Lastly the case was taken up in the 112 th meeting held on and. the case was deferred.

Size: px
Start display at page:

Download "Lastly the case was taken up in the 112 th meeting held on and. the case was deferred."

Transcription

1 1 Minutes of the 113 th meeting of State Environment Impact Assessment Authority held on. 28 th May, 2018 under the Chairmanship Sh. Bharat Bhushan IAS (Retd.), Chairman, SEIAA held in the meeting room of office of SEIAA Haryana, Sector-2 Panchkula, regarding Environmental Clearance under EIA Notification dated All the members are present. The project proposals as recommended by SEAC for Environmental Clearance or otherwise and listed in the Agenda item circulated vide letter No. 518 to 520 dated were discussed following decisions were taken:- Item No.[1] Environment Clearance for proposed Sand Minor Mineral at Dadyana Block/AMB B-8, ML Area-2.85 Ha, Village Dadyana and District- Ambala by Sh. Devender Sharma, S/o Sh. Gauri Shankar Vashishta, the case was deferred. In the today s meeting the reply dated submitted by the project proponent was considered. It was observed by the Authority that: [1] As per Office memorandum dated of MoEF & CC, in case of river sand mining project since the lease area 2.85 Ha, mining activity shall be done manually then how the diesel is required? [2] The project proponent should submit location and layout/ topology of the area indicating the distance from bridge and embankment. [3] How the project proponent would ensure that no in-stream mining would take place? [4] How the project proponent would ensure that the mining operations will not intersect groundwater table so that no natural water course/water body would be obstructed due to any mining operations?. [5] The project proponent has proposed to use treated water for dust suppression and sprinkling to conserve water. Has the project proponent identified any source of treated water? [6] The project proponent should submit NOC/approved conservation plan from Forest Department. [7] How would the project proponent ensure that the depth of mining should be restricting to 3 meter so that water level is not exposed? [8] How the project proponent would reclaim the area concerned and reclamation plan of the mining site should be submitted. [9] The project proponent should submit the topography of the mine area to ensure that leasing of mine does not result into a cluster situation. In view of the above, the Authority decided to agree with the recommendations of SEAC and EC would be accorded to project proponent provided they submits the satisfactory clarification to the above raised observations within 15 days.

2 2 It was also decided that the project proponent shall supply the copies of information to all the members of SEIAA and after their approval the EC letter shall be issued. Item No.[2] Environment Clearance for construction of Sewage Treatment Plant (4.0 MLD) at Village-Kithwari, Tehsil-Palwal, District-Palwal, Haryana by Public Health Engineering Department. the case was deferred. In the today s meeting the reply dated submitted by the project proponent was considered. It was observed by the Aurhotity that: [1] The project proponent should submit the plan to segregate bio-degradable and non-biodegradable waste of the incoming sewage to the plant. In view of the above, the Authority decided to agree with the recommendations of SEAC and Environment Clearance would be accorded to project proponent provided they submits the satisfactory clarification to the above raised observations within 15 days. It was also decided that the project proponent shall supply the copies of information to all the members of SEIAA and after their approval the Environment Clearance letter shall be issued. Item No.[3] Environment Clearance for Expansion of Commercial Colony on the land measuring acres in the revenue estate of Village Maidawas, Sector-67, Gurugram- Manesar urban Complex by M/s Martial Buildcon Pvt. Ltd. the case was deferred. The reply submitted by the PP is as under: In the today s meeting the reply dated submitted by the project proponent was considered. The project proponent has submitted the revised water balance diagram while reducing the demand from 259 KLD to 227 KLD. After detailed deliberation the Authority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[4] Environment Clearance for proposed Boulder, Gravel and Sand Minor Mineral Mines at Karanpur Block PKL B-3 over an area of 8.23 ha with production capacity of 3.9 Lakhs TPA near Village Karanpur, Tehsil-Pinjore, District-Panchkula (Haryana) by Sh. Sushil Kumar S/o Sh. Mam Chand, the case was deferred. The reply submitted by the PP is as under: In the today s meeting the reply dated submitted by the project proponent was considered. It was observed by the Authority that:

3 3 [1] As per Office memorandum dated of MoEF & CC, in case of river sand mining project since the lease area 8.23 Ha, mining activity shall be done manually then how the diesel is required? [2] The project proponent should submit location and layout/ topology of the area indicating the distance from bridge and embankment. [3] The project proponent should submit NOC/approved conservation plan from Forest Department. [4] How would the project proponent ensure that the depth of mining should be restricting to 3 meter that water level is not exposed? [5] How the project proponent would ensure that no in-stream mining would take place? [6] How does project proponent ensure that water from washing of wheels may be done efficiently & minimum water is consumed? What is location of Water trough? [7] The project proponent has proposed to use treated water for dust suppression and sprinkling to conserve water. Has the project proponent identified any source of treated water? [8] The project proponent should submit the plan to ensure no natural water course/water body would be obstructed due to any mining operations or dumping of the materials. [9] How the project proponent would reclaim the area concerned and reclamation plan of the mining site should be submitted. [10] The project proponent should submit the topography of the mine area to ensure that leasing of mine does not result into a cluster situation. In view of the above, the Authority decided to agree with the recommendations of SEAC and EC would be accorded to project proponent provided they submits the satisfactory clarification to the above raised observations within 15 days. It was also decided that the project proponent shall supply the copies of information to all the members of SEIAA and after their approval the EC letter shall be issued. Item No.[5] Environment Clearance for Affordable Group Housing Colony located at Village-Badshahpur, District- Gurugram Haryana by M/s Sai Aaina Farms Pvt. Ltd., the case was deferred. The reply submitted by the PP is as under: In the today s meeting the reply dated submitted by the project proponent was considered. The project proponent has submitted the details of requirement of water for visitors and parking plan.

4 4 After detailed deliberation the Authority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[6] Environment Clearance for proposed Commercial Colony at Sector-65, Gurgaon, Manesar Urban Complex, Haryana by M/s Wellworth Project Developers Pvt. Ltd. the Authority decided to defer this case and to depute Sh. Hitender Singh, Member SEAC to visit the site and submit the report at the earliest possible. As per the site visit report submitted by the member, It was concluded that the excavation had been done after obtaining prior Environmental Clearance in There is no construction / construction activity at site at present. In the today s meeting the reply dated submitted by the project proponent was considered. The project proponent has submitted the revised water balance diagram while reducing the demand from 253 KLD to 224 KLD along with the complete area statement showing proposed green area sqm (25.19%) of net plot area, sqm as proposed ground coverage and sqm under road and paved area keeping the net plot area at sqm. After detailed deliberation the Authority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[7] Environment Clearance for construction of Ruhil Township (Plotted Development) at Sector-36, Jhajjar, Bahadurgarh, Haryana by M/s GNEX Realtech Pvt. Ltd. the Authority was of the unanimous opinion that it needs more time to study and analyze the case, therefore it has been deferred for the next meeting. In the today s meeting the Authority decided to defer this case and to depute Sh. Hitender Singh, Member SEAC to visit the site and submit the report at the earliest possible. Item No.[8] Extension of EC for Group Housing Complex Parikarma at Sec-20, Village Kundli, Panchkula, Haryana by M/s Santur Projects Pvt. Ltd. the Authority decided to defer this case with the decision that the project proponent should be heard before taking a final view on this issue as per the request of authorized signatory of M/s Santur Projects Pvt. Ltd. In the today s meeting after detailed deliberations the Authority unanimously decided that it needs more time to study and analyse the case and Authority decided to give an opportunity to the project proponent to personally present and plead

