1 PRE-FEASIBILITY REPORT For PROPOSED INTEGRATED STEEL PLANT of 0.7 MTPA By M/s. MUKAND Ltd. At Village- Kanakapur, Taluka & District- Koppal, Karnataka Conducted & Prepared By GREEN CIRCLE, INC. Integrated HSEQR Consulting Engineers, Scientists & Trainers (MoEF Recognized Environment Laboratory) (An ISO: 9001, 14001, OHSAS: Certified Organization & GPCB approved Environment Auditor Schedule II) Gujarat High Court Stay Order for QCI NABET No. C/SCA/10311/2012 dated Corp. Office & Environmental Research Laboratory: Green Empire (Anupushpam), Above Axis Bank, Nr. Yash Complex, Gotri Road, Vadodara (Gujarat) India Tel: Mumbai office Flat No 6,Ground Floor,Shakuntala Niwas, M G Road,Borivali (E),Mumbai Tel : /60 ALSO AT E: info@greencircleinc.com BENGALURU RUDRAPUR NEW DELHI HYDERABAD PUNE RAIPUR KOLKATA GOA OVERSEAS AUSTRALIA OMAN KUWAIT AFRICA VIETNAM 1

2 TABLE OF CONTENTS Sr. No. Particulars Page No. 1 EXECUTIVE SUMMARY 4 2 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT 5 3 PROJECT LOCATION AND PROJECT DESCRIPTION 9 4 PLANNING CONCEPT 28 5 PROPOSED INFRASTRUCTURE R & R PLAN 31 7 PROJECT SCHEDULE AND COST ESTIMATE 31 8 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION) 32 LIST OF TABLES Table. No. Particulars Page No. 1.1 Proposed Production Capacities Plant capacity & equipments Raw Material Consumption Water Balance Table Power Requirement Waste (Hazardous & Non-Hazardous) details Control Equipments for Air Pollution Wastewater Sources and its Treatment land use pattern of the project site Estimated Project Cost 32 2

3 LIST OF FIGURES Fig. No Particulars Figure 3.1: Location Map of the Project site Google image of the Proposed Project Site Schematic diagram/ Layout plan of the proposed project Schematic Process Steps for Iron & Steelmaking ETP plant layout similar to the existing interlinked project (Unit-I) STP plant layout similar to the existing interlinked project (Unit-I) Page No

4 1. EXECUTIVE SUMMARY Mukand Ltd. (Formerly known as Mukand Iron & Steel Works Ltd.), is one of the largest producer of Alloys and Special Steels and Stainless Steels in the country meeting the requirements of Original Equipment Manufacturers (OEM) for automobiles, auto-component industries as also of railways, defence, transportation and engineering industries. M/s. Mukand Ltd. has proposed to set up an Integrated Steel Plant capacity in 0.7 MTPA at Village- Kanakapur, Taluka & District- Koppal, Karnataka. The total land area required for the proposed project is approximately 300 acre. The proposed project site is easily approachable and is located near the National Highway No. 63. The coordinates of the site is N and E. In Integrated Steel Plant and basic raw materials required for its operation are Iron Ore, Coking Coal, Limestone and Dolomite. It is proposed that in the Integrated Steel Plant Billets and Blooms in sizes of 160 x 160 mm to 280 x 320 mm shall be produced. Cast Billets will be rolled into Wire Rods and Bars. It is also proposed to roll heavy section bars from Blooms. Total fresh water requirement for the project will be 18 MLD, which will be sourced from downstream of Tungabhadra Reservoir. Approval has been obtained vide Government of Karnataka letter no WRD.15/MTP/2013 dated 22 December Power requirement for the proposed project will be 60 MW, out of which 30 MW will be sourced from the proposed Captive Power Plant by captive power generation from waste gases of Blast Furnaces and Coke Ovens and 30 MW from KPTCL/GESCOM. The project will generate direct employment both during construction of about 1000 persons and during operation i.e. post construction phase locally and regionally, it is expected that 730 Managers, Supervisor, Skilled and Unskilled workers will be required. Appropriate pollution control measures will be installed to abate air pollution. Waste water generated from the process will be reused in the process or used in gardening and dust suppression after proper treatment. There will be significant socio-economic and infrastructure development due to this project. Overall the project will have a positive impact on socio-economic environment. 4

5 2.0 INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT M/s. Mukand Ltd. proposes to set up an Integrated Steel Plant of 0.7 MTPA capacity in Village- Kanakapur, Taluka & District- Koppal, Karnataka. Established in 1937, Mukand Ltd. (Formerly known as Mukand Iron & Steel Works Ltd.), is one of the largest producer of Alloys and Special Steels and Stainless Steels in the country meeting the requirements of Original Equipment Manufacturers (OEM) for automobiles, autocomponent industries as also of railways, defence, transportation and engineering industries. It is also the largest manufacturer of stainless steel long products, bulk of which is exported to international markets. Mukand is a part of the Bajaj Group and Mr. Niraj Bajaj is the Chairman and Mr. Rajesh Shah is the Co-Chairman of the company. Mukand Ltd. desires to set up an Integrated Steel Plant of capacity 700,000 Tons / Year of rolled long products in phases. However, initially the rolling capacity will be 550,000 Tons / year. The Steel Plant shall be erected in modular form so that the capacity can be increased in a phased manner. Mukand Ltd. desires to set up the plant in Karnataka next to the existing Hospet Steels Plant. This will facilitate in transportation of the basic raw materials viz. Iron Ore, Metallurgical Coke, Coal etc. Presently Mukand produces more than 400 grades of steel and is approved by the original automobile equipment manufacturer to supply steel to the manufacturers of Auto components, High Tensile Fasteners, Cold Forge components, Industrial Bearings, Automobile Coil Springs, Industrial Chains and Bright Bar industries. The company is ISO 9001, ISO and ISO/TS compliant and is among one of the leading practitioners of Total Productive Maintenance (TPM) system, which is increasingly being adopted by all major manufacturing companies worldwide. Mukand s products are manufactured to international quality standards. 2.2 BRIEF DESCRIPTION OF THE NATURE OF THE PROJECT. M/s Mukand ltd. has proposed to set up Integrated Steel Plant of 0.7 MTPA capacity in Village- Kanakapur, Taluka & District- Koppal, Karnataka. The process route envisaged is Blast Furnace, E.O.F, Ladle furnaces, Vacuum degassing, Continuous Casting Machine, Wire Rod cum Bar mill. This liquid iron from the Blast Furnace in the form of hot metal shall be poured in the Energy Optimizing Furnace (EOF) and necessary Ferro alloys and other ingredients added in the 5

6 Ladle Furnaces and thereafter cast through the continuous casting machine there by manufacturing various grades of steel. These Blooms and Billets shall then be rolled to the required sizes and forms. The proposed Integrated Steel Plant of 0.7 Million MTPA capacity shall be set up in Village- Kanakapur, Taluka & District- Koppal, Karnataka on a total land area of approx 300 acres. The company intends to use Iron ore which is abundantly available in Bellary-Hospet sector and imported and indigenous coal from South Africa, China, Indonesia and Singareni Collieries Company Limited (SCCL), Andhra Pradesh. 2.3 Production Capacities of the proposed project: Mukand Ltd. has proposed to set up a Integrated Steel Plant of 700,000 Ton / Year capacity of rolled long products in phases. However initially rolling capacity will cater to 550,000 Tons/ Year. Table 1.1 Production Capacities Sr. No. Product Phase I (MT/Year) Phase II (MT/Year) Total (MT/Year) 1 Wire Rods 550, ,000 Cold heading wire rods, low carbon/boron steels, special steel wire rods i.e. semi free/free cutting/alloy steels/high carbon/mild steel rods 2 Bar Products Special steel bar products 150, ,000 Total 550, , , NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND REGION. One of the most useful and versatile material, steel is considered to be the backbone of human civilization. As the steel industry has tremendous forward and backward linkages in terms of material flow, income and employment generation, the growth of an economy is closely related to the quantity of steel used by it. Steel has been one of the oldest industrial sectors in India. It has also been the first to get liberalized and controls lifted partially in There have been massive capacity additions by all steel majors and several new groups made foray into primary and secondary steel market in the first phase of liberalization in early 90s. The major costs in steel making are the costs of Iron Ore, Metallurgical Coke, Limestone, Coal and Power. While the country is rich in 6

