Update on FCPS Construction/Renovation Projects. August 2016
|
|
- Scott Dorsey
- 5 years ago
- Views:
Transcription
1 Update on FCPS Construction/Renovation Projects
2 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (10): $289, Scheduled Contract Completion Date: July 2017 % of Contract Completed: 59.35% Revised Completion Date per GC: No Change
3 New High at Winchester Road Schematic Rendering of Final Façade
4 New High at Winchester Road Work Completed to Date: Curb/gutter continued with sections replaced. DGA started in SW parking lot. Site wall footings completed on west side and site concrete continued. Brick completed on Area D and bathroom & concessions buildings brick continues on Fieldhouse & dugouts. Steel joists & deck have been completed on the Fieldhouse. Steel at loading dock area has continued. Standing Seam roofing has started on Area C & the Aux. Gym. Air Barrier has continued at Fieldhouse. Metal wall panel & flashing has continued in Areas B & C. Window installation in Areas B & C has been completed. Drywall finishing continued in Area B. Terrazzo prep work has begun in Area C. Ceiling grid has started in Area C. Blockfill has continued in Area E3 & E4. First coat of finish paint is nearing completion in Area C. Bleacher installation has begun on the visitors side of the football field. Mechanical VAV installation was completed in Area C, duct pressure testing is underway in Area B, and plumbing & HVAC rough-ins continued in Areas A & E1-4. Plumbing rough-ins continued in Area D. Above-slab rough-ins and underground waterlines continued at Athletic Complex.
5 New High at Winchester Road Current Work Effort (August): Curb and gutter should be completed. DGA and base layer of asphalt will continue. Permanent water should be ready for use. Auditorium concrete floors will be completed. Site concrete will continue. Brick will continue on Fieldhouse & dugouts. All steel joist/deck will be completed on the Academic building. Air barrier will continue. Roofing will continue on Areas C & B. Roof dry-in will continue on Area E1. Metal wall panels will continue in Areas C & B. Clerestory windows at Gym & Area A windows will be completed. Drywall finishing will be completed in Area B & continue in Area E3. Ceiling Grid will be completed in Area C & begin in Area E4. Paint will start in Main Gym; first coat of finish paint will begin in Area E4. Terrazzo will continue on 2 nd floor of Area C. Bleachers will continue on visitors side and will begin on home side of the football field. Electrical wall rough-ins, overhead conduits, panel tubs, branch wire, main feeders & termination of panel boards will continue. Main electrical feed will begin from KU transformer pad (pending KU setting the transformer). Underground site conduits, lightning protection, voice/data and fire alarm & security cabling will continue. Athletic pole lighting will begin.
6 New High at Winchester Road Overall View from South Standing Seam Metal Roofing Clerestory Windows Science Pop-out Window
7 New High at Winchester Road Football Field w/ Visitor Bleachers Ceiling Grid Fieldhouse, Concessions & Restroom Buildings Aerial View
8 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (14): $275, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 97.7% Revised Completion Date per GC:
9 Squires Elementary -- Renovation Rendering of Final Façade
10 Squires Elementary -- Renovation Work Completed to Date: Paving, striping, and pavers installed/completed in the lower level parking lot (Phase 3). Cafeteria rubber floor tile installed (Phase 3). Kitchen equipment installed/inspected (Phase 3). Lower Level student and teacher restrooms complete (Phase 3). Stage has been painted and lighting installed (Phase 3). Current Work Effort (August): Complete Bus Drop-Off Canopy (Change Order 13). Complete terrazzo flooring and base (Phase 3). Complete Gym (Phase 3). Complete site work and landscaping (Phase 3). Complete roofing/trim outs (Phase 3).
11 Squires Elementary -- Renovation Lower Level Parking Lot Bus Drop-off Canopy Lower Level Curtain Wall Site Work for Playground
12 Squires Elementary -- Renovation Café Kitchen Terrazzo Corridor Computer Classroom
13 Coventry Oak Elementary Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (12): $51, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 99% Revised Completion Date per GC:
14 Coventry Oak Elementary Rendering of Final Façade
15 Coventry Oak Elementary Work Completed to Date: Mechanical, plumbing completed, electrical on-going. Landscaping installation on-going. Painting, VCT/rubber flooring, ceiling grid/pads, doors/hardware completed. Aluminum dock rail will complete. Test and Balancing will complete. Current Work Effort (August): Certificate of Occupancy issued 8/5/16. Work to complete punch list items.
16 Coventry Oak Elementary Site Clearing Front Entrance Lobby
17 Coventry Oak Elementary Gym Rear Lobby Media Ctr. Classroom
18 July 2009
19
20 Garrett Morgan Elementary Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (12): $132, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 100% Revised Completion Date per GC: No Change
21 Garrett Morgan Elementary Rendering of Final Façade
22 Garrett Morgan Elementary Work Completed to Date: Completed site work. Systems commissioning completed. Punch list items. Current Work Effort (August): Certificate of Occupancy issued 8/1/16. Work to complete punch list items.
