Facilities Construction

Size: px
Start display at page:

Download "Facilities Construction"

Transcription

1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction October 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION Richard De La Cruz, P.E. ASSISTANT DIRECTOR OF ENGINEERING Bernal Middle School

2 BERNAL MIDDLE SCHOOL (Formerly STEVENS RANCH AREA MIDDLE SCHOOL) Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor Bartlett Cocke, Inc. Construction Budget - $41,408, Construction Period - January 2013 May 2014 Project Scope New 1200 Student Middle School Site work package issued September 9, 2012 NTP issued October 20, 2012 (54% Complete) Site work in progress. Concrete floor framing and columns complete. Roofing, exterior CMU walls and brick in progress. MEP infrastructure in progress. Structural steel erection in progress. Interior walls in progress. Interior painting (block fill) in progress. Site work and fields in progress.

3 BERNAL MIDDLE SCHOOL (Aerial September 6, 2013)

4 BERNAL MIDDLE SCHOOL (Perspective of Front Entrance)

5 BERNAL MIDDLE SCHOOL (September 30, 2013)

6 ELLISON ELEMENTARY SCHOOL (Formerly CIELO VISTA SOUTH ELEMENTARY) Architect Garza Bomberger Architects Project Architect Roy Lewis, AIA NISD Project Manager Marilyn Sevedge Risk Contractor Joeris General Contractor Construction Budget - $19,877, Construction Period - February 2013 May 19, 2014 (62% Complete) Project Scope 800 Student Elementary School Exterior Brick, Site Fencing, Lighting and Detention Pond in progress. Continuing MEP, Roof System Dried in. Installing Windows, continuing Off-Site Utilities and some Drywall Tape and Floating, Painting and Ceramic Tile.

7 ELLISON ELEMENTARY SCHOOL (Aerial Sept. 23, 2013)

8 ELLISON ELEMENTARY SCHOOL (Perspective of Front Entrance)

9 ELLISON ELEMENTARY SCHOOL (September 30, 2013)

10 NISD ANNEMARIE TENNIS CENTER Engineer MTR Project Engineer Ron Ramirez NISD Project Manager Christopher Parker Contractor Journeyman Construction Cost - $3,665, Construction Period - July 2013 January 2014 (35% Complete) Project Scope Replacement of existing courts, addition of new courts and renovations at existing restrooms. Site preparation in progress. Demolition complete. Light Pole bases set; Base has been processed; Final Grading complete and Concrete Beams being executed.

11 NISD ANNEMARIE TENNIS CENTER (September 30, 2013)

12 NISD ANNEMARIE TENNIS CENTER (Existing Site Plan)

13 NISD ANNEMARIE TENNIS CENTER (Proposed Site Plan)

14 NISD ANNEMARIE TENNIS CENTER (Proposed Site Plan Aerial)

15 NISD ANNEMARIE TENNIS CENTER (Main Street View)

16 LOCKE HILL ELEMENTARY (Bus Loop Improvement) Engineer MTR Project Engineer Ron Ramirez NISD Project Manager Thomas Curiel Contractor Suburban Construction Co. Construction Cost - $1,332, Construction Period - June 2013 November 2013 (29% Complete) Project Scope New Bus Loop and Paving; Rock removal completed. Utility installation, Bus Loop Concrete, Asphalt, Retaining Walls and Canopy Structure complete. Roof Panels have started.

17 LOCKE HILL ELEMENTARY (Bus Loop Improvement) (Oct. 1, 2013)

18 LOCKE HILL ELEMENTARY (Bus Loop Improvement Aerial Exhibit)

19 LOCKE HILL ELEMENTARY (Bus Loop Improvement Site Plan)

20 CABLE ELEMENTARY SCHOOL (Window Replacement) Architect Garza Architects Project Architect Jesse Garza, AIA NISD Project Manager Christopher Parker Contractor DL Bandy Construction Budget - $750, Construction Period June 10, 2013 October 7, 2013 (99% Complete) Project Scope Window Replacement Close Out in progress.