7 iron ore and limestone, its quality of coal is poor and power costs are high. The industry enjoys inherent advantages in terms of availability of raw material and cheap labour. India is the 3 rd largest producer of steel in the world accounting for production of million tons of crude steel in the Calendar year It also holds the third position in consumption of steel. Thus there is great potential of steel industry in India. Honorable Prime Minister Shri Narendra Modi has envisaged the growth of steel sector to attain a production capacity of 300 Million Tonnes by 2020, hence in order to achieve this capacity, it is essential to create the facilities based on local resources to produce steel. In view of these facts, the proposed project is envisaged as a Integrated Steel Plant with Coke Oven plant, Blast Furnace, E.O.F., Ladle Furnaces, Vacuum Degassing, Billet/Bloom Continuous Casting Machine, Wire Rod cum Bar Mill and Captive Power Plant. All these production technologies make the project a better energy efficient project due to which a substantial amount of Green House Gas (GHG) emissions would be avoided or reduced than the baseline emission. 2.5 DEMAND AND SUPPLY GAP The scenario of Steel Industry is clearly looking upward and the latest data on Steel Industry is as follows: An overview of Indian Steel sector- Rapid rise in production has resulted in India becoming the 3rd largest producer of crude steel and the largest producer of Sponge Iron or DRI in the world. As per the report of the Working Group on Steel for the 12th Plan, there exist many factors which carry the potential of raising the per capita steel consumption in the country, currently at 59.4 kg per annum in These include among others, an estimated infrastructure investment of nearly a trillion dollars, a projected growth of manufacturing from current 8% to 11-12%, increase in urban population to 600 million by 2030 from the current level of 400 million, emergence of the rural market for steel currently consuming around 10 kg per annum buoyed by projects like Bharat Nirman, Pradhan Mantri Gram Sadak Yojana, Rajiv Gandhi Awaas Yojana among others. When the global steel industry is witnessing slow growth, India is the only exception with 6.7% growth in demand in If Indian Economy is expected to grow at 8-9% in coming years, the demand potential for steel is very high. The High Level Committee on Manufacturing (HLCM) under the Hon. Prime Minister has set a target of raising annual crude steel making capacity to 300 million tonnes by

8 Major Objectives of the National Steel Policy 2012 are as follows: To attract investments in Indian steel sector from both domestic and foreign sources and facilitate speedy implementation of investment intentions on board so far so as to reach crude steel capacity level of 300 million tonnes by to meet the domestic demand fully. To ensure easy availability of vital inputs and necessary infrastructure to achieve a projected production level of 275 million tonnes by IMPORTS V/S. INDIGENOUS PRODUCTION Iron ore and non-cocking coal are available in abundance in India, but coking coal reserves are not very much. Thus steel production facilities added during the last 10 years in India are well established based on Coal Rotary Sponge Iron Kilns. Prior to implementation of the Sponge Iron Kiln based steel making the gap between demand and supply was fulfilled by import of steel. The Chinese manufacturers are giving tough competition to Indian steel producers because of their cheaper production cost. Therefore, in order to face the competition being poised by the Chinese manufacturer, it is important to provide good quality washed coal to existing Sponge Iron Plants in India and also to provide them with good quality Iron Ore / Pellets. In view of this, it is necessary to have good quality washeries. The Indian infrastructure sector is likely see a massive growth due to increasing economic status. 2.7 EXPORT POSSIBILITY Export of Steel is always possible, the Government of India is also encouraging export of steel, and however most of the quantity will be domestically consumed. The world steel market is for about 1500 Million Tonnes, out of which about 50% is being produced by China. But, China is in the process of cutting excess capacity and reducing its production in coming years. It offers a room for Indian steel manufacturers to export. by increasing its production in an energy efficient manner. 2.8 DOMESTIC/EXPORT MARKETS While the demand for steel will continue to grow in traditional sectors such as infrastructure, construction, housing, Automobiles, steel tubes and pipes, consumer durables, packaging, and ground transportation, specialised steel will be increasingly used in hi-tech engineering industries such as power generation, petrochemicals, fertilizers, etc. The new airports and railway metro projects will require a large amount of stainless steel. 8

9 Domestic market with real estate, infrastructure project, industrial projects will require steel which is estimated to be around 80 million tonnes per annum. The estimated growth in infrastructure is likely to increase the demand of steel to more than 150 million tonnes by the year In view of this it is required advance planning be made for creating the facility and infrastructure to meet this demand. The domestic market as well as export market both will require good quality steel, produced with minimum energy consumption and minimum cost of production. 2.9 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT. The total manpower required for the proposed project will be around 730 permanent executives during operation of the Plant. Employment generation due to the project is direct & indirect. Local people will be employed as per their qualification and skills. Phase Construction phase Operation phase No of Employees 1000 (tentatively inc. contract persons) 730 plus Persons on Contract 3. PROJECT DESCRIPTION: (i) Project Location & Connectivity M/s Mukand Limited has proposed to set up the Integrated Steel Plant of 0.7 MTPA capacity in Village- Kanakapur, Taluka & District- Koppal, Karnataka. The total land area required for the proposed project is approx. 300 Acre. The coordinates of the site is N and E. The proposed project site is easily approachable. The nearest Highway is NH-63 (adjacent to the Plant) and NH-13 (13.5 Km to the East). The nearest cities are Koppal and Hospet, which are situated at a distance of 11 km and 16 km in the west and east directions respectively. The nearest Railway station is Ginigera at a distance of 1 km, NW. Railway line is 0.5 km from the Plant in northern direction. The site is about 11 kms by rail from Koppal. The Tungabhadra reservoir is at a distance of 5.2 km in south western direction. Nearest Airport is Hubbali which is 125 Km in West. The company has chosen this site mainly due to its proximity to raw material sources and also better access to market. Also four Sea ports are within km distance. 9

10 (ii) Topography (along with map): Topography of the area is plain and undulating at some places. Topographic map of the study area is enclosed as Annexure Toposheet. (iii) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river), CRZ, In case of notified industrial area, a copy of the gazette: The Land acquired for the proposed project is arid and rocky will be converted for industrial use. There are no forests, national parks, wild life sanctuaries and eco sensitive zones situated in the 10 km study area. (iv) Soil classification: The proposed project site has rocky soil. The Taluka has some Rocky Mountains with xerophytic vegetation. The type of rocky soil in the taluka is clayey-loamy in scattered areas. (v) Climatic data from secondary sources: Koppal district experiences a semi-arid type climate, characterized by hot summer and low rainfall. It is cool and pleasant during major part of the year except during the summer months of March to middle of June. The coldest period is December to January minimum temperatures reaches up to 16 C and maximum reaches 45 C during hot summer during which period the district is characterized by dryness for the major part of the year. Because of less rainfall the monsoon season is pleasant. The annual normal rain fall is mm and normally rain commences from June and continues up to November. Heavy rainfall is received during the months of September and October, about 65% of which is from south west monsoon with normal average rain days of 40 in a year. (Source: A Report of CGWB) 10

11 3.1 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT BOUNDARY & PROJECT SITE LAYOUT) WITH COORDINATES. Figure 3.1: Location Map of the Project site 11

12 Figure 3.2: Google image of the proposed project site covering 5 Km radius 12

13 Figure 3.3 Schematic diagram/ Layout plan of the proposed project 13

14 3.2 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECT IF ANY. M/s Mukand Limited has proposed to set up an Integrated Steel Plant of 0.7 MTPA capacity in Village- Kanakapur, Taluka & District- Koppal, Karnataka. The Project shall have MBF, Coke Oven Plant, EOF, Ladle Furnace, Vacuum Degassing, Billet & Bloom Caster, Wired Rod/Bar Mill, Sinter Plant and Captive Power Plant (2x15.0 MW). 3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE HIGHLIGHTED: Since the selected site is strategically located, no alternate site has been considered for the proposed project. The project area is indicated in the Layout Plan/Schematic Diagram, which has been earmarked for industrial use. 3.4 PROJECT DESCRIPTION WITH PROCESS DETAILS COMPONENTS OF STEEL MANUFACTURING PROCESS: Sr. No. Table 3.1: Plant capacity & equipments (for 700,000 MT/year) Main Equipment Capacity For Phase I For Phase II Total (MT) Remarks Per day (Nos) (Nos) (phase I+ phase II) 1. Blast Furnace 2x450M %Sinter feed + P.C.I 2. DRI Purchased from local plant 3. Coke Ovens Balance requirement will be purchased 4. E.O.F 70T Ladle furnace 2x70MT/1 5MVA 6. Vacuum degassing With alloy feeding systems and 5 deg Celsius /min heating rate 2x70T

