MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13

Size: px
Start display at page:

Download "MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13"

Transcription

1 PROPOSITION R PROGRAM UPDATE MONTHLY EXECUTIVE UPDATE MARCH 21,

2 CENTRAL PLANT BOILERS--- COMPRESSORS--- CONDENSERS--- PIPING--- COMMISSIONING PREPARATIONS 2

3 Central Plant Accomplished in March: Condenser and the boiler room piping are nearing completion Electrical panel work and control systems testing in progress Initial Commissioning and Plant Start-up meeting held Planned for April: Receive Engineers options and recommendations for plant Start-up, commissioning, and operation Complete piping and insulation. Rollup door delivery Selected equipment testing 3

4 FIELD HOUSE CLASSROOM BUILDING NAIL WALL 8TH AND 9TH LIFTS--- DEWATERING--- PERMANENT GRAVITY CANYON DRAIN 4

5 Field House Classroom Building Accomplished in March: Complete 7th lift of nail wall and started final 8th and 9th lift Temporary drainage system operating as designed Planned for April: Begin work on collection system for Permanent canyon gravity drain Plan for additional geotechnical exploration and investigation as part of infrastructure planning and assessment...seeking cause Hydrologist / Civil Engineer / Geologist / Infrastructure Master Plan 5

6 DEVORE STADIUM OUTER BUILDINGS TICKET BOOTH--- CURBS AND GUTTERS--- FENCING--- BUILDING FINISHES 6

7 DeVore Stadium Outer Buildings Accomplished in March: Grading and preparations for concrete and Asphalt work Fencing and curbing work started Preparations for epoxy floor work Removed Musco stadium lighting poles Planned for April Complete epoxy flooring and Stainless counters installation Drill foundations for Musco poles Start electrical and other building finishes 7

8 PRACTICE FIELDS PUNCH LIST PROCESS UNDERWAY--- QUOTES FOR FENCING AND GATES 8

9 Practice Fields Accomplished in March: Artificial turf installation complete Punch list inspection completed Planned for April: Start fencing and Gates added to make the field containment secure and contiguous Approx. 380 feet of additional 5ft chain link fencing and gates Complete work on Punch list items 9

10 PARKING LOT O AND BIO SWALE DSA REVIEW APRIL 11---ENTRANCE /ACCESS IMPROVEMENTS---SWPPP COMPLIANCE 10

11 Parking Lot O Bio-Swale Accomplished in March: Design complete. Storm-Water compliance item DSA review appointment: April 11 Planned for April: Validate Parking Lot O requirements in new master plan Prepare RFP for summer 2013 construction 11

12 Other Projects and Initiatives Accomplished in March: Pilot project for Blue Emergency Phones started Lot A and Safety Office SWC had booth at CMAA owners night in February Information about building program and the developing facilities master plan provided to interested contractors/designers/and vendors. Planned for April Facilities Master plan review. Start RFP process for project design 12

13 Project Schedule # Corner Lot ON-HOLD-1-REPLANNING-PENDING-MASTER-PLAN-FINALIZATION Central Plant Field House, Fields Project Name # 729 Landscaping and Entry COMPLETE 8 TBD Techonology Project ON-HOLD-1-REPLANNING-PENDING-MASTER-PLAN-FINALIZATION 9 TBD Emergency Blue-Lights ON-HOLD-1-REPLANNING-PENDING-MASTER-PLAN-FINALIZATION National City New 2-Story Facility ON-HOLD-1-REPLANNING-PENDING-MASTER-PLAN-FINALIZATION Ph 1 - Equipment for Buildings !!!!!!!LEGEND Planning Design DSA Review Bid / Award Construction / Close-out Separate Procurement / Install Southwestern!College Proposition!R!00!Breakdown!of!Phase!1!"NEW!LOOK" Data-Date-1-3/18/