23 Garrett Morgan Elementary Site Clearing Typical Classroom
24 Garrett Morgan Elementary Café Media Ctr. Gym Art Room
25
26
27 THANK YOU!!! External Partners Tate Hill Jacobs Architects JRA Architects Moody-Nolan Architects Clotfelter-Samokar Architects Griggs Enterprises, Inc. D.W. Wilburn, Inc. Facility Design & Construction Bill Wallace Lars Finneseth Lisa Clark Betsy Kallop
Update on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. September 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationCapital Projects Progress Report. January Presented by
Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428
More informationNew Ringgold Middle School. Project Slideshow August 26, 2017
New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More informationCollins Middle School
Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationMerritt Island High School
Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationFACILITY COMPONENTS - MIDDLE SCHOOL
SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls
More informationNorth Allegheny School District
North Allegheny School District January 18, 2017 Preparing all students for success in a changing world NAI was last renovated in 1997 Money was set aside during recent bond issue for renovations to occur
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationHeritage High School
Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery
More informationPRESENTATION JANUARY 24, 2017
4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationBoard Work Session Feasibility Study. January 9, 2017
Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Pate Elementary School Observed By: Creed/Carter Principal: Grade
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationCapital Projects Progress Report. September Presented by
Capital Projects Progress Report September 2018 Presented by October 5, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationWILKINSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationPROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationOwen County School District
Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #135 Douthit Hills Student Community, Clemson University Project Tony Greene
September 8, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Received Certificate of Occupancy for Bldgs E, F, & G. Completed Spreading Topsoil North of Building B. Completed Footings at Building
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationCONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More informationPROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationPROJECT STATUS REPORT De Anza High School - Baseball Field Improvements Period Ending: 8/19/2010 Scope: Baseball Field Improvements Construction Status: Architect: Vallier Design Associates & DLM Architects
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab
More informationYardmen Arena Expansion & Renovation Project Update
For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan
ATHLETIC FACILITIES High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan SWARTZ CREEK HIGH SCHOOL STADIUM 1 Dragon Drive, Swartz
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Cain Elementary School Observed By: Creed/Carter Principal: Grade
More informationBirmingham Public Schools
Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress
More informationSECTION ALTERNATES
SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationRevised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi
Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationLOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN
INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationPROJECT STATUS REPORT Coronado Elementary School - - Reconstruction Period Ending: 5/31/2015 Scope: Reconstruction Project Construction Status: Architect: WLC Architects Project Manager: Project Engineer:
More informationBARNARD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As
More informationMonthly Report #7 November 15 December 15, 2011
CENTENNIAL SCHOOL DISTRICT NEW REGION 1 ELEMENTARY SCHOOL Monthly Report #7 November 15 December 15, 2011 Page 1 of 42 New Region 1 Elementary Table of Contents Monthly Progress Report #7 November 15 December
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationNYC Department of Education
Asset: Building Assessment Survey 2017-2018 PRE-K CENTER @ 132-10 JAMAICA AVENUE - QUEENS, 132-10 JAMAICA AVENUE, New York, 11418 Inspection Id Inspection Type Time In Last Edited SA : Architectural -
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationNew Hall High School Project Summary Report to the Board of Education June 3, 2015
New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete
More informationCOOLIDGE SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationN o v e m b e r
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More information2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014
2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls
More informationCivic Center Renovation News
Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene
October 27, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Tie-in & Start-up of HUB Sanitary Lift Station. Completed Brick on Stair Walls West of Building C. Completed Pouring the
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationMOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS
MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade
More informationCATAMARAN TOWER - 1 Seef Area Plot 19, 20
STATUS REPORT NO 18 [As on September 30, 2017] This report is intended as a status report and covers only the activities completed till date, non-completed works and work-in-progress. A. Project Details
More informationProp S Update. August 07, BIDS BEING REVIEWED o RFP #: PS Fencing at Beaumont and Gateway High Schools
August 07, 2012 Prop S Update BIDS BEING REVIEWED o RFP #: PS71-1112 Fencing at Beaumont and Gateway High Schools OUT FOR BID o RFP #: PS61-1213 IP Clock District Wide Schools 08/17/2012 o RFP #: PS75-1213
More informationStanwood-Camano School District No SUMMER 2017 CAPITAL PROJECTS Status Report August 2017
Stanwood-Camano School District No. 401 SUMMER 2017 CAPITAL PROJECTS Status Report August 2017 CAPITAL PROJECTS MONTHLY REPORT AUGUST 2017 OVERALL FUND UPDATE: The FY 17-18 Capital Projects Fund budget
More informationMAURY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationSHEPHERD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE
More informationEASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923
INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationNYC Department of Education
Building Assessment Survey 2017-2018 Asset: SAINT FRANCIS COLLEGE - BROOKLYN, 180 REMSEN STREET, New York, 11201 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-02-05
More informationSTRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC
CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION
More informationUnity Office Building 400 Unity Street Latrobe, PA 15650
Unity Office Building 400 Unity Street Latrobe, PA 15650 1 2 3 4 Unity Industrial Commons 410 Unity Street Latrobe, PA 15650 5 Unity Industrial Commons Area Information Possibilities by Industry: Warehousing
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL
More informationDIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS
DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More information