15 7. Billet/Bloom Caster 2x12/20 radius to cast 160x160m m to 4 strands 2x280x32 0mm 4 strands Sizes depending upon product mix for wire rod / Bar mill 8 Wire rod Mill/Bar 120 MT/Hr 2200T 1 Mill 9 Sinter Plant 2x50 M Tonnes 10 Oxygen Plant 2x MT Tonnes per day 11 Power Plant 2x15MW MW 1 700,000 TPA of Wire Rods & Bars - For EOF shop & 2% enrichment To produce power from waste gases MANUFACTURING PROCESS Pig Iron Plant Major raw materials for the pig iron manufacturing process are iron ore, coke and small quantities of dolomite, lime stone, etc. The raw material received in the plant is handled using mobile equipment and conveyor system. All the required raw materials are stored in day bins for 24 hr requirements. Coke below 50 mm is conveyed to a screen for further screening of 6 mm and coke size between 6-15 mm is conveyed back to one of the day bins. A weighing and batching system ensures the dosing of 6 to 15 mm coke along with ore. Fluxes, Manganese ore and quartzite feeds are controlled through vibro feeder. Depending on the sequence signal, the raw material is discharged to charging conveyor to be dropped into rotary hopper. Blast Furnace (BF) is the basic unit in a pig iron plant. The blast furnace process consists of charging iron ore and coke (as fuel), lime stone and dolomite (as fluxing material) into the top of the furnace and blowing preheated air near the bottom for burning the coke and providing the heat required for melting of the charge coming down. The hot air is generated in Metallic Blast Pre-heaters (MBPs) and introduced into the blast furnace through tuyeres, at the bottom. The iron ore with high Iron content mixed with metallurgical coke is charged into the blast furnace from the top along with fluxes in a predetermined proportion. The heated air rising up from the bottom starts combustion of the coke to yield carbon monoxide. The carbon 15

16 monoxide gas that rises up the column of the charge reduces the iron oxide. The reduced iron on reaching the bosh starts to melt due to the high temperature encountered in this zone into molten iron and slag and drops into the hearth of the furnace. In the hearth the slag and metal get separated. The molten iron accumulates at the bottom and on top of it molten slag layer settles. At regular intervals the accumulated molten metal is tapped in ladles and sent for steel making. The molten slag is granulated with high-pressure water jet and collected separately. The top gas from MBF units is conveyed to Gas Cleaning Plant (GCP) where dust is removed from the top gas by wet scrubbing system. The flow sheet for Pig Iron and Steel making is shown in Figure Sinter plant To utilize the fines generated during mining and processing of calibrated iron ore, a sinter plant shall be set-up. Sinter plant shall also use all waste material of the plant i.e. coke fines, mill scales etc. sinter is known to give higher productivity and lowers the consumption of coke in the blast furnace Coke ovens Productivity is decided by coke input and as such it is proposed that coke shall be produced at the plant site by bringing coal. Coke oven plant is proposed to be set up for blast furnaces. The coke ovens shall be non-recovery type and shall produce with sized dry coke of mm size (mean size of 50 mm). The coke produced shall be with stamp charging technology so as to give higher density thus leading to higher productivity of the blast furnaces and lower consumption of 500 kg/mt of gross and dry coke Proposed Blast Furnace Plant The blast furnace shop will be provided with a conveyorized stock house with screening facilities for coke and iron ore. All the charge materials will be weigh-batched in predetermined quantities automatically and charged to the blast furnace through a conveyor system. The furnace is provided with bell less top charging system, hot blast stoves of internal combustion chamber type, cast house with one tap hole for iron and one slag notch. A fleet of 45 tonnes open top hot metal ladles is provided. The hot metal produced in the Blast Furnace shall be transported to Steel Making shop by ladle transfer car. Surplus hot metal, if any, shall be cast into pigs in existing Pig casting Machine. Slag produced from Blast Furnace shall be granulated in slag granulation plant. A cast house slag granulation plant with Grab bucket crane for loading of granulated slag into trucks shall be provided. An emergency dry slag pit shall be provided to handle emergency situations. The blast furnace 16

17 gas will be cleaned in dust catcher and gas cleaning plant and distributed to various consumers. Steel Manufacturing Process Energy Optimizing Oxygen Furnace The oxygen process is the most common process for producing steel. The Energy-optimizing oxygen furnace (EOF) involves this process using combined submerged (bottom) and atmospheric (top) blowing. The hot metal from KSL unit is taken into the EOF; the 20-30% scrap is then added into the hot metal. The necessary fluxes (ferro-alloys, calcined lime, iron ore) are also added to the bath. Oxygen is blown into the bath through water-cooled lances using combined bottom and top blowing. EOF will be designed to have a blowing time of less than 20 minutes and overall cycle time less than 40 minutes per heat. During blowing operation, oxygen oxidizes iron into iron oxide and carbon into carbon monoxide. The iron oxide immediately transfers the oxygen to the tramp elements, which leads to formation of reactive slag. As blowing continues, there is a continuous decrease of carbon, phosphorous, manganese and silicon within the melt. The refining process is completed when the desired carbon content is attained. The steel is tapped into the Ladle Furnace by a transfer trolley. The slag is discharged into the slag pot Ladle furnace and Vacuum Degassing Unit The Ladle furnace acts as a buffer between EOF and Continuous Casting Machine. It is utilized to maintain high levels of steel cleanliness, desulphurisation and accurate temperature control. The required temperature is maintained with the help of small electrodes, while the melt is homogenized by introduction of inert nitrogen/ argon gas. The ladle is then lifted and taken to Vacuum Degassing unit. Vacuum Degassing refines the molten steel by removing unwanted hydrogen and nitrogen gases. The molten metal ladle from LF is placed under vacuum generated by multiple stage steam ejectors. After sampling of the steel and temperature measurement, the ladle is shifted to continuous casting machine. The Vacuum-degassing unit utilizes steam generated by a boiler run by furnace oil Continuous Casting Machines It is proposed to install two S type casters to cast (Billets) of size 160 x 160 mm and (Blooms) of 280 x 320 mm size. All products shall be cast with ladle to tundish and tundish to mould shroud with mould flux lubrication. The casters, shall be of 4 strands so as to cast heat in min cycle with high speed casting. The casters shall be designed with turret to have long sequences and flying tundish practice. Casters shall have Auto Mould Controller and Electro 17

18 Magnetic Stirrer to achieve superior internal quality of Billets / Blooms. Large Size Tundish with T shape and dams shall be designed to get high level of cleanliness with no entrapment of non-metallic macro inclusions. Caster shall cast 20 heats / day with desired quality level so that no Billet conditioning is required before rolling Billet / Bloom Inspection Area Sample cutting and inspection facility to control the quality shall be provided in the Caster Bay. This facility shall provide constant feedback to the shops Wire rod / Bar Mill facility (1 Nos) It is proposed to roll 60,000 MT per month of Billets of 160 x 160 mm in Bar cum Wire rod mills (1 nos). The mill shall be designed to roll 5.5 to 36.0 mm dia. size in coil form of 2 MT each and 20mm to 60mm dia. in straight lengths. A walking beam type furnace with heating rate 120 MT / hour having 10.5 Meter length to accommodate 160 x 160 mm cross section shall be designed. Mill shall roll wire rods / bars at an average of 110 MT / hour. At 80 % utilization of the Mill, it shall produce 2200 MT / day of finished products. The Wire rod mill shall have roughing, intermediate and two finishing blocks to finish from 5.5 to 20mm dia. through Block Mill and balance through Garret route. Mill shall be designed to have 80 to 100 m walking beam type cooling bed to roll 20 mm to 60mm dia. bars in straight lengths. Cold shears shall cut the bars in specific lengths. Mill shall have conveyer to inspect end cuts, strap and weigh the coils before unloading for final dispatch. As such, no off line activities shall be required for handling of coils. Part of the product, which require heat treatment shall be transferred to heat treatment section. Bars thus produced which need crack detection / MPI test shall be shifted to the Bar Mill Inspection area for descaling (by straightening), magnaflux particle testing, other inspection and final strapping before dispatch Lime Kiln To produce high quality steel for stringent application, good quality lime is required for the steel Plant. The consumption shall be 150 MT / day, hence it is proposed to have 2 Kiln of 100 MT / day. Lime stone with % CaO content shall be converted to Lime with 92 % min. CaO and 4 % Max Loss Of Ignition. 18

