QUARTERLY REPORT. October 1, 2013 December 31, 2013
|
|
- Angela Lyons
- 6 years ago
- Views:
Transcription
1 QUARTERLY REPORT
2 Coast Community College District Program Summary Closed CCC NBLC Lease Revenue Bond Retirement Completed DIST Help Desk Software OCC Gym Acoustic Retrofit OCC Large Lecture Hall Seating OCC Music Modernization OCC Landscape Improvements In Construction DIST Active Directory Consolidation DIST Banner Server Upgrade GWC Classroom Seating Upgrades GWC IT Infrastructure Improvements GWC Classroom Technology Improvements OCC Technology Infrastructure OCC Classroom Technology Upgrades OCC EMS Upgrades OCC Business, Math, Computing Center DIST International Students Application Software PreConstruction/Bidding GWC Elevator Repair/Replacement GWC Classroom Repairs/Improvements In Design GWC Security, Access, Surveillance Infrastructure OCC Recycling Center OCC Maritime Academy Expansion OCC Sailing Dock Renovation OCC Campus Interior Signage OCC Planetarium In Queue GWC Math & Science Building GWC Language Arts Complex OCC Language/Social Science Building OCC Chemistry Expansion/Renovation Planned (Series A) CCC LeJao Student Resource Center D/W Technology Upgrades D/W Energy Efficiency Upgrades GWC Criminal Justice Training Center GWC Student Services Center GWC Campus Safety Building OCC Adaptive P/E, Gym, Pool Renovation OCC Parking Structure OCC Student Services Improvements Page 2
3 Coastline Community College Upcoming Projects Project Total Project Budget Beginning of Construction College Center Restroom Renovation $219, Technology Infrastructure $1,150, Technology Refresh $1,650, LeJao Student Resource Ctr. Renovation $1,415, Student Kiosks, Wayfinding, and Signage $800, Page 3
4 Golden West College Upcoming Projects Project Total Project Budget Beginning of Construction Campus Safety Building $1,787, Classroom Improvements $4,000, Elevator Repairs/Replacement $1,500, Rehab Center/Training Room $242, Security & Access Infrastructure $3,000, Technology Infrastructure $1,850, Technology Refresh $1,750, Criminal Justice Training Center $23,950, Student Services Center $20,887, Math/Science Building (Measure M: $29,021,952) $82,983, Page 4
5 Orange Coast College Business, Math, Computing Center OCC Contact: Rich Pagel (714) Architect: LPA, Inc. Construction Manager: Sundt Construction Inspection: UCMI Project Scope: Construction of a new 90,000 squarefoot multidiscipline instructional complex consisting of lecture space, faculty offices, and computer labs. This is Phase I of a twophase project. Phase I is the Math, Business, and Computing Center. Phase II is the Social Science and Literature and Languages building. Project Timeline: Design Phase: DSA Approval: Bid Phase: Construction Phase: Nov 2009 Jan 2014 Jan Aug 2014 July 2014 Sept 2014 Sept 2014 Sept 2015 Project Status: Math, Business, and Computing Center is under construction and currently on target for completion in the Summer Page 5
6 Page 6 Orange Coast College Business, Math, Computing Center
7 Orange Coast College Business, Math, Computing Center Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Architectural & Engineering Services $ 2,000, ,660 80,711 $ 271,371 $ 1,728,629 Construction $ 36,902,000 1,031,136 1,312,675 $ 2,343,811 $ 34,558,189 Escalation $ 284,000 $ $ 284,000 Testing & Inspection $ 800,000 91,917 $ 91,917 $ 708,083 Site Services $ 20, ,015 $ 5,636 $ 14,364 Project Management $ 1,700, ,151 $ 360,151 $ 1,339,849 Contingency $ 2,258,000 $ $ 2,258,000 Equipment $ 3,508,000 1,925 $ 1,925 $ 3,506,075 Other Misc. $ 225,000 2,962 10,597 $ 13,559 $ 211,441 Totals $ 47,697,000 $ 3,088,370 $ 44,608,630 Page 7
8 Orange Coast College Recycling Center OCC Contact: Rich Pagel (714) Architect: Dougherty and Dougherty Construction Manager: TBD Inspection: TBD Project Scope: Site improvements to enhance accessibility to the center, accommodate additional parking (8 spaces to 45 spaces), and relocate the buildings, as necessary, to support these logistical objectives. Project Timeline: Design Phase: DSA Approval: Bid Phase: Construction Phase: Jan 2013 Apr 2014 May 2014 Sept 2014 Aug 2014 Oct 2014 Nov 2014 Dec 2015 Project Status: The campus has had a series of meetings with the City of Costa Mesa and this project is currently under analysis as part of the California Environmental Quality Act (CEQA) study scheduled for completion in Summer Page 8
9 Orange Coast College Recycling Center Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Architectural & Engineering Services $ 400,000 $ $ 400,000 Construction $ 4,400,000 12,167 8,088 $ 20,255 $ 4,379,745 Escalation $ 264,000 Testing & Inspection $ 154,000 $ $ 154,000 Site Services $ $ $ Project Management $ 186,560 $ $ 186,560 Contingency $ 286,000 $ $ 286,000 Equipment $ 418,000 $ $ 418,000 Other Misc. $ 156,440 2,962 $ $ 156,440 Totals $ 6,265,000 $ 20,255 $ 5,980,745 Page 9
10 Orange Coast College Planetarium OCC Contact: Rich Pagel (714) Architect: Hill Partnership Construction Manager: TBD Inspection: TBD Project Scope: New construction of 10,000square foot planetarium, scheduled to start relocation activities in the Summer of 2015, demolition in Fall of 2015, and new construction in January The facility will house a 150seat planetarium/lecture hall, a Foucault pendulum, and an interactive exhibit space. Project Timeline: Design Phase: DSA Approval: Bid Phase: Demolition/Site Prep: Construction Phase: Nov 2012 May 2014 May 2014 Jan 2015 Apr 2015 June 2015 Aug 2015 Dec 2015 Jan 2016 June 2017 Project Status: Drawings are 50 percent completed and scheduled to go to DSA in the Spring Kitchell Construction has been hired to conduct a constructability review and provide comments to the campus. These comments will be reviewed in February/March Page 10
