1 PRE FEASIBILITY REPORT Capacity enhancement of Sugar Plant at crush rate of 4500 TCD expandable to 8000 TCD For DUDHGANGA VEDHGANGA SAHAKARI SAKHAR KARKHANA LTD. At Bidri, Mouninagar, Tal. Kagal, Dist. Kolhapur Prepared by

2 1.1 Introduction- Identification of project and project proponent This project is proposed by M/s. Dudhganga Ved Sakhar Karkhana Ltd., (KSSKL). The sugar factory is located at village Bidri, Mouninagar, Tal. Kagal, Dist. Kolhapur, Maharashtra. It is one of the progressive co-operative sugar factories in Maharashtra, set up in the year October The factory is registered under the Registration no. G279 of 1956, dated 10/10/1956. Hon able Shri Arun P. Kakade is President Administrative Board of the factory. The present installed capacity of the sugar factory is 4,500 TCD. The management of the factory has undertaken extensive cane development activities and due to Increasing sugarcane plantation in area of operation, the factory has decided to expand its crushing capacity from 4,500 TCD to 8000 TCD (installed capacity). 1.2 Project Setting Since, the project is capacity enhancement of existing sugar unit, the VDSKL management has decided to install the proposed units within the existing premises. The factory is holding adequate land for the proposed units. The site meets the guidelines prescribed by Ministry of Environment, Forest and Climate Change for sitting of an industry. It is at Bidri. The factory is having connectivity with Kolhapur Railway Station which is at 40 Km from the project site. The geographical coordinates of the site are N, E. 1.3 Highlights of the Project Table 1.1 Project Highlights 1. Name of the Proponent M/s. Dudhganga Vedganga sahakari Sakhar Karakhana. (DVSSKL) 2. Location of the project Ravindra Digamber Desai (Managing Director) Shri. Dudhganga Vedganga sahakari Sakhar Karakhana LTD., Bidri (Mouninagar), Tal.- Kagal, Dist.- Kolhapur Tel. No.: to 26. Fax No.: klp_bidrisgr@sancharnet.in Klp_bidrisgr@rediffmail.com purchase.bidri@yahoo.in 3. Land Total land available with the factory = sq.mt. Built up area= Sq.mt. including, Boiler, bagasse storage yard etc. Area available for the use of treated sewage / trade effluent for gardening / irrigation sq.mt. No need of acquisition of land as the proposed project will be set up in existing factory premises only 4 Project Capacity Enhancement of Sugar unit from 4,500 to 8000 TCD 5 Product Sugar Unit (Production figures are based on operational capacity of 8000 TCD) 6 Operation days per Average 160 days and Maximum 200 days annum 7 Raw material Sugar Unit (based on operational capacity) Sugar Cane: Lime Sulfur 8 Water Requirement

3 The water requirement for the project is received from Dudhganga, Vedgang and Chikotra River. 1.4 Need of project and its importance to the country and region India is one of the largest producers of sugarcane as well as sugar in the world. The sugar cane is cash crop for farmers. There are about 564 installed sugar factories in India. Most of the sugar industries are located in rural areas providing employment to rural masses. Cooperative sugar factories from Maharashtra is the backbone of rural economy. These factories have contributed for the development of conomy as well as infrastructure in rural areas, generated ample of employment opportunity to local people. The project proponent is one of the cooperative sugar factories from the region of Maharashtra. The cultivation of sugar cane is increasing every year in the command area of the factory and it is anticipated to grow gradually for next few seasons. In addition, the sugar factory is having plans to promote and support the cane development programme, in it command area. Sr. No Season Table 1.2: Expected cane availability for next five years Sugarcane Yield (MT/ area (Ha) Ha) Total cane Production (Lakhs MT) Cane available to the factory (LMT) Expected Sugar Recovery (%) It is seen from the above table that more than Lakh MT of the cane availability from the season of the sustainable basis of the evident and SDVSSKL will not face any major difficulty for achieving targeted crushing. 1.5 Power Table 1.3.Need of power for sugar unit particular Season Off season Electricity consumption Import vs. Indigenous production The processes of manufacturing for sugar are simple and straight line, available indigenously. The technologies even for the pollution control/disposal are also available indigenously. 1.7 Export Possibility The finished goods Sugar are having excellent potential of export. 2.0 PROJECT DESCRIPTION 2.1 Type of project Proposed project is capacity enhancement of existing sugar factory from 4,500 TCD to 8000 TCD. The project is placed under item 5 (j)-for sugar unit under B category as per EIA Notification, 2006 (as amended in 2009) and will be appraised at state level.

4 2.2 Location with coordinate Project coordinates: N E Figure 2.2: Satellite Image of the project site Fig. 2.3 Master Layout 2.3 Details of alternative site consider and basis of selecting the proposed site Alternative sites for the proposed project are not considered, because of following reasons. i) The project is capacity enhancement of existing units. ii) The project proponents are having adequate land for the proposed capacity enhancement as well as ancillary units thereof such as storage, treatment, disposal units, etc. iii) The present site meets the guidelines for sitting of an industry prescribed by MoEF/CPCB 2.4 Size or magnitude of operation After Capacity Enhancement installed capacities of the project units will be Sugar unit of 4,500 TCD (installed capacity) and operational capacity will be 8000 TCD efficiency. 2.5 Project description with process details Process: Extraction of Juice The sugarcane is passed through preparatory devices like knives for cutting the stalks into fine chips before being subjected to crushing in a milling tandem comprising 4 to 6 roller mills. In the best milling practice, more than 95% of the sugar of cane gets extracted into the juice.