21 CABLE ELEMENTARY SCHOOL North Elevation A Wing (Window Replacement)

22 CABLE ELEMENTARY SCHOOL (Window Replacement) April 11, 2013

23 CABLE ELEMENTARY SCHOOL (Window Replacement) (Sept. 9, 2013)

24 MARY HULL ELEMENTARY SCHOOL (Window Replacement/ADA Improvements) Architect Garza Architects Project Architect Jesse Garza, AIA NISD Project Manager Christopher Parker Contractor DL Bandy Construction Cost - $1,150, Construction Period June 10, 2013 October 7, 2013 (99% Complete) Project Scope Window Replacement TCO in place. Closeout in progress. Final CO in process.

25 MARY HULL ELEMENTARY SCHOOL (Window Replace/ADA Improvements) (Sept. 9, 2013)

26 WESTWOOD TERRACE ELEMENTARY (Window Replacement/ADA Improvements) Architect Garza Architects Project Architect Jesse Garza, AIA NISD Project Manager Christopher Parker Contractor DL Bandy Construction Cost - $1,030, Construction Period June 10, 2013 October 7, 2013 (95% Complete) Project Scope Window Replacement TCO in place. Closeout in progress. Final CO in process.

27 WESTWOOD TERRACE ELEMENTARY Site Plan (Window Replacement/ADA Improvements)

28 WESTWOOD TERRACE ELEMENTARY (Window Replace/ADA Improvements) Feb. 26, 2013

29 WESTWOOD TERRACE ELEMENTARY (Window Replace/ADA Improvements) (Sept. 9, 2013)

30 REDDIX CENTER (ADA Improvements) Architect Garza Architects Project Architect Jesse Garza, AIA NISD Project Manager Christopher Parker Contractor DL Bandy Construction Cost - $365, Construction Period June 10, 2013 October 7, 2013 (99% Complete) Project Scope Accessibility Improvements Sitework Complete. Railing Adjustments and Finalization of Punch List items in Progress.

31 REDDIX CENTER (ADA Improvements) (October 1, 2013)

32 THORNTON ELEMENTARY ROOFING PROJECT Roof Consultant Hollon+Cannon Contractor Cram Roofing Construction Budget - $1,271, Construction Period - June 2013 October 2013 (99% Complete) Project Scope Roof Repair & Replacement. Notice to Proceed in June. Contractor mobilized; tear off has begun.

33 THORNTON ELEMENTARY ROOFING PROJECT (September 6, 2013)

34 McDERMOTT ELEMENTARY ROOFING PROJECT Roof Consultant Hollon+Cannon Contractor Dean Contracting Co. Construction Budget - $1,415, Construction Period - June 2013 October 2013 (97% Complete) Project Scope Roof Repair & Replacement. Notice to Proceed in June. Contractor mobilized; tear off has begun.

35 MYERS ELEMENTARY ROOFING PROJECT Roof Consultant Hollon+Cannon Contractor Port Enterprises Construction Budget - $1,583, Construction Period - June 2013 October 2013 (99% Complete) Project Scope Roof Repair & Replacement. Notice to Proceed in June.

36 INSELMANN BASEBALL FIELD (Replacement of Existing Facilities) Architect Garza Bomberger & Assoc. Project Architect Roy Lewis, AIA Contractor TBD Construction Budget - $2,700, Construction Period May 2014 October 2014 (% Complete) Project Scope Replacement of Existing Field and associated Facilities.

37 INSELMANN BASEBALL FIELD (Bird s Eye View)

38 KALLISON RANCH HIGH SCHOOL Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor TBD Construction Cost - TBD Construction Period - TBD Project Scope New 2800 Student High School Design only project at this time.

39 KALLISON RANCH HIGH SCHOOL Schematic Design Site Plan

40 REDBIRD RANCH ELEMENTARY SCHOOL Architect NoonanRittimann Project Architect John Rittimann NISD Project Manager Thomas Curiel Contractor Joeris General Contractor Construction Budget - $20,000, Construction Period - TBD Project Scope New 800 Student Elementary School Departmental Reviews in progress.

