur 440020 director@neeri.res.in The mining

More information

Maiden Inferred Iron Ore Resources for Gum Flat

Maiden Inferred Iron Ore Resources for Gum Flat 30 April 2009 The Manager ASX Announcements Maiden Inferred Iron Ore s for Gum Flat Lincoln Minerals Limited ( LML ) is pleased to announce Inferred s for its Gum Flat Iron Ore Project on southern Eyre

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

Project Proponent: Shri Kuldeep Pratap Singh Bhati Page - 11

Project Proponent: Shri Kuldeep Pratap Singh Bhati Page - 11 1.0 EXECUTIVE SUMMARY This is a new mining lease of Ball Clay Silica Sand, M.L. No.- 48/2011, located near Village- Indo Ka Bala, Tehsil-Kolayati, District Bikaner (Rajasthan) over an area of 4.2464 hectares.

More information

Welcomes. H.E. Milan Hovorka, Ambassador, The Czech Republic to India & Czech Business Delegation. 09 th Nov 2017 CIL HQ, Kolkata

Welcomes. H.E. Milan Hovorka, Ambassador, The Czech Republic to India & Czech Business Delegation. 09 th Nov 2017 CIL HQ, Kolkata Welcomes H.E. Milan Hovorka, Ambassador, The Czech Republic to India & Czech Business Delegation 09 th Nov 2017 CIL HQ, Kolkata A Presentation on Coal India Limited & Business Opportunities Coal Industry

More information

ENVIRONMENTAL IMPACT ASSESSMENT AND YOU

ENVIRONMENTAL IMPACT ASSESSMENT AND YOU ENVIRONMENTAL IMPACT ASSESSMENT AND YOU PARTICIPATING IN PUBLIC CONSULTATIONS FOR: COAL FUELED THERMAL POWER PLANTS C A G Citizen consumer and civic Action Group 1. What are Thermal Power Plants? Electricity

More information

Torpa Small Hydro Power Project

Torpa Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

209 million 36.1% Fe

209 million 36.1% Fe ASX ANNOUNCEMENT 29 August 2011 ASX Code: BDR MAIDEN IRON ORE RESOURCE ON BEADELL S MINING CONCESSION - BRAZIL 209 million tonnes @ 36.1 Fe Beadell Resources Limited ( Beadell ) is pleased to announce

More information