5 Clarification The treated juice on boiling fed to continuous clarifier from which the clear juice is decanted while the settled impurities known as mud is sent to rotary drum vacuum filter for removal of unwanted stuff called filter cake. It is discarded or returned to the field as fertilizer. Evaporation The syrup is again treated with sulphur dioxide before being sent to the pan station for crystallization of sugar. Crystallization takes place in single-effect vacuum pans, where the syrup is evaporated until saturated with sugar. At this point seed grain is added to serve as a nucleus for the sugar crystals, and more syrup is added as water evaporates. Centrifugation The massecuite from crystallizer is drawn into revolving machines called centrifuges. The perforated lining retains the sugar crystals, which may be washed with water, if desired. The mother liquor molasses passes through the lining because of the centrifugal force exerted and after the sugar is purged it is cut down leaving the centrifuge ready for another charge of massecuite. Gradation & Packing The final product in the form of sugar crystal is dropped through pan section and this sugar is graded and picked in to the bags. The grade of the sugar depends on the size of the crystal viz. Small (S) and Medium (M).

6 Figure 2.4: Flowchart sugar manufacturing process

7 Raw Materials for Finished Products Raw materials for the proposed project will be available from the local market. Bagasse used as a fuel and molasses as raw material will be available from in-house only. Product wise raw material consumption is given below. 2.6 Resource optimization / recycle and reuse envisaged in the project In the proposed project, optimum utilization of the available resource is strived by the management, by using a renewable energy source of bagasse. Bagasse is a by-product of sugar factory; it will be used as a fuel for boilers that produces process steam Water Requirement and Its source Necessary water requirement for the proposed project will be met from Dudhganga, Vedhganga, Chikotra and canal 1 Km. Water will be required for domestic, process and utility purpose. Used for Gardening and greenbelt ~ 400 cu.m. per day (Greenbelt area of ~ 20 acres) Seed plot and cane plantation area = 20 acres Water required for plantation and seed plot = 400 cu.m/day Treated water from ETP for irrigation = 290 cu.m. Excess condensate used for irrigation = 110 cu.m Power & Fuel requirement and its source The existing power requirement is sourced from existing 20 MW back pressure TG set. Existing 2 Nos. of D.G. set of 320 KVA is/will be used as standby. A new 15 MW double extraction cum condensing (DECC) TG set will be installed for meeting the power requirement of proposed expansion. The total power generated during average crushing season of 160 days will be MW. After meeting the in-plant requirements for factory, Co-generation unit, the power exported to the grid will be MW. And during off-season total power generated will be MW out of which 9.86 MW will be exported to the grid. Bagasse is the main fuel which will be used for proposed cogeneration expansion, which is sourced from own sugar factory. The power requirement of the proposed project in season is units and in off season units. Waste generation & disposal scheme Quantity of waste to be generates & scheme for their disposal are given in following chart: A. Liquid waste Sugar and cogeneration unit Effluent will be sent to sugar ETP and utilized for gardening/irrigation. Condensate water will be treated in condensate polishing unit (CPU). Sugar condensate water will be reused in sugar as well as proposed distillery unit to minimize the fresh water intake. Hot water from various sources will be cooled in cooling pond and recycled to respective activity after reaching to ambient temperature. The factory is having ~20 acres plantation area where treated water will be utilized.

8 Figure 2.6: Flowchart for effluent generation from Sugar along with cogeneration unit

9 B. Solid waste The proposed industrial activity at SDVSKL gives solid waste in the form of ETP sludge which is biodegradable and boiler ash. The solid waste will be used as a filler material in the composting process and for manufacturing of Briquette. The quantity and disposal technique is brief in following table. Table 2.5: Solid waste generation and disposal # Waste Treatment Disposal Remark 1. Sugar ETP Disposal into Sold to member Organic land/soil farmer/own plot 2. Ash Disposal into land/soil Used as a soil enriching material Organic + Inorganic Figure 2.7: Schematic Diagram of Existing ETP

10 2.7 Air Emission & Control There are existing DG set with adequate stack height and acoustic enclosures. 2.8 Noise Control Steam turbine generator will be the major noise source of the proposed project. Apart from that, noise is anticipated from pumps, motor drives, utilities etc. The plant and equipments will be specified and designed with a view to minimize noise pollution. The major noise producing equipments will be provided with sound proof devices and silencers. DG set will be provided with acoustic enclosures. Ear Plugs and ear muffs will be provided to the workers in utility section. Greenbelt will be developed. 2.9 Health and Safety Measures Being a cooperative sugar mill KSSKL is committed to the Health and Safety of all its employees. It strives to provide hygienic & safe work place and continually improve the effectiveness of Health & Safety system. To meet these objectives the SDVSKL will; Comply with all relevant Laws, regulation, statutory provisions & codes of practice. Continually asses Risks & Hazards so as to evolve establish & upgrade hazard control measures, emergency preparedness, & risks mitigation and correct the deficiency identified in timely manner. Ensure safe handling, storage, use and disposal of all substance & materials which are classified as hazardous to Health & Environment. Create awareness in employees by providing appropriate training, motivation information s so as to create individual sense of duty, responsibility & participations & an institutionalize culture of continually improvement in Safety, Health & Environment matters. Make HOD responsible to communicate the safety policy to all concerned in his department. Make supervisors responsible or implementation of the safety precautions, use of safety devices, & the safety of the people. Empower employees at all levels to be responsible & accountable for their personal health & safety. Fire protection system shall be provided in accordance to the LPA regulations. The fire fighting system shall consist of a hydrant network. Factory has already a fire protection system including electric driven pump, one diesel engine pump, and one jockey pump. Portable fire extinguishers shall be provided in strategic locations in new construction area.