11 Orange Coast College Planetarium Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Architectural & Engineering Services $ 1,376, ,497 $ 338,497 $ 1,037,503 Construction $ 12,800,000 $ $ 12,800,000 Escalation $ 1,417,000 Testing & Inspection $ 449,400 $ $ 449,400 Site Services $ 40,000 3,600 $ 3,600 $ 36,400 Project Management $ 513,600 $ $ 513,600 Contingency $ 834,000 $ $ 834,000 Equipment $ 1,220,000 $ $ 1,220,000 Other Misc. $ 332,000 2,962 $ $ 332,000 Totals $ 18,982,000 $ 342,097 $ 17,222,903 Page 11
12 Orange Coast College Upcoming Projects Project Total Project Budget Beginning of Construction Campus Signage $564, Solar (Photovoltaic) Field $9,897, Adaptive P/E, Gym, Pool $29,350, Maritime Academy and Dock Relocation $8,924, Parking Structure (OC Fair & Events Center) $35,668, Administration/Student Support Center $23,044, Student Union Complex $67,720, Page 12
13 District Wide Information Technology Projects District Contact: Richard Patterson (714) Project Scope: Several District wide Information Technology initiatives are underway, which seek to increase operational efficiency and student accessibility consistent with the Vision 2020 Master Plan. The initiatives are summarized below: Goals: Est. Completion: Create a single Districtwide user ID for students, faculty, and staff with password syncing between systems. Summer 2014 Improve operational and employee efficiencies through consolidation of the District s April /Calendars , calendar systems, and data centers. Ongoing Data Centers Provide a single employee portal (SharePoint) to improve document sharing, committee communication, and staff collaboration with a secure document depository. Summer 2015 Increase the Enterprise Resource Program (ERP) response time and reliability by separating production and test/development servers, storage, and databases. Winter 2015 Increase the District s international student enrollment by offering a Districtwide online application process. April 2014 Establish a standard process for requesting IT services by implementing a centralized IT service desk. Completed Jan 2014 Provide reliable and modern information technology services by refreshing EndOfLife (57 years) classroom, administrative, and infrastructure equipment. Ongoing Page 13
14 Coastline College Information Technology Projects Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Classroom/ Instructional Technologies (Traditional & Online) $ 600,000 $ $ 600,000 Computer Replacement $ 500,000 3,428 $ 3,428 $ 496,572 Software upgrade & replacement Cycle $ 200,000 $ $ 200,000 Student Services Technology $ 170,000 $ $ 170,000 Cisco Telepresence & Lecture Capture $ 500,000 $ $ 500,000 Data Center Infrastructure Equipment $ 200,000 $ $ 200,000 Systems & Network Security $ 100,000 $ $ 100,000 Projectors & collateral A/V Systems integration, replacement, and management $ 200,000 $ $ 200,000 Mobile Technologies $ 100,000 $ $ 100,000 Printer & copiers upgrade & replacement cycle $ 150,000 $ $ 150,000 Fully Integrated Student Interactive Kiosks, Wayfinding & Emergency Notification & Promotional Signage Airblown Multimode Fiber IntraBuilding Connectivity $ 800,000 $ $ 800,000 $ 80,000 $ $ 80,000 Page 14 Totals $ 3,600,000 $ 3,428 $ 3,596,572
15 District Wide Information Technology Projects Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Project Endeavor Migrate and consolidate the District's 4 Active Directory and Exchange systems Banner System Upgrade and Architecture Redesign Upgrade the database servers and storage; separate the Production from TEST and Development Environments $ 1,650, , ,180 $ 969,967 $ 680,033 $ 1,850, ,675 $ 724,675 $ 1,125,325 Online International Student Application System $ 342, ,500 $ 342,500 $ Districtwide Helpdesk System $ 50,000 46,084 $ 46,084 $ 3,916 Totals $ 3,892,500 $ 2,083,226 $ 1,809,274 Page 15
16 Golden West College Information Technology Projects Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Computer Replacement $ 1,400,000 1,295,578 $ 1,295,578 $ 104,422 Network Infrastructure $ 1,350, ,046 $ 186,046 $ 1,163,954 Multimode Fiber Replacement to SingleMode AirBlow n $ 500,000 $ $ 500,000 Classroom Technology $ 350,000 $ $ 350,000 Totals $ 3,600,000 $ 1,481,624 $ 2,118,376 Page 16
17 Orange Coast College Information Technology Projects Estimate 1st QTR 2nd QTR 3rd QTR 4th QTR 2013/14 (Actuals) Total Remaining Desktop/Laptops $ 648, ,489 $ 547,489 $ 100,512 Projectors $ 100,000 5,153 $ 5,153 $ 94,847 Document Cameras $ 60,000 $ $ 60,000 A/V Sw itching Units (in carts) $ 80,000 $ $ 80,000 DVD/VCR $ 10,000 $ $ 10,000 Security Devices $ 125,000 $ $ 125,000 Servers $ 50,000 $ $ 50,000 Storage $ 225, ,913 $ 100,913 $ 124,088 Netw ork $ 625,000 $ $ 625,000 Wireless $ 150,000 $ $ 150,000 UPS $ 100,000 $ $ 100,000 Printers $ 60,000 $ $ 60,000 Totals $ 2,233,000 $ 653,554 $ 1,579,446 A total of $1,000,000 has been allocated to the OCC Technology Committee to fund new campus technology endeavors. $367,000 of the $3,600,000 remain unallocated. Page 17
18 Measure M Bond Second Qtr District Project Endeavor 5699 Software License Fees 139, District Project Endeavor 5899 Other Services 12, District Project Endeavor 6401 Equipment Capitalized 77, District Project Endeavor 6402 Equipment Capitalized Technology 212, , Banner Server Upgrade 5699 Software License Fees 564, , Application Software Int'l Students 5112 Consultants Indep Contractors Application Software Int'l Students 5699 Software License Fees Application Software Int'l Students 5899 Other Services Application Software Int'l Students 6129 Site Services Application Software Int'l Students 6250 Building Improvements Helpdesk Software 5112 Consultants Indep Contractors Helpdesk Software 5699 Software License Fees 13, , Page 18