5 5 his case. The project proponent may please appear with all the necessary documents in the next SEIAA meeting. Item No.[9] Environment Clearance for the Revision and Expansion of Group Housing Colony located at Village Chauma, Sector-110A & 111, Gurgaon, Haryana by M/s Puri Construction Pvt. Ltd. Lastly the case was taken up in the 98 th meeting held on and the Authority decided to defer this case with the decision that the project proponent may be asked to submit satisfactory reply within 15 days and Sh. Hitender Singh and Sh. S. N. Mishra, Members SEAC shall visit the site for inspection and shall submit the report within 15 days period. In the today s meeting, it was noticed that the site visit report is not received from the members. The project proponent has submitted a request for withdrawing their case for Revision and Expansion of Group Housing Colony located at Village Chauma, Sector-110A & 111, Gurgaon, Haryana. The project proponent informed that the expansion part of project will be undergoing re-design to avail additional FAR as per the TOD (Transit Oriented Development) norms. After detailed deliberations the Authority unanimously decided to defer this case till the receipt of site visit report. Item No.[10] Environment Clearance for proposed Expansion of Miri Piri Institute of Medical Sciences and Research Campus at Shahbab markanda, Ku rukshetra, Haryana by M/S Miri Piri Institute of Medical Sciences & Research (Charitbale Trust) The SEAC has recommended this project for Environmental Clearance subject to stipulation stated therein. The Project Proponent has proposed Expansion of Miri Piri Institute of Medical Sciences and Research Campus at Shahbab markanda, Ku rukshetra, Haryana on a total plot area of sqm (25.14 Acres). The total built up area shall be sqm. The proposed project comprise of Hospital Building, Institute Building, Animal House, Mortuary, Laundry/Workshop, auditorium, Boys Hostel, Girls Hostel, Type IV (64 no. of Unit), Type III (32 no. of Unit), Type II (16 no. of Unit), Type I (8 no. of Unit), Laundry/Workshop, Incinerator. The maximum height of the building shall be 18 meters. The total water requirement shall be 470 KLD. The fresh water requirement shall be 345 KLD. The waste water generation shall be 268 KLD which will be treated in the STP of 323 KLD capacity. The total power requirement shall be 5700 KVA which will be supplied by UHBVN. The Project Proponent has proposed to develop green belt on sqm (30%) of project area (Green belt Plantation sqm + Peripheral Plantation is 1769 sqm + Avenue Plantation 2370 sqm + Lawn area sqm). The Project Proponent proposed to construct 25 rain water harvesting pits as approved by the Central Ground Water Authority (CGWA). The solid waste generation will be 1854 kg/day. The total parking spaces proposed are 487 ECS.

6 6 The above recommendation of SEAC was taken up for consideration in the today s meeting. The case has been thoroughly examined and pointed out that: [1] Since the Rudraksh Enviro Care Pvt. Ltd. has not got any Environment Clearance, hence project proponent cannot be allowed to have agreement with this firm. [2] The project proponent has not explained as to how they would handle and dispose the bio-medical waste they are advised to come up with proposal as how they would dispose are handle of bio-medical waste with latest technology. After detailed deliberations the Authority unanimously decided to defer this case with the decision that the project proponent may be asked to submit reply to the above raised observation within 15 days period and give presentation on the technology being proposed to install. Item No.[11] Environment Clearance for proposed Boulder, gravel and Sand (Minor Mineral) at Charnia Block/PKL B 4 at Village Karanpur, Johluwala, Charnian, Kiratpur, Tehsil- Pinjore, District-Panchkula (Haryana). by M/s Shiri Ganesh Royalty Co., The SEAC has recommended this case for Environment Clearance to M/s Shiri Ganesh Royalty Co for Mining of Boulder, gravel and Sand at Charnia Block/PKL B 4 at Village Karanpur, Johluwala, Charnian, Kiratpur, Tehsil- Pinjore, District- Panchkula (Haryana) by imposing stipulations stated therein. It was noticed that the Mines and Geology Department has granted lease for a period of 10 years subject to the terms and conditions as indicated in Letter of Intent (LOI) dated The lease has been granted for an area of Ha having Village Karanpur, Johluwala, Charnian, Kiratpur, Tehsil- Pinjore, District-Panchkula. The project proponent on uploaded online application along with copy of approved Mining Plan under category B-1. The validity of Mining Scheme in the Mining plan is for 5 years. NOC from Forest Department has been obtained. Brief details of the project: 1. Category/Item no. (in schedule): 1 (a) B-1 2. Location of Project Village Karanpur, Johluwala, Charnian, Kiratpur, Tehsil- Pinjore, District-Panchkula 3. Project Details Mining of Boulder, gravel and Sand at Charnia Block/PKL B 4 an area of Ha Khasra No. Charnia Block/PKL-B-4 Karanpur 162 min Johluwala 16 min Charnia 12 min Kiratpur 548 min, 549 min & 598 min Production capacity 14,00, Trips/day (25 Ton/Trip) 4. Project Cost 5 Crore

7 7 5. Water Requirement & Source 64 KLD through Tankers Dust suppression Plantation Drinking 6. Environment Management Plan 20 lakh Budget 7. CSR Activates Budget 15 Lakh 48 KLD 12 KLD 4 KLD 8. Production The proposed production for the five years 14,00,000 TPA. Ground water will not be contaminated as river bed mining will be restrected up to depth of 3 m where as the general ground water talble is 8-10 meter bgl. The Bench mrl will be for five years. 9. Corner Coordinates of the lease area Block Latitude Longitude Charnia Block/PKL- B-4 N30 50'19.20 to N30 51'44.2 E76 50 '53.80" to E76 51 '51.5" 10. Green belt/ plantation Year of Plantation Proposed Plantation I Yr Trees II Yr Trees III Yr Trees IV Yr Trees V Yr Trees 11. Machinery required Excavator/ JCB Tipers/Trucks, Water Tanker Light Vehicles/Geep and Maintaniance Van The above recommendation of SEAC was taken up for consideration in the today s meeting. The case has been thoroughly examined and pointed out that: [1] The project proponent should submit location and layout/ topology of the area indicating the distance from bridge and embankment. [2] How would the project proponent ensure that the depth of mining should be restricting to 3 meter so that water level is not exposed? [3] How the project proponent would ensure that no in-stream mining would take place? [4] How does project proponent ensure that water from washing of wheels may be done efficiently & minimum water is consumed? What is location of Water trough? [5] The project proponent has proposed to use treated water from nearby STP for dust suppression and sprinkling. Have the project proponent identified the source of STP or have they entered any MoU with the supplier of water? [6] The project proponent should submit the plan to ensure no natural water course/water body would be obstructed due to any mining operations or dumping of the materials.

