1 ATHLETIC FACILITIES High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan

2 SWARTZ CREEK HIGH SCHOOL STADIUM 1 Dragon Drive, Swartz Creek Site Information / Condition: See site map included. - Site Entrance: Home fans enter from 1 Dragon Drive on the north side of the site. Visiting fans enter from west side of site from parking lot accessed from Cappy Lane. - Parking: Uses existing high school parking lots. - Asphalt Paved Sidewalks: Overall in fair condition. - Site Lighting: Two (2) headed poles located on the north edge of southwest parking lot. - Track: Newer six (6) lane granular rubber surfaced in good condition. Track and event areas should have additional granular rubber material added as needed. - Football Field: Natural grass field in good condition. Should consider re-crowning field in near future. - Home Seating 1600 (20 per seat): Pre-cast concrete risers on steel under structure. Center section of under structure is enclosed with CMU walls and is used for storage. Overall steel structure and pre-cast concrete risers are in good condition, however ramps to seating are not ADA compliant. Aluminum seats vary in widths and need maintenance and in some areas replaced. Also, all railings should be replaced. - Visitors Seating 1400 (20 per seat): Aluminum bleacher units are in poor condition. - Home Fan Entry Gate and Ticket Booths: Entry from Dragon Drive is very steep and is not ADA compliant. - Visitors Entry Gate and Ticket Booths: Small wood structure in fair condition. - Concessions Building: Masonry building with asphalt shingle roof in fair condition. Restroom Building: Masonry building with asphalt shingle roof in fair condition. Restrooms are not ADA compliant. - Landscaping: Generally consists of lawn. Swartz Creek Community Schools - Facility Study Swartz Creek High School Stadium - Page 1

3 Code Deficiencies: - Home entry point/gate not ADA compliant. Grade is too steep. - Ramps to home seating are not ADA compliant. - Restrooms are not ADA compliant. Suggested Facility Upgrades: - Renovate and convert home seating to visitor seating. Renovate press box for visiting team. - Replace visitor seating with new grandstands with new press box for home seating. - Construct new ticket entry gate for new home grandstands. - Construct new concessions, restrooms and team rooms. - Construct retaining wall and flag platform at north end of field. - Expand track to 8 lanes from current 6 lanes. - Install artificial turf on football field. - Replace all fencing with new. Swartz Creek Community Schools - Facility Study Swartz Creek High School Stadium - Page 2

4 CAGE FIELDHOUSE 4110 Morrish Road, Swartz Creek General Information: - Year Built: Building Size: 41,600 square feet - Site Size: 7 acres - Utilities: o Natural Gas: Consumers Energy o Electricity: Consumers Energy o Water: City of Swartz Creek o Sanitary: City of Swartz Creek Site Information / Condition: See site map included. - Site Entrance: Enter from Morrish Road. - Parking: 250 spaces. Parking lot surrounds building on all sides. - Asphalt Pavement: All areas need to be resurfaced. Area in front of dumpster should be removed and replaced with deep strength asphalt pavement or concrete paving. - Concrete Sidewalks: Overall in very good condition. Minor replacement is required at the main entry. Building Information: - Number of Stories: One. - Construction Type: Pre-engineered building with masonry walls to 8 feet and metal wall panels above. - Buildings Condition: Exterior and interior condition of building is in very good condition. Ceramic tile flooring in restrooms has unbounded from substrate and needs to be replaced. Swartz Creek Community Schools - Facility Study Swartz Creek High School Stadium - Page 3

5 Code Deficiencies: - None were observed. Suggested Facility Upgrades: - Replace restroom ceramic tile flooring. - Install removable mullion between doors at main entry. - Construct storage room addition. Swartz Creek Community Schools - Facility Study Swartz Creek High School Stadium - Page 4