19 Page 19 Measure M Bond Second Qtr Fringe Benefit Clearing 3230 PERS Retirement Non Instr Fringe Benefit Clearing 3330 OASDI Non Instr Fringe Benefit Clearing 3360 Medicare Non Instr Fringe Benefit Clearing 3430 Health and Welfare Non Instr Fringe Benefit Clearing 3460 Future Retiree Benefits Non Instr Fringe Benefit Clearing 3530 Unemplyment Ins Non Instr Fringe Benefit Clearing 3630 Workers Comp Non Instr District IT Program/Infrastructure 6402 Equipment Capitalized Technology District IT Program/Infrastructure 6412 Equipment Technology District Energy Efficiency Upgrades 6120 Site Improvements District Planning/Administration 2150 Classified Mgmt Non Instr Contr 24, District Planning/Administration 3230 PERS Retirement Non Instr 2, District Planning/Administration 3330 OASDI Non Instr 1, District Planning/Administration 3360 Medicare Non Instr District Planning/Administration 3430 Health and Welfare Non Instr 4,32 District Planning/Administration 3460 Future Retiree Benefits Non Instr District Planning/Administration 3530 Unemplyment Ins Non Instr District Planning/Administration 3630 Workers Comp Non Instr District Planning/Administration 4320 Copy Charges District Planning/Administration 5112 Consultants Indep Contractors 12,07 District Planning/Administration 6250 Building Improvements 46,380.65
20 Measure M Bond Second Qtr OCC IDC Bus, Math, Computing 4320 Copy Charges 10, OCC IDC Bus, Math, Computing 5472 Insurance 36,90 OCC IDC Bus, Math, Computing 5880 Labor Compliance 10, OCC IDC Bus, Math, Computing 6122 Site Inspections Consult OCC IDC Bus, Math, Computing 6127 Site Testing and Lab Fees 22, OCC IDC Bus, Math, Computing 6129 Site Services 5, OCC IDC Bus, Math, Computing 6204 Bldg Architect Fees 80, OCC IDC Bus, Math, Computing 6205 Bldg Inspection Consultants 69,02 OCC IDC Bus, Math, Computing 6210 Bldg Hazard Mat and Asbestos Abate OCC IDC Bus, Math, Computing 6250 Building Improvements 56, OCC IDC Bus, Math, Computing 6254 Building New Construction 1,209, OCC IDC Bus, Math, Computing 6260 Building Construction Manager 360, OCC IDC Bus, Math, Computing 6411 Equipment 1, ,862, OCC Recycling Center 6127 Site Testing and Lab Fees 8, OCC Recycling Center 6254 Building New Construction 8, Page 20
21 Measure M Bond Second Qtr OCC Music Modernization 4312 General Supplies 9, OCC Music Modernization 4316 Classroom Furniture and Fixtures 18, OCC Music Modernization 6120 Site Improvements 1, OCC Music Modernization 6124 Landscaping 12,85 OCC Music Modernization 6129 Site Services 2, OCC Music Modernization 6204 Bldg Architect Fees OCC Music Modernization 6205 Bldg Inspection Consultants OCC Music Modernization 6250 Building Improvements 11, OCC Music Modernization 6252 Building Lease Temp Facilities 58, OCC Music Modernization 6269 Building Services OCC Music Modernization 6401 Equipment Capitalized 656, OCC Music Modernization 6411 Equipment 2, OCC Music Modernization 6412 Equipment Technology 117, OCC Music Modernization 6421 Equipment Replacement 9, , OCC Maritime Academy 6250 Building Improvements Page 21
22 Measure M Bond OCC Student Svcs/Admin Improvement OCC Student Svcs/Admin Improvement Second Qtr 4318 Office Furniture and Fixtures 6250 Building Improvements OCC Language/Social Sciences 6254 Building New Construction OCC Adaptive PE, Gym, Pool 6254 Building New Construction OCC Planetarium 5112 Consultants Indep Contractors OCC Planetarium 6127 Site Testing and Lab Fees OCC Planetarium 6128 Site Architect Fees 338, OCC Planetarium 6129 Site Services 3,60 OCC Planetarium 6206 Bldg Testing and Lab Fees OCC Planetarium 6254 Building New Construction 342, OCC Parking Structure 6204 Bldg Architect Fees 2,05 OCC Parking Structure 6254 Building New Construction 2,05 Page 22
23 Measure M Bond Second Qtr 6250 Building Improvements OCC Chemistry Expansion/Renovation OCC Gym Accoustic Retrofit 6204 Bldg Architect Fees OCC Gym Accoustic Retrofit 6250 Building Improvements 8, , OCC Sailing Center Dock Renovation 6126 Site Engineering Fees 4,37 OCC Sailing Center Dock Renovation 6129 Site Services , OCC Campus Interior Signage 6204 Bldg Architect Fees 5, , OCC Large Lecture Hall Seating 6250 Building Improvements 102, OCC Large Lecture Hall Seating 6256 Building Installations 2, , OCC Landscape Improvements 6120 Site Improvements 44,23 OCC Landscape Improvements 6121 Sites Supplies 1, OCC Landscape Improvements 6124 Landscaping 15, , Page 23
24 Measure M Bond Second Qtr OCC IT Program/Infrastructure 4315 Supplies Technology OCC IT Program/Infrastructure 6205 Bldg Inspection Consultants OCC IT Program/Infrastructure 6402 Equipment Capitalized Technology OCC Classroom Technology Upgrades 4315 Supplies Technology OCC Classroom Technology Upgrades 5699 Software License Fees OCC Classroom Technology Upgrades 6250 Building Improvements OCC Classroom Technology Upgrades 6402 Equipment Capitalized Technology OCC Classroom Technology Upgrades 6411 Equipment 16, OCC Classroom Technology Upgrades 6412 Equipment Technology OCC Classroom Technology Upgrades 6421 Equipment Replacement 20, , OCC EMS System Upgrades 6250 Building Improvements 190,33 190, OCC Energy Efficiency Upgrades 6120 Site Improvements OCC Planning/Administration 5112 Consultants Indep Contractors 71, OCC Planning/Administration 6126 Site Engineering Fees OCC Planning/Administration 6129 Site Services OCC Planning/Administration 6204 Bldg Architect Fees OCC Planning/Administration 6250 Building Improvements OCC Planning/Administration 6411 Equipment 71, Page 24
25 Measure M Bond Second Qtr GWC Student Services Center 6254 Building New Construction GWC Campus Safety Building 6254 Building New Construction GWC Math and Science Building 6254 Building New Construction GWC Criminal Justice Training Ctr 6250 Building Improvements GWC Elevator Repair/Replacement 5650 Building Repairs GWC Elevator Repair/Replacement 6250 Building Improvements GWC Classroom Seating 4316 Classroom Furniture and Fixtures GWC Classroom Refurbishment 6250 Building Improvements GWC IT Program/Infrastructure 6214 Bldg Technology Infrastructure GWC IT Program/Infrastructure 6402 Equipment Capitalized Technology GWC IT Program/Infrastructure 6411 Equipment Page 25