11 3.0 SITE ANALYSIS 3.1 Connectivity The site is well connected by road, railway as well as air network. It is having proper connectivity of Roads and Highway. Kolhapur Railway station is about. The international air port of Kolhapur is the nearest air ports to the site. 3.2 Land form, land use and ownership The sugar factory is holding more than 77 acres of land. The land is flat, open and already under the industrial use (i.e. sugar factory and allied units).total Built up area of the project is Sq.mt. Area available for the use of treated sewage / trade effluent for gardening / irrigation is Sq.mt. 3.3 Topography The terrain is almost flat, no hills in the surroundings. The geographical coordinates of the area are N E. 3.4 Salient Features The proposed project requires no additional land. Therefore, no social issues are involved. There won tbe change in the land use pattern since the land is already used for industrial purpose. There is no sanctuary, bio-sphere reserve or national park in the 10km radius area. The project surrounding land is either fallow land or used for agricultural purpose Meteorological Conditions The climate of the region is tropical maritime with high relative humidity throughout the year. The general climatic regime is fairly equitable since seasonal fluctuations of temperature are not significantly large. The moderating effects of the nearby sea and the fairly high amount of relative humidity in the atmosphere have restricted the variability. The seasonal variation of temperature follows closely the course of the sun. January is invariably the coldest month and May the warmest. With the onset of monsoon in early June the temperature decreases and remains more or less steady. Again the temperature rises in October and falls gradually till January. The maximum day temperature ranges in between 35 C to 42 C while the minimum temperature ranges in between 17 C to 28 C. The average relative humidity varies from owest in the month of December to the highest of 65 % during July. The humidity is relatively higher in the morning hours than in the evening hours. The daily humidity values do not show any significant or sudden changes. The relatively high humidity has a considerable impact on the atmosphere in reducing its variability. The monsoon generally sets in around the second week of June and continues till late September. July and August are the wettest months all over the region Sources of Information- Secondary information on meteorological conditions has been collected from Temperature, relative humidity, rainfall, wind speed and direction are measured twice a day viz., at 0830 and 1730 hr. The wind speed and direction data of IMD, station has been obtained. The data for the remaining parameters has been collected for the last 10 years and processed.

12 Chapter 4 RISK ASSESSMENT AND SAFETY MANAGEMENT Risk Assessment involves the identification and assessment of risks the persons involved in the proposed project and the neighboring populations are exposed to as a result of hazard occurrence. This requires a thorough knowledge of failure probability, credible accident scenario, vulnerability of population etc. Consequently, the risk analysis is often confined to maximum credible accident scenario and the analysis of the potential effects of environmental hazards to human health. These accidents can be minimized to a great extent by proper procedures, handling and training. But it may be difficult to reach zero risk or absolute safety level. Whenever such incidents do occur in order to prevent loss of lives and damage to property, it becomes necessary to take immediate steps to control the situation. This can be achieved through a planned advance preparation to face such a situation with respect to both on site and off site emergencies.

13 Chapter 5 PROJECT SCHEDUE AND COST 5.1 Proposed Schedule for Approval & Implementation Company has obtained consent from MPCB Manufacturer has proposed addition of new products and applied for consent to establish from Maharashtra Pollution Control Board. The manufacturing of new product has planned to start after one month from obtaining environmental clearance. 5.2 Project Cost` The estimated cost for proposed expansion is about Lakhs

14 Chapter 6 PROJECT BENEFITS 6.1 Introduction The proposed project will be provided job opportunity at maximum extent to the surrounding population. The project shell affect the socio-economy, physical infrastructure and biological environment. The project will result in the improvement of life relative localities. Some important beneficial impact of the projects as follows: Improvement in the physical infrastructure Improvement in the social infrastructure Employment 6.2 Improvement in the Social Infrastructure This project will be provided better livelihood to the local people. After the set up of this project all basic facilities would be here. This zone will de attracts the people at global level. And this area would be connected with world other areas in the respect of transportation, communication etc. 6.3 Employment The project will provide employment opportunity for the local community in the construction phase as well as in operation phase. Tender specification for construction and operation would include a favorable employment opportunities for the locals. The main principles are outlined below: Employment strategy would provide for preferential employment of local labor. General recruitment procedures will be transparent, public and open to all. Recruitment procedures will be publicized in advance. There will be no discrimination on basis of gender, caste or other factors. Contractors would be required to abide to employment priority towards locals and abide by the Indian labor laws regarding standards on employee terms and conditions.

15 CONCLUSIONS Chapter-7 We may conclude as under: The proponents are following all the safety rules and regulations as prescribed by Ministry of Environment and Forest, Government of India and MPCB. Wastewater will be treated in full-fledged Wastewater Treatment Plant. Ambient Air Quality of the project site will be within the permissible limit as prescribed by National Ambient Air Quality Standards. Noise is expected to be on higher side during construction phase. In the operational phase it will be only due to the machines. No significant impact is seen on flora and fauna. The project will generate employment opportunities during construction stage and also at operational phase. The standard of living of local people due to employment is likely to be better, so we may say that it is positive socioeconomic impact. In short we can say that this project has no negative impact on environment.

PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY AND INTRODUCTION OF THE PROJECT

PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY AND INTRODUCTION OF THE PROJECT PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY AND INTRODUCTION OF THE PROJECT Shri Dudhganga Vedganga Sahakari Sakhar Karkhana Limited, (SDVSSKL) located at Bidri (Mouninagar), Tal.: Kagal, Dist.: Kolhapur,

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT 1.0 INTRODUCTION OF THE PROJECT Pannageshwar Sugar Mills Ltd. (PSML), At: Pangaon, Tal.: Renapur, Dist.: Latur, Maharashtra was registered vide registration no. 11-130803 dated 01.01.2001.

More information

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi - 416108, Taluka - Shirol, Dist Kolhapur, Maharashtra Compliance of Conditions Stipulated in environmental clearance granted

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY AND INTRODUCTION OF THE PROJECT Shivneri Sugars Ltd., A/p. - Ganesh tekadi, Nhavi (Bk.), Tal.: Koregaon, Dist.: Satara, Maharashtra State was registered vide

More information

Water Conservation in Sugar Industry

Water Conservation in Sugar Industry Nature Environment and Pollution Technology An International Quarterly Scientific Journal ISSN: 0972-6268 Vol. 12 No. 2 pp. 325-330 2013 Original Research Paper Water Conservation in Sugar Industry Baban

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT 1.0 INTRODUCTION OF THE PROJECT Deshbhakt Ratnappa Kumbhar Panchganga Sahakari Sakhar Karkhana Ltd. (D.B.R.K. Panchganga S.S.K.L.) leased unit of Shree Renuka Sugars Ltd. is located

More information

ADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry

ADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry ADDITIONAL STUDIES 7 7.1 PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry of Environment, Forest and Climate Change (MoEFCC),

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

Application of Low and Non Waste Technology in the production process;

Application of Low and Non Waste Technology in the production process; 9.0 ENVIRONMENT MANAGEMENT PLAN (EMP) 9.1 INTRODUCTION Environment Management Plan is required for ensuring sustainable development. It should not affect the surrounding environment adversely. The management

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR DYES, PIGMENTS AND DYE INTERMEDIATES MANUFACTURING PLANT IN GIDC, DAHEJ-II Of M/s. SHREEJI INDUSTRIES Plot No. D2/CH/24, Dahej-II, GIDC Industrial Estate,

More information

Amendment required in the existing EC

Amendment required in the existing EC Amendment required in the existing EC Change/Addition in Phase I; 250 KLPD Grain based Distillery with 20 MW Co-gen Power Plant / Molasses 160 KLPD based distillery with 12 MW Co-gen Power Plant in Environmental

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

M/s NSL SUGARS LTD, UNIT III, (Formerly Jay Mahesh Sugars Ltd)

M/s NSL SUGARS LTD, UNIT III, (Formerly Jay Mahesh Sugars Ltd) Location Nearest Railway station Nearest Airport Nearby towns Salient features of the plant Land Area in acres Pawarwadi Village, Majalgaon Tk, Beed Dist, Maharashtra. Manwat Road : 30 KM; Parbhani : 75

More information

ADDITIONAL ATTACHMENT LIST OF ANNEXURE

ADDITIONAL ATTACHMENT LIST OF ANNEXURE ANNEXURE ADDITIONAL ATTACHMENT LIST OF ANNEXURE TITLE I. Copy of Environment Clearance (EC) of unit for distillery II. III. IV. Valid consent Copy (CTO/CC&A) Details of Production & Raw Material Consumption

More information

PRODUCT, BY-PRODUCT, RAW MATERIAL

PRODUCT, BY-PRODUCT, RAW MATERIAL PRODUCT, BY-PRODUCT, RAW MATERIAL Sr. No. Name of Product Existing Quantity (30 KLPD) Expansion Quantity (30 KLPD) Total (60 KLPD) 1. Ethanol 8100 KL/Annum 8100 KL/Annum 16200 KL/Annum 2. Rectified Spirit

More information

PREFEASIBILITY REPORT. Jakraya Sugar Ltd. (JSL), Watwate, Tal.: Mohol, Dist.: Solapur was registered vide registration no.u15421pn2007plc

PREFEASIBILITY REPORT. Jakraya Sugar Ltd. (JSL), Watwate, Tal.: Mohol, Dist.: Solapur was registered vide registration no.u15421pn2007plc PREFEASIBILITY REPORT 1.0 INTRODUCTION OF THE PROJECT Jakraya Sugar Ltd. (JSL), Watwate, Tal.: Mohol, Dist.: Solapur was registered vide registration no.u15421pn2007plc130078. As per the provision of EIA

More information

PRE-FEASIBILITY REPORT INTEGRATED SUGAR 5000 TCD, COGEN 18 MW AND NEW 30 KLPD DISTILLERY GAT NO.10, 11/1, 11/2, 15/3(PART), KAVATHE

PRE-FEASIBILITY REPORT INTEGRATED SUGAR 5000 TCD, COGEN 18 MW AND NEW 30 KLPD DISTILLERY GAT NO.10, 11/1, 11/2, 15/3(PART), KAVATHE PRE-FEASIBILITY REPORT OF INTEGRATED SUGAR 5000 TCD, COGEN 18 MW AND NEW 30 KLPD DISTILLERY AT GAT NO.10, 11/1, 11/2, 15/3(PART), KAVATHE MALKAPUR, TAL. SANGAMNER, DIST. AHMEDNAGAR, MAHARASHTRA BY M/S.