8 8 [7] How the project proponent would reclaim the area concerned and reclamation plan of the mining site should be submitted. [8] The project proponent should submit the topography of the mine area to ensure that leasing of mine does not result into a cluster situation. In view of the above, the Authority decided to agree with the recommendations of SEAC and EC would be accorded to project proponent provided they submits the satisfactory clarification to the above raised observations within 15 days. It was also decided that the project proponent shall supply the copies of information to all the members of SEIAA and after their approval the EC letter shall be issued. Item No.[12] Environment Clearance for mining of Boulder, Gravel and Sand (Minor Mineral) at Dhanaura Block/YNR B-18, over an area of Ha. at Village Dhanaura, District-Yamuna Nagar (Haryana) by M/s JPY Consortium Pvt. Ltd, The SEAC has recommended this case for Environment Clearance to M/s JPY Consortium Pvt. Ltd, for Boulder, Gravel and Sand (Minor Mineral) at Dhanaura Block/YNR B-18, over an area of Ha. at Village Dhanaura, District-Yamuna Nagar (Haryana) by imposing stipulations stated therein. It was noticed that the Mines and Geology Department has granted lease for a period of 10 years subject to the terms and conditions as indicated in Letter of Intent (LOI) dated The lease has been granted for an area of Ha having Village Dhanaura, District-Yamuna Nagar (Haryana). The project proponent on uploaded online application along with copy of approved Mining Plan under category B-2. The validity of Mining Scheme in the Mining plan is for 5 years. It was noticed that The Mines & Geology, Department has clarified that no other mine lease exists within 500 meter radius of this mine accordingly the SEAC appraised this project as category B-2. NOC from Forest Department has been obtained. Brief details of the project: 1. Category/Item no. (in schedule): 1 (a) B-2 2. Location of Project Village Dhanaura, District-Yamuna Nagar (Haryana) 3. Project Details Mining of Boulder, gravel and Sand at Dhanaura Block/YNR B-18, over an area of Ha. Khasra No. Dhanaura Block/YNR B-18 Production capacity 67, 72 min, 75 min, 74,73,72,71,68/1,68/2,68/3 min, 68/4, 68/5, 68/6, 68/7, 68/8, 68/9, 68/10, 69/3 min, 69/4,69/5,69/6,69/7,69/8, 69/9, 69/10, 69/11 min, 69/12, 69/13. 69/14, 69/15, 69/16, 69/17, 69/18,89/1, 89/2, 89/3, 89/4, 89/5, 89/6, 89/7, 89/8 min, 89/9, 89/10, 89/11, 89/12, 89/13, 89/14, 89/15, 89/16, 89/17, 89/18 min, 89/19, 89/20, 89/21, 89/22 min, 89/26 min, 89/27, 89/28, 89/29, 89/30 min, 88/1 min, 86/27, 69/19 9,50, MT/day, Truck / Dumper (142 Nos.)

9 9 4. Project Cost 3.5 Crore 5. Water Requirement & Source 25 KLD through Tankers Dust suppression Plantation Drinking 6. Environment Management Plan lakh Budget 7. CSR Activates Budget 8.75 Lakh 13 KLD 9 KLD 3 KLD 8. Production The proposed production for the five years 14,00,000 TPA. Ground water will not be contaminated as river bed mining will be restrected up to depth of 3 m where as the general ground water talble is 8-10 meter bgl. The Elevation Rang of the mine site will be Amsl, for five years. 9. Corner Coordinates of the lease area Block Latitude Longitude Dhanaura Block/YNR B-18 N30 25'48.5 to N30 26'7 E77 22 '25" to E77 22 '49.3" 10. Green belt/ plantation Year of Plantation Proposed Plantation I Yr Trees II Yr Trees III Yr Trees IV Yr Trees V Yr Trees 11. Machinery required Excavator/ JCB Tipers/Trucks, Water Tanker Light Vehicles/Geep and Maintaniance Van The above recommendation of SEAC was taken up for consideration in the today s meeting. The case has been thoroughly examined and pointed out that: [1] As per Office memorandum dated of MoEF & CC, in case of river sand mining project since the lease area Ha, mining activity shall be done manually then how the diesel is required? [2] The project proponent should submit location and layout/ topology of the area indicating the distance from bridge and embankment. [3] How would the project proponent ensure that the depth of mining should be restricting to 3 meter that water level is not exposed? [4] How the project proponent would ensure that no in-stream mining would take place? [5] How the project proponent would ensure that the mining operations will not intersect groundwater table so that no natural water course/water body would be obstructed due to any mining operations?. [6] The project proponent should submit NOC/approved conservation plan from Forest Department.

10 10 [7] How does project proponent ensure that water from washing of wheels may be done efficiently & minimum water is consumed? What is location of Water trough? [8] The project proponent should submit the topography of the mine area to ensure that leasing of mine does not result into a cluster situation. [9] The project proponent has proposed to use treated water for dust suppression and sprinkling to conserve water. Has the project proponent identified any source of treated water? [10] How the project proponent would reclaim the area concerned and reclamation plan of the mining site should be submitted. In view of the above, the Authority decided to agree with the recommendations of SEAC and EC would be accorded to project proponent provided they submits the satisfactory clarification to the above raised observations within 15 days. It was also decided that the project proponent shall supply the copies of information to all the members of SEIAA and after their approval the EC letter shall be issued. Item No.[13] Environment Clearance for the Common Bio-Medical Waste Treatment Facility at Dhor, Tehsil-Beri, Distt-Jhajjar, Haryana by Tokas Waste Management, The recommendation of SEAC was taken up in the today s meeting and it was noticed that the project proponent vide letter dated for withdrawal of their case due to some unavoidable reasons / circumstances. After detail deliberation the Authority decided to accept the recommendations of SEAC and allow the project proponent to withdraw the case. Item No.[14] Environment Clearance for proposed Group Housing project at Village Sukhrali, Sector-28, Gurugram, Haryana by M/s Silverglades Infrastucture Pvt. Ltd., The SEAC has recommended this project for Environmental Clearance subject to stipulation stated therein. The Project Proponent has proposed the construction of Group Housing project at Village Sukhrali, Sector-28, Gurugram, Haryana on a total plot area of sqm (4.85 Acre). The total built up area shall be sqm. The Group Housing project shall comprise of 15 Towers, 2 Basement + 19 Floors. The proposed project shall have 543 Dwelling units (Main Units EWS units 48 + Service Units 221), Community facilities, Office Buildings, Commercial Buildings and Club. The maximum height of the building shall be meter. The total water requirement shall be 383 KLD. The fresh water requirement shall be 180 KLD. The waste water generation shall be 234 KLD which will be treated in the STP of 280 KLD capacity. The total power requirement shall be KVA which will be supplied by DHBVN. The Project Proponent has proposed to develop green belt on sqm (25.24%) of project area (Green belt plantation sqm + peripheral plantation

