1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Engineering Services 2014 Bond March 2017 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Richard De La Cruz, P.E. DIRECTOR OF ENGINEERING 0

2 PROJECTS IN CONSTRUCTION 1

3 CHILLER REPLACEMENTS PE/Athletics Dressing/Locker Room AC Installation and Chiller Replacement at Marshall HS Engineering Firm Clearly Zimmermann Engineers NISD Project Manager Rob Ibarra Contract Amount - $1,795,700 Contractor International Mechanical Services, Inc. Construction Period June 2016 March 2017 Construction Status: 97% Project Scope Replace chiller plant and A/C installation in boys and girls locker room. Chiller Water Pump 2

4 = Chiller Replacement & Lighting Upgrades at Reddix Center Engineering Firm Clearly Zimmermann Engineers NISD Project Manager Carlos Rodriguez Contract Amount - $418,000 Contractor Gillette Air Conditioning Co, Inc. Construction Period January 2017 March 2017 Construction Status: 50% Project Scope Replace two chillers and upgrade lighting fixtures to LED lighting. Pad Site for the New Chiller 3

5 FIRE ALARM SYSTEM REPLACEMENTS Fire Alarm Systems & Plumbing Upgrades at NW Crossing ES Engineering Firm TLC Engineering for Architecture NISD Project Manager Ramiro Guerrero Contract Amount - $273,340 Contractor Quinney Electric, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Replace total fire alarm system and walk-in freezer and cooler in the Cafeteria. Typical Fire Alarm Panel 4

6 HVAC RENOVATION HVAC Renovation/Boiler Replacement/PE/Athletics Dressing/Locker Room AC Installation at Clark HS Engineering Firm Wallis Engineering Group, Inc. NISD Project Manager Richard De La Cruz, P.E., Rob Ibarra Contract Amount - $16,200,000 Contractor Bartlett-Cocke General Contractors Construction Period June 2016 August 2018 Construction Status: 40% Construction Overall (Phase IV of IX in Progress) Project Scope Replace entire HVAC system including boiler and piping; install air conditioning and heating in boys and girls locker rooms. Phase IV began February 27, Existing Job Site New Installed Chillers 5

7 LIGHTING UPGRADES Lighting Upgrades at Child Nutrition Warehouse Engineering Firm TTG Engineers, Inc. NISD Project Manager Carlos Rodriguez Contract Amount - $125,517 Contractor HJD Capital Electric, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Replace ballast and 32 watt lamps in office area with 28 watt lamps. Replace existing lamps with high output lamps in dry storage area. 6

8 MECHANICAL UPGRADES Mechanical Upgrades at Evers ES & Leon Springs ES Engineering Firm Clearly Zimmermann Engineers NISD Project Manager Rob Ibarra Contract Amount - $2,977,400 Contractor International Mechanical Services, Inc. Construction Period June 2016 August 2017 Construction Status: 75% Construction Overall Project Scope Evers ES: Replace unit ventilators with fan powered boxes. Leon Springs ES: Replace air handler for Admin, Library and Cafeteria. Evers ES 7

9 Mechanical Upgrade & Energy Controls Upgrade at Elrod ES Engineering Firm DBR Engineering Consultants, Inc. NISD Project Manager Ramiro Guerrero Contract Amount - $2,345,820 Contractor Comfort-Air Engineering, Inc. Construction Period June 2017 August 2018 Construction Status: 0% Project Scope Replace unit ventilators throughout the campus with VAV systems, replace two chillers and HVAC controls throughout. Elrod ES Phasing Plan 8

10 Mechanical Upgrades at Glass ES Engineering Firm Wallis Engineering Group, Inc. NISD Project Manager Rob Ibarra Contract Amount - $201,000 Contractor Tezel & Cotter A/C, L.P. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Replace existing rooftop units at the Cafeteria; replace existing ductwork and air devices. 9

11 Mechanical Upgrades & PE/Athletics Dressing/Locker Room AC Installation at John Jay HS Engineering Firm Silber & Associates Consulting Engineers, Inc. NISD Project Manager Rob Ibarra Contract Amount - $788,189 Contractor Flo-Aire Service, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Mechanical upgrades and AC installation in the PE and Athletic areas. 10

12 Mechanical Upgrades & PE/Athletics Dressing/Locker Room AC Installation at Neff MS Engineering Firm DBR Engineering Consultants, Inc. NISD Project Manager Ramiro Guerrero Contract Amount - $748,505 Contractor Flo-Aire Service, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Mechanical upgrades and AC installation in the PE and Athletic areas. Replace two rooftop units at Coach s offices. 11