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT 1.0 INTRODUCTION OF THE PROJECT Padmashree Dr. D. Y. Patil Sahakari Sakhar Karkhana Ltd. (PDDPSSKL), Dnyanshantinagar, Vesaraf - Palsambe, Tal: Gaganbavda, Dist.: Kolhapur was registered

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY M/s Arti Chemical Industries is a project located at Plot No. E-22, Vilayat G.I.D.C. Tal: Vagra area of Bharuch district in Gujarat. M/s Arti Chemical Industries

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

INSPIRE INDUSTRIES PVT. LTD.

INSPIRE INDUSTRIES PVT. LTD. For Proposed 0.999 MTPA Coal Washery At Village: Bhelai, Tehsil: Baloda, District: Janjgir-Champa, Chhattisgarh Envirotech East (P) Limited An ISO 9001:2008, 14001:2004 & OHSAS:18001:2007 Company Laboratory

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY Shri Ashok Patel Partner of M/s. Patel Polymers is planning to manufacture organic chemical Different Types of Resins, for proposed expansion project at Plot

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF BAKELITE POWDER MANUFACTURING UNIT of M/S. HINDUSTAN BAKELITE COMPANY PLOT NO. J-3436, GIDC ESTATE, ANKLESHWAR, DISTRICT: BHARUCH-393002, GUJARAT 0 CONTENTS

More information

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT Of M/s. SHREE RAM INDUSTRIES PLOT NO.5117, GIDC-ANKLESHWAR, PIN-393002 TAL: ANKLESHWAR, DIST: BHARUCH, GUJARAT

More information

FP1_final MODELLING A CONTINUOUS PAN INSTALLATION USING SUGARS FOR WINDOWS. Englewood, Colorado USA

FP1_final MODELLING A CONTINUOUS PAN INSTALLATION USING SUGARS FOR WINDOWS. Englewood, Colorado USA FP1_final MODELLING A CONTINUOUS PAN INSTALLATION USING SUGAS FO WINDOWS By L. WANE WEISS 1, JOSÉ F. ALVAEZ 2, TISO M. CAEJA 3 AND BABAA SIGNO 2 1 Sugars International LLC Englewood, Colorado USA Email:

More information

Date: M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaranji, Kolhapur.

Date: M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaranji, Kolhapur. Date: 04.06.2018 M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaraji, Kolhapur. Compliance to the Environmental Clearance for Co-generation Plant 30 MW. Ref: SEAC 2009/CR16/TC2, Dated: 18

More information

Proposed TOR Calix Industries

Proposed TOR Calix Industries 1 A tabular with index for point-wise compliance of below mentioned TORs. 2 Executive summary of the project giving a prima facie idea of the objectives of the proposal, use of resources, justification,

More information

ANNEXURE A DETAILS OF PRODUCTS

ANNEXURE A DETAILS OF PRODUCTS Annexures to Form 1 & Pre Feasibility Report Proposed Project for manufacturing of Dyes Intermediates of M/s Jay Dyechem, Narol-Vatva Road,Ta : City, District : Ahmedabad, Gujarat. ANNEXURE A DETAILS OF

More information

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT LG Polymers India Pvt. Ltd. Sy. No.s

More information

ADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry

ADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry ADDITIONAL STUDIES 7 7.1. PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry of Environment, Forest and Climate Change (MoEFCC),

More information

Pre - Feasibility Report. For. Modernization of Sugar Unit. Located at

Pre - Feasibility Report. For. Modernization of Sugar Unit. Located at Pre - Feasibility Report For Modernization of Sugar Unit Located at At & Post Village Sayan, Taluka Olpad, District Surat, Gujarat-394130 Of M/s. Shree Sayan Vibhag Sahakari Khand Udhyog Mandli Ltd. SUMMARY

More information

V: PROJECT SCOPING & METHODOLOGY

V: PROJECT SCOPING & METHODOLOGY V: PROJECT SCOPING & METHODOLOGY 5.0 INTRODUCTION The scoping exercise is carried out to define the focus and scope of the EIA Study. The scoping exercise is required to understand the type of activities

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

ANNEXURES. 1 Google image showing proposed project site. 3 Manufacturing process details. 4 Details of hazardous waste management

ANNEXURES. 1 Google image showing proposed project site. 3 Manufacturing process details. 4 Details of hazardous waste management ANNEXURES Annexure No. Description 1 Google image showing proposed project site 2 Plant Lay-Out 3 Manufacturing process details 4 Details of hazardous waste management 5 Details of Effluent Treatment Plant

More information

Product Profile. Quantity in MT/Month CAS Solvent Dark Violet R Solvent Black

Product Profile. Quantity in MT/Month CAS Solvent Dark Violet R Solvent Black Annexure - A Product Profile Sr. No. Product Name Quantity in MT/Month CAS Existing Proposed Ultimate Number End Users 1 Acid Dyes 5.000-5.000 0.000 -- -- Solvent Yellow 82 12227-67-7 Solvent Dark Violet

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW PROJECT (PIGMENT MANUFACTURING PLANT) Of M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) CONTENTS Sr.