11 sqm + Avenue plantation sqm + Lawn area sqm). The Project Proponent proposed to construct 5 rain water harvesting pits. The solid waste generation will be 1817 kg/day. The bio-degradable waste will be treated in the project area by adopting appropriate technology. The total parking spaces proposed are 1180 ECS. In the today s meeting it was noticed that the project proponent has submitted the proposed final green area is sqmt (25.17%) of plot area and also submitted undertaking in this regard. The Project proponent has submitted revised water balance diagram with total 78 KLD water for HVAC cooling. The Project proponent has submitted affidavit regarding no untreated water to be discharged in external sewer, structural stability certificate and submitted reply as asked under point 2.1, 2.2, 2.3, 2.13 and 5.4 of form-1a. After detailed deliberation the Aauthority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[15] Environment Clearance for construction of Affordable Residential Plotted Colony project at Village-Kailash, Sector-28 A, Karnal, Haryana M/s Fantabulous Town Developers Pvt. Ltd, The SEAC has recommended this project for Environmental Clearance subject to stipulation stated therein. The Project Proponent has proposed the construction of Affordable Residential Plotted Colony project at Village-Kailash, Sector-28 A, Karnal, Haryana on a total plot area of sqm (15 Acre). The total built up area shall be sqm. The proposed project shall comprise of Residential plotts, Commercial facilities and community building. Office Buildings, Commercial Buildings and Club. The maximum height of the building shall be meter. The total water requirement shall be 412 KLD. The fresh water requirement shall be 244 KLD. The waste water generation shall be 278 KLD which will be treated in the STP of 340 KLD capacity. The total power requirement shall be 1155 KWA which will be supplied by UHBVN. The Project Proponent has proposed to develop green belt on sqm (20.03%) of project area (Green belt plantation sqm + peripheral plantation sqm + Avenue plantation sqm + Lawn area sqm). The Project Proponent proposed to construct 15 rain water harvesting pits. The solid waste generation will be 1982 kg/day. The bio-degradable waste will be treated in the project area by adopting appropriate technology. The total parking spaces proposed are 822 no s of Scooter parking. In the today s meeting it was noticed that the project proponent has submitted the location of 15 RWH pit and proposed landscape of the plot area 12, sqm. The Project proponent has submitted affidavit regarding no untreated water to be discharged in external sewer, structural stability certificate and submitted reply as asked under page no. 70 complete detail of soil erosion of form-1a.

12 12 After detailed deliberation the Aauthority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[16] Environment Clearance for construction of Affordable Residential Plotted Colony project at Village-Kailash, Sector-28 A, Karnal, Haryana by M/s MAA Vaishno Net-Tech Pvt. Ltd, The SEAC has recommended this project for Environmental Clearance subject to stipulation stated therein. The Project Proponent has proposed the construction of Affordable Residential Plotted Colony project at Village-Kailash, Sector-28 A, Karnal, Haryana on a total plot area of sqm (15 Acre). The total built up area shall be sqm. The proposed project shall comprise of Residential plots, Commercial facilities and Commercial / Convenient shopping facilities. The maximum height of the building shall be meter. The total water requirement shall be 410 KLD. The fresh water requirement shall be 243 KLD. The waste water generation shall be 277 KLD which will be treated in the STP of 340 KLD capacity. The total power requirement shall be 1478 KW which will be supplied by DHBVN. The Project Proponent has proposed to develop green belt on sqm (20.119%) of project area (Green belt plantation sqm + peripheral plantation sqm + Avenue plantation sqm + Lawn area sqm). The Project Proponent proposed to construct 15 rain water harvesting pits. The solid waste generation will be 1965 kg/day. The bio-degradable waste will be treated in the project area by adopting appropriate technology. The total parking spaces proposed are 822 no s of Scooter parking. In the today s meeting it was noticed that the project proponent has submitted visitor parking, population detail to Form-IA, detail of Area Statement and an Affidavit regarding no release of un-treated water in external sewer against the queries raised. In view of the above the Authority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the standard conditions in practice. Item No.[17] Environment Clearance for shopping/commercial Building on acres site (Mall of India) in Block-V, DLF City Phase-III, Sector-25 A, Gurgaon, Haryana by M/s DLF City Centre Ltd. The SEAC has recommended this project for approval of TOR subject to stipulation stated therein. The Project Proponent has proposed shopping/commercial Building on acres site (Mall of India) in Block-V, DLF City Phase-III, Sector-25 A, Gurgaon, Haryana. In the today s meeting the SEIAA approved the Terms of Reference and it was decided that the project proponent will prepare the EIA by using Model Terms of Reference of MoEF & CC along with the following additional terms of reference:

13 13 Specific condition 1. The project proponent should submit traffic study and impact on the air ambient quality along with mitigation measures. 2. The PP should submit joint study report conducted with HUDA. 3. The PP should submit traffic circulation plan including traffic of nearby projects and overall impact of the national highway along with mitigation measurement. 4. The PP should submit fire fighting plan with hydraulic ladder. 5. The PP should submit green belt plan for 25%. 6. The PP should submit the drainage plan of 5 KM surrounding area. 7. The PP should submit aravali NOC. Item No.[18] Environment Clearance for proposed Textile Park(for manufacturing activity on an area measuring acre ( sqm) at 80 Mile Stone, NH-1, Village Diwana, Tehsil and District-Panipat, Haryana by M/s Aalishan Eco Textile Park Pvt. Ltd, The case was taken up for approval of Terms of Reference in 168th meeting of the SEAC held on for approval of Terms of Reference. adjournment. The project proponent neither attended the meeting nor requested for It was revealed that project proponent has applied under category 8(b) i.e. Township and Area Development Projects whereas the said project is covered under category 7(h) as the project relate to CETP. After discussion the Authority allow the project proponent to withdraw the project and project proponent may be advised to apply afresh under Category 7(h) of the EIA Notification, Item No.[19] Environment Clearance for Expansion/Modification of Residential Plotted Colony (Green wood city) at Sector-26, 26A & 27, Sonipat, Gurgaon, Haryana by M/S Jai Krishna Artec-J.V. 8-B, The SEAC has recommended this project for approval of TOR subject to stipulation stated therein. The Project Proponent has proposed Expansion/Modification of Residential Plotted Colony (Green wood city) at Sector-26, 26A & 27, Sonipat, Gurgaon, Haryana. In the today s meeting the SEIAA approved the Terms of Reference and it was decided that the project proponent will prepare the EIA by using Model Terms of Reference of MoEF & CC along with the following additional terms of reference: Specific condition 1. The PP should submit the approved building plans as well as zoning plan. 2. The PP should submit the area details such as Area of services laid down in the plotted colony and area of EWS Houses constructed if any.