6 HIGH SCHOOL FOOTBALL STADIUM Proposed Site Work: Quantity of Work: Estimate of Cost: New Home Bleachers / Pressbox 1500 seats $ 533, Renovate Existing Bleachers / Pressbox Lump Sum $ 187, for Visitors New Concrete Walks / Plaza 5900 sq feet $ 41, Replace Existing Asphalt Walks with 6200 sq feet $ 62, Concrete Expand Track to 8 Lanes Lump Sum $ 325, Install Artificial Turf on Football Field Lump Sum $ 740, New Goal Posts with Padding Lump Sum $ 8, Replace Football Field Lighting 4 poles $ 130, New 4 ft Fencing Around Football Field 1248 linear feet $ 24, New 8 ft Perimeter Fencing 1000 linear feet $ 30, New Electronic Scoreboard Lump Sum $ 12, Unit Block Retaining Wall 340 linear feet $ 102, New Flagpoles with Ground Lighting 3 poles $ 10, Total Opinion of Probable Cost of Site Work: $2,207, Proposed Building Renovation Work: Quantity of Work: Estimate of Cost: Upgrade Existing Concessions Building 860 sq feet $ 43, Upgrade Visitor s Entry / Ticket Booth $ 48, Total Opinion of Probable Cost of Building Renovation Work: $ 91, Proposed Building Construction: Quantity of Work: Estimate of Cost: New Home Ticket Booth, Concessions and Restroom Building 2400 sq feet (12 men/24 women) $ 475, Home and Visitor Team Room Building 1735 sq feet $ 358, Total Opinion of Probable Cost of Building Additions: $ 834, Swartz Creek Community Schools - Facility Study Athletic Facilities - Page 5

7 CAGE FIELDHOUSE Proposed Site Work: Quantity of Work: Estimate of Cost: Resurface Parking Lot 100,000 sq feet $ 135, Total Opinion of Probable Cost of Site Work: $ 135, Proposed Building Additions: Quantity of Work: Estimate of Cost: Storage Room 600 sq feet $ 54, Add Removable Mullions on Front Doors 2 units $ 1, Total Opinion of Probable Cost of Building Additions: $ 55, Swartz Creek Community Schools - Facility Study Athletic Facilities - Page 6

8

9

10 CAGE FIELDHOUSE ROOF CONDITION REPORT

11

12

Schematic Design Report Johnson City ISD Football Stadium

Schematic Design Report Johnson City ISD Football Stadium Schematic Design Report Johnson City ISD Football Stadium March 30, 2015 Fromberg Associates, Ltd :: Architecture 2406 Lake Austin Blvd. Austin, Texas 78703 512.495.9171 Issued under the authority of Randall

More information

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

CONTRACT ADDENDUM # 1

CONTRACT ADDENDUM # 1 date: January 5, 09 project: Bear River Bleachers CONTRACT ADDENDUM # by: Design West Architects subject: Revisions The Work shall be carried out in accordance with the following supplemental instructions

More information

Assessment Report Burgess Park Gymnasium. Summary

Assessment Report Burgess Park Gymnasium. Summary Assessment Report Burgess Park Gymnasium Summary The existing Burgess Park Gymnasium is an approximately 17,460 gross square feet singlestory structure built of concrete, wood and steel. The building,

More information

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely

More information

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156 FOR SALE 8800 Miller Dr (SW 56 Street) Miami, FL 33156 Completely 12,820 SF 1.87 Acres Presented exclusively by Dimitri Kiosseff of Brown Harris Stevens BHSMiami.com NEW YORK CITY THE HAMPTONS PALM BEA

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District ATHLETIC FACILITY CAMPUS DATA ATHLETIC FACILITY 22628 Hwy 105 West, Montgomery TX 77356 1 MASTER PLAN 2 CIVIL - SITE General Existing Conditions and Deficiencies Overall concrete site paving: Good Overall

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014

HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014 HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014 1. Upgrade Video Security and Surveillance Systems - Replace with New a. Existing

More information

Capital Project Recommendations Presented to the Board of Education 9/23/2014

Capital Project Recommendations Presented to the Board of Education 9/23/2014 Capital Project Recommendations Presented to the Board of Education 9/23/2014 The administration has been working to identify a division of the proposed $15M in capital projects between the athletic field

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Civic Center Renovation News

Civic Center Renovation News Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented

More information

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Herricks Union Free School District Capital Improvements Bond Update. August 31, 2017

Herricks Union Free School District Capital Improvements Bond Update. August 31, 2017 Herricks Union Free School District 2016 Capital Improvements Bond Update August 31, 2017 Timeline to Date December 6, 2016 December, 2016 January, 2017 Successful Bond Referendum Vote BBS conducts field