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

Using Sugars for mill optimization projects. Fikadu M Beyene

Using Sugars for mill optimization projects. Fikadu M Beyene Using Sugars for mill optimization projects Fikadu M Beyene Presented at the annual ASSCT meeting - Louisiana division Lafayette LA, February 9, 2011 Objectives 1. Present modeling of a sugar cane factory

More information

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Pre Feasibility Report On STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Submitted to MINISTRY OF ENVIRONMENT & FOREST STATE LEVEL ENVIRONMENTAL

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS OF M/s. MAYUR COLOUR AND CHEMICALS LOCATED AT Plot No. 5148, GIDC Industrial Estate, Ankleshwar

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE For PROPOSED RESIDENTIAL AND COMMERCIAL DEVELOPMENT AT Plot bearing survey no. 86/1, 86/2, 86/3 (pt), 86/4 (pt), 86/5 (pt), 115/1 (pt), 115/2 (pt), 115/3 (pt), 115/4 (pt), 115/5

More information

UNSATURATED POLYESTER RESIN

UNSATURATED POLYESTER RESIN PROJECT REPORT ON UNSATURATED POLYESTER RESIN BY AQUA CHEM INDUSTRIES Survey No. 50/2, Jodhpar (Nadi), Morbi - 363641, Gujarat. I N D E X Sr. No. Contents Page No. 1 Introduction 3 2 Project Description

More information

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh EXECUTIVE SUMMARY SUBMITTED BY M/s. Lakshmanan Cements Pvt Ltd No. 58-A, 25

More information

SUMMARY ENVIRONMENTAL IMPACT ASSESSMENT REPORT. 380 MW Gas Based Combined Cycle Power Plant at

SUMMARY ENVIRONMENTAL IMPACT ASSESSMENT REPORT. 380 MW Gas Based Combined Cycle Power Plant at SUMMARY ENVIRONMENTAL IMPACT ASSESSMENT REPORT for 380 MW Gas Based Combined Cycle Power Plant at Vijaipur, District: Guna MADHYA PRADESH NOVEMBER 2011 1 CONTENTS 1.0 Project Description Page 3 2.0 Description

More information

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location 1. SUMMARY PRE-FEASIBILITY REPORT Project Stone Quarry Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location Village Taluka District State Rupapali Basna Mahasamund Chhattisgarh 1 Mining Lease

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,

More information

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT Subject: Compliance report of Environmental Clearance for CDR & Revamp Reference: J-11011/272/2007-IA,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For EXPANSION IN EXISTING MANUFACTURING PLANT Of M/s. SHIVA DYE STUFF PVT. LTD Plot no. A2-11/6104,G.I.D.C. Industrial Estate, Ankleshwar-393002, Gujarat. 1 CONTENTS Sr. No. Description

More information

The Sugarcane: An Agriculture Aspect

The Sugarcane: An Agriculture Aspect Chapter 2 The Sugarcane: An Agriculture Aspect 2.1 Introduction Sugarcane growing countries of the world are lying between the latitude 36.70 0 north and 31.00 0 south of the equator extending from tropical

More information

EXECUTIVE SUMMARY OF THE PROPOSED FERTILISER UNIT OF M/s. SUMAN PHOSPHATES & CHEMICAL LTD., MATRALA, MADHYA PRADESH

EXECUTIVE SUMMARY OF THE PROPOSED FERTILISER UNIT OF M/s. SUMAN PHOSPHATES & CHEMICAL LTD., MATRALA, MADHYA PRADESH EXECUTIVE SUMMARY OF THE PROPOSED FERTILISER UNIT OF M/s. SUMAN PHOSPHATES & CHEMICAL LTD., MATRALA, MADHYA PRADESH 1.0 INTRODUCTION M/s. Suman Phosphates and Chemical Ltd., has proposed to set-up a Single

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

ANDHRA PRADESH POLLUTION CONTROL BOARD, REGIONAL OFFICE, TIRUPATI

ANDHRA PRADESH POLLUTION CONTROL BOARD, REGIONAL OFFICE, TIRUPATI M/s. JANANY CEMENT INDUSTRIES PRIVATE LIMITED SURVEY NO 462, INDUSTRIAL PARK, GUNTAKINDAPALLI VILLAGE, SRIKALAHASTI MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH EXECUTIVE SUMMARY SUBMITTED BY M/s.Janany Cement

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan Of Dr. Mittal Laboratories Pvt. Ltd. Plot No. C-10/2, SARA Industrial Estate Ltd., Village Rampur, Dehradun - Chakrata Road, Selaqui, Dehradun, Uttrakhand For Manufacturing

More information

PRE FEASIBILITY REPORT. New Molasses Based 30 KLPD Distillery Unit of. M/s. Prasad Sugar & Allied Agro Product Ltd. (PSAAPL)

PRE FEASIBILITY REPORT. New Molasses Based 30 KLPD Distillery Unit of. M/s. Prasad Sugar & Allied Agro Product Ltd. (PSAAPL) PRE FEASIBILITY REPORT of New Molasses Based 30 KLPD Distillery Unit of M/s. Prasad Sugar & Allied Agro Product Ltd. (PSAAPL) At/Post-Vambhori, Taluka Rahuri, Dist. Ahmednagar, Maharashtra413704 Prepared

More information

COMPLIANCE STATUS REPORT

COMPLIANCE STATUS REPORT COMPLIANCE STATUS REPORT Sona Alloys Pvt. Ltd. Additional Director (IA) Ministry of Environment & Forests, Paryavaran Bhavan, CGO Complex, Lodhi Road, New Delhi 11003 Date: 08.02.2014 Sub: Compliance Status