19 Captive Power Plant It is proposed to set up a power plant by utilizing waste gases of coke ovens and blast furnaces to produce 30 MW power by using waste gas recovery boilers and turbines. This shall supplement the power drawn from the state electricity grid. The process flow diagram of Power Plant is enclosed as Annexure III in additional Annexures. 19

20 Iron Ore Coke Flux Iron Ore DRI Coal MBF Return Scrap Hot Metal Energy Optimizing Furnace (EOF) Ladle Furnaces with Alloy Feeding / Injection Vacuum Degassing Continuous Casting Machine Blooms /Billets Billets Continuous Bar Mill Wire Rods /Coils / Straight Lengths Round Bars Dispatch Fig Schematic Process flow for Iron & Steelmaking 20

21 3.5 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY LIKELY SOURCE MARKETING AREA OF FINAL PRODUCT/S,MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT. Raw material- Requirement, Storage & Handling System The proposed requirement of raw materials in the manufacturing of steel units is detailed in the Table below. Table 3.2 Raw Material Consumption Sr. No. Raw Material Quantity (Tonnes)/Day 1. Iron Ore 1,581,300 MT/Year 2. Coking Coal 350,000 MT/Year 3. Limestone 200,000 MT/Year 4. Dolomite 70,000 MT/Year Miscellaneous small quantities of Quartz, Coke breeze etc. shall also be required and the same shall be sourced suitably Sources of Raw Materials The major raw materials as indicated above are iron ore, limestone and coke. The iron ore mines in Bellary-Hospet area are the main source for iron ore, which shall be transported by road to the plant. Limestone will be brought from Bagalkot, Karnataka (Approx. 200 km) by road. Coke shall primarily be imported and transported from the nearest port by road. Other required raw materials will be obtained locally and transported by road to the plant Receipt, Storage and Handling of Raw Materials Raw materials received in tripper trucks/road dumpers will be unloaded either at designated storage area of respective material or in tripper truck unloading pit directly. Raw materials unloaded in storage area will be stacked in heap by bulldozers. Reclaiming of raw materials from stacked heap will be carried out by pay loaders for transportation to tripper truck unloading pit by tripper trucks/road dumpers. Onward transportation of raw materials from the above pit to BF stock house will be done through conveyor belts. The raw materials transported from storage area will be distributed into respective bunkers through a reversible shuttle conveyor belt envisaged at the top of stock house. The holding capacity of bunkers will be adequate to cater to 2-shifts requirement of raw materials for blast furnace. Screening of coke, nut coke and iron ore will be carried out in the BF stock house. Screened coke, nut coke, iron ore and additives will be conveyed to blast furnace 21

22 top through weigh hoppers and charging belt conveyors. Fines collected from screens in BF stock house will be stored in a separate fine storage building by belt conveyors. Fine coke (0-25) mm will be further screened in the fine collection building for coke to segregate coke of 0-6mm & 6-25 mm. Nut coke (6-25mm) will be sent back to BF stock house through storage yard by trucks whereas fines (0-6 mm) will be disposed off by truck. For transportation of raw materials a covered conveyor from the storage yard to the stock house is proposed. The raw materials required for the production of the sponge iron are the iron ore fines, coal, limestone and bentonite. The Fe content of Iron ore should preferably be 65% and above with Gangue content below 5%. In respect of coal the fixed carbon should be 57% or higher, with ash not more than 15%. Limestone, which is used as a desulphuriser, should have a Calcium oxide content of above 45%.Trucks will be used daily for the transportation of raw materials and finished products. 3.6 RESOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE PROJECT IF ANY SHOULD BE BRIEFLY OUTLINED: The waste water generated from the process will be treated as per suitable technique used in Effluent Treatment Plant. Cooling tower and Boiler blow down water will be continuously re-circulated in the cooling water circuits, heat exchangers and discharged to the guard pond. DM backwash, cooling tower and boiler blow down will be neutralized in a neutralization tank and used for gardening and dust suppression. Domestic effluent will be treated in sewage treatment plant. 3.7 AVAILABILITY OF WATER AND POWER AND THEIR SOURCES WATER REQUIREMENT Total water requirement for the proposed project will be 18 MLD. Source of Water is from downstream of Tungabhadra Reservoir. Tungabhadra River is a perennial river and caters to the need of irrigation and potable water. Water from downstream of reservoir will be drawn within the sanctioned capacity of 18 MLD by the Government of Karnataka s letter no. WRD.15/MTP/2013 dated 22 December A new reservoir capacity of 650,000M 3 is proposed to be constructed. 22

23 Table 3.2 Water Balance Table Sr. No. Type of use Water requirement (M 3 /Day) 1. Domestic, if any Industrial a. R.O/D.M b. Boiler 233 c. Process 2097 d. Cooling Tower (fresh) 3262 e. Cooling Tower (Reuse) 233 f. Other activities (including washing) Total Ind. Water(Fresh) Total Ind. +Domestic Water (Fresh) Total (Reuse) TOTAL WATER Waste water Generation, m3/day 583 The total Waste water generation will be 583 KLD. Domestic & Trade effluents shall be treated in Sewage Treatment Plant & Effluent Treatment Plant similar to the interlinked Unit. Treated water will be reused for process, dust suppression and gardening purposes. There will be no discharge of water outside the plant premises POWER REQUIREMENTS, SUPPLY AND SOURCE: The electrical and instrumentation has been so designed to meet the continuous operation of the plant. As the plant will be running 24 hrs in three shifts, the necessary power supply, illumination, instrumentation and control system is envisaged. Total Power requirement will be 60 MW. Out of which 30 MW shall be met by captive power generation from waste gases of Blast Furnaces and Coke Ovens and rest of the 30 MW will be sourced from the state utility grid (KTPCL/GESCOM). Three no. of D.G. sets of 1250 KVA each will be used for power back-up. Table 3.3 power requirement Sr. No. Source Phase I Phase II Total 1 Captive Power Plant 15 MW 15 MW 30 MW 23

24 2 Total Demand 33 MVA 27 MVA 60 MVA 3 Power (Max demand) 18 MVA 12 MVA 30 MVA from Grid- KPTCL/GESCOM 4 Consumption (million units/month) 5 D.G. Set (Back-up) 1250x3 KVA x3 KVA 3.8 WASTE GENERATION AND THEIR MANAGEMENT AND DISPOSAL SOLID WASTE MANAGEMENT: The various types & quantities of solid and hazardous wastes generated from the plant are indicated in Table 5.4. Hazardous wastes generated are handled as per Hazardous Waste Management & Handling Rules, S. No Type of waste Table 3.4 Waste (Hazardous & Non-Hazardous) details: Classification as per Schedule I Proposed Quantity Disposal Used Oil KL/Annum Sold to HW Authorized parties. 1 Oil Soaked Cotton Waste MT/Annum Sold to HW Authorized parties. 2 ETP Sludge NA - ETP Sludge is used in Blast Furnace 3 Slag Non-Hazardous 1,40,000 TPA Reuse for Brick making/road making/dump in low lying areas/sold to authorized parties DETAILS OF THE CONTROL EQUIPMENTS FOR AIR POLLUTION (TABLE 3.5) Sr. No. 1 Source Capacity Control Equipments Performa nce Efficiency MBF 2x450m 3 One Wet type GCP having dust catcher, saturator, 2 stage venturi scrubber, cyclone separator & sludge Stack Ht. (m) 97% 30 24