14 14 Item No.[20] Environment Clearance for expansion of area of Group Housing Colony ( acres) under mix land use at Sector-53, Gurugram, Haryana by M/s Vipul Ltd, The SEAC has recommended this project for approval of TOR subject to stipulation stated therein. The Project Proponent has proposed expansion of area of Group Housing Colony ( acres) under mix land use at Sector-53, Gurugram, Haryana. In the today s meeting the SEIAA approved the Terms of Reference and it was decided that the project proponent will prepare the EIA by using Model Terms of Reference of MoEF & CC along with the following additional terms of reference: Specific condition 1. The PP should submit traffic study and impact on the air ambient quality along with mitigation measures. 2. The PP should submit traffic circulation plan including traffic of nearby projects along with mitigation measurement. 3. The PP should submit compliance report from Regional Director, MoEF as per OM dated 29 th August, The PP should submit fire fighting plan with hydraulic ladder. 5. The PP should submit green belt plan for 35.20%. 6. The PP should submit the drainage plan of 5 KM surrounding area. 7. The PP should submit aravali NOC. Item No.[21] Environment Clearance for Proposed Group Housing Colony Joyville on Plot area measuring 17.9 Acres in Sector-102, Gurugram Manesar Urban Complex, Gurgaon, Haryana by M/s Eventual Builders Pvt. Ltd. The SEAC has recommended this project for approval of TOR subject to stipulation stated therein. The Project Proponent has proposed Group Housing Colony Joyville on Plot area measuring 17.9 Acres in Sector-102, Gurugram Manesar Urban Complex, Gurgaon, Haryana. In the today s meeting the SEIAA approved the Terms of Reference and it was decided that the project proponent will prepare the EIA by using Model Terms of Reference of MoEF & CC along with the following additional terms of reference: Specific condition 1. The PP should submit permission for disposal of sewerage from competent authority. 2. The PP should submit rain water harvesting plan. 3. The PP should submit solar power generation plan. 4. The PP should submit affidavit for BS-VI fuel for DG set.

15 15 Item No.[22]Request for confirmation regarding extension of validity of Environment Clearance granted for setting up Residential Plotted Colony measuring acres at Sector & 89, Faridabad being developed by M/s Countrywide Promoters Pvt. Ltd. The case has been transferred by MOEF & CC, GOI to SEIAA in purview of OM dated for further consideration. In the today s meeting it was noticed that the MoEF GoI vide letter dated granted Environmental Clearance for setting up Residential Plotted Colony measuring acres at Sector & 89, Faridabad being developed by M/s Countrywide Promoters Pvt. Ltd. Then validity of the environment clearance was up to The project proponent submitted application to MOEF on with respect to extension of validity of EC within validity period but no decision has been taken by MOEF. The project proponent within the validity period of EC submitted application for extension of validity of EC to the SEIAA, Haryana on as per MOEF GOI Notification dated and subsequently clarification dated The case has been taken up in the 133 rd meeting of SEAC held on and it was decided to constitute a sub-committee for site visit. The report of sub-committee was placed before the committee in the 148 th meeting of SEAC held on and committee recommended for extension of validity of EC for period of 3 years. The case was again taken up in the 149 th meeting of SEAC held on and SEAC recommend the case to SEIAA for transfer the case to MOEF & CC, New Delhi in purview of MoEF & CC Notification dated The case has been taken up in the 102 nd meeting of SEIAA held on and decided that the case pertain to more than 3 lakhs sqmt of built up area; as per notification dated ; the case transferred to MOEF & CC, GOI on Now the case has been transferred by MOEF & CC, GOI to SEIAA in purview of OM dated for further consideration. After detail deliberation the Authority decided to grant extension for two year from the date of issuance of letter. *****

The SEAC has examined the proposal in the light of amended Notification dated

The SEAC has examined the proposal in the light of amended Notification dated 1 Minutes of the 85 th meeting of State Environment Impact Assessment Authority held on. 09.12.2015, under the Chairmanship Sh. Bharat Bhushan IAS (Retd.), Chairman, SEIAA held in the meeting room of office

More information

meeting held on meeting held on The SEAC observed that:

meeting held on meeting held on The SEAC observed that: Excerpt pertaining to item no. 147.14 of 147 th meeting of SEAC held on 30.06.2016 Item no.147.14: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for area development

More information

SIA/PB/NCP/53462/2016)

SIA/PB/NCP/53462/2016) Item No.148.08: Application for environmental clearance under EIA notification dated 14.09.2006 for the development of group housing project namely SSL Highway Towers at Chandigarh-AmbalaHighway, Dera

More information

2. The expected cost of the project is Rs.50 crores.

2. The expected cost of the project is Rs.50 crores. Subject Application for obtaining Environmental Clearance for development of an "Integrated Municipal Solid Waste Management System for Pathankot Cluster" by Municipal Council, Pathankot at Village Kalanaur,

More information

27493 sqm (6.79 Acres) Built up area sqm sqm sqm No. of Floors 1 Tower + 3 Basements + GF +21 floor

27493 sqm (6.79 Acres) Built up area sqm sqm sqm No. of Floors 1 Tower + 3 Basements + GF +21 floor 1 Minutes of the 115 th meeting of State Environment Impact Assessment Authority held on. 25 th July, 2018 under the Chairmanship Sh. Bharat Bhushan IAS (Retd.), Chairman, SEIAA held in the meeting room

More information

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS Annexure No - 13 SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS File No : Name of the Project: Proposed Commercial project called Bagmane Tech Park RIO Campus of M/s. Bagmane Developers

More information

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project Building Stone (Basalt) Quarry of M/s. Sharada Construction Pvt. Ltd.