13 P.A. INTERCOM SYSTEM P.A. Intercom Systems, Lighting Upgrades & Electrical Upgrades at Michael ES, Meadow Village ES & Ward ES Engineering Firm TLC Engineering for Architecture NISD Project Manager Ramiro Guerrero Contract Amount $235,687 Contractor Quinney Electric, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Meadow Village ES Main power for portables will be upgraded. Ward ES & Michael ES Replace PA System to include the callback feature; lighting upgrades at both campuses. 12

14 PAVING / DRAINAGE UPGRADES Paving & Drainage Upgrades at Braun Station ES & Sul Ross MS Engineering Firm MTR Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Contract Amount $425,200 Contractor Pronto Sandblasting & Coating & Oil Field Services Co., Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Upgrade paving for staff parking and bus loop at both campuses. 13

15 P.E./ATHLETICS DRESSING/LOCKER ROOM AC INSTALLATION P.E./Athletics Dressing/Locker Room AC Installation at Rawlinson MS Engineering Firm Alderson & Associates, Inc. NISD Project Manager Troy Spear Contract Amount $265,000 Contractor Flo-Aire Service, Inc. Construction Period June 2017 August 2017 Construction 0% Project Scope AC installation in the PE and Athletic areas. 14

16 PLAYGROUND UPGRADES Playground Upgrades at Beard ES, Blattman ES, Braun Station ES, Elrod ES, Glass ES, Leon Valley ES, Oak Hills Terrace ES & Raba ES Engineering Firm MTR Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Contract Amount $535,790 Contractor R.L. Rhode General Contracting, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Geodesic dome replacement at eight campuses and full upper replacement at Blattman ES. Typical Playscape 15

17 Playground Upgrades at Fernandez ES, Fisher ES, Galm ES, Rhodes ES, Scarborough ES, Thornton ES & Timberwilde ES Engineering Firm CDS Muery Engineering NISD Project Manager Jacob Villarreal, P.E. Contract Amount $219,600 Contractor Pronto Sandblasting & Coating & Oil Field Service, Co. Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Geodesic dome replacement at seven campuses. 16

18 Playground Upgrades at Henderson ES, Knowlton ES, Kuentz ES, Lewis ES, Linton ES & Myers ES Engineering Firm Cude Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Contract Amount $209,000 Contractor R.L. Rhode General Contracting, Inc. Construction Period June 2017 August 2017 Construction Status: 0% Project Scope Geodesic dome replacement at six campuses. 17

19 TENNIS COURT UPGRADES Tennis Court Resurfacing at Luna MS Engineering Firm Cude Engineers, LLC NISD Project Manager Troy Spear Contract Amount $35,000 Contractor Premier Courts Limited Company Construction Period June 2017 June 2017 Construction Status: 0% Project Scope Tennis court resurfacing. Typical Resurfaced Court 18

20 PROJECTS IN DESIGN/PLANNING 19

21 ATHLETICS UPGRADES Track & Field Upgrades at Jay HS Engineering Firm Cude Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Budget Amount $1,700,000 Contractor - TBD Construction Period April 2017 August 2017 (100% Design) Project Scope Full replacement of track and football field with synthetic turf and synthetic track surfacing. (2007/2014 Bond Funds). Tennis Court Upgrades at Sul Ross MS & Stevens HS Engineering Firm MTR Engineers, LLC NISD Project Manager Troy Spear Budget Amount $105,000 Contractor - TBD Construction Period April 2017 August 2017 (95% Design) Project Scope Upgrade tennis courts at both campuses. 20

22 LIGHTING UPGRADES Lighting Upgrades at Galm ES, Timberwilde ES & Alternative HS Engineering Firm TLC Engineering for Architecture NISD Project Manager Ramiro Guerrero Budget Amount $165,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope Lighting upgrades at three campuses. Lighting Upgrades at Rhodes ES Engineering Firm MS2 Inc. Consulting Engineers NISD Project Manager Carlos Rodriguez Budget Amount $70,000 Contractor - TBD Construction Period - June 2017 August 2017 (100% Design) Project Scope Lighting upgrades. 21

23 FIRE ALARM SYSTEM REPLACEMENTS Fire Alarm & Lighting Upgrades at Raba ES & Electrical Upgrades at Central Office Engineering Firm CNG Engineering, PLLC NISD Project Manager Carlos Rodriguez Budget Amount $270,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope Raba ES: Fire alarm and lighting upgrades. Central Office: Electrical upgrades. 22