25 Energy Optimizing Furnace Rolling Mill Reheating Furnace Boiler in Vaccum Degassing Power Plant Boiler thickener. 70 T Wet Type GCP having Quench Chamber, 97% 39 Venturi, Cyclone Separator, Sludge Thickener. - Chimney T Chimney x15 MW Chimney INDUSTRIAL WASTE WATER MANAGEMENT: TABLE 3.6 WASTEWATER SOURCES AND ITS TREATMENT Waste Water Sources Treatment and Reuse DM Plant/ Softner Plant Regenration Entire effluent is recycled to Pig Casting Machine and Slag granulation Process after neutralization, clarification and aeration Filter Backwash Recycled to slag granulation process Energy Optimising furncace (Evaporation/Blowdown) Blowdown is collected in Guard pond and reused for dust suppression & green belt development Gas Cleaning Plant (Evaporation/Blowdown) Blowdown is collected in Guard pond and reused for dust suppression & green belt development Vaccum Degassing (Evaporation/Blowdown) Blowdown is collected in Guard pond and reused for dust suppression & green belt development Machine cooling / Mould cooling Blowdown is collected in Guard pond and reused for dust suppression & green belt development (Evaporation/Blowdown) Waste water from Rolling Mill Blowdown is collected in Guard pond and reused for dust suppression & green belt development Sanitary Waste Treated in STP and used for green belt development within the plant premises 25

26 Figure 3.5: ETP plant layout Sewage Treatment Plant Process The sewage treatment plant is designed for treating the sewage and canteen Wastewater. The system adopted for sewage treatment is extended aeration activated sludge. The system consists of bar Screen Manually Cleaned (near Canteen), Float Trap (Near Canteen), Sewage Sump, Aeration Tank, Secondary Setting tank, Secondary Treated Water Storage Tank. System Working The Wastewater from canteen is screened in Screen chamber to remove coarse solids and floating matter in float trap before taking sewage to the aeration tank Sewage is Pumped to Aeration Tank using submersible pump. In aeration tank sewage is treated with biological method using extended aeration activated sludge process where Sewage is treated with microbes which eat up organics and reduce organics (BOD/ COD) in sewage. The oxygen required for growth of microorganism is supplied by surface aerator. The growth in microbial population takes place and biofloc are formed. The biofioc with treated sewage is taken to secondary settling tank where biofloc settles and clear water overflows to secondary treated sewage storage tank. To keep the microbial population in aeration tank constant sludge from secondary settling tank is recalculated 26

27 to aeration tank using Sludge Recirculation pumps. Excess bio-sludge is dried on sludge drying beds. The treated sewage from secondary storage tank is disinfected in Storage Tank prior to taking for reuse for reuse for Gardening. Figure 3.6: STP plant layout 27

28 4.0 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, TRANSPORTATION ETC) TOWN AND COUNTRY PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION: 4.1 BASIS OF PLANNING: The active manpower estimate is based on production technology proposed level of mechanization and automation, the layout of the plant, operating shifts for the various plant units etc. 4.2 POPULATION PROJECTION: There will be temporary population projection due to direct and indirect employment to the nearby people. The Project area is surrounded with Sponge Iron, Steel & other industries viz. Hospet Steels Ltd. (Integrated Steel Plant), Xindia Steels Limited (Pellet Plant), Harekrishna Sponge (Sponge Iron plant), HRG (Sponge Iron plant), Dhraudesh (Sponge Iron plant), Hospet Ispat (Sponge Iron plant), Scan Steels (Sponge Iron plant), Ultratech (Cement Plant), Kirloskar Ferrous Limited (Pig Iron Plant). 4.3 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC) Total Land acquired for the proposed project is 300 acre/1,213,800 m 2. Land is owned by the Company for Industrial purpose. TABLE 4.1 land use pattern of the project site Sr. No. Description Area (m 2 ) 1 Plant Storage Utility Administrative Building Effluent treatment plant Green belt Parking Colony & Open area Total 1,213,800 28

29 4.4 ASSESSMENT OF INFRASTRUCTURE DEMAND M/s. Mukand Ltd. will provide utilities and other infrastructural facilities for its employees in the proposed project. All the employees and workers will be sourced from nearby villages hence no residential colony is proposed. All other infrastructure facilities like market; education; communication etc are well developed in the nearest area. Mukand Ltd. has assessed the infrastructural demand of the study area, based on the detailed plan of action as part of proposed CSR activities with a budget of Rs 10 Lac is proposed. M/s. Mukand Ltd. as a corporate body has taken up following Social Development works: Providing Medical facilities for Primary Health Centre in near by villages. Providing Education implements to Primary School in near by villages. Providing School uniforms, Books, Sports facilities to the school children of near by villages. Providing Ambulance facilities for nearby villagers. Providing funds for Cultural activities & community celebrations to nearby villagers from Sponge Iron Manufacturers Association. 4.5 SOCIAL COMMITMENT PLAN Socio-economic development activities done by Mukand ltd. (Unit-I) in the surrounding area are listed below; Establishment of RO drinking water treatment plant in Kanakapur. Construction of concrete roads and drains at Ginigera. Free eye check up camp along with distribution of spectacles for lower income groups in Ginigera and Kanakapur. Provision of solar lanterns to local high school students at Ginigera. Provision of desks, benches and utensils to local village schools Provision of tuition fees for students scoring low marks in English, Mathematics and Science in SSLC Ginigera High School. Development of health, hygiene and nutrition programs for villagers. Trucks are used for transportation of raw materials and finished products which are covered with tarpaulin. Proper measures are taken for controlling pollution. 29

30 5.0 PROPOSED INFRASTRUCTURE. 5.1 PLANT AREA All plant units, office building, stores, laboratories etc. will be provided with all amenities. 5.2 RESIDENTIAL AREA: All the manpower in the proposed project is sourced from the neighboring villages hence no colony/ residential area is proposed in the project. 5.3 GREEN BELT Green belt will be developed in and around the proposed project site in an effective way as per prescribed norms by CPCB to check pollutants and their dispersion into surrounding areas. The degree of pollution attenuation by a green belt depends on its height and width, foliage surface area and density. The main objective of green belt is as follows: i. Mitigation of impacts due to fugitive emissions caused by vehicles ii. Attenuation of noise levels iii. Ecological restoration iv. Creation of aesthetic environment 5.4 SOCIAL INFRASTRUCTURE All the infrastructural facilities like market; education; communication etc are well developed in the nearby area. Mukand Ltd. has assessed the infrastructural demand of the study area. 5.5 CONNECTIVITY The proposed project site is easily approachable. The nearest Highway is NH-63 (adjacent to Plant) and NH-13 (13.5 Km, East). THE nearest cities are Koppal and Hospet, which are situated at a distance of 11 km and 18 km in west and east directions respectively. The nearest Railway line is Ginigera at a distance of 1 km, NW. Railway line is 0.5 km from the Plant in northern direction and the nearest railway station is Ginigera. The site is about 10 km by rail from Koppal. Nearest Airport is Hubbali which is 125 Km in West 5.6 DRINKING WATER The source of water for the project will be supplied by Tungabhadra Dam. Previous studies reveal that, for the ground water quality is meeting with Drinking Water standards. The company proposes to use water for domestic purpose as well as Drinking water is made available for all the workers in the plant premises. 30

31 5.7 SEWERAGE SYSTEM The domestic / canteen wastes are treated in the STP, which consists of equalization/ neutralization unit, aeration tank followed by settling pond. The treated water, after confirming to prescribed norms, is used for greenbelt development. The domestic waste from the colony is treated separately in septic tank and soak pits. A Sewage Treatment Plant has also been proposed for the colony. 5.8 INDUSTRIAL WASTE MANAGEMENT Proposed project will not be major source of hazardous waste generation. However the substances that are hazardous are spent oil etc. solid wastes generated will be reused in the process or sold to authorized vendors. 5.9 POWER REQUIREMENT & SUPPLY/ SOURCE The total power required will be 60 MW, which will be met from Captive Power Plant by support of 30 MW and rest of the requirement of 30 MW will be met by state electricity grid (KTPCL/GESCOM). 6.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN R & R plan is not applicable at this stage of project, as the land ownership has already been obtained and Displacement of people is not involved in the project. 7.0 PROJECT SCHEDULE AND COST ESTIMATE 7.1: LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE GIVEN) It is estimated that in Phase-I 550,000 Tonnes per year Steel production capacity project shall be completed in 30 months time from the date of breaking the ground. Thereafter Phase-II - additional 150,000 Tonnes per year Steel production shall be completed in 24 months time after commissioning Phase I. 7.2: ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT. The total project cost is estimated Rs Crore, based on quotations obtained in consultation with technical consultant, for various major plant and machinery items. 31