More information

FORM-1 FOR PROPOSED API PLANT AT MADURAI, TAMIL NADU. Name of Products. Products. 1 Metformin Hydrochloride Paracetamol Bronopol 25

FORM-1 FOR PROPOSED API PLANT AT MADURAI, TAMIL NADU. Name of Products. Products. 1 Metformin Hydrochloride Paracetamol Bronopol 25 3 ANNEXURES Annexure 1: Production Details Name of Products Products Production Capacity in MT/Month 1 Metformin Hydrochloride 1000 2 Paracetamol 1200 3 Bronopol 25 By-Products Total 2225 1 Acetic acid

More information

5. ENVIRONMENT MANAGEMENT PLAN

5. ENVIRONMENT MANAGEMENT PLAN 5. ENVIRONMENT MANAGEMENT PLAN The environmental management plan consist of the set of mitigation measures, management and, monitoring measures to be taken during construction and operation phase to eliminate

More information

PRE FEASIBILTY REPORT

PRE FEASIBILTY REPORT PRE FEASIBILTY REPORT FOR ENVIRONMENT CLEARANCE OF PROPOSED NEW PROJECT S. O. CHEMICALS (5 f Category) Proposed By: COREL PHARMA CHEM PVT. LTD. SURVEY NO. 473 & 481, BORISANA, KADI THOL ROAD, KADI, DIST

More information

M/S. HETERO INFRASTRUCTURE SEZ LIMITED

M/S. HETERO INFRASTRUCTURE SEZ LIMITED ENVIRONMENTAL STATEMENT (FORM - V) FOR THE FINANCIAL YEAR ENDING MARCH-2016. M/S. HETERO INFRASTRUCTURE SEZ LIMITED N.NARASAPURAM(V),NAKKAPALLI(M) VISAKHAPATNAM DISTRICT. SUBMITTED TO : ANDHRA PRADESH

More information

M/s NSL KRISHNAVENI SUGARS LTD

M/s NSL KRISHNAVENI SUGARS LTD Location Nearest Railway station Nearest Air port Nearby towns Salient features of the plant Land Area in acres Year of Establishment Specification of Sugar Plant Ramakrishnapur Village, Kothakota Mandal,

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

M/s. VITTHAL REFINED SUGARS LTD

M/s. VITTHAL REFINED SUGARS LTD PREFEASIBILITY REPORT (Sugar 5000 TCD, Co-generation 29.5 MW, Grain based distillery 45KLPD & Molasses/sugarcane juice/ Sugar Beet based distillery 60KLPD) A/p Pande, Tal. Karmala, Dist. Solapur, Maharashtra

More information

REQUIREMENTS FOR AMENDMENT IN ENVIRONMENTAL CLEARANCE JUSTIFICATION FOR MODIFICATION IN THE SCHEME FOR SPENT WASH HANDLING IN THE DISTILLERY PLANT

REQUIREMENTS FOR AMENDMENT IN ENVIRONMENTAL CLEARANCE JUSTIFICATION FOR MODIFICATION IN THE SCHEME FOR SPENT WASH HANDLING IN THE DISTILLERY PLANT AMENDMENT IN ENVIRONMENTAL CLEARANCE GRANTED BY MINISTRY OF ENVONMENT AND FORESTS, NEW DELHI VIDE FILE NO. J-11011/773/2007 IA II (I) DATED 16 TH JANUARY, 2008 REQUIREMENTS FOR AMENDMENT IN ENVIRONMENTAL

More information

M/S. Dain Colour Chem

M/S. Dain Colour Chem PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of M/S. Dain Colour Chem Plot No.: 5, Nilkanth Estate, Village: Dhanot, Ta.: Kalol, Dist.: Gandhinagar-382729, Gujarat 1 CONTENTS

More information

Dheeru Powergen Private Limited.

Dheeru Powergen Private Limited. Executive Summary Of The Proposed 2 x 300 MW Dhanras Thermal Power Station At Dhanras Village Katgora Taluk, Korba District, Chhattisgarh. Implemented By Dheeru Powergen Private Limited. Submitted to CHHATTISGARH

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT FOR EXPANSION OF ALUMINA REFINERY (FROM 1.5 TO 3.0 MTPA) & CAPTIVE CO-GENERATION POWER PLANT (FROM 90 TO 150 MW) OF UTKAL ALUMINA INTERNATIONAL LIMITED AT DORAGUDA, RAYAGADA DIST,

More information

Executive Summary For Integrated Sugar (5000TCD), Ethanol (60KLPD) And Cogeneration Power Plant (30 MW) At Kapshi, Phaltan, Satara (Maharashtra) By,

Executive Summary For Integrated Sugar (5000TCD), Ethanol (60KLPD) And Cogeneration Power Plant (30 MW) At Kapshi, Phaltan, Satara (Maharashtra) By, Executive Summary For Integrated Sugar (5000TCD), Ethanol (60KLPD) And Cogeneration Power Plant (30 MW) At Kapshi, Phaltan, Satara (Maharashtra) By, Sharayu Agro Industries Ltd.( Formerly known as Lokmanya

More information

STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala

STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala-147001. No. SEAC/80/37967 Dated 15/10/2008 Speed Post To M/s Green Planet Energy Pvt.