26 Measure M Bond Second Qtr 6412 Equipment Technology 1,140, GWC Classroom Technology Upgrades 1,140, GWC Security, Access, Surveillance 6120 Site Improvements GWC Security, Access, Surveillance 6202 Bldg Engineering Fees 8,75 8, GWC Energy Efficiency Upgrades 6120 Site Improvements GWC Planning/Administration 5112 Consultants Indep Contractors 33, GWC Planning/Administration 6126 Site Engineering Fees 33, CCC IT Program/Infrastructure 6402 Equipment Capitalized Technology CCC IT Program/Infrastructure 6412 Equipment Technology CCC Classroom Technology Upgrades 6412 Equipment Technology Page 26
27 Measure M Bond Second Qtr CCC Energy Efficiency Upgrades 6250 Building Improvements CCC Planning/Administration 4315 Supplies Technology CCC Planning/Administration 5112 Consultants Indep Contractors CCC Planning/Administration 6250 Building Improvements Dist General Reserves 5841 Investment Svc Charge 35, Dist General Reserves 7114 Debt Retirement GO Bond Dist General Reserves 7310 Transfer Out 14,545, ,580, Dist General Reserves 5841 Investment Svc Charge 2, , Second Quarter Measure M Bond $20,509, Page 27
28 Measure M Bond Inception December 31, 2013 Cumulative District Project Endeavor 5112 Consultants Indep Contractors 76,28 District Project Endeavor 5699 Software License Fees 146, District Project Endeavor 5899 Other Services 12, District Project Endeavor 6401 Equipment Capitalized 77, District Project Endeavor 6402 Equipment Capitalized Technology 238, , Banner Server Upgrade 5699 Software License Fees 564, , Application Software Int'l Students 5112 Consultants Indep Contractors 144,00 Application Software Int'l Students 5699 Software License Fees 162,50 Application Software Int'l Students 5899 Other Services Application Software Int'l Students 6129 Site Services Application Software Int'l Students 6250 Building Improvements 306, Helpdesk Software 5112 Consultants Indep Contractors Helpdesk Software 5699 Software License Fees 13, , Page 28
29 Measure M Bond Inception December 31, 2013 Cumulative Fringe Benefit Clearing 3230 PERS Retirement Non Instr Fringe Benefit Clearing 3330 OASDI Non Instr Fringe Benefit Clearing 3360 Medicare Non Instr Fringe Benefit Clearing 3430 Health and Welfare Non Instr Fringe Benefit Clearing 3460 Future Retiree Benefits Non Instr Fringe Benefit Clearing 3530 Unemplyment Ins Non Instr Fringe Benefit Clearing 3630 Workers Comp Non Instr District IT Program/Infrastructure 6402 Equipment Capitalized Technology District IT Program/Infrastructure 6412 Equipment Technology District Energy Efficiency Upgrades 6120 Site Improvements Page 29
30 Measure M Bond Inception December 31, 2013 Cumulative District Planning/Administration 2150 Classified Mgmt Non Instr Contr 32, District Planning/Administration 3230 PERS Retirement Non Instr 3, District Planning/Administration 3330 OASDI Non Instr 2, District Planning/Administration 3360 Medicare Non Instr District Planning/Administration 3430 Health and Welfare Non Instr 5,76 District Planning/Administration 3460 Future Retiree Benefits Non Instr District Planning/Administration 3530 Unemplyment Ins Non Instr District Planning/Administration 3630 Workers Comp Non Instr District Planning/Administration 4320 Copy Charges District Planning/Administration 5112 Consultants Indep Contractors 12,07 District Planning/Administration 6250 Building Improvements 57, Page 30
31 Page 31 Measure M Bond Inception December 31, 2013 Cumulative OCC IDC Bus, Math, Computing 4320 Copy Charges 13, OCC IDC Bus, Math, Computing 5472 Insurance 1,043, OCC IDC Bus, Math, Computing 5880 Labor Compliance 10, OCC IDC Bus, Math, Computing 6122 Site Inspections Consult OCC IDC Bus, Math, Computing 6127 Site Testing and Lab Fees 22, OCC IDC Bus, Math, Computing 6129 Site Services 5, OCC IDC Bus, Math, Computing 6204 Bldg Architect Fees 271, OCC IDC Bus, Math, Computing 6205 Bldg Inspection Consultants 69,02 OCC IDC Bus, Math, Computing 6210 Bldg Hazard Mat and Asbestos 24, Abate OCC IDC Bus, Math, Computing 6250 Building Improvements 56, OCC IDC Bus, Math, Computing 6254 Building New Construction 1,209, OCC IDC Bus, Math, Computing 6260 Building Construction Manager 360, OCC IDC Bus, Math, Computing 6411 Equipment 1, ,088, OCC Recycling Center 6127 Site Testing and Lab Fees 20, OCC Recycling Center 6254 Building New Construction 20,255.50
32 Measure M Bond Inception December 31, 2013 Cumulative OCC Music Modernization 4312 General Supplies 91, OCC Music Modernization 4316 Classroom Furniture and Fixtures 18, OCC Music Modernization 6120 Site Improvements 1, OCC Music Modernization 6124 Landscaping 33, OCC Music Modernization 6129 Site Services 4, OCC Music Modernization 6204 Bldg Architect Fees 20, OCC Music Modernization 6205 Bldg Inspection Consultants 30,88 OCC Music Modernization 6250 Building Improvements 394, OCC Music Modernization 6252 Building Lease Temp Facilities 58, OCC Music Modernization 6269 Building Services 9, OCC Music Modernization 6401 Equipment Capitalized 656, OCC Music Modernization 6411 Equipment 2, OCC Music Modernization 6412 Equipment Technology 127, OCC Music Modernization 6421 Equipment Replacement 9, ,461, OCC Maritime Academy 6250 Building Improvements Page 32
33 Measure M Bond Inception December 31, 2013 Cumulative OCC Student Svcs/Admin 4318 Office Furniture and Fixtures Improvement OCC Student Svcs/Admin Improvement 6250 Building Improvements OCC Language/Social Sciences 6254 Building New Construction OCC Adaptive PE, Gym, Pool 6254 Building New Construction OCC Planetarium 5112 Consultants Indep Contractors OCC Planetarium 6127 Site Testing and Lab Fees OCC Planetarium 6128 Site Architect Fees 338, OCC Planetarium 6129 Site Services 3,60 OCC Planetarium 6206 Bldg Testing and Lab Fees OCC Planetarium 6254 Building New Construction 342, OCC Parking Structure 6204 Bldg Architect Fees 2,05 OCC Parking Structure 6254 Building New Construction 2,05 Page 33