24 MECHANICAL UPGRADES HVAC Mechanical Upgrades & Chiller Replacement at Cable ES Engineering Firm Silber & Associates Consulting Engineers, Inc. NISD Project Manager Jacob Villarreal, P.E. Budget Amount $900,000 Contractor - TBD Construction Period May 2017 August 2017 (100% Design) Project Scope Mechanical upgrades and chiller replacement. Mechanical Upgrades at Jordan MS Engineering Firm Wallis Engineering Group, Inc. NISD Project Manager Rob Ibarra Budget Amount $6,700,000 Contractor - TBD Construction Period June 2018 August 2020 (95% Design) Project Scope Mechanical upgrades and chiller replacement. 23

25 Mechanical Upgrades at Oak Hills Terrace ES Engineering Firm Cleary Zimmermann Engineers NISD Project Manager Carlos Rodriguez Budget Amount $75,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope Mechanical upgrades. 24

26 PAVING / DRAINAGE UPGRADES Paving & Drainage Upgrades at Howsman ES & Zachry MS Engineering Firm CDS Muery Engineers NISD Project Manager Jacob Villarreal, P.E. Budget Amount $455,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope Upgrade paving at bus loop and staff parking lot. Paving & Drainage Upgrades at Marshall HS & O Connor HS Engineering Firm Cude Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Budget Amount $419,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope Marshall HS: Upgrade paving and drainage. O Connor HS: Upgrade drainage. 25

27 P.E. / ATHLETICS DRESSING / LOCKER ROOM AC INSTALLATION PE/Athletics Dressing/Locker Room AC Installation & Fire Alarm Upgrades at O Connor HS Engineering Firm Cleary Zimmermann Engineers NISD Project Manager Rob Ibarra Budget Amount $1,080,000 Contractor - TBD Construction Period June 2017 August 2017 (100% Design) Project Scope AC installation in the PE and Athletic areas and fire alarm upgrade. 26

28 SCHOOL FLASHERS School Flashers at Harlan HS & Kallison ES Engineering Firm Cude Engineers, LLC NISD Project Manager Jacob Villarreal, P.E. Budget Amount $300,000 Contractor - TBD Construction Period May 2017 July 2017 (100% Design) Project Scope Installation of school flashers at both campuses.

29 NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Facilities Construction 2014 Bond March 2017 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION Harlan High School

30 NEW PROJECTS IN CONSTRUCTION

31 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor Joeris General Contractor GMP - $110,800,000 Construction Period October 2014 Summer 2017 Construction Status: 93% Complete Project Scope New 2800 Student High School Site grading, utilities, landscaping. Interior CMU walls, drywall framing. Interior painting. MPE / Tech systems. Concrete drives and parking areas in progress. Final Punch in progress.

32 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Feb. 20, 2017) Aerial looking from West

33 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance Front Entry Rendering

34 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017) Cafeteria

35 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (March 22, 2017) Auditorium Seating

36 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (March 22, 2017) Stage at Auditorium

37 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (March 22, 2017) View of Stage

38 KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY) Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor Guido Construction GMP - $24,640,000 Construction Period March 2016 July 2017 Construction Status: 60% Complete Project Scope New 800 Student Elementary School Masonry, brick, MPE / Tech Systems and roofing in progress.

39 KALLISON ELEMENTARY SCHOOL Front Entrance Front Entry Rendering

40 KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017) Aerial Image

41 KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017) Aerial Image

42 KALLISON ELEMENTARY SCHOOL (February 28, 2017) Classroom Wing

43 KALLISON ELEMENTARY SCHOOL (March 1, 2017) Interior Corridor

44 ADDITIONS AND RENOVATION PROJECTS IN CONSTRUCTION

45 GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor McGoldrick Construction Co. Construction Amount - $3,750,000 Construction Period June 2016 June 2017 Construction Status: 50% Complete Project Scope New Administration Building Roofing, interior walls, MPE / Tech Systems in progress.