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project Building Stone (Basalt) Quarry of M/s. Sharada Construction Pvt. Ltd. SEIAA KARTAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS Name of the Project Building Stone (Basalt) Quarry of M/s. Sharada Construction Pvt. Ltd. Sl. No DOCUMENTS / X 1 Form -1 2 Pre-Feasibility Report

More information

Pre- Feasibility RepoRt

Pre- Feasibility RepoRt Pre- Feasibility RepoRt AREA- 59.28 ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY

More information

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In earlier project planning the total plot area

More information

EIA-EMP REPORT GRAVEL QUARRY (Category-B2)

EIA-EMP REPORT GRAVEL QUARRY (Category-B2) EIA-EMP REPORT GRAVEL QUARRY (Category-B2) EXTENT : 4.00.0 Hectares S. F. No : 436/1A (P) VILLAGE TALUK DISTRICT STATE : IYANPAPPAKKUDI : MADURAI : MADURAI : TAMIL NADU PROJECT PROPONENT Thiru P. Ayyanar

More information

Greater Mohali Area Development Authority (GMADA) vide its letter dated has applied for obtaining environmental clearance as

Greater Mohali Area Development Authority (GMADA) vide its letter dated has applied for obtaining environmental clearance as Excerpt pertaining to the item no. 142.1.8 from the proceedings of the 142 nd meeting of SEAC held on 11.03.2016 in Committee Room, Punjab Pollution Control Board, Patiala. Item No.142.1.8: Application

More information

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative) Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT

More information

BRIEF SUMMARY OF THE PROJECT

BRIEF SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT Office Complex at Plot No. 5A & 5B, Shopping Mall, Vasant Kunj Phase - II, New Delhi Developed by M/s Oil and Natural Gas Corporation Limited BRIEF DESCRIPTION OF THE PROJECT

More information

Minutes of 292 nd SEAC Meeting Date 20/09/2016

Minutes of 292 nd SEAC Meeting Date 20/09/2016 A presentation was made by Shri Sudheer Kumar Singh, authorized representative of project proponent along with their consultant M/s Prakriti Consultants Services, Lucknow. The committee noted that letter

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

SIX MONTHLY COMPLIANCE REPORT JUNE 2015

SIX MONTHLY COMPLIANCE REPORT JUNE 2015 M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 SIX MONTHLY COMPLIANCE REPORT JUNE 2015 (GROUP HOUSING COMPLEX) At Sector-86, Gurgaon, Haryana Being developed by M/s Deepanshu Projects

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Of Shri Upendra Suryawanshi At Khasra No. 413/1, 413/3 Vill.-Ambada, Tehsil-Amla, District-Betul (M.P.) Production Capacity: Max 6,320 Cu.mt/year Area 1.00Hectare Proponent Name

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project : Building Stone Quarry of Sri. B. Narendra Kumar

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project : Building Stone Quarry of Sri. B. Narendra Kumar SEIAA KARTAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS Name of the Project : Building Stone Quarry of Sri. B. Narendra Kumar Sl. No DOCUMENTS / X 1 Form -1 2 Pre-Feasibility Report [PFR] in the format

More information

Check list for construction Project of EC [Category 8(a)]:

Check list for construction Project of EC [Category 8(a)]: Check list for construction Project of EC [Category 8(a)]: Provide authenticated (with stamp & Signature) hard copy of this check-list during submission of hard copy of ToR application. Sr. no. Checklist

More information

Sh. Amit Kumar, Deputy Manager of M/s Ascenso Enviro Pvt. Ltd., Noida is the Environmental Consultant, presented the case before the SEAC as under:

Sh. Amit Kumar, Deputy Manager of M/s Ascenso Enviro Pvt. Ltd., Noida is the Environmental Consultant, presented the case before the SEAC as under: Proceedings of the 141st meeting of SEAC held on 27.02.2016 (Online).doc Proceedings of 2nd part of the Agenda (On-line Cases) of 141 st meeting of State Expert Appraisal Committee held on 27.02.2016 at

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Six Monthly Compliance Report June-2015 M/s Mahagun Real Estate Pvt. Ltd SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex Mahagunpuram AT VILLAGE Mehrauli, Dasna, Ghaziabad, U.P. Being developed

More information

CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT M/s. DAR Housing Ltd. Proposed Group Housing Project ATS Rhapsody, At Plot No. GH-12/1, Sector-01, Greater Noida (U.P.), having Plot

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT (B) PREFEASIBILITY REPORT OF EXISTING SAND MINING PROJECT OF RAJESHBHAI BHAGUBHAI PATEL AT VILLAGE:- Panchlai, TALUKA:- Pardi, DIST.:-Valdad. 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra.

Pre- feasibility Report. For. At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Pre- feasibility Report For Shiv Kailasha At Plot No. 242, 241, 238/2, 239, 237/1, 238/1, 247/1 of Village Sondapar, Tehsil :HingnaDistrict- Nagpur, Maharashtra. Proposed By M/S Om Shivam Buildcon Private

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF (B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF Makwana Dineshbhai Khimjibhai AT VILLAGE:- Tithava, TALUKA:- Wankaner, DIST.:- Morbi 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXCUTIVE SUMMARY

More information

ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING

ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING 1. Name and Address of Quarry Lease Holder: a. Name of applicant Priyesh Singh Thakur S/o Shri Karan Singh Thakur b. Designation of applicant Owner c. Name

More information

Health and safety norms of CPWD should be followed during construction.

Health and safety norms of CPWD should be followed during construction. Status of Compliance of Conditions of the Environmental Clearance Issued to Riveria Commercial Developers Ltd. DLF Center, Sansad Marg, New Delhi 110001- Construction of "YASHWANT PLACE COMMUNITY CENTRE"

More information

(A govt. of Kerala Undertaking)

(A govt. of Kerala Undertaking) Annexure - 1 Basic Information Important Note: Please send the information by e-mail in word format and a signed & scanned copy to the Member Secretary prior to the EAC meeting. Please also provide a copy

More information

2) Sri. Punati Sridhar - Secretary (SEAC) 5) Dr. T.V. Rama Chandra - Member (SEAC) 10) Dr. H.R. Raj mohan - Member (SEAC)

2) Sri. Punati Sridhar - Secretary (SEAC) 5) Dr. T.V. Rama Chandra - Member (SEAC) 10) Dr. H.R. Raj mohan - Member (SEAC) PROCEEDINGS OF THE 12 th SEAC KARNATAKA MEETING HELD ON 11 th April 2008. Members Present: 1) Dr. R. Raghavendra Rao - Chairman (SEAC) 2) Sri. Punati Sridhar - Secretary (SEAC) 3) Dr. S. Manjappa - Member

More information

After detailed discussions, the following shortcomings were concluded:

After detailed discussions, the following shortcomings were concluded: Page 1 of 151 Minutes of the 134 th Meeting of the State Expert Appraisal Committee, constituted for considering Environmental Clearance of Projects (B category) under Government of India Notification

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

Dt:18/04/2016. Dear Sir,

Dt:18/04/2016. Dear Sir, Dt:18/04/2016 Dear Sir, As per amendment to EIA notification S.O. no. 141(E) dated 15.01.2016, this is a minor mineral mining project of marble and the proposal falls under cluster situation for which

More information

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location 1. SUMMARY PRE-FEASIBILITY REPORT Project Stone Quarry Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location Village Taluka District State Rupapali Basna Mahasamund Chhattisgarh 1 Mining Lease

More information

The Chairman welcomed all the members of the Committee and thereafter agenda items were taken up for deliberations.