More information

Appendix VI-A-3 Infrastructure Inventory

Appendix VI-A-3 Infrastructure Inventory Pennsylvania State System of Higher Education Facilities Manual Appendix VI-A-3 Infrastructure Inventory Form Format and Definitions Figure Column Headings Infrastructure means the communications, utility,

More information

Council Rock School District. Scope of repairs and ADA improvements Per request of Facilities Committee

Council Rock School District. Scope of repairs and ADA improvements Per request of Facilities Committee Scope of repairs and ADA improvements Per request of Facilities Committee 3-22-12 COUNCIL ROCK HIGH SCHOOL NORTH Walt Snyder Stadium Repairs 03.23.12 Thanks to the Schradergroup for use of the base PowerPoint

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

Central Washington University Board of Trustees Work Session November 2, ) EXECUTIVE SUMMARY - Tomlinson Stadium Upgrades

Central Washington University Board of Trustees Work Session November 2, ) EXECUTIVE SUMMARY - Tomlinson Stadium Upgrades Central Washington University Board of Trustees Work Session November 2, 2017 1.) EXECUTIVE SUMMARY - Tomlinson Stadium Upgrades Tomlinson Stadium, constructed in 1959, is the home of the Wildcat Football

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: FRANCIS LEWIS AF - QUEENS, 58-20 UTOPIA PKWY, New York, 11365 Inspection Id Inspection Type Time In Last Edited SA : Architectural -

More information

Amos Alonzo Stagg Elementary School 7424 S Morgan St Chicago, IL 60621

Amos Alonzo Stagg Elementary School 7424 S Morgan St Chicago, IL 60621 2 S Morgan St Chicago, IL 21 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Construction Project Project Project Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Arlington High School 8,752,608 12,545,469 Building Additions 5,975,000 8,695,418 12.4% 9,773,649 1,198,608

More information

Stephen Decatur Classical Elementary School 7030 N Sacramento Ave Chicago, IL 60645

Stephen Decatur Classical Elementary School 7030 N Sacramento Ave Chicago, IL 60645 030 Sacramento Ave Chicago, IL 04 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

Public and Institutional Development

Public and Institutional Development Public and Institutional Development Facts to Know INTRODUCTION: In the City of Commerce City, there is one Public zone district, as follows: PUBLIC: Public Zone District Each zone district in Commerce

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Report on Campus Construction Projects

Report on Campus Construction Projects Report on Campus Construction Projects May 8, 2015 Facilities Planning & Construction SUNY Geneseo Facilities Planning & Construction is pleased to present our summer construction report which details

More information

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 WORK LEGEND OVERALL WORK TO BOTH BUILDINGS 1 2 3 4 Existing corridors will receive new

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade

More information

Request for Proposal Design Build Services Kiel High School Athletic Field Improvements

Request for Proposal Design Build Services Kiel High School Athletic Field Improvements Request for Proposal Design Build Services Kiel High School Athletic Field Improvements I. General The Kiel Area School District is accepting written proposals from qualified firms to provide Design build

More information

CITY OF ELKO BID TABULATION FOR Sports Complex

CITY OF ELKO BID TABULATION FOR Sports Complex CITY OF ELKO BID TABULATION FOR Sports Complex 2017-2018 NAME Granite Construction Great Basin Engineering Contractors Road & Highway Builders CLEARING EARTHWORK 1 33701200 Mobilization @ Per Lump Sum

More information

Z SYSTEMS CORPORATION 4902 Roy J Smith Drive Killeen, TX 76543

Z SYSTEMS CORPORATION 4902 Roy J Smith Drive Killeen, TX 76543 Z SYSTEMS CORPORATION 4902 Roy J Smith Drive Killeen, TX 76543 1 Warehouse Facility Layout 4 Size and Capacity Z Systems Killeen, TX Warehouse has expansion capacity 15 Acre Rail load / commercial truck

More information

Velma F Thomas Early Childhood Center

Velma F Thomas Early Childhood Center Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

NYC Department of Education

NYC Department of Education Building Assessment Survey 2017-2018 Asset: SAINT FRANCIS COLLEGE - BROOKLYN, 180 REMSEN STREET, New York, 11201 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-02-05