34 Measure M Bond Inception December 31, 2013 Cumulative OCC Chemistry Expansion/Renovation 6250 Building Improvements OCC Gym Accoustic Retrofit 6204 Bldg Architect Fees 8,75 OCC Gym Accoustic Retrofit 6250 Building Improvements 165, , OCC Sailing Center Dock Renovation 6126 Site Engineering Fees 13,57 OCC Sailing Center Dock Renovation 6129 Site Services , OCC Campus Interior Signage 6204 Bldg Architect Fees 12, , OCC Large Lecture Hall Seating 6250 Building Improvements 225, OCC Large Lecture Hall Seating 6256 Building Installations 2, , OCC Landscape Improvements 6120 Site Improvements 53,73 OCC Landscape Improvements 6121 Sites Supplies 1, OCC Landscape Improvements 6124 Landscaping 21, , Page 34
35 Measure M Bond Inception December 31, 2013 Cumulative OCC IT Program/Infrastructure 4315 Supplies Technology OCC IT Program/Infrastructure 6205 Bldg Inspection Consultants 50,70 OCC IT Program/Infrastructure 6402 Equipment Capitalized Technology 50, OCC Classroom Technology Upgrades 4315 Supplies Technology 4, OCC Classroom Technology Upgrades 5699 Software License Fees 222, OCC Classroom Technology Upgrades 6250 Building Improvements OCC Classroom Technology Upgrades 6402 Equipment Capitalized Technology 82, OCC Classroom Technology Upgrades 6411 Equipment 16, OCC Classroom Technology Upgrades 6412 Equipment Technology 201, OCC Classroom Technology Upgrades 6421 Equipment Replacement 20, , OCC EMS System Upgrades 6250 Building Improvements 1,432, ,432, OCC Energy Efficiency Upgrades 6120 Site Improvements Page 35
36 Measure M Bond Inception December 31, 2013 Project Project Descriptaion Account Account Description Cumulative OCC Planning/Administration 5112 Consultants Indep Contractors 71, OCC Planning/Administration 6126 Site Engineering Fees OCC Planning/Administration 6129 Site Services 3, OCC Planning/Administration 6204 Bldg Architect Fees OCC Planning/Administration 6250 Building Improvements OCC Planning/Administration 6411 Equipment 74, GWC Student Services Center 6254 Building New Construction GWC Campus Safety Building 6254 Building New Construction GWC Math and Science Building 6254 Building New Construction GWC Criminal Justice Training Ctr 6250 Building Improvements GWC Elevator Repair/Replacement 5650 Building Repairs GWC Elevator Repair/Replacement 6250 Building Improvements Page 36
37 Measure M Bond Inception December 31, 2013 Cumulative GWC Classroom Seating 4316 Classroom Furniture and Fixtures 36, , GWC Classroom Refurbishment 6250 Building Improvements 10, , GWC IT Program/Infrastructure 6214 Bldg Technology Infrastructure GWC IT Program/Infrastructure 6402 Equipment Capitalized Technology GWC IT Program/Infrastructure 6411 Equipment GWC Classroom Technology Upgrades 6412 Equipment Technology 1,278, ,278, GWC Security, Access, Surveillance 6120 Site Improvements GWC Security, Access, Surveillance 6202 Bldg Engineering Fees 8,75 8, GWC Energy Efficiency Upgrades 6120 Site Improvements GWC Planning/Administration 5112 Consultants Indep Contractors 33, GWC Planning/Administration 6126 Site Engineering Fees 33, Page 37
38 Measure M Bond Inception December 31, 2013 Cumulative CCC IT Program/Infrastructure 6402 Equipment Capitalized Technology CCC IT Program/Infrastructure 6412 Equipment Technology CCC Classroom Technology Upgrades 6412 Equipment Technology CCC Energy Efficiency Upgrades 6250 Building Improvements CCC Planning/Administration 4315 Supplies Technology CCC Planning/Administration 5112 Consultants Indep Contractors CCC Planning/Administration 6250 Building Improvements Dist General Reserves 5841 Investment Svc Charge 1,778, Dist General Reserves 7114 Debt Retirement GO Bond Dist General Reserves 7310 Transfer Out 14,545, ,323, Dist General Reserves 5841 Investment Svc Charge 4, , Measure M Bond from Inception to December 31, 2013 $26,714, Page 38
Completed projects. Projects in progress. Program developments
1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site
More informationWATER CONSERVATION ACTION PLAN
WATER CONSERVATION ACTION PLAN CONTENTS Purpose History Regulations Monitoring & Verification Water Conservation Measures Program Notes PURPOSE This plan is written to provide an actionable continuous
More informationWATER CONSERVATION ACTION PLAN
WATER CONSERVATION ACTION PLAN CONTENTS Purpose History Regulations Monitoring & Verification Water Conservation Measures Program Notes PURPOSE This plan is written to provide an actionable continuous
More information3D/International. Facility Condition Assessment Report. Coast Community College District
Facility Condition Assessment Report Coast Community College District February 28, 2003 INTRODUCTION...2 Table of Contents ASSESSMENT OF EXISTING FACILITIES...4 Background Facilities Summary of Findings
More informationDistrict IT Service Catalog
2014 15 District IT Catalog District IT Catalog This Catalog provides a listing of each service offered by District IT. Each described service includes a service level agreement (SLA) and how a particular
More informationEast Los Angeles College Project Priority List Occupancy Date
East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media
More informationFacilities and Planning Department Measure E Update March 2017
State Seismic Mitigation Program (SSMP) The District s application for SSMP funds for Horace Mann Building A will be reviewed for approval by the State Allocation Board at its next scheduled meeting on
More informationLandscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues
February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803
More informationKENTUCKY STATE UNIVERSITY
KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000
More informationCoast Community College District Strategic Technology Plan December 5, 2016
Coast Community College District Strategic Technology Plan 2016 2019 December 5, 2016 Contents I. Overview, Mission, and Vision... 3 Overview... 3 District Vision Statement... 3 District Mission Statement...