The Chairman welcomed all the members of the Committee and thereafter agenda items were taken up for deliberations. The 212 th meeting of the State Expert Appraisal Committee (SEAC) was held on 7 th August, 2015 under the Chairmanship of Shri K.P. Nyati for discussion on the query responses submitted by the PP and the

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF ALAMPUR THIKARIYA SAND DEPOSIT QUARRY KHASRA NO. 149, TOTAL AREA- 8.0 Hect. (MALENI RIVER) AT VILLAGE- ALAMPUR THIKARIYA, TEHSIL-JAORA, DISTRICT- RATLAM, STATE-MADHYA PRADESH

More information

To M/s Jai Ganesh BKO, Sh. Mohinder Kumar, # 1057, Sec-21-B, Chandigarh.

To M/s Jai Ganesh BKO, Sh. Mohinder Kumar, # 1057, Sec-21-B, Chandigarh. STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

Annexure III: Public Hearing Notice, Attendence Sheets, Proceedings and Replies

Annexure III: Public Hearing Notice, Attendence Sheets, Proceedings and Replies Annexure III: Public Hearing Notice, Attendence Sheets, Proceedings and Replies Hindustan Times Dated 17-12-2015 Jaipur Bhaskar 17-12-2015 Summary/details of public hearing in tabular form: Issues

More information

Dated: 22 nd June, To The Director, Mjs Vulcan Waste Management Pvt. Ltd., 1046, Sector-31, Gurgaon, Haryana

Dated: 22 nd June, To The Director, Mjs Vulcan Waste Management Pvt. Ltd., 1046, Sector-31, Gurgaon, Haryana F.No.10-12/201S-IA.III Government of India Ministry of Environment, Forest & Climate Change (IA.IIISection) Indira Paryavaran Bhawan, Jor Bagh Road, New Delhi - 110 003. To The Director, Mjs Vulcan Waste

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project : Siddapur Natural Sand Mining in Patta land

SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS. Name of the Project : Siddapur Natural Sand Mining in Patta land SEIAA KARNATAKA CHECK LIST FOR MINING/ QUARRYING PROJECTS Name of the Project : Siddapur Natural Sand Mining in Patta land Sl. No DOCUMENTS / X 1 Form -1 2 Pre-Feasibility Report [PFR] 3 Environmental

More information

BRIGADE RESIDENTIAL DEVELOPMENT

BRIGADE RESIDENTIAL DEVELOPMENT BRIGADE RESIDENTIAL DEVELOPMENT Terms of Reference (TOR) At Plot No. R5 and Plot No. R8, Hi Tech, Defense and Aerospace park (Hardware Sector), KIADB Industrial Area, Jala Hobli, Yelahanka Bengaluru North

More information

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan Report on 1. PROJECT LOCATION & LAND USE The Ganesh Park 3 is a residential building project constructed on plot 608 to 613/5 Vil: GIDC Ankleshwar in Bharuch district of Gujarat state. The project land

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR AT VILLAGE:- BRAHMPURI, TALUKA:- Sayla, DIST.:-Surendranagar 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE

More information

CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING ON 11th MAR 2017 and 1st April, 2017

CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING ON 11th MAR 2017 and 1st April, 2017 Prefab BHK,BHK & EWS Housing For Delhi Development Authority Pocket, Sector AA4, Narela, New Delhi FOLLOWING IS PRESENTATION OF THE CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING

More information

CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING ON 11th MAR 2017 and 1st April, 2017

CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING ON 11th MAR 2017 and 1st April, 2017 Prefab BHK,BHK & EWS Housing For Delhi Development Authority Pocket 4, Sector AA4, Narela, New Delhi FOLLOWING IS PRESENTATION OF THE CLARIFICATIONS / SUBMITTALS TO THE QUERIES AS RAISED AFTER SEAC MEETING

More information

EIA NOTIFICATION

EIA NOTIFICATION EIA NOTIFICATION - 2006 Building Construction projects/ Area Development projects and Townships New Delhi, 12 th August 2010. BHARAT BHUSHAN DIRECTOR, Ministry of Environment & Forests, Government of India,

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India. Registered

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India. Registered STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) 1) Executive Summary Project Name of Company / Mine Owner Location Village Taluka District State Girgita Limestone Mine M/s KJS

More information

No. SEIAA/2015/5519 Dated:

No. SEIAA/2015/5519 Dated: STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

No. SEIAA/2016/859 Dated: To M/s Uggarsain BKO, Sh. Varinder Kumar, Village Kakrala, Tehsil & Distt. Patiala.

No. SEIAA/2016/859 Dated: To M/s Uggarsain BKO, Sh. Varinder Kumar, Village Kakrala, Tehsil & Distt. Patiala. STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

(A) Cases recommended by SEAC for Prior Environmental Clearance

(A) Cases recommended by SEAC for Prior Environmental Clearance Minutes of the 33 rd SEIAA Meeting held on 10 th May, 2010 The 33 rd meeting of the State Level Environment Impact Assessment Authority was convened on 10 th May, 2010 at 3.00 P M at the Authority's office

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

A. PROOF OF CLAY MINING FOR BRICK KILN

A. PROOF OF CLAY MINING FOR BRICK KILN A. PROOF OF CLAY MINING FOR BRICK KILN Documents related to Brick Kiln 1. NOC /CTO of PCB for Brick Kiln 2. Paid Advance Royalty receipts, Panchayat, TIN number of Kiln and paid TT B. IDENTIFICATION OF

More information

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB MINISTRY OF ENVIRONMENT AND FORESTS, GOVERNMENT OF INDIA

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB MINISTRY OF ENVIRONMENT AND FORESTS, GOVERNMENT OF INDIA STATE EXPERT APPRAISAL COMMITTEE, PUNJAB MINISTRY OF ENVIRONMENT AND FORESTS, GOVERNMENT OF INDIA O/O PUNJAB POLLUTION CONTROL BOARD, VATAVARAN BHAWAN, NABHA ROAD, PATIALA 147 001 Telefax:- 0175-2215802

More information

No. SEIAA/3757 Dated: To Sh. Bhushan Kumar, M/s Mangla BKO, Bhagat Ram Joshi Street, Near PNB, Barnala.