14 Risk Summary Proposition R RISK ANALYSIS Revision Date: March 2013 NBR ITEM ASSESSMENT POSSIBLE IMPACT MITIGATION PLAN Original Prior Current (Cost and/or Schedule) Growth in construction program Recommend adjustments in construction program scope as new forecast to complete from "Scope priorities are identified. Executive team review and 1 M M Increase in forecasted cost to complete. Creep" during the design and Superintendent approval required for increases to original construction phase. project budgets. 2 Construction material increases L L 3 Community relations. Impacts resulting from the start of the construction program--avoid surprises. M M 4 Project Budgets H M Increase in forecasted cost to complete (steel, fuel, asphalt, concrete, ) Possible re-work of designs and /or construction schedules. Facilites Master Plan phasing schedule, forecasts to complete, revenue/bond sale plan Continue to monitor the market Include annual escalation in master plan project estimates. Continue aggressive construction schedule Continue proactive communications via the local media. Include executive team in planning, design and phasing decisions. Set baseline project budgets from the master plan. Include all project costs (soft, hard, infrastructure, IT, FFE) in project budgets. Ensure annual escalation included 5 As-Built information and building assessments including Infrastructure location and assessment. M M Cost impact: Increase in project forecasts to complete Incorporate lessons learned from current projects. Include adequate allowances in construction contracts. Complete Infrastructure location and assessment project as part of master plan programming and planning. Building focus on mechanical electrical, plumbing, and building envelope (roof, windows doors) 6 DeVore Stadium ground water impacts H M Cost and Schedule impacts 7 8 Central Plant commissioning and completion without the planned utility loading from the original corner lot plan. Campus Information technology nework and communciations master plan H H M H Possible damage to chillers and equipment. Increases in cost to preventative maintenance plan and operating costs. Very costly to chase "most current" technology project by project. Possible rework as building program moves forward. Risk Status: H=high M=medium L=low Temporary drainage installed. Canyon gavity drain system designed and under construction. Engineers to provide additional waterproofing/membrane recommendations at building wall and foundation/floor systems. (70 yr building). Continue efforts to identify cause/source of water. Part of wet utility assessment planning. In discussion with engineers and equipment provider Some loading possible on the installed energy loop, but is it enough to prevent damage from equipment cycling. Engineers preparing report with options. Commissionoing date linked to completion of field house building, providing sufficient load to test equipment. Perform a communications and IT data/network structure assessment with recommendations for system equipment location and hard wired network plan. Include in infrastructure master planning.utility layering where possilbe. 15

15 PROPOSITION R PROGRAM UPDATE MONTHLY EXECUTIVE UPDATE MARCH 21,

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Port KC RFP NORTHLAND PARK BUILDING V

Port KC RFP NORTHLAND PARK BUILDING V Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018. Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan ATHLETIC FACILITIES High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan SWARTZ CREEK HIGH SCHOOL STADIUM 1 Dragon Drive, Swartz

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803

More information

Auburn University Construction Project Update June 2010

Auburn University Construction Project Update June 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,

More information

Capital Projects Progress Report. January Presented by

Capital Projects Progress Report. January Presented by Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

10 Year Plan. Facilities Planning Guide. December 15, 2014

10 Year Plan. Facilities Planning Guide. December 15, 2014 10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)

More information

SAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub

SAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub SAMPLE WORK PLAN You have just been awarded a $500,000 construction contract as a prime bidder. You will perform 60% of the work in-house (including your suppliers) and 40% will be performed by 3 different

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

Accessory Building/Detached Building Permit

Accessory Building/Detached Building Permit Accessory Building/Detached Building Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

PROPOSITION R Citizen s Bond Oversight Committee

PROPOSITION R Citizen s Bond Oversight Committee PROPOSITION R Citizen s Bond Oversight Committee June 15, 2011 Southwestern Community College District 900 Otay Lakes Road, Room L246 Chula Vista, CA 91910 Proposition R AGENDA 1. Call to Order / Roll

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018 FACILITIES COMMITTEE MEETING APRIL 17, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure Johnson Student Center Johnson Demolition Science Center & Building J Demolition

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Projects Upgrades in Multipurpose Building 1300 In order to meet the needs of the building s three distinct uses administrative gatherings, recreational program space, and as a general venue and event

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications During the review of the application materials submitted with the Bishop Place Economic Hardship

More information

University of New Mexico Environmental Services Design & Development Standard Requirements

University of New Mexico Environmental Services Design & Development Standard Requirements University of New Mexico Environmental Services Design & Development Standard Requirements Please review the following standards to be considered on all construction specifications. Your consideration

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

Project Information Session / Meet and Greet # 3

Project Information Session / Meet and Greet # 3 ATL WEST DECK COMPONENT Project Information Session / Meet and Greet # 3 Holder-Austin-Moody-Bryson, a Joint Venture October 10 th, 2017 Agenda 1. HAMB, a JV Company Overview 2. ATL West Deck Project Description

More information

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017 Facilities Maintenance & Operations Update Presidents Executive Cabinet March 6, 2017 1 Update Proposition 39 Year 4: March 6 March 31 Will complete all exterior lighting upgrades to LED Aquatic Center

More information

Capital Projects Progress Report. September Presented by

Capital Projects Progress Report. September Presented by Capital Projects Progress Report September 2018 Presented by October 5, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York

More information

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER Denis Creedon, B.E., MIEI. CONSULTING ENGINEER PROPERTY INSPECTION REPORT PROPERTY: CLIENT: DATE: Denis Creedon, B.E., MIEI, CONSULTING ENGINEER Tel: 02221157, 0868072327 N0.6 Chapel Lane, Mallow, Co.