46 GLENOAKS ELEMENTARY (Rendering of Front Elevation) Front Entry Rendering

47 GLENOAKS ELEMENTARY Administration Upgrades (February 2017) Front Entry Image

48 HOLMES HS FINE ARTS BUILDING Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor Bartlett Cocke Construction Budget - $27,000,000 Construction Period June 2017 December 2018 Construction Status 1% Complete Project Scope Fine Arts Building Replacement Status Phase 1 Portables Complete 2 MDF Relocate in Progress 3 Demolition / Abatement in Progress (Spring to Summer 2017) 4 Building Design / Construction (Summer 2017 to Fall 2018)

49 HOLMES HS FINE ARTS BUILDING Portable Village View of Portable Village

50 HOLMES HS FINE ARTS BUILDING Existing Auditorium View of Existing Auditorium

51 CHILD NUTRITION CENTER Renovation Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Henry Acosta Contractor Workman Commercial Contract Amount - $5,726,500 Construction Period July 2016 January 2017 Construction Status: 70% Complete Project Scope Warehouse Renovation Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings. Demo complete, rough-ins in progress. Walk in cooler/freezer floor complete. Office area drywall complete, tape & float (finishes in progress), new switch gear being installed, new CPS transformer on its way. Walk-in cooler/freezers, walls, racks and ceilings being installed. Condensers set.

52 CHILD NUTRITION CENTER Renovation (March 3, 2017) Paving

53 CHILD NUTRITION CENTER Renovation (Feb 16, 2017) Corridor

54 CHILD NUTRITION CENTER Renovation (Feb 16, 2017) Freezer Area

55 PAUL TAYLOR FIELD HOUSE RENOVATIONS Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Stoddard Construction Management, Inc. Construction Amount - $3,400,000 Construction Period February 2017 August 2017 Construction Status 2% Complete Project Scope ADA Interior/Exterior Renovations Site Mobilization and Demolition in Progress.

56 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017) Wood Gym Floor - Protected

57 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017) Demolition in Progress

58 PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017) Northeast View

59 NORTHSIDE ACTIVITY CENTER RENOVATIONS Architect Richard Sanchez Architects, Inc. Project Architect Richard Sanchez NISD Project Manager Thomas Curiel Contractor O Haver Contractors Co. Construction Budget - $4,000,000 Construction Period February 2017 January 2018 Construction Status 1% Complete Project Scope Addition and Renovation of Meeting Rooms Mobilization and Demolition in progress.

60 PROJECTS IN BID/DESIGN PHASE

61 GROSENBACHER AREA ELEMENTARY (Prototype of Boldt ES and Cole ES) Architect Noonan Rittiman Project Architect John Rittiman NISD Project Manager Tom Curiel Contractor DL Bandy Construction Amount - $22,465,000 Construction Period March 2017 May 2018 Construction Status 0% Complete Project Scope New 800 Student Elementary School Notice to Proceed Issued.

62 2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor CGC General Contractors Construction Amount - $1,293,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope New Security Lobby for (9) Elementary Schools: Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES Notice to Proceed Issued.

63 GLENOAKS ELEMENTARY - Window Upgrades / ADA Work Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $1,100,000 Construction Period June 2017 December 2017 Construction Status 0% Complete Project Scope Window Upgrades and ADA Work Bids to be received March 29, 2017.

64 BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Jim Berg Contractor TBD Construction Budget - $4,040,000 Construction Period June 2017 May 2018 Construction Status 0% Complete Project Scope Administration Upgrades, Bus/Student Walkway Canopy Modifications Construction Documents in progress.

65 COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work Architect Huckabee Architects Project Architect Jeff Rodriquez NISD Project Manager Chris Parker Contractor TBD Construction Budget - $2,000,000 Construction Period June 2017 October 2017 Construction Status 0% Complete Project Scope Window Upgrades and ADA Work Contractor submitted for March Board Approval.

66 GLASS ELEMENTARY Window Upgrades / ADA Work Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,500,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Window Upgrades and ADA Work Master Plan in progress.

67 HELOTES ELEMENTARY Window Upgrades / ADA Work Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $700,000 Construction Period June 2017 November 2017 Construction Status 0% Complete Project Scope Window Upgrades and ADA Work Master Plan in progress.

68 POWELL ELEMENTARY Window Upgrades / ADA Work Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $700,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Window Upgrades and ADA Work Master Plan in progress.

69 GLENN ELEMENTARY School Building Replacements / Security Lobby Architect LPA Project Architect Mark Oppelt / Lowell Tacker NISD Project Manager Jim Berg Contractor TBD Construction Budget - $4,800,000 Construction Period June 2017 August 2018 Construction Status 0% Complete Project Scope Replacement of Buildings Bids to be received March 23, 2017.

70 KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition Architect Pfluger Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor TBD Construction Budget $2,200,000 Construction Period June 2017 November 2017 Construction Status 0% Complete Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Contractor submitted for March Board Approval.