No. SEIAA/3757 Dated: To Sh. Bhushan Kumar, M/s Mangla BKO, Bhagat Ram Joshi Street, Near PNB, Barnala. STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB. Ministry of Environment and Forests, Government of India

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB. Ministry of Environment and Forests, Government of India STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India O/O PUNJAB POLLUTION CONTROL BOARD, VATAVARAN BHAWAN, NABHA ROAD, PATIALA 147 001 Telefax:- 0175-2215802

More information

No //6/2/2(1-1), 27//14(7-11), 15(7-7), 16(8-0), 33//4/3(2-4),5(8-0),6/1

No //6/2/2(1-1), 27//14(7-11), 15(7-7), 16(8-0), 33//4/3(2-4),5(8-0),6/1 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

CRZ Clearance for Proposed Construction of RO RO Jetties at Narangi-Kharawadashri, Tal. & Dist. palghar by MMB

CRZ Clearance for Proposed Construction of RO RO Jetties at Narangi-Kharawadashri, Tal. & Dist. palghar by MMB Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:August 2, 2017 To, Chief Executive Officer,Maharashtra Maritime Board,Indian Mercantile Chambers,3rd Floor,Ramjibhai

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

Site Hadbast No (5-16), 97 (7-16), 102/1 (2-9)

Site Hadbast No (5-16), 97 (7-16), 102/1 (2-9) STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala

STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala-147001. No. SEAC/80/37967 Dated 15/10/2008 Speed Post To M/s Green Planet Energy Pvt.

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri Door No. 39/49/39,

More information

STANDARD OPERATING PROCEDURE

STANDARD OPERATING PROCEDURE STANDARD OPERATING PROCEDURE Consent to Established/Operate Procedural Guidelines Consent to Establish NOC Check List Consent to Operate NOC Check List Renewal to Consent to Operate Check List Time Frame

More information

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:- 0175-2215802

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN At Narmada River Mining Project:-Category B2 Lease Area: 20.000 Hect. Khasra No. 735 Vill.-Boras, Tehsil- Udaipura District- Raisen (M.P) Project Proponent M/s Shiva Corporation

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment

More information

CRZ Clearance for Proposed construction of Ghodbundar Jetty, Thane by MMB

CRZ Clearance for Proposed construction of Ghodbundar Jetty, Thane by MMB Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:August 9, 2017 To, Chief Executive Officer,Maharashtra Maritime Board,Indian Mercantile Chambers,3rd Floor,Ramjibhai

More information

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0. ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.920ha) 1.1 Introduction The subject quarry is proposed for metal stone on 0.920

More information

During the discussions, the Committee finalized the following additional TOR for further study:

During the discussions, the Committee finalized the following additional TOR for further study: Finalization of ToR for development of Visakhapatnam?Kakinada Corridor for the Establishment of Petroleum, Chemicals and Petrochemicals Investment Region (VK- PCPIR), Andhra Pradesh by M/s VK- PCPIR Special

More information

1726M/1, 1725M/2, 1724M, 1056M, 1058M,

1726M/1, 1725M/2, 1724M, 1056M, 1058M, To, Date 22.03.2018 Member Secretary Expert Appraisal Committee II Infrastructure Development, Coastal Regulation Zone, Building/Construction and Miscellaneous projects Ministry of Environment, Forest

More information

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-

More information

Registered. M/s Baba Jiwan Singh Baba Dalip Singh Educational Trust, Goindwal Sahib Road, Tarn Taran.

Registered. M/s Baba Jiwan Singh Baba Dalip Singh Educational Trust, Goindwal Sahib Road, Tarn Taran. No. SEIAA/ 2309 To STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road,

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN VILLAGE - KUNDLA TEHSIL - NAGDA DISTRICT - UJJAIN STATE - MADHYA PRADESH KHASRA NO. - 574 AREA - 8.00 Hectare PRODUCTION - 98800 cu.m/ Year PREPARED UNDER RULE 42 C OF MP MINOR

More information

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests Vatavaran Bhawan, Nabha Road, Patiala-147001 Telefax:- 0175-2215802 No.SEIAA/2009/32235

More information

Registered. M/s Simmro Infrastructure & Developers Pvt. Ltd., B-3, Greater Kailash Enclave-2, New Delhi.

Registered. M/s Simmro Infrastructure & Developers Pvt. Ltd., B-3, Greater Kailash Enclave-2, New Delhi. No. SEIAA/ 2273 To STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road,

More information

No. SEIAA/2016/2161 Dated Sh. Rakesh Gupta, M/s GGP Buildtech (P) Ltd., Kharar Landran Road, Sector-115, Kharar.

No. SEIAA/2016/2161 Dated Sh. Rakesh Gupta, M/s GGP Buildtech (P) Ltd., Kharar Landran Road, Sector-115, Kharar. STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, PUNJAB MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, GOVERNMENT OF INDIA O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147

More information

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: -

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Conceptual plan Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Area of plot= 5293SQM, Sanctioned FAR = 10586SQM as per earlier sanctioned.(2) Sanctioned Built up Area=19480.63

More information

COMPLIANCE INDEX TO ENVIRONMENTAL NORMS & ENVIRONMENTAL SAFEGUARDS

COMPLIANCE INDEX TO ENVIRONMENTAL NORMS & ENVIRONMENTAL SAFEGUARDS COMPLIANCE INDEX TO ENVIRONMENTAL NORMS & ENVIRONMENTAL SAFEGUARDS (Building & Construction Sector) S. No. Conditions Under prevailing laws/ Environmental norms with adequate environmental safeguards 1.

More information

I N D E X. Item No. Description

I N D E X. Item No. Description I N D E X Item No. Description 16.1 Confirmation of the minutes of 14 th meeting of SEAC held on 1/11/2008. 16.2 Action taken on the proceedings of the 14 th meeting of SEAC held on 1/11/2008. 16.3 Re-consideration

More information

Details of the proposed project as presented before the committee are tabulated below:

Details of the proposed project as presented before the committee are tabulated below: Shrungal Homes Block No. 141, F.P.No.42, O.P.No.42, T.P.S.No.58 (Bamroli), Choryasi, Surat. Screening & scoping / appraisal. Details of the proposed project as presented before the committee are tabulated

More information

Consolidated Statement on various Environmental Aspects for Construction Project

Consolidated Statement on various Environmental Aspects for Construction Project Consolidated Statement on various Environmental Aspects for Construction Project S.N. Particular 1 Name of Project Development of IKEA Store in Navi Mumbai, India 2 Name, contact number & address of proponent

More information

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND EXECUTIVE SUMMARY Kumhari Stone Mine is situated in Village - Kumhari, P.O. Basia, P.S. - Basia, District : Gumla, Jharkhand over an area of 2.02 Hectares or 5.00 Acres [ Plot no. 2085(P)]. Kumhari Stone

More information

Item no Confirmation of the minutes of 56 th meeting of State Level Environment Impact Assessment Authority held on

Item no Confirmation of the minutes of 56 th meeting of State Level Environment Impact Assessment Authority held on Proceedings of the 57 th meeting of State Level Environment Impact Assessment Authority held on 10.01.2014 at 11.00 AM in the Regional Office, Punjab Pollution Control Board, Phase-2, Opposite Bassi Cinema,

More information

5. ENVIRONMENT MANAGEMENT PLAN

5. ENVIRONMENT MANAGEMENT PLAN 5. ENVIRONMENT MANAGEMENT PLAN The environmental management plan consist of the set of mitigation measures, management and, monitoring measures to be taken during construction and operation phase to eliminate