32 Sr. No. Particulars Table 7.1 Estimated Project Cost Estimated cost (Rs. In Crores) 1 Phase Phase I Phase II Cumulative Capacity (MT/year) Land procurement and site development 350, , , last Furnace + PCM Steel Melt Shop (E.O.F, Ladle 3 Furnace, VD, Caster) Wire rod cum bar mill + Bar Mill Captive Power Plant (2 x 12 MW) Lime Kiln (150 T / day) Raw material handling, Power distribution, Communication facilities etc. 8 Coke Oven Plant (2x120,000 TPA) Margin money for working capital Sinter Plant (2x50 M2) Interest etc. (during project execution) Contingency (7.5%) Total ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION) Looking at the present market scenario, it is concluded that the project is not only feasible and viable, but it will also increase the employment Opportunity and developmental activities of the area in future. 32

KALYANI STEELS LIMITED

KALYANI STEELS LIMITED SUMMARY 1. Kalyani Steels Limited (KSL), in strategic alliance with Mukand Limited is operating Hospet Steels Limited, an integrated steel plant in Koppal district of Karnataka. The existing plant capacity

More information

Environment Consultant:

Environment Consultant: MODERNIZATION CUM EXPANSION OF INDUCTION FURNACE PRODUCTION(2,05,000 TPA TO 6,00,000 TPA) AND ROLLING MILL PRODUCTION (3, 69,000 TPA TO 6,00,000 TPA) at Sy. No. 158 (part) 159 (part), 166 170, village

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR DYES, PIGMENTS AND DYE INTERMEDIATES MANUFACTURING PLANT IN GIDC, DAHEJ-II Of M/s. SHREEJI INDUSTRIES Plot No. D2/CH/24, Dahej-II, GIDC Industrial Estate,

More information

TOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY. By N. Ramachandran, Ion Exchange (India) Ltd

TOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY. By N. Ramachandran, Ion Exchange (India) Ltd TOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY By N. Ramachandran, Ion Exchange (India) Ltd Large quantities of water are required to produce steel and steel products - typically 180-200 m 3 of water per

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF BAKELITE POWDER MANUFACTURING UNIT of M/S. HINDUSTAN BAKELITE COMPANY PLOT NO. J-3436, GIDC ESTATE, ANKLESHWAR, DISTRICT: BHARUCH-393002, GUJARAT 0 CONTENTS

More information

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF (B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF Makwana Dineshbhai Khimjibhai AT VILLAGE:- Tithava, TALUKA:- Wankaner, DIST.:- Morbi 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXCUTIVE SUMMARY

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT PREPARED FOR SHIV SHANTHI CEMENT PRIVATE LIMITED Sy. Nos. 92, 93 & 94, Tatiguda Village, Garividi Mandal, Vizianagaram District, Andhra Pradesh. PREPARED BY ISO 9001: 2008 Certified

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT (B) PREFEASIBILITY REPORT OF EXISTING SAND MINING PROJECT OF RAJESHBHAI BHAGUBHAI PATEL AT VILLAGE:- Panchlai, TALUKA:- Pardi, DIST.:-Valdad. 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

M/s. MID India Power & Steel Pvt. Ltd. has proposed to establish Steel Plant at Dongartola

M/s. MID India Power & Steel Pvt. Ltd. has proposed to establish Steel Plant at Dongartola 0 1.0 INTRODUCTION M/s. MID India Power & Steel Pvt. Ltd. has proposed to establish Steel Plant at Dongartola Village, Kotma Tehsil, Annupur District, Madhya Pradesh. 10.29 Acres of land is envisaged for

More information

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT For CHHATTISGARH ENVIRONMENT CONSERVATION BOARD CHHATTISGARH 0 P a g e 1.0 INTRODUCTION SUMIT ISPAT PVT. LTD. has proposed to establish Submerged

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY M/s Arti Chemical Industries is a project located at Plot No. E-22, Vilayat G.I.D.C. Tal: Vagra area of Bharuch district in Gujarat. M/s Arti Chemical Industries

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

PRE-FEASIBILITY REPORT OF M/s ILC IRON & STEEL PVT.LTD

PRE-FEASIBILITY REPORT OF M/s ILC IRON & STEEL PVT.LTD PRE-FEASIBILITY REPORT OF M/s ILC IRON & STEEL PVT.LTD 1. Introduction of the project M/s ILC Iron &Steel Pvt.Ltd is incorporated by a team of directors namely Sri K. Somasekhar and Sri K. Chandrasekhar.

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT FOR INCREASING THE PRODUCTION CAPACITY of EXISTING BLAST FURNACES From 2,92,000 TPA to 3,50,000 TPA (Increase by 58000 TPA) BY Process Optimization & Efficiency Improvement LOCATION

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

Mars Power & Steel Ltd.

Mars Power & Steel Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Mars Power & Steel Ltd. Village : Baihamura Tehsil : Ghargoda District : Raigarh Submitted to: Page 1 CHHATTISGARH ENVIRONMENT CONSERVATION BOARD Executive

More information

M/S. Dain Colour Chem

M/S. Dain Colour Chem PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of M/S. Dain Colour Chem Plot No.: 5, Nilkanth Estate, Village: Dhanot, Ta.: Kalol, Dist.: Gandhinagar-382729, Gujarat 1 CONTENTS

More information

Simran Industries Pvt. Ltd.

Simran Industries Pvt. Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Patharra Village Bemetara Tehsil Durg District Chhattisgarh Submitted to: CHHATTISGARH ENVIRONMENT CONSERVATION BOARD Raipur, Chhattisgarh 1.0 INTRODUCTION

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT Of M/s. SHREE RAM INDUSTRIES PLOT NO.5117, GIDC-ANKLESHWAR, PIN-393002 TAL: ANKLESHWAR, DIST: BHARUCH, GUJARAT

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW PROJECT (PIGMENT MANUFACTURING PLANT) Of M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) CONTENTS Sr.

More information

Capacity as per EC Dt commissioned 1 Sponge Iron 2.0 MTPA 1.0 MTPA 0.4 MTPA 0.6 MTPA 2 Captive Power Plant Co-generation Power Plant (WHRB)

Capacity as per EC Dt commissioned 1 Sponge Iron 2.0 MTPA 1.0 MTPA 0.4 MTPA 0.6 MTPA 2 Captive Power Plant Co-generation Power Plant (WHRB) Brief Note Prakash Industries Limited (PIL) is existing Integrated Steel Plant located at Hathneora, Champa Villages, Janjgir-Champa District, Chhattisgarh. Existing plant has obtained Environment Clearance

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

Accord Energy Corporation India Pvt. Ltd.

Accord Energy Corporation India Pvt. Ltd. Accord Energy Corporation India Pvt. Ltd. PRE-FEASIBILITY REPORT ON ENVIRONMENTAL ASPECTS OF PROPOSED INCREASE IN CAPACITY 2 x 150 MW to 2 x 180 MW OF EXISTING ENVIRONMENTAL CLEARANCE ( J-13012/107/ 2009-IA-II

More information

PRE-FEASIBILITY REPORT OF SAND QUARRY

PRE-FEASIBILITY REPORT OF SAND QUARRY PRE-FEASIBILITY REPORT OF SAND QUARRY Survey No Village Taluka District Lease area : 1 Paiki : Marigana : Anjar, : Kutch, Gujarat, : 2.00 Ha. Submitted to MINISTRY OF ENVIRONMENT & FORESTS STATE LEVEL

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

Shri Girija Alloy & Power (I) Pvt. Ltd.

Shri Girija Alloy & Power (I) Pvt. Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Shri Girija Alloy & Power (I) Expansion of Ferro Alloys unit at Submitted to ANDHRA PRADESH POLLUTION CONTROL BOARD 0 1.0 PROJECT DESCRIPTION Shri Girija

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

PARTH ISPAT (INDIA) PRIVATE LIMITED

PARTH ISPAT (INDIA) PRIVATE LIMITED CHAPTER 1: INTRODUCTION 01.01 General Steel being a basic commodity for all industrial activities, quantum of its consumption is considered as an index of industrial prosperity. Since independence, there

More information

Hot Rolled Products Analyst Site Visit Port Kembla

Hot Rolled Products Analyst Site Visit Port Kembla Hot Rolled Products Analyst Site Visit Port Kembla Lance Hockridge 19 May, 2003 Originally issued by BHP Steel. On 17 November 2003 BHP Steel became BlueScope Steel Limited. Port Kembla Steelworks Overview

More information

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR AT VILLAGE:- BRAHMPURI, TALUKA:- Sayla, DIST.:-Surendranagar 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE

More information

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Pre Feasibility Report On STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Submitted to MINISTRY OF ENVIRONMENT & FOREST STATE LEVEL ENVIRONMENTAL

More information

The below is a detailed evaluation of the EIA report, based on a community request from Ekta Parishad, a local NGO in Chhattisgarh.