More information

Request for Proposals: New Hangar Building Project, Port of St. Helens Scappoose Industrial Airpark

Request for Proposals: New Hangar Building Project, Port of St. Helens Scappoose Industrial Airpark Request for Proposals: New Hangar Building Project, Port of St. Helens Scappoose Industrial Airpark Columbia City, Oregon December 2017 Purpose The Port of St. Helens, a municipal corporation and port

More information

NEW NORWOOD HIGH SCHOOL

NEW NORWOOD HIGH SCHOOL TOWN OF NORWOOD NEW NORWOOD HIGH SCHOOL MONTHLY PROGRESS REPORT MARCH 2010 Prepared by: 266 Main Street Suite 31A Medfield, MA 02052 www.compasspminc.com Table of Contents: I. Executive Summary II. III.

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks Site Bldg Fiscal Yr System Sub-System Site site 2014/15 Parking Paving Site site 2014/15 Sidewalks Skill Center L 2015/16 Architectural Partitions Site Site 2015/16 Parking Striping Arc Center M 2014/15

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Boynton High School & Blackford Site

Boynton High School & Blackford Site Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

Application for Commercial Plan Review and Building Permit. Address:

Application for Commercial Plan Review and Building Permit. Address: City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial

More information

ADDENDUM #4 FOR THE WEST VALLEY FACILITIES INCREMENT 2 REPLACEMENT PROJECT WEST VALLEY COLLEGE

ADDENDUM #4 FOR THE WEST VALLEY FACILITIES INCREMENT 2 REPLACEMENT PROJECT WEST VALLEY COLLEGE ADDENDUM #4 FOR THE WEST VALLEY FACILITIES INCREMENT 2 REPLACEMENT PROJECT AT WEST VALLEY COLLEGE Owner West Valley-Mission Community College District Saratoga, California Bid #01-1516 12-22-15 WEST VALLEY-MISSION

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

CONTRACT ADDENDUM # 1

CONTRACT ADDENDUM # 1 date: January 5, 09 project: Bear River Bleachers CONTRACT ADDENDUM # by: Design West Architects subject: Revisions The Work shall be carried out in accordance with the following supplemental instructions

More information

SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut

SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut SUFFIELD PUBLIC SCHOOLS Suffield, Connecticut DATE: January 30, 2018 TO: FROM: RE: Karen Berasi Bill Hoff Board Approval of Final Spaulding Roof Cost Estimates and Plans The Board of Education approved

More information

Current Construction Projects in Progress. Thru January 31, 2016

Current Construction Projects in Progress. Thru January 31, 2016 Current Construction Projects in Progress Thru January 31, 2016 Orange Ave Pump Station Improvements Before After Project consist of the removal of the existing pumps, housing and piping. Remove and replace

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies

More information

SMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT

SMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT ADDENDUM 01 SMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT 06/08/2017 DSA NO. A03-117787/File No.19-96 Prepared By DLR Group Project No. 75-07256-24 SECTION 00 91 00 GENERAL ADDENDUM 01 1.01 The following

More information

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY DATE: November 20, 2012 SDSU requests approval of this Facility Design Plan to continue planning the

More information

PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS

PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS Urban infill on a previously developed site. The new building was built over an existing parking lot. Landscaping is composed of all native plants

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

DIVISION PARKING STRUCTURES

DIVISION PARKING STRUCTURES DIVISION 13 00 40 PARKING STRUCTURES 1. Design Requirements 1.1. A parking design professional must be used to provide the functional and structural design of the facility. 1.2. A traffic analysis is required

More information

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Construction Project Project Project Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Arlington High School 8,752,608 12,545,469 Building Additions 5,975,000 8,695,418 12.4% 9,773,649 1,198,608

More information

New Raised Courtyard Terrace Pavers and Retaining Walls. Line of Steps Above. New Wood Framed Stair

New Raised Courtyard Terrace Pavers and Retaining Walls. Line of Steps Above. New Wood Framed Stair Building Program Wall Construction to Remain Religious Education New Wall Construction New Furring on Wall Construction, See Partition Types, Community Room New Galvanized Steel Window Well Patch Wall