71 TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor TBD Construction Budget $2,200,000 Construction Period June 2017 November 2017 Construction Status 0% Complete Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Bids to be received March 22, 2017.

72 2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS Architect Chesney Morales Project Architect Richard Morales NISD Project Manager James Evans Contractor TBD Construction Budget $117,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Replacement of Door Hardware for Accessibility Construction Documents in progress.

73 2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary Architect CWS Architect Project Architect Robert Watts NISD Project Manager Chris Parker Contractor TBD Construction Budget $230,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Replacement of Flooring Proposal opening March 22, 2017.

74 2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS Architect Huckabee Architects Project Architect Jeff Rodriguez NISD Project Manager Chris Parker Contractor TBD Construction Budget $325,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Replacement of Flooring Contractor submitted for March Board Approval.

75 NEFF MS COMPETITION GYM FLOORING AND BLEACHERS Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Chris Parker Contractor TBD Construction Budget $200,000 Construction Period June 2017 August 2017 Construction Status 0% Complete Project Scope Replacement of Flooring and Bleachers Contractor submitted for March Board Approval.

76 MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovations Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Tom Curiel Contractor TBD Construction Budget $4,400,000 Construction Period June 2017 March 2018 Construction Status 0% Complete Project Scope Renovations and Additions Master Plan in progress.

77 SCIENCE LAB ADDITIONS/RENOVATIONS Alternative North MS Architect C.J. Lammers & Associates Project Architect Chris Lammers NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget $600,000 Construction Period June 2017 December 2017 Construction Status 0% Complete Project Scope Renovation of Science Labs

78

79 2016 HAIL DAMAGE ROOFING PROJECTS

80 LIST OF SCHOOLS Hail Damage Roofing Projects Phase I Carnahan Elementary School Beard Elementary School Clark High School South Transportation Stevenson Middle School Carlos Coon Elementary School Elrod Elementary School Fernandez Elementary School Phase II Esparza Elementary School Nichols Elementary School Connally Middle School Howsman Elementary School Leon Valley Elementary School Scarborough Elementary School Alternative ES & MS - North Burke Elementary School Brauchle Elementary School Leon Springs Elementary School Raba Elementary School

81 Thank you Citizens Bond Advisory Committee!

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction March 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction May 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Facilities Construction 2014 Bond March 2018 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction July 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction September 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Facilities Construction 2014 Bond September 2018 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction October 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction December 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

PROJECT UPDATE August 28, 2014

PROJECT UPDATE August 28, 2014 PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

PROJECT UPDATE SEPTEMBER 11, 2014

PROJECT UPDATE SEPTEMBER 11, 2014 PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As

More information

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

2019 Construction

2019 Construction 2019 Construction Estimates @ 18 10 01 1 Oak Flat Elementary IDENTIFIED BASE BID SCOPE ITEMS Project BSSD replace door hardware to meet ADA, including re-key to master system $ 75,000 Shelter Lockdown

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

Frost Technical Center

Frost Technical Center Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. August 2016 Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Table of Contents. Project Status: Bowden Academy Project Status: Bowden Academy. Executive Summary

Table of Contents. Project Status: Bowden Academy Project Status: Bowden Academy. Executive Summary Committee Meeting December 12, 2018 : Bowden Academy : Bowden Academy Table of Contents Executive Summary Project Update Report Bowden Academy J.T. Brackenridge Elementary School Irving Dual Language Academy

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Basic renewal/restoration and safety projects

Basic renewal/restoration and safety projects Basic renewal/restoration and safety projects Board Update September 9, 2013 Bond Team Support Team Agenda Program Management Goals Program Budget Status 2013 Project Updates Labor Distribution Study 2014

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

BARNARD ELEMENTARY SCHOOL

BARNARD ELEMENTARY SCHOOL INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

DRAFT FY15/16. TBD Roof Repairs $50,000

DRAFT FY15/16. TBD Roof Repairs $50,000 FY15/16 Building Albemarle HS Design: Main Gym Floor Replacement $35,000 Burley MS Fieldhouse Restroom Facility Repairs $60,000 Burley MS Gym Partition Replacement with Curtain $30,000 CATEC Building Envelope

More information

Volusia County Schools Construction Project Tracking Report February 5, 2018

Volusia County Schools Construction Project Tracking Report February 5, 2018 Construction Tracking Report February 5, 2018 Manager Atlantic Replace Exterior Doors 184634 9/26/2017 Blom, Ken CPH Inc. Atlantic Renovations for Aquaculture Lab 184636 9/26/2017 Blom, Ken CPH Inc. Atlantic