The below is a detailed evaluation of the EIA report, based on a community request from Ekta Parishad, a local NGO in Chhattisgarh. EIA Review of Nalwa integrated steel plant (NSPL) Background Nalwa integrated steel plant (0.198 MTPA sponge iron), located near village Taraimal, Raigarh district, Chhattisgarh proposes to expand its

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

Welspun Maxsteel Limited

Welspun Maxsteel Limited 00 Summary 00.01 Introduction The US$ 3.5 billion Welspun Group is one of India s fastest growing conglomerates having registered a CAGR of 30% over the last decade. It has a presence across five business

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

PRE-FEASIBILITY REPORT. NR TMT (India) Private Limited

PRE-FEASIBILITY REPORT. NR TMT (India) Private Limited SUBMISSION TO STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, CHHATTISGARH By NR TMT (India) Private Limited at Plot No.: 211, 213 (Part) & 212 (Part), Sector L, O.P. Jindal Industrial Park, Village Punjipathra,

More information

Kirloskar Ferrous Industries Limited, Bevinahalli Village, Koppal Taluk & Dist Karnataka

Kirloskar Ferrous Industries Limited, Bevinahalli Village, Koppal Taluk & Dist Karnataka 0 FORM V (See rule 14) ENVIRONMENTAL STATEMENT FOR THE FINANCIAL YEAR ENDING THE 31 ST MARCH-2017 PART A i. Name and address of the owner: Mr. R. V. Gumaste Occupier of the industry Managing Director Operation

More information

ENVIRONMENTAL STATEMENT FOR THE YEAR

ENVIRONMENTAL STATEMENT FOR THE YEAR ENVIRONMENTAL STATEMENT FOR THE YEAR 2016-17 6 MTPA STEEL PLANT OF TATA STEEL AT KLAINGANAGAR INDUSTRIAL COMPLEX, ODISHA ENVIRONMENTAL DEPARTMENT TATA STEEL KALINGANAGAR Kalinga Nagar Industrial Complex,

More information

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report Limestone Mining Project (Area: 16.18 ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For MINING ACTIVITY CATEGORY B2 UNDER

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri Door No. 39/49/39,

More information

PRE-FEASIBILITY REPORT FOR ORDINARY SAND

PRE-FEASIBILITY REPORT FOR ORDINARY SAND PRE-FEASIBILITY REPORT FOR ORDINARY SAND Proponent NISANT TRADERS At- Opp. Survey No.- 3 Panam River Area-2.50.00 Hectare Village-Ramji-ni-Nal, Taluka- Shahera Dist.- Panchmahal Mob.- +91924040782 CONTENTS

More information

SHADEED IRON & STEEL OMAN, SOHAR PORT THE FIRST HOTLINK STEEL PLANT

SHADEED IRON & STEEL OMAN, SOHAR PORT THE FIRST HOTLINK STEEL PLANT OMAN, SOHAR PORT THE FIRST HOTLINK STEEL PLANT 1 TOPICS Introduction SHADEED Project History SHADEED Design Basis DRI Hotlink Technology Advantages of Hotlink Melt shop Design basis Conclusions 2 SHADEED

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS OF M/s. MAYUR COLOUR AND CHEMICALS LOCATED AT Plot No. 5148, GIDC Industrial Estate, Ankleshwar

More information

STEEL INDUSTRY OVERVIEW

STEEL INDUSTRY OVERVIEW Slide No 1 Schenck Process weighing feeding screening automation STEEL INDUSTRY OVERVIEW Slide No 2 IBS Heavy Industries: Cement Sand & gravel Coal (users) Steel NF-metals Power plants (fossil) Foundries

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Lecture 19: Emerging Steelmaking Technologies

Lecture 19: Emerging Steelmaking Technologies Lecture 19: Emerging Steelmaking Technologies Contents: Basis Energy Optimizing Furnace CONARC Key words: EOF, CONARC Basis: To develop ecological balance technology. Such a technology would require processing

More information

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant PRE FEASIBILITY REPORT FOR Silica Sand Beneficiation Plant BY Shree Silicaam Minerals LLP VILLAGE : CHOKI TALUKA : JAGADIA DIST : BHARUCH GUJARAT (INDIA) PRE-FEASIBILITY REPORT: SILICA SAND BENIFICIATION

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

State Investment Promotion Board List of M.o.U.'s Signed by C.S.I.D.C. & Govt. of Chhattisgarh Updated on Name of Products Annual Capacity

State Investment Promotion Board List of M.o.U.'s Signed by C.S.I.D.C. & Govt. of Chhattisgarh Updated on Name of Products Annual Capacity State Promotion Board List of M.o.U.'s Signed by C.S.I.D.C. & Govt. of Chhattisgarh Updated on 01.10.2007 3- Steel Products 205000 TPA 4- Coal Washery 2500000 TPA 5- Aluminium Plant 50000 TPA 6- Ferro

More information

at Sarora Village, Tilda Tehsil, Raipur District, Chhattisgarh in 64 acres of land. Now

at Sarora Village, Tilda Tehsil, Raipur District, Chhattisgarh in 64 acres of land. Now 1.0 INTRODUCTION M/s Khetan Sponge & Infrastructure Pvt. Ltd. is and existing sponge iron plant at Sarora Village, Tilda Tehsil, Raipur District, Chhattisgarh in 64 acres of land. Now it has been proposed

More information

SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT. Village : Taraimal, Tehsil : Gharghoda District : Raigarh

SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT. Village : Taraimal, Tehsil : Gharghoda District : Raigarh SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Village : Taraimal, Tehsil : Gharghoda District : Raigarh Submitted to: CHHATTISGARH ENVIRONMENT CONSERVATION BOARD Raipur, Chhattisgarh 1.0 INTRODUCTION

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

BEST PRACTICES ON ENERGY EFFICIENCY

BEST PRACTICES ON ENERGY EFFICIENCY BEST PRACTICES ON ENERGY EFFICIENCY > JSW Steel Limited, Dolvi Works Key Themes: Lowest Energy Consuming unit amongst Integrated Steel Plant in India Continuously Improving Energy

More information

Expression of Interest

Expression of Interest Expression of Interest (Advertisement to be published in the Newspapers) Sub: Expression of Interest ( EOI ) for appointment of Rolling Mills (RM) for Conversion of Billets into CTD/TMT Rebars and Structurals

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY Shri Ashok Patel Partner of M/s. Patel Polymers is planning to manufacture organic chemical Different Types of Resins, for proposed expansion project at Plot

More information

IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA

IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA M/s. ARTEMIS BIO TECH LTD., (A Division of Themis Medicare Ltd.,) PLOT NO. 1 & 5, Phase I, IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA PRE FEASIBILITY REPORT Artemis Bio tech Ltd.,

More information

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT LG Polymers India Pvt. Ltd. Sy. No.s

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For EXPANSION IN EXISTING MANUFACTURING PLANT Of M/s. SHIVA DYE STUFF PVT. LTD Plot no. A2-11/6104,G.I.D.C. Industrial Estate, Ankleshwar-393002, Gujarat. 1 CONTENTS Sr. No. Description

More information

Expression of Interest

Expression of Interest Expression of Interest (Advertisement to be published in the Newspapers) Sub: Expression of Interest ( EOI ) for appointment of Steel Processing Units (SPU) / Rolling Mills (RM) for Conversion of Billets

More information

Manufacture of Iron & Steel. Prepared By: John Cawley

Manufacture of Iron & Steel. Prepared By: John Cawley Manufacture of Iron & Steel Prepared By: John Cawley Presentation Objectives Identify the basic steps in the production of steel. Identify the properties and uses of iron ore and pig iron. Differentiate

More information

UTILIZATIONOF SOLID WASTE FROM STEEL MELTING SHOP. A House of Engineering Excellence