More informationAnnual subscriptions to newspapers, newsletters, magazines
Supplies & Materials: 411000 Textbooks Books to be used in the classroom. Books used by various programs, such as the 231 Literacy Grant or Community Education Civics courses. BOOK 421000 Books, Magazines,
More informationASPE LOCAL 18 & CSI LOS ANGELES CHAPTER LACCD CONSTRUCTION BOND PROGRAM
ASPE LOCAL 18 & CSI LOS ANGELES CHAPTER LACCD CONSTRUCTION BOND PROGRAM David Salazar, Chief Facilities Executive March 28, 2018 www.jacobs.com worldwide AGENDA Program Overview Measure CC Implementation
More informationLangara College. Information Technology. IT Info-Session Oct 2016 INFORMATION TECHNOLOGY
Langara College Information Technology IT Info-Session Oct 2016 Agenda IT Strategic Plan IT Governance IT Service Desk New Building Update Printing & A/V Updates Project Updates Email Migration: O365 Update
More informationInformation Technology
Program Review - 2015-2016 Department Purpose Describe the purpose of the Discipline/Program/Service. IT department plans, designs, implements, and coordinates a variety of information technologies to
More information1.0 EXECUTIVE SUMMARY
1.0 EXECUTIVE SUMMARY 1.1 Campus Program Summary There are five (5) projects in pre-design and programming; four (4) are in design; and five (5) in construction. A summary of the Trade-Tech construction
More information/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions
Page 1 7-101 Definition A. Alternative Construction Delivery Methods: Building Delivery Processes that vary from the more standard Design-Bid-Build model. These may include Construction Manager-At-Risk
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationRATIONALE AND REASONING
RATIONALE AND REASONING Background The main tenant residing in BMH is the Anthropology Department. Most of the building systems constructed in the building are over forty years old and are at the end of
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationGoverning Board Presentation
SONOMA COUNTY JUNIOR COLLEGE DISTRICT Governing Board Presentation Facilities Master Plan Project Priority List November 8, 2016 Capital Projects Purchasing Items Gensler/QKA Contract: Irrigation Standards
More informationACEC/MA 15th Annual State Markets Conference
University of Massachusetts Building Authority ACEC/MA 15th Annual State Markets Conference April 6, 2017 1 University of Massachusetts Building Authority General Overview 2 Designer Procurement Process
More informationLANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent
RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural
More informationA PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM
A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register
More informationFEASIBILITY STUDY SEPTEMBER 1 8,
FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study
More informationFY INTERNAL AUDIT ACCOMPLISHMENTS REPORT AND ANNUAL STRATEGIC WORK PLAN
COAST COMMUNITY COLLEGE DISTRICT FY 2015-2016 INTERNAL AUDIT ACCOMPLISHMENTS REPORT AND ANNUAL STRATEGIC WORK PLAN Internal Audit Department Rachel A. Snell, MPA Internal Audit Director CIA, CFE, CRMA,
More informationSCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA
SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA 25 August 2009 All meetings are at 3:15 p.m. unless otherwise noted. Meeting dates are scheduled in advance and dates without agendas may or may not be
More informationInformation Resource Committee (IRC) Report for
Information Resource Committee (IRC) The Information Resource Committee (IRC) moved forward with the recommendations submitted with its 2015-2016 Executive Summary Report, addressing the following action
More informationReport By: Ben Seaberry District Technology Plan Project List (Select Fields) Last Updated: 5/23/16. Page 1
ID PROJECT NAME Project Description Project Status Percent Due Date Completion Date Accreditation Location Impact 52 District Technology Plan update for 2012-2013 Update District wide technology plan project
More informationPerimeter Site Improvements
Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff
More informationNORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT DISTRICT INFORMATION SERVICES TECHNOLOGY PLAN
NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT DISTRICT INFORMATION SERVICES TECHNOLOGY PLAN 2011-2015 Reviewed by Technology Advisory Committee 12-14-2010, 6-19-12, 6-18-13, 6-17-14; Updated Status 12-13-2011,
More informationOctober 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:
October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents
More informationGOING GREEN BIG TIME. Terence Williams Architect, Inc. 1
GOING GREEN BIG TIME Surplus land, free sun and wind, business partnerships, program development, and a commitment to sustainable practices can lead to a money-making, self-sustainable campus 1 GOING GREEN
More informationMcCollum Hall Classroom Renovation Project Profile LEED-CI Gold, August 2007
Project Highlights McCollum Hall Classroom Renovation Project Profile LEED-CI Gold, August 2007 > 42.7% reduction in potable water usage achieved with high-efficiency low-flow fixtures > 94.6% of the construction
More informationSeptember 28, Measure TT Un-Prioritized Projects Nelson Cayabyab, Chief of Facilities
September 28, 2017 Measure TT Un-Prioritized Projects Nelson Cayabyab, Chief of Facilities UN-PRIORITIZED MASTER PLAN SITES September 28, 2017 Priority # Location Project Construction cost 60/40 contribution
More informationBusiness School Program Plan Revision 2
UNIVERSITY OF COLORADO DENVER Business School Program Plan 2 August 18, 2009 Business School Program Plan 2 Business School Program Plan 2 University of Colorado Denver I. Executive Summary The Business
More informationCOMPUTING TECHNOLOGY SUPPORT GOALS & OBJECTIVES ACCOMPLISHMENTS. Information Technology Services AND MAY 1, 2013 SUBMITTED BY:
Information Technology Services COMPUTING TECHNOLOGY SUPPORT GOALS & OBJECTIVES AND ACCOMPLISHMENTS 2012-2013 MAY 1, 2013 SUBMITTED BY: ALEXIS A. MORALES ASSISTANT DIRECTOR, COMPUTING TECHNOLOGY SUPPORT
More informationKingsborough Community College
Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2018-19 through FY 2022-23 Project Funding Type Five - Year Plan Total ( $ 000 s ) Performing Arts Renovations
More informationBasic IT Bundle Service Level Expectation
Basic IT Bundle Service Level Expectation November 2016 Service Level Expectation Template 1 Basic Information Technology Bundle Service Level Expectation Document Service Overview... 3 Service Features...
More informationSRJC SYSTEMS CHANGE UPDATE SIS
SRJC SYSTEMS CHANGE UPDATE SIS S I S R E P L A C E M E N T H I S T O R Y / U P D A T E / P L A N J A N U A R Y 2 5, 2 0 1 7 D R. S C O T T C O N R A D I T D I R E C T O R, S R J C AGENDA Goals/ SIG Evaluation
More informationCONSTRUCTION UPDATE SEPTEMBER 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE SEPTEMBER THIS IS AUBURN. JORDAN-HARE STADIUM VIDEO BOARD INSTALLATION ATHLETICS DEPARTMENT ENGINEER: LBYD, INC. CONSTRUCTION MANAGER: BRASFIELD & GORRIE $13.9 AUGUST The video board
More informationEXECUTIVE DIRECTOR - FACILITIES DEVELOPMENT AND PLANNING
PERSONNEL COMMISSION Class Code: 5084 Salary Range: 60 (M2) EXECUTIVE DIRECTOR - FACILITIES DEVELOPMENT AND PLANNING JOB SUMMARY Under the direction of the Chief Business and Financial Officer, plan, implement
More informationProjects Currently in Planning, Design and Construction. April 12, 2017
Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space
More informationCONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.