More information

ADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:

ADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows: DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION 00 91 11.02 ADDENDUM NUMBER TWO June 22, 2016 TO: PLANHOLDERS SUBJECT: PCT TRUCK STAGING PROJECT PROJECT NO. 091606 CONTRACT NO. 070287 This

More information

ADDENDUM # 3 DATE: February 16, 2018

ADDENDUM # 3 DATE: February 16, 2018 ADDENDUM # 3 DATE: February 16, 2018 REFERENCE: Invitation for Bid No.: S-LB-18607 IFB Issue Date: January 25, 2018 Title: Stonewall Middle School Addition and Renovations Architect/Engineer: Architecture

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

REHABILITATION STANDARDS CHECKLIST

REHABILITATION STANDARDS CHECKLIST Project Name Date Built Date Last Rehabilitated (If applicable) EXTERIORS REHABILITATION STANDARDS CHECKLIST ROOF Age (Yrs) Poor Fair Good Excellent Roof /Pitch/Flat # of Layers Substrate Material Insulation

More information

Scope of Work Bid Package C-4 - West Polished Concrete

Scope of Work Bid Package C-4 - West Polished Concrete Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

CITY OF ELKO BID TABULATION FOR Sports Complex

CITY OF ELKO BID TABULATION FOR Sports Complex CITY OF ELKO BID TABULATION FOR Sports Complex 2017-2018 NAME Granite Construction Great Basin Engineering Contractors Road & Highway Builders CLEARING EARTHWORK 1 33701200 Mobilization @ Per Lump Sum

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

City of North Mankato 1001 Belgrade Avenue North Mankato, MN (507)

City of North Mankato 1001 Belgrade Avenue North Mankato, MN (507) City of North Mankato 1001 Belgrade Avenue North Mankato, MN 56003 (507) 625-4141 BUILDING PERMIT GUIDELINES Building Permits are required for all improvements with a value** of $300.00 or more. Sheds,

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

FACILITIES Summer Projects. September 8, 2015 Board Meeting

FACILITIES Summer Projects. September 8, 2015 Board Meeting FACILITIES 2015 Summer Projects September 8, 2015 Board Meeting On January 27, 2015 the Laguna Beach Unified School District Board of Education approved a 10-year facilities plan. The plan identified numerous

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 PROJECT: 300 Seneca New Academic Campus DATE: September 23, 2013 300 Seneca Ave., S.F.,

More information

Lincoln Akerman School Hampton Falls, NH

Lincoln Akerman School Hampton Falls, NH Lincoln Akerman School for Proposed Gym Addition September 29, 2016 The following list of items is intended to assist you in understanding any assumptions that have been made in the preparation of the

More information

Portsmouth Middle School Additional Funding Request

Portsmouth Middle School Additional Funding Request City Council Work Session Portsmouth Middle School Additional Funding Request Monday March 18, 2013 Project Background School Board selected Parrott Avenue site after lengthy, comprehensive and public

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7 TABLE OF CONTENTS ( = Rev 11/15) Update #7 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes (New) B-9 Record Drawings B-10 Variance Procedure

More information

Engineer s Report Infrastructure Improvements

Engineer s Report Infrastructure Improvements Gulfstream Polo Community Development District Engineer s Report Infrastructure Improvements Prepared for: Gulfstream Polo Community Development District Board of Supervisors Palm Beach County, Florida

More information

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8 TABLE OF CONTENTS ( = Rev 04/17) Update #8 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes B-9 As-Builts and Record Drawings B-10 Variance

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services

ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services ADDENDA #5- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services Addenda Dated: 01/16/2018 PURPOSE: The purpose of this Addenda #5 is to provide a

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 2-1 Issue date: September 2012 1. General SITEWORK OVERVIEW This Directive outlines the Fund s requirements for the Consultant relative to the development, design and presentation of documents

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District ATHLETIC FACILITY CAMPUS DATA ATHLETIC FACILITY 22628 Hwy 105 West, Montgomery TX 77356 1 MASTER PLAN 2 CIVIL - SITE General Existing Conditions and Deficiencies Overall concrete site paving: Good Overall

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1A-8 Issue date: October 2014 CONSTRUCTABILITY REVIEW 1. The Consultant shall be required to perform a constructability review with the College, Fund s Design Coordinator, Fund s Construction

More information

James E McDade Elementary Classical School 8801 S Indiana Ave Chicago, IL 60619

James E McDade Elementary Classical School 8801 S Indiana Ave Chicago, IL 60619 880 S Indiana Ave Chicago, IL 09 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information