UTILIZATIONOF SOLID WASTE FROM STEEL MELTING SHOP. A House of Engineering Excellence UTILIZATIONOF SOLID WASTE FROM STEEL MELTING SHOP 1 UTILIZATION OF SOLID WASTE FROM STEEL MELTING SHOP Presentation by Shri Bikas Pandey, MECON Limited, Ranchi At MECON Community Hall MIST 2016, 30 th

More information

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32 CONTENTS CHAPTER 1... 1 1.0 PROJECT SUMMARY... 1 CHAPTER 2... 2 2.0 INTRODUCTION... 2 (I) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT... 2 (II) BRIEF DESCRIPTION OF NATURE OF THE PROJECT... 2 (III)

More information

Water Management at Sesa Industries Limited Pig Iron Plant-Amona, Goa SIL-PIP

Water Management at Sesa Industries Limited Pig Iron Plant-Amona, Goa SIL-PIP Water Management at Sesa Industries Limited Pig Iron Plant-Amona, Goa 1 SIL-PIP 1 Company Profile Sesa Goa Limited is the largest producer & exporter of iron ore, in the private sector, in India with mining

More information

Concast Steel & Power Limited. Opportunity overview

Concast Steel & Power Limited. Opportunity overview Concast Steel & Power Limited Opportunity overview Key Investment Highlights 1 Integrated operations across the value chain from 4 Integrated manufacturing facilities in West Bengal, sponge iron production

More information

ANDHRA PRADESH POLLUTION CONTROL BOARD, REGIONAL OFFICE, TIRUPATI

ANDHRA PRADESH POLLUTION CONTROL BOARD, REGIONAL OFFICE, TIRUPATI M/s. JANANY CEMENT INDUSTRIES PRIVATE LIMITED SURVEY NO 462, INDUSTRIAL PARK, GUNTAKINDAPALLI VILLAGE, SRIKALAHASTI MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH EXECUTIVE SUMMARY SUBMITTED BY M/s.Janany Cement

More information

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh EXECUTIVE SUMMARY SUBMITTED BY M/s. Lakshmanan Cements Pvt Ltd No. 58-A, 25

More information

SINGHAL ENTERPRISES PRIVATE LIMITED

SINGHAL ENTERPRISES PRIVATE LIMITED SINGHAL ENTERPRISES PRIVATE LIMITED (INTEGRATED MINI STEEL & POWER PLANTS) Taraimal Village, Gharghoda Mandal, Raigarh District, Chattisgarh State. 1.0 INTRODUCTION SINGHAL ENTERPRISES PRIVATE LIMITED

More information

Production of Iron and Steels

Production of Iron and Steels MME 131: Lecture 24 Production of Iron and Steels Prof. A.K.M.B. Rashid Department of MME BUET, Dhaka Topics to discuss 1. Importance of iron and steels 2. The smelting of iron in Blast Furnace 3. The

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

MANUFACTURE OF IRON OR STEEL (preliminary treatment of ferrous ores or scrap C22B 1/00; electric heating H05B)

MANUFACTURE OF IRON OR STEEL (preliminary treatment of ferrous ores or scrap C22B 1/00; electric heating H05B) CPC - C21B - 2017.08 C21B MANUFACTURE OF IRON OR STEEL (preliminary treatment of ferrous ores or scrap C22B 1/00; electric heating H05B) The production of iron or steel starting from iron ores, e.g. the

More information

View of SBQ Markets from Bursa. Tolga Şölen

View of SBQ Markets from Bursa. Tolga Şölen View of SBQ Markets from Bursa Tolga Şölen PRESENTATION PLAN Who we are, where we stand currently. How we view the industries that affect SBQ usage in Turkey and in other markets What challenges and opportunities

More information

ArcelorMittal South Africa

ArcelorMittal South Africa Introduction to ArcelorMittal South Africa 1. History ArcelorMittal is one of the world s largest inland steelworks. The increasing demand for steel during the late 1930 s and the early years of the Second

More information

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad Annexure Prefeasibility Report (PFR) File PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of Shri Hari Dyes & Chemicals Work & Regd. Office: CONTENTS Sr. No. Description 1.

More information

PRE FEASIBILTY REPORT

PRE FEASIBILTY REPORT PRE FEASIBILTY REPORT FOR ENVIRONMENT CLEARANCE OF PROPOSED NEW PROJECT S. O. CHEMICALS (5 f Category) Proposed By: COREL PHARMA CHEM PVT. LTD. SURVEY NO. 473 & 481, BORISANA, KADI THOL ROAD, KADI, DIST

More information

D R I V I N G I N N O V A T I O N KALYANI STEELS LTD

D R I V I N G I N N O V A T I O N KALYANI STEELS LTD KALYANI STEELS LTD B. N. Kalyani Group Chairman PHILOSOPHY To use our specialized skills and innovative technology to contribute to the welfare of society. It is our intention to grow along with our employees

More information

Asil Çelik, with m2 land, is located nearby Bursa. Bursa is mainly the center of the automotive industry in Turkey.

Asil Çelik, with m2 land, is located nearby Bursa. Bursa is mainly the center of the automotive industry in Turkey. THE COMPANY PROFILE Asil Celik was established in 1974 to produce special and alloyed steel mainly for the automotive industry, automotive components, machine tool manufacturing and defence industries.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT ANVITHA LIFE CARE PLOT NO. 6, ATTIVARAM INDUSTRIAL PARK, ATTIVARAM VILLAGE, OZILI MANDAL, SPSR NELLORE DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT ANVITHA LIFE CARE PLOT NO. 6, ATTIVARAM INDUSTRIAL

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT By Sugna Metals Limited [Expansion of Steel Plant] At Sy. Nos. 142 & 143 of NarayanpurVillage, Pargi Mandal, Vikarabad District (formerly Ranga Reddy), Telangana INDEX S.No Item

More information

INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT

INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT 1 EXECUTIVE SUMMARY AIA Engineering Limited proposes expansion to install induction furnace for the manufacturing of Alloy Steel castings with production capacity of another 2,20,000 MT/year (existing

More information

Pre-feasibility report

Pre-feasibility report Pre-feasibility report Suryadev Alloys & Power Pvt. Ltd. [] at Sirupuzhalpet and New Gummidipoondi Village, Gummidipoondi Taluk,Tiruvollur District, Tamil Nadu 0 Chapter - 1 EXECUTIVE SUMMARY 1.1 ABOUT

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

Presently we are operating two numbers of Induction Furnace unit with installed

Presently we are operating two numbers of Induction Furnace unit with installed To, Dated: 03.09.2012 The Secretary C.G. State Level Expert Appraisal Committee, Commercial Complex, Housing Board Colony, Kabir Nagar, Raipur (C.G.) 492099 Subject : Application for Environmental Clearance

More information

VANDANA GLOBAL LIMITED

VANDANA GLOBAL LIMITED Certificate of Merit Sponge Iron VANDANA GLOBAL LIMITED Siltara, Raipur (Chhattisgarh) Unit Profile M/S Welspun Steel Ltd. has commissioned manufacturing of Sponge Iron, TMT bars & Billets in Kutch. Vandana

More information

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance]

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Project Proposal: Expansion of Cement Plant capacity from 1.5 to 2.20 MTPA of Clinker and

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT

More information

APPENDIX A: CORRESPONDENCE WITH DEDEA

APPENDIX A: CORRESPONDENCE WITH DEDEA APPENDIX A: CORRESPONDENCE WITH DEDEA Public Process Consultants A.1 Correspondence from Agni Steels SA to DEDEA notifying DEDEA of proposed changes to the Project Description, 13 December 2010 Public

More information

INSPIRE INDUSTRIES PVT. LTD.

INSPIRE INDUSTRIES PVT. LTD. For Proposed 0.999 MTPA Coal Washery At Village: Bhelai, Tehsil: Baloda, District: Janjgir-Champa, Chhattisgarh Envirotech East (P) Limited An ISO 9001:2008, 14001:2004 & OHSAS:18001:2007 Company Laboratory

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Of Shri Upendra Suryawanshi At Khasra No. 413/1, 413/3 Vill.-Ambada, Tehsil-Amla, District-Betul (M.P.) Production Capacity: Max 6,320 Cu.mt/year Area 1.00Hectare Proponent Name