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Yardmen Arena Expansion & Renovation Project Update

Yardmen Arena Expansion & Renovation Project Update For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 42 - MANHATTAN, 71 HESTER STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior

More information

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY DATE: November 20, 2012 SDSU requests approval of this Facility Design Plan to continue planning the

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

2. House Designs. SAL Review

2. House Designs. SAL Review 2. House Designs 1 Roof has a minimum of 6:12 pitch 2 Minimum roof overhang is 2 feet 3 Roof design must incorporate dormers or gables to the 4 Long slopes of unbroken roof line will not be accepted 5

More information

PROFESSIONAL OFFICE SUITES FOR LEASE PRIYA PROFESSIONAL OFFICE CENTRE 122 CANAL STREET POOLER, CHATHAM COUNTY, GEORGIA 31322

PROFESSIONAL OFFICE SUITES FOR LEASE PRIYA PROFESSIONAL OFFICE CENTRE 122 CANAL STREET POOLER, CHATHAM COUNTY, GEORGIA 31322 PROFESSIONAL OFFICE SUITES FOR LEASE PRIYA PROFESSIONAL OFFICE CENTRE 122 CANAL STREET POOLER, CHATHAM COUNTY, GEORGIA 31322 PRESENTED BY WHITLEY AND ASSOCIATES, INC. 800 COMMERCIAL COURT, SUITE TWO SAVANNAH,

More information

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) S Pioneer

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) S Pioneer 1065 N Canyon St, Ste. 8, Hildale, UT 84784-0283 Cell: (435) 819-0128 125 S Pioneer 1065 N Canyon St, Ste. 8, Hildale, UT 84784-0283 Cell: (435) 819-0128 CRITICAL IMPROVEMENTS Framing Demo Tin Fence Exterior

More information

Commercial Development

Commercial Development Commercial Development Facts to Know INTRODUCTION: In the City of Commerce City, there are three commercial zone districts. They are as follows: C-1: Local Commercial District C-2: General Commercial District

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information

National Property Inspections

National Property Inspections National Property Inspections Anywhere, USA (325) 382-8754 Property Location 9375 Burt Street Anywhere USA Prepared for John Investor Consultant Al Standard (325) 382-8754 Page 1 of 27 TABLE OF CONTENTS

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: I.S. 364 AX (POOL&GYM)-BROOKLYN, 1540 VAN SICLEN AVE, New York, 11239 Inspection Id Inspection Type Time In Last Edited SA : Architectural

More information

Frederic Chopin Elementary School

Frederic Chopin Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls

More information

SHEPHERD ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Entellus 75 NORTH STREET MERRILL SHERIFF CONSTRUCTION. 181 North 200 West, Suite #4. Bountiful, UT Phone

Entellus 75 NORTH STREET MERRILL SHERIFF CONSTRUCTION. 181 North 200 West, Suite #4. Bountiful, UT Phone Entllus DUMPSTER PAD AND REPLACE WITH NEW BETWEEN THESE TWO POINTS SAWCUT ALONG DEMO LINE REMOVE PARKING SPOTS CURB, GUTTER, ASPHALT AND LANDSCAPING, WITHIN HATCHED AREA FOR NEW ADDITION CURB & GUTTER

More information

WIBLE BARBER Architects

WIBLE BARBER Architects WIBLE BARBER Architects Billingsley School Bleacher Replacement 2246 County Road 77 / Billingsley, Alabama 36006 BC PROJECT NO: 2017499 WBA PROJECT NO: 170901 ADDENDUM NO. 2 GENERAL: November 28, 2017

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

N o v e m b e r

N o v e m b e r WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. August 2016 Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:

More information

James E McDade Elementary Classical School 8801 S Indiana Ave Chicago, IL 60619

James E McDade Elementary Classical School 8801 S Indiana Ave Chicago, IL 60619 880 S Indiana Ave Chicago, IL 09 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: BOYS & GIRLS AF - BROOKLYN, 1700 FULTON STREET, New York, 11213 Inspection Id Inspection Type Time In Last Edited SA : Architectural