More informationCENTENNIAL SCHOOL DISTRICT
CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites
More informationInformation Technology Agency Overview
Information Technology Agency Overview Agency Mission The mission of the Information Technology (IT) Department is to provide services to all City agencies for computer usage, software development, personal
More informationBOARD OF REGENTS AUDIT/COMPLIANCE AND INVESTMENT COMMITTEE 3 STATE OF IOWA FEBRUARY 6-7, 2013 INTERNAL AUDIT REPORTS ISSUED
STATE OF IOWA FEBRUARY 6-7, 2013 INTERNAL AUDIT REPORTS ISSUED Action Requested: Receive the original and follow-up internal audit reports. Contact: Todd Stewart Executive Summary: Completed institutional
More informationProject Delivery Method
Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect
More informationInformation Technology Agency Overview
Agency Overview Agency Mission The mission of the Information Technology (IT) Department is to provide services to all City agencies for computer usage, software development, personal computer support,
More informationAccount Managers Group. April 28, 2017
Account Managers Group April 28, 2017 Account Managers Group Welcome Valarie Maxwell Account Managers Group Fair Labor Standards Act (FLSA) Dawn Fisher Fair Labor Standards Act On November 22, 2016 Judge
More informationAdministrative & Student Information Systems Refresh: Phase I Project Update
Administrative & Student Information Systems Refresh: Phase I Project Update Treasurer s Town Hall @ Rutgers University Newark J. Michael Gower Senior Vice President for Finance and Treasurer October 7,
More informationCapital Improvement Program Monthly Status Report
Districtwide Mechanical, Electrical and Controls Equipment Upgrades This project replaces aged mechanical, electrical and controls equipment that have reached the end of their service lives with modern
More informationService Level Agreement for University Facilities
Service Level Agreement for University Facilities Facilities-related departments within the Office of the Executive Vice President and Chief Operating Officer (EVP & COO) will provide services to university
More informationMADISON HIGH SCHOOL // Executive Summary
MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*
More informationFacilities Council Minutes October 4, 2016
Facilities Council Minutes October 4, 2016 Building I, Room I-202 3:00 p.m./3:05 pm Attendees: Melinda Merrell, Barry Baker, Mark Daniels, Mike Biell, Dave Parker, Mark White, Jose Perdomo, Doug Medbury,
More informationLOVEJOY Independent School District
Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $
More informationWESTERN KENTUCKY UNIVERSITY
WESTERN KENTUCKY UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2002-2004 0001 Renovate Science Campus - Phase II $33,000,000
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More informationDallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009
Dallas/Fort Worth International Airport ASCE Presentation Terminal Development Program November, 2009 ASCE PRESENTATION, NOVEMBER 2009 Background Objective The objective of today s presentation 1. Review
More informationStrategic Plan. The College of New Jersey Information Technology
Strategic Plan The College of New Jersey Information Technology Information Technology The College of New Jersey Introduction Information Technology at The College of New Jersey is comprised of four separate
More informationEnergy Reduction Strategy Through 2020
Through 2020 Revised: August 2017 Executive Summary Auburn University is a land, sea and space grant university established in 1856. The university consists of 11,629,000 square feet on 1,840 acres and
More informationShared Service Centers
Shared Service Centers Communication Ambassadors Update January 24, 2012 Today s Discussion SSC Leadership Staff LAS-SSC Timeline LAS-SSC Staffing Plans: Waves 2 4 Wave 1 Staffing Financial Manager Position
More informationCapital Improvement Program Monthly Status Report
Districtwide Security Camera Upgrades The project will take the existing multiple security camera systems currently used throughout the District and replace them with a single integrated Districtwide,
More informationFacility Study Update
Facility Study Update January 18, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Focus Groups Forums Surveys Revise / Refine Engagement Strategic
More informationEXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5
EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...
More informationTEXAS A&M ENGINEERING
TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas
More informationCalifornia State Polytechnic University. Department Safety Coordinator Manual
California State Polytechnic University Department Safety Coordinator Manual Environmental Health and Safety October 28, 2010 TABLE OF CONTENTS 1.0 Reference 2.0 Policy 3.0 Purpose 4.0 Responsibilities
More informationM $336M .73 S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS A BETTER WAY TO BUILD. YEARS OF CONSTRUCTION SERVICES DESIGN-BUILD PROJECTS
A BETTER WAY TO BUILD. S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS Our team of construction professionals has more than 30 years of building experience in New England. We pride ourselves on the personal
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance Consent ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance Consent AGENDA ITEM: 4 P DATE: December 5-7, 2017 ****************************************************************************** SUBJECT FY19 HEFF M&R Projects
More informationNEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST
NEW HAVEN UNIFIED SCHOOL DISTRICT BOND PROJECT LIST The New Haven Unified School District will use bonds funds to provide up to date classrooms, renovate athletic fields and related facilities, replace
More informationINFORMATION TECHNOLOGY Business Plan Abe Kani, IT Director/CIO
INFORMATION TECHNOLOGY 2017 Business Plan Abe Kani, IT Director/CIO INFORMATION TECHNOLOGY Agenda Mission & Vision Priorities Organization & Environment Accomplishments & Challenges Workforce Development
More informationBuilding Careers in Sustainable Facilities Design and Management
Building Careers in Sustainable Facilities Design and Management November 29, 2017 11:15 am 12:15 pm Presented By Robert T. Mejia, Executive Director, Economic, Resource, and Community Development, San
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationCapital Improvement Program Monthly Status Report
Districtwide Mechanical, Electrical and Controls Equipment Upgrades This project replaces aged mechanical, electrical and controls equipment that have reached the end of their service lives with modern
More informationArlington Fire District 2018 Budget Worksheet