41 REDBIRD RANCH ELEMENTARY SCHOOL Site Plan

42 REDBIRD RANCH ELEMENTARY SCHOOL Front Entrance Perspective

43 REDBIRD RANCH ELEMENTARY SCHOOL Floor Plan

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction December 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction September 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction March 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction May 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction July 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul

More information

Engineering Services

Engineering Services NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Engineering Services 2014 Bond March 2017 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Facilities Construction 2014 Bond March 2018 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2014 CITIZENS BOND ADVISORY COMMITTEE Facilities Construction 2014 Bond September 2018 Update Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

LLANO ISD SCHOOL BOARD MEETING. January 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016 LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS

More information

PROJECT UPDATE SEPTEMBER 11, 2014

PROJECT UPDATE SEPTEMBER 11, 2014 PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte ISD 2014 Bond Program ADMINISTRATION: Superintendent: Lloyd Graham Deputy Superintendent: Dr. Linda Wadleigh

More information

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. August 2016 Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Dat e: August 2018 March Update Lemm restoration contract awarded to ICI Construction on March 2nd Contractor began mobilization on March 5th

More information

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156 FOR SALE 8800 Miller Dr (SW 56 Street) Miami, FL 33156 Completely 12,820 SF 1.87 Acres Presented exclusively by Dimitri Kiosseff of Brown Harris Stevens BHSMiami.com NEW YORK CITY THE HAMPTONS PALM BEA

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

PROJECT UPDATE August 28, 2014

PROJECT UPDATE August 28, 2014 PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

a collaborative process

a collaborative process 2017 Referendum Belleville Public Schools July 26, 2017 a collaborative process Introduction Di Cara Rubino Architects Jerry Rubino, AIA Firm Principal Allen Barnett, AIA, LEED AP Senior Project Manager

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

Drexel Hill Middle School

Drexel Hill Middle School 150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel

More information

Southwest Health System Construction Newsletter October 7, 2017

Southwest Health System Construction Newsletter October 7, 2017 Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS:

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS: ADDENDUM NO. 1 CITY OF PORT ARANSAS ELLIS MEMORIAL EXISTING LIBRARY RENOVATIONS AND REPAIRS CSP #2016-22 700 W. AVE A PORT ARANSAS, TX 78373 Issue Date: 01/07/2019 The following additions, deletions, modifications,

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

Owen County School District

Owen County School District Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

PROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction

More information

2016 BOND INFORMATION

2016 BOND INFORMATION 2016 BOND INFORMATION This publication is provided as a public service by the offices of Operations and Maintenance, Communications and Financial Services. www.svvsd.org @svvsd 395 South Pratt Parkway,

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

Part I: Summary PHA Name/Number WV004 The Huntington WV Housing Authority

Part I: Summary PHA Name/Number WV004 The Huntington WV Housing Authority Part I: Summary PHA Name/Number WV004 The Huntington WV Housing Authority A. Development Number and Name Statement for Year 1 FFY 2013 Locality (City/County & State) Huntington, Cabell Co., West Virginia

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

Structural Condition Assessment

Structural Condition Assessment 108 6 th Street, Garland, Texas Engineering Report Date: September 29, 2016 RLG No. : 16729 Prepared for: Mr. Jeff D. Bulls III AIA 3030 LBJ Freeway, Suite 1220 Dallas, TX 75234 PM: Harold F. Phillips

More information

January 2017 Project Update

January 2017 Project Update January 2017 Project Update Overall Referendum Project Status: ON SCHEDULE/ON BUDGET All elements of the project completed to date have been completed on or ahead of schedule and final costs were under

More information

PRELIMINARY STRUCTURAL INVESTIGATION REPORT

PRELIMINARY STRUCTURAL INVESTIGATION REPORT 124 E. Broadway Tucson, AZ Prepared for: CBRE Brokerage Services 3719 N. Campbell Ave. Tucson, AZ 85719 BACKGROUND: The Tucson Veterans of Foreign Wars building, located at 124 E. Broadway, Tucson, AZ

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

N o v e m b e r

N o v e m b e r WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why

More information

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

Facilities Feasibility Study Frederick Douglass HS Condition Assessment Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies

More information

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan ATHLETIC FACILITIES High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan SWARTZ CREEK HIGH SCHOOL STADIUM 1 Dragon Drive, Swartz

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

Town of Enfield. Parks & Recreation P.O. Box 699 Enfield NC (252) telephone (252) fax