More information

Your Pump Solution for the Sugar Industry.

Your Pump Solution for the Sugar Industry. Your Pump Solution for the Sugar Industry. Gentle handling of raw materials. Sugar mills are classified into the areas of: the receiving yard, which includes beet or cane washing and effluent treatment

More information

2. The expected cost of the project is Rs.50 crores.

2. The expected cost of the project is Rs.50 crores. Subject Application for obtaining Environmental Clearance for development of an "Integrated Municipal Solid Waste Management System for Pathankot Cluster" by Municipal Council, Pathankot at Village Kalanaur,

More information

Ramans Enviro Services Pvt. Ltd. Ahmedabad. Annexure A. Product Profile. Crude OBA AND/OR Crude OBA-CBS-X. Standardized OBA Solid AND/OR

Ramans Enviro Services Pvt. Ltd. Ahmedabad. Annexure A. Product Profile. Crude OBA AND/OR Crude OBA-CBS-X. Standardized OBA Solid AND/OR Annexure A Product Profile Sr. No. 1 2 Product Crude OBA AND/OR Crude OBA-CBS-X Standardized OBA Solid AND/OR Standardized OBA Liquid Proposed Qty (MT/ M) 400 400 1600 Note : For making Standardized OBA

More information

Annexure-I List of Products

Annexure-I List of Products Annexure-I List of Products Sr. No. Name of Products Quantity (MT/Month) 1. Mono Chloro Acetic Acid (MCA) 300 2. Chloro Acetyl Chloride (CAC) 150 3. Tri Chloro Acetyl Chloride (TCAC) 150 4. Aluminum Chloroide

More information

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32 CONTENTS CHAPTER 1... 1 1.0 PROJECT SUMMARY... 1 CHAPTER 2... 2 2.0 INTRODUCTION... 2 (I) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT... 2 (II) BRIEF DESCRIPTION OF NATURE OF THE PROJECT... 2 (III)

More information

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous chemicals may include, but not limited to the following

More information

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance]

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Project Proposal: Expansion of Cement Plant capacity from 1.5 to 2.20 MTPA of Clinker and

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

Benefits of variable speed drives in sugar production

Benefits of variable speed drives in sugar production W H I T E PA P E R Benefits of variable speed drives in sugar production Table of contents 1. Introduction challenges facing sugar producers 2. How can VSD systems help? 3. A solution for almost every

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Excavation of Brick Earth (Total Mining Area 1.112Ha.) (For Manufacturing of Bricks) Submitted By M/s New Kaptan Brick Field Shri Krishna Kr. Singh S/o Shri Brahma DevSingh Pure

More information

TABLE OF CONTENTS. Para No. Contents Page No

TABLE OF CONTENTS. Para No. Contents Page No TABLE OF CONTENTS Para No. Contents Page No Chapter-1 Introduction 1.0 Preamble 1 1.1 Location of the project 1 1.2 Objectives of the EIA study 3 1.3 Methodology of study 3 1.4 Structure of EIA report

More information

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan ENVIRONMENTAL MANAGEMENT PLAN Of Hotel Project for Mohamed Ilyas & Ms. Alamzahan at Khasra No. 269Ga, 269Kh, 266Kh & 270 Village Majra, Tehsil Central Doon, District Dehradun (Uttarakhand) GENERAL ENVIRONMENTAL

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

Process Design For Optimum Energy Efficiency

Process Design For Optimum Energy Efficiency Process Design For Optimum Energy Efficiency Steve Peacock Tongaat Hulett Sugar INTRODUCTION The average SA sugar factory has a bagasse supply capable of supporting a steam on cane of just under 60% Assuming

More information

BRIEF DESCRIPTION OF THE PROJECT

BRIEF DESCRIPTION OF THE PROJECT BRIEF DESCRIPTION OF THE PROJECT. Introduction M/s Indorama Industries Limited is proposing to expand their project known as Indorama Spandex for manufacture of manmade textile fibre using petro chemical

More information

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal ANNEXURE Annexure 1: Production Details Annexure 2: Site Location Map Annexure 3: Site Layout Map & Area breakup for Terminal Annexure 4: Operation Philosophy Annexure 5: Copy of Consent to Operate Annexure

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY M/s Merino Industries Limited has proposed for manufacturing Phenol Formaldehyde Resin, Melamine Formaldehyde Resin at Plot No D2 CH 36, Dahej Phase II, Dist. Bharuch, Gujarat. The

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Product Profile. Annexure A. Annexures to Form - I & PFR. MT/ M Consented Ultimate. Crude OBA AND/ OR Standardized OBA liquid/ powder 190 AND/ OR 2600

Product Profile. Annexure A. Annexures to Form - I & PFR. MT/ M Consented Ultimate. Crude OBA AND/ OR Standardized OBA liquid/ powder 190 AND/ OR 2600 Annexure A Product Profile Sr. No. 1 Product Crude OBA AND/ OR Standardized OBA liquid/ powder MT/ M Consented Ultimate 525 190 AND/ OR 2600-23 - Annexure - B Details of Raw Materials Qty (Kg/ Kg) Qty/

More information

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:- 0175-2215802

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment

More information

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29)

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29) 1 By: Speed-Post State Level Expert Appraisal Committee (Formed as per S.O. no. 1533 dated 14 th Sept 2006 of Government of India, Ministry of Environment & Forests) PARYAWARAN PARISAR, E-5, ARERA COLONY,

More information