More information

Commercial Tax Abatement

Commercial Tax Abatement A confirmation letter is issued by the City upon receipt of this application. This application is not effective and not considered filed until the confirmation letter has been issued. Filing does not assure

More information

Field House Proposal

Field House Proposal Field House Proposal For Experienced Dependable Resourceful 5802 Akron Cleveland Rd. Hudson, OH 44236 Table Of Contents Cost Projection 3 Funding Summary 4 Site Plan 5 Field House Layout 6 Field House

More information

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1 GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept

More information

State College Area School District Memorial Field Phase 2 Update

State College Area School District Memorial Field Phase 2 Update State College Area School District Memorial Field Phase 2 Update The State College Area School District Is continuing renovations to its primary outdoor sporting venue, known as Memorial Field. The Design

More information

AVAILABLE FOR LEASE OR SALE

AVAILABLE FOR LEASE OR SALE AVAILABLE FOR LEASE OR SALE CLASS A OFFICE/WAREHOUSE 13124 TRINITY DRIVE, STAFFORD, TX 77477 +/- 78,465 SF YOUR SIGN HERE FOR ADDITIONAL INFORMATION, PLEASECONTACT: David Husid Director 713.599.5149 DHusid@ngkf.com

More information

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

NEW TO MARKET +/- 78,465 SF CLASS A OFFICE/WAREHOUSE TRINITY DRIVE, STAFFORD, TX YOUR SIGN HERE

NEW TO MARKET +/- 78,465 SF CLASS A OFFICE/WAREHOUSE TRINITY DRIVE, STAFFORD, TX YOUR SIGN HERE NEW TO MARKET CLASS A OFFICE/WAREHOUSE 13124 TRINITY DRIVE, STAFFORD, TX 77477 +/- 78,465 SF YOUR SIGN HERE FOR ADDITIONAL INFORMATION, PLEASECONTACT: David Husid Director 713.599.5149 DHusid@ngkf.com

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

Facilities Condition Assessment Qualcomm Stadium

Facilities Condition Assessment Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment Qualcomm Stadium Facilities Condition Assessment AECOM San Diego, California April 2011 Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment

More information

CITY OF NOVI. Police Department

CITY OF NOVI. Police Department CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master

More information

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for

More information

Crown Mountain Park Reserve Study Update

Crown Mountain Park Reserve Study Update Reserve Study Update Reserve Study Update Project No. 16033 Prepared for Crown Mountain Park El Jebel, Colorado Prepared by PO Box 3890 Parker, Colorado 80134 October 28, 2016 TABLE OF CONTENTS Crown Mountain

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

Maps are enclosed of the larger areas to be included in the projects. The area in yellow are the proposed areas.

Maps are enclosed of the larger areas to be included in the projects. The area in yellow are the proposed areas. January 20, 2015 Contractor: The Park Hill School District is soliciting bids for asphalt and concrete repairs and additions for parking lots, curbs and sidewalks at various schools. A Mandatory Pre-Bid

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

NYC Department of Education

NYC Department of Education Building Assessment Survey 2017-2018 Asset: P.S. 65 - BROOKLYN, 158 RICHMOND STREET, New York, 11208 Inspection Id Inspection Type Time In Last Edited Architectural - Senior 2018-05-15 11:22 AM 2018-06-12

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive

More information

Mystic Shores Property Owners Association Unit 7 DCCR/Supplement and Design Guidelines Requirements

Mystic Shores Property Owners Association Unit 7 DCCR/Supplement and Design Guidelines Requirements Mystic Shores Property Owners Association Unit 7 DCCR/Supplement and Design Guidelines Requirements Note: This checklist is for the convenience of the Mystic Shores Architectural Control Committee. In

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

HIDDEN VALLEY ELEMENTARY SCHOOL

HIDDEN VALLEY ELEMENTARY SCHOOL SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Asset: NEW DORP AF (NEW)-STATEN ISLAND, 465 NEW DORP LANE, New York, 10306 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-04-11 11:11 AM 2018-04-18

More information

NYC Department of Education

NYC Department of Education NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 81 ANNEX (OLD 75) - QUEENS, 511 SENECA AVENUE, New York, 11385 Inspection Id Inspection Type Time In

More information

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies

More information