Town of Enfield. Parks & Recreation P.O. Box 699 Enfield NC (252) telephone (252) fax Town of Enfield Parks & Recreation P.O. Box 699 Enfield NC 27823 (252) 445-3146-telephone (252) 445-1019-fax www.enfieldnc.org Request for Proposals for the Renovation and/or Construction of the Recreation

More information

Fleet Elementary School

Fleet Elementary School Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

Auburn University Construction Project April

Auburn University Construction Project April Small Animal Teaching Hospital Phase I: Construction Cost: $8.8 million. Phase I consists of (1) constructing an addition to the Overton-Rudd Auditorium to expand classroom and lecture hall capacity, (2)

More information

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form. Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,

More information

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic

More information

August 2018 PROGRESS REPORT. Cobb County PARKS 2011 SPLOST Program

August 2018 PROGRESS REPORT. Cobb County PARKS 2011 SPLOST Program August 2018 Cobb County PARKS 2011 SPLOST Program September 11, 2018 Mr. Tom Bills Senior Project Manager, Construction Cobb County PARKS 1772 County Services Parkway Marietta, Ga.30008-4026 RE: 2011 PARKS

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

FACILITIES Summer Projects. September 8, 2015 Board Meeting

FACILITIES Summer Projects. September 8, 2015 Board Meeting FACILITIES 2015 Summer Projects September 8, 2015 Board Meeting On January 27, 2015 the Laguna Beach Unified School District Board of Education approved a 10-year facilities plan. The plan identified numerous

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

Fees and Permit requirements are regulated by the Township s Building By-law

Fees and Permit requirements are regulated by the Township s Building By-law Frequently Asked Questions This is a guide only and is intended to help you, the homeowner/builder, to better understand the steps to follow in obtaining a Building Permit; it is not a substitute for the

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community. SYLVAN MIDDLE SCHOOL The mission of Sylvan Middle School is consistent with that of the San Juan Unified School District, which is to inspire each student tosucceed and responsibly contribute to a radically

More information

Fleet Elementary School

Fleet Elementary School Fleet Elementary School Community Newsletter (August 2018) This is the August update on the status and progress of construction for the project. All monthly updates will also be posted to the project website

More information

Moonlight Architecture, Inc. Architecture Interior Design Site Planning

Moonlight Architecture, Inc. Architecture Interior Design Site Planning Moonlight Architecture, Inc. Architecture Interior Design Site Planning 22 May 2018 18057 Mr. Michael J. Petit de Mange, County Administrator Kent County Levy Court 555 Bay Road Dover, DE 19901 RE: Facilities

More information

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ WINNER 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016 Ivey Lane Elementary

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent 8353 University Boulevard, Moon Township, PA 15108 Thesis Proposal THIRD REVISION 3/19/2010 Table of Contents Executive

More information

Richard L. Johnson Associates, Inc. Architects Interior designers. ARCHITECT S FIELD REPORT No. 13

Richard L. Johnson Associates, Inc. Architects Interior designers. ARCHITECT S FIELD REPORT No. 13 Richard L. Johnson Associates, Inc. Architects Interior designers ARCHITECT S FIELD REPORT No. 13 Project: Addition and Renovation to Millikin Elementary School Architect s Project No.: 15-032 Date: 9-29-16

More information

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020

More information

PROJECT STATUS REPORT Collins Elementary School - Fire Alarm Upgrade Period Ending: 10/31/2012 Scope: Construction Status: Architect: AE3 Architects U

PROJECT STATUS REPORT Collins Elementary School - Fire Alarm Upgrade Period Ending: 10/31/2012 Scope: Construction Status: Architect: AE3 Architects U PROJECT STATUS REPORT Collins Elementary School - Fire Alarm Upgrade Period Ending: 10/31/2012 Scope: Construction Status: Architect: AE3 Architects Upgrade of Fire Alarm System in existing buildings Project

More information

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in historic Marigny

More information

Al Behrman Elementary School

Al Behrman Elementary School Mulberry Street Al Behrman Elementary School Relocate reception and principal s office to be adjacent to main entrance doors; provide secure entrance sequence and increase transparency to the exterior

More information

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information