More information

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets

More information

Volusia County Schools Construction Project Tracking Report

Volusia County Schools Construction Project Tracking Report Construction Tracking Report School / Facility Name No. Replace Exterior Doors 184634 9/26/2017 Blom, Ken CPH Inc. Renovations for Aquaculture Lab 184636 9/26/2017 Blom, Ken CPH Inc. Athletic Field Lighting

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

2006 FUSD Bond Information Guide

2006 FUSD Bond Information Guide Message from Superintendent Hickman On behalf of the Flagstaff Unified School District (FUSD) staff and members of the Governing Board, I extend my appreciation to the voters of our community, who have

More information

Volusia County Schools Construction Project Tracking Report

Volusia County Schools Construction Project Tracking Report Construction Tracking Report School / Facility Name No. Atlantic Replace Exterior Doors 184634 9/26/2017 Blom, Ken CPH Inc. Atlantic Renovations for Aquaculture Lab 184636 9/26/2017 Blom, Ken CPH Inc.

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

N o v e m b e r

N o v e m b e r WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

Merritt Island High School

Merritt Island High School Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry

More information

Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016

Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016 Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation June 13, 2016 Schedule/Major Milestones 2015 November December Data Collection Board Meeting- Update 2016 January

More information

Volusia County Schools Construction Project Tracking Report April 23, 2018

Volusia County Schools Construction Project Tracking Report April 23, 2018 Construction Tracking Report April 23, 2018 Atlantic Replace Exterior Doors 184634 9/26/2017 Blom, Ken CPH Inc. 2/13/2018 Atlantic Renovations for Aquaculture Lab 184636 9/26/2017 Blom, Ken CPH Inc. Atlantic

More information

STUART-HOBSON MIDDLE SCHOOL

STUART-HOBSON MIDDLE SCHOOL INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

Volusia County Schools Construction Project Tracking Report March 27, 2018

Volusia County Schools Construction Project Tracking Report March 27, 2018 Construction Tracking Report March 27, 2018 Atlantic Replace Exterior Doors 184634 9/26/2017 Blom, Ken CPH Inc. 2/13/2018 Atlantic Renovations for Aquaculture Lab 184636 9/26/2017 Blom, Ken CPH Inc. Atlantic

More information

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000

More information

Santa Teresa High School

Santa Teresa High School Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools Priority 1 Maintenance Projects Total Investment Needed: $54,875,317 Appleton Elementary Elementary Schools Total Priority 1 Need: $1,513,280 * Replace roofing in 3 areas * Add air handling units in cafeteria,

More information

Prop S Update. August 07, BIDS BEING REVIEWED o RFP #: PS Fencing at Beaumont and Gateway High Schools

Prop S Update. August 07, BIDS BEING REVIEWED o RFP #: PS Fencing at Beaumont and Gateway High Schools August 07, 2012 Prop S Update BIDS BEING REVIEWED o RFP #: PS71-1112 Fencing at Beaumont and Gateway High Schools OUT FOR BID o RFP #: PS61-1213 IP Clock District Wide Schools 08/17/2012 o RFP #: PS75-1213

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Lesky, Superintendent of Schools Board of School Directors Lewis F.

More information

Building Condition Report. Building Condition

Building Condition Report. Building Condition Price Memorial Building #0001 Present Building Use: The Administration building currently houses offices for the President, and Senior Administration. Building History: Built in 1879 Overall Size: 24,922

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

MAURY ELEMENTARY SCHOOL

MAURY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

Independence Adult Center

Independence Adult Center Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015 FACILITIES PROJECTS UPDATE BOARD OF EDUCATION August 11, 2015 AGENDA Measure R Bond Projects Fund 40 Capital Projects Maintenance Projects MEASURE R BOND PROJECTS KINDERGARTEN MODERNIZATIONS PROGRAM BUDGET:

More information

ROD Grant Round 4 Presentation June 9, 2014

ROD Grant Round 4 Presentation June 9, 2014 ROD rant Round 4 Presentation June 9, 2014 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 2 Agenda NJDOE Application

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017 Facilities Maintenance & Operations Update Presidents Executive Cabinet March 6, 2017 1 Update Proposition 39 Year 4: March 6 March 31 Will complete all exterior lighting upgrades to LED Aquatic Center

More information

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included

More information

DAVIS ELEMENTARY SCHOOL

DAVIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

James Lick High School

James Lick High School James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.

More information

Drexel Hill Middle School

Drexel Hill Middle School 150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information