Worksheet Income Taxes-Town Poughkeepsie 0 Interest 8,000 In Lieu of Taxes 550,600 Rentals 0 Sale of Equipment 0 Insurance Recoveries 0 Freedom of Information Fee 0 Refund of Expenditures 0 Gifts & Donations
More informationBridgewater State University Information Technology
Bridgewater State University Information Technology Project Management Office Monthly Report March 2018 Table of Contents Executive Summary... 3 Purpose... 3 Highlights... 3 Looking Ahead... 4 FY17 Project
More informationNext Generation Enterprise Network- Recompete (NGEN-R) End User Hardware (EUHW)
Next Generation Enterprise Network- Recompete (NGEN-R) End User Hardware (EUHW) Ms. Susan Eaton End User PMW-205 25 January 2017 Topics The Plan OMB & DoD Policy NGEN-R EUHW Scope Intended NGEN-R EUHW
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationUNIVERSITY OF NORTH CAROLINA PEMBROKE
PROGRAM FOR RENOVATIONS AND ADDITIONS 30 June 2011 B A Livermore Library Renovations C B GPAC Additions & Renovations F A D C Business Education Renovations D D.F. Lowry Renovations E Old Main Renovations
More informationEasthampton High School Building Project. Public Information Forum #3
Building Project Public Information Forum #3 May 4, 2010 CAOLO & BIENIEK ASSOCIATES, INC. Architecture Planning Interior Design Presentation Agenda Introduction - Michael Buehrle, Chair EHS Building Committee
More informationTO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM
GB1 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For the Meeting of May 20, 2015 ACTION ITEM AMENDMENT OF THE BUDGET AND APPROVAL OF EXTERNAL FINANCING, CLINICAL SCIENCES
More informationKingsborough Community College
Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY 2016-17 through FY 2020-21 Project Funding Type Five - Year Request Total ( $ 000 s ) Roof Replacement
More informationArchitectural Services
Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District
More informationMott Community College Job Description
Title: Department: Office of Physical Plant Reports To: Chief Financial Officer Date Written/Revised: September 22, 2006; Revised July 3, 2017, March 13, 2018 Purpose, Scope and Dimension of Job: Purpose:
More informationLIFE OF A CAPITAL PROJECT
LIFE OF A CAPITAL PROJECT CAPITAL ASSET STRATEGIES (CAS) ARCHITECTS AND ENGINEERS (A&E) 5/4/2017 EARLY STEPS OF A MAJOR CAPITAL PROJECT (>$750,000) Scoping & Feasibility Project sponsor and campus leadership
More informationManagement. Construction. Development. WE PROVIDE A complete roster of building services to streamline the construction process
WE ARE: We are a family-owned construction company providing construction services to general contractors and real estate owners throughout the San Francisco Bay Area. Founded in 2001, Argo Construction
More informationDRINKING WATER IN CHILD CARE CENTERS & SCHOOLS MINNESOTA State Policy Profile
PHAI Public Health Advocacy Institute DRINKING WATER IN CHILD CARE CENTERS & SCHOOLS MINNESOTA State Policy Profile Access to safe and appealing drinking water in child care and schools is a key strategy
More informationUCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017
UCSF Mission Bay & Dogpatch Construction Community Meeting Agenda Welcome Project Communications Construction Context Project Updates Minnesota Housing Center for Vision Neuroscience Precision Cancer Medicine
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 6 O DATE: December 5-7, 2017 ****************************************************************************** SUBJECT USD Dakota Dome Renovation
More informationR2R Program (School of Continuing Studies) October 2, 2017
R2R Program (School of Continuing Studies) October 2, 2017 Agenda R2R in sum Vision and expected benefits Processes in scope Guiding principles R2R timeline Service Delivery Model timeline & context High-level
More informationConstruction Management Department Annual Goals, Plans and Status Report
Construction Management Department Annual Goals, Plans and Status Report Unit Name: Construction Management Department Year: 2012-2013 Department Mission: Prepare students for professional construction
More informationLangara College. Information Technology. IT Info-Session May 2016 INFORMATION TECHNOLOGY
Langara College Information Technology IT Info-Session May 2016 Agenda 1 2 3 4 5 6 7 8 9 10 IT Strategic Plan IT Governance IT Service Desk New Building Update A/V Updates Project Updates ESSSE & Telephone
More informationJackson Miracle Building Plan Outreach Roundtable. February 14, 2017
Jackson Miracle Building Plan Outreach Roundtable February 14, 2017 $1.8 billion Expanded Footprint Improved Patient Experience World-Class Facilities Innovative, Leading-Edge Care A Stronger, More Competitive
More informationFacilities Management Department Division and Unit Goals
Facilities Management Department 2017-18 Division and Unit Goals Administration Division Goals Business Operations Unit 1. BOPS staff is going to work internally to better standardize and document our
More informationDAT MEETING NOTES # 3
DAT MEETING NOTES # 3 MOA ARCHITECTURE Design Advisory Team 821 17 th Street, Suite 400 Denver, Colorado 80202 303.308.1190 Phone 303.308.1197 Fax Project: Superior Elementary School Date: 16 December
More informationCOMMODITY BUYER EXT APPLIANCES BELL ROBINS ARCHITECTURAL SERVICES RAMONA REID ARMORED CAR SERVICES BELL ROBINS 55108
APPLIANCES ARCHITECTURAL SERVICES ARMORED CAR SERVICES ART EQUIP/ SUPPLIES, MTCE CONTRACTS, ATHLETIC EQUIPMENT & SUPPLIES ATHLETIC TRAINER SERVICES AUDIO VISUAL EQUIP/SUPPLIES, MTCE AUDIT SERVICES - FINANCIAL
More informationRFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018
Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as
More informationFUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013
Project Summary and Total Project Cost NEW CONSTRUCTION PROJECTS A. Campus Center Replacement $ 29,474,691 B. East Campus Classroom and Office Building(s) $ 34,674,804 C. Wake Center Replacement $ 40,051,128
More informationCreative Performing Media Arts Middle School
Dawne St Kilkee St Enelra Pl Creative Performing Media Arts Middle School 5050 Conrad Ave. San Diego, CA 92117 Sub-district: A Cluster: Madison Year School Opened: 2002 Grades: 6-8 Arlene Pl 3 2 Conrad
More information90% Draft - NOT FINAL. A Presentation For: the architectural studio. By Principals: George Moore & Curt Santee October 28th 2014
A Presentation For: By Principals: George Moore & Curt Santee October 28th 2014 1 the architectural studio 2014 District Exterior Wall Forensic Study Warrior Run School Brick Study Completed on High School
More informationIn Process. Hold for SCT. 1. State MIS Data, HR Staff & IPEDS Reporting***
1. State MIS Data, HR Staff & IPEDS Reporting*** Design completed for Student, Fin Aid, and HR specifications. Programming completed for Fin Aid and Student. Pending HR portion. Project on